Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Aug 03, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Talan Industries LLC | www.talanindustries.com

Talan Industries LLC Manufacturing

Division

Cage Code 7PEZ4

Page 2: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Talan Industries LLC | www.talanindustries.com

• Radiator Manufacturing in Nuevo Laredo, Mexico –

Majority of Parts Coming From USA and Qualifying

Countries

• 45,000 Sq. Ft Facility

• Specializing in Copper, Brass and Steel Construction

of Radiators, Radiator Cores, Radiator Accessories –

tanks, surge tanks, Charge Air Coolers and AC

Condensers

• 135 Full Time Staff – Heat Rejection Engineer,

Mechanical Engineers, Physical Engineers

• Provider to United States Department of Defense,

OEM and Private Industry

Page 3: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Talan Industries LLC | www.talanindustries.com

• State of the Art Testing Facility – Burst Pressure,

Leak, Corrosion, etc.

• Manufacturing Meets US EPA and Employee Safety

Standards. No Child Labor at any Steps of the

Process

• Test and Quality System AS9003

• Finishing Based on Clients Needs

• Manufacturing Tailored to Meet Clients Specific

Needs and Specs

• Small Business Set Aside

Page 4: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Engineering / DesignEngineering / Design: Engineers utilize both AutoCAD and Solidworks. CAM2000 is utilized for CNC equipment and CADMAN for CNC Press Brakes.

Page 5: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Core AssemblyCore Tubes:Brass strip is roll formed, solder coated and cut to length.

CT Style or Flat Fin:Copper strip is fed into the machine tools resulting in the finished fin.

Page 6: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Core AssemblyCore Assembly:Copper fins and brass tubes are stacked onto a core fixture table and strapped together.

Header Installation:Headers are installed onto cores completing the core assembly.

Page 7: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Stamping / PressesPart fabrication is done on various machinery; Amada punch presses, Mechanical Presses and Hydraulic Presses. All have capability of both large and small parts.

Page 8: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Stamping / Presses / Shearing

Page 9: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Fabrication

Fabrication Capability:LVD 2K Watt Laser Work Center, LVD CNC 3-Axis Press Brakes.

Page 10: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Robotic WeldingRobot Work Stations: Programmable for repetitive production needs.

Page 11: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Welding and Fabrication

Welding Stations: Operators Mig Weld metal parts for both production and custom order parts.

Page 12: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Core Bake / Radiator Assembly

Core Bake: Cores are baked in either of 2 ovens. Hanging Conveyor or flat conveyor.

Radiator Assembly: Radiators are assembled in Soldering Stations for solder type radiator or Bolt On Jigs for Bolt type radiators.

Page 13: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

TestingRadiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part does not leak.

Fabricated Radiator Tanks: All tanks are tested for leaks prior to assembly or shipment.

Page 14: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Paint and PackagingPaint: Radiators are painted in a hanging conveyor preheat / curing oven.

Packaging: Radiators are boxed and labeled then sent to the Shipping Area.

Page 15: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Tool/Machine Shop

Tool/Machine Shop: Capable of making / repairing tooling. CNC Machine Center, Mills, Lathe, Surface Grinder.

Page 16: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Stock Room

Page 17: Talan Industries LLC Manufacturing Division · Testing Radiator Testing: All radiators are leak tested by completely submerging the radiator under pressure to verify that the part

Talan Industries LLC | www.talanindustries.com

Talan Industries LLCCage Code 7PEZ4

Office/Mailing Address732 Northhampton Ct

Delaware, OH 43015

740-815-7601

Todd Hanks

[email protected]

Manufacturing PlantNuevo Laredo, Mexico 88190

Repair FacilityRiverview, MI 48174