Top Banner
Tank 85 Foundation View of poured auger pile. Setting up for next pile. This process repeated itself 310.
16

Tank 85 Foundation

Nov 12, 2014

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Tank 85 Foundation

Tank 85 Foundation Tank 85 Foundation

View of poured auger pile.

Setting up for next pile.

This process repeated itself 310.

Page 2: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Tying the cages for the poured piling.

Auger pile boring in progress.

New cage ready to place when gout is poured.

Page 3: Tank 85 Foundation

Tank 85 Foundation

The grout in some piling settled and was repaired. Grout was chipped to a clean surface and re-poured.

Pouring the repair.

Page 4: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Excavating to sub-grade for the mud slab.

Excavating continues while the mud slab is being poured.

Page 5: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Mud slab complete and form setting in progress. Laying out support bars for re-bar work to begin.

Form setting for the slab well under way.

Page 6: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

First mat of re-bar placed Oct. 24/25,06

Placing top mat Oct. 26/27,06

Page 7: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Re-bar is complete and ready for concrete pour Oct. 28, 06.

Page 8: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Tying wall dowels and support dowels Oct 27, 06.

Water-stop placed so it can be repositioned while the concrete is being poured

Page 9: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

5AM Oct 28,06. First two loads of concrete.

Pouring with two pump trucks

Page 10: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

5:45 AM, pour well under way.

Page 11: Tank 85 Foundation

Tank 85 FoundationTank 85 Foundation

Grading in progress prior to setting panels Nov. 2,06.

Preparing to set inner ring wall.

Page 12: Tank 85 Foundation

Tank 85 Foundation

7AM Sat. anchor bolts set and checked, re-bar complete, ready to pour.

Pour approximately 40 % at 9:30 AM

Page 13: Tank 85 Foundation

Tank 85 Foundation

Ring wall completely poured.

Ring wall stripped and grading for tank contractor started

Page 14: Tank 85 Foundation

Tank 85 Foundation

Liner installation well under way.

Liner nearly completed.

Page 15: Tank 85 Foundation

Tank 85 Foundation

Ramp in place for placing of sand and entrance of crane and materials. 11-13-06

First of many loads of sand, 11-14-06

Page 16: Tank 85 Foundation

Tank 85 Foundation

Sand fill covered for the night. 11-15-06

Compacting first lift of sand. Tested at 105-108.