Top Banner
214

Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Jul 12, 2018

Download

Documents

ngominh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers
Page 2: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers
Page 3: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

TOC i

Table of Contents

EXECUTIVE SUMMARY ...................................................................................... 1

INTRODUCTION ................................................................................................ 13

1.0 Project Definition: Scope and Costs ......................................................... 13

1.1 9BProject Definition and Scope ............................................................................... 13 1.2 10BCurrent Plan and Costs ....................................................................................... 15 1.3 11B2012 Annual Program Evaluation (APE) ............................................................. 25

1.3.1 23BCost and Revenue Challenges, Risk Factors, and Opportunities ............... 25 41B1.3.1.1 Construction Costs and Variability ......................................................... 26 42B1.3.1.2 Sales And Use Tax Forecast Change .................................................... 28 1.3.1.3 Management Reserve Fund 43B ................................................................... 30 1.3.1.4 Railroad Negotiations ............................................................................. 31 44B1.3.1.5 Grant Opportunities ................................................................................ 31

1.3.2 24BResults of the 2012 APE ............................................................................ 32 45B1.3.2.1 Major Changes from 2011 APE .............................................................. 32 47B1.3.2.2 Financial Plan Alternatives Considered .................................................. 34 48B1.3.2.3 RTD Board Financial Plan Selection ...................................................... 36

1.3.3 25BCollaborative Efforts ................................................................................... 36 49B1.3.3.1 Metro Mayors FasTracks Task Force ..................................................... 36 50B1.3.3.2 Sales and Use Tax Forecast Working Group ......................................... 38 51B1.3.3.3 FasTracks Construction Inflation Workshop ........................................... 39 1.3.3.4 FasTracks Construction Review Council ................................................ 39

1.4 12BStatus of FasTracks Lines ................................................................................... 42 1.4.1 26BCentral Rail Extension ................................................................................ 42 1.4.2 27BDenver Union Station ................................................................................. 44 1.4.3 28BEagle Project ............................................................................................. 48

53B1.4.3.1 East Rail Line ......................................................................................... 50 54B1.4.3.2 Gold Line ............................................................................................... 52 55B1.4.3.3 Northwest Rail Line – Phase 1 ............................................................... 54 56B1.4.3.4 Commuter Rail Maintenance Facility ...................................................... 56

1.4.4 29BI-225 Rail Line ............................................................................................ 58 1.4.5 30BMaintenance Facilities ................................................................................ 60

57B1.4.5.1 Light Rail Maintenance Facility ............................................................... 60 1.4.6 31BNorth Metro Rail Line ................................................................................. 62 1.4.7 32BNorthwest Rail Line – Phase 2 ................................................................... 64 1.4.8 Northwest Rail Line – Phase 3 ................................................................... 64 1.4.9 Northwest BRT ........................................................................................... 66 1.4.10 33BSoutheast Rail Extension ......................................................................... 68 1.4.11 34BSouthwest Rail Extension......................................................................... 70 1.4.12 35BUS 36 Bus Rapid Transit (BRT) Line - Phase 1 ........................................ 73 1.4.13 36BUS 36 Bus Rapid Transit (BRT) Line - Phase 2 ........................................ 73 1.4.14 West Rail Line .......................................................................................... 76

2.0 2BSummary of Financial Plan ....................................................................... 78

3.0 3BImplementation Schedule .......................................................................... 79

3.1 14BModifications to Line/Project Schedules .............................................................. 79 3.2 15BStatus of Environmental Process ........................................................................ 85

4.0 4BBus Service Levels ..................................................................................... 88

Page 4: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

TOC ii

5.0 BOperating Characteristics ......................................................................... 88

6.0 6BTransit Oriented Development (TOD) ....................................................... 98

7.0 7BDowntown Denver Circulator .................................................................. 102

8.0 8BOther FasTracks Plan Elements.............................................................. 104

8.1 16BLegislative Update ............................................................................................ 104 8.1.1 38BSenate Bill 11-223, concerning state sales tax revenues retained by a vendor as compensation for expenses incurred by the vendor in the collection and remittance of such tax revenues to the state, and making an appropriation therefore. ............................................................................................................. 104

8.2 7BQuality Management Oversight ......................................................................... 104 8.3 18BQuality of Life (QoL) .......................................................................................... 105 8.4 19BFasTracks Public Information/Public Outreach Program ................................... 105 8.5 20BCitizens Advisory Committee (CAC) ................................................................. 109 8.6 21BSustainability Program ...................................................................................... 109 8.7 22BFastConnects .................................................................................................... 111 8.8 Workforce Initiative Now (WIN) .......................................................................... 113 8.9 Transformation through Transportation (T3) Industry Forum ............................. 113

List of Figures

Figure 1: FasTracks Plan - Rapid Transit Lines ............................................. 14

Figure 2: Historical Copper Prices .................................................................. 26

Figure 3: Historical Crude Oil Barrel Prices ................................................... 27

Figure 4: Unit Costs for Running Rail (per ton) .............................................. 27

Figure 5: Unit Costs for Reinforcing Steel (Cwt) ............................................ 28

Figure 6: Projected Sales and Use Tax Growth 2005-2035, 2011 vs. 2012 APE .................................................................................................................... 30

Figure 7: FasTracks Program Capital Cost Summary (YOE$) ...................... 33

Figure 8: Historical Perspective of Tax Revenue Forecasts 2005-2035 ....... 33

Figure 9: Central Rail Extension ...................................................................... 43

Figure 10: Denver Union Station Transit Improvements ............................... 44

Figure 11: Denver Union Station ..................................................................... 45

Figure 12: Eagle Project ................................................................................... 49

Figure 13: East Rail Line .................................................................................. 51

Figure 14: Gold Line ......................................................................................... 53

Figure 15: Northwest Rail Line ........................................................................ 55

Figure 16: CRMF Site Location ........................................................................ 57

Figure 17: I-225 Rail Line .................................................................................. 59

Page 5: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

TOC iii

Figure 18: Light Rail Maintenance Facility ..................................................... 60

Figure 19: North Metro Rail Line ...................................................................... 63

Figure 20: Northwest Rail Line ........................................................................ 65

Figure 21: Northwest BRT ................................................................................ 67

Figure 22: Southeast Line ................................................................................ 69

Figure 23: Southwest Rail Line ........................................................................ 71

Figure 24: US 36 BRT Line ............................................................................... 75

Figure 25: West Rail Line ................................................................................. 77

Figure 26: FasTracks SB 208 Original Schedule (2004) & 2012 Financial Plan Schedule ................................................................................................... 81

Figure 27: FasTracks SB 208 2010 Report Schedule & 2012 Financial Plan Schedule ............................................................................................................ 83

Figure 28: Updated Rail Operating Plan and Peak Hour Capacities for FasTracks Lines in 2035 ................................................................................... 91

Figure 29: BRT Peak Hour Capacities (Opening Day) ................................... 92

Figure 30: Downtown Denver Circulator Proposed Route .......................... 103

Figure 31: FastConnects ................................................................................ 112

List of Tables

Table 1: Comparison of 2010 & 2011 FasTracks Capital Cost Characteristics ............................................................................................................................ 17

Table 2: Opening Day Parking by Line ............................................................ 23

Table 3: FasTracks Projected Costs by Project ............................................. 24

Table 4: Growth in Sales and Use Tax Revenues 1992 – 2011...................... 29

Table 5: FasTracks Estimated Capital Sources of Funds Through 2022 (Millions of Dollars) ........................................................................................... 79

Table 6: FasTracks Plan Bus Service Levels ................................................. 88

Table 7: FasTracks Rail Line Capacity and Year 2035 Maximum Line Loads ............................................................................................................................ 90

Table 8: Northwest BRT and US 36 BRT Routes ............................................ 96

Page 6: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

TOC iv

ACRONYMS

ABT Additional Bonds Test

ACEC American Consulting Engineers Council

ADA Americans with Disabilities Act

ANPRM Advanced Notice of Proposed Rulemaking

APE Annual Program Evaluation

ARRA American Recovery and Reinvestment Act

BE Basic Engineering

BNSF Burlington Northern Santa Fe

BRT Bus Rapid Transit

CAC Citizens Advisory Committee

CCA Colorado Contractors Association

CCD City and County of Denver

CDOT Colorado Department of Transportation

CE Categorical Exclusion

CLC Colorado Legislative Council

CM/GC Construction Manager/General Contractor

CMAQ Congestion Management Air Quality

COMTO Conference of Minority Transportation Organization

CPI Consumer Price Index

CRC Construction Review Council

CRMF Commuter Rail Maintenance Facility

DBFOM Design-Build-Finance-Operate-Maintain

DEIS Draft Environmental Impact Statement

DIA Denver International Airport

DMAP Denver Multimodal Access Plan

DMU Diesel Multiple Unit

DOT Department of Transportation

DRCOG Denver Regional Council of Governments

DTP Denver Transit Partners

DUS Denver Union Station

DUSPA Denver Union Station Project Authority

EA Environmental Assessment

EE Environmental Evaluation

EIS Environmental Impact Statement

EMU Electric Multiple Unit

EPA Environmental Protection Agency

Page 7: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

TOC v

FCRC FasTracks Construction Review Council

FEIS Final Environmental Impact Statement

FFGA Full Funding Grant Agreement

FONSI Finding of No Significant Impact

FRESC Front Range Executive Service Corps

FTA Federal Transit Administration

HCC Hispanic Contractors of Colorado

IBEW International Brotherhood of Electrical Workers

MMC Metro Mayors Caucus

MOS Minimum Operable Segment

MOW Maintenance-of-Way

MPO Metropolitan Planning Organization

NPRM Notice of Proposed Rulemaking

NTP Notice to Proceed

NWES Northwest Rail Electrified Segment

P3 Public-Private Partnership

PE Preliminary Engineering

Penta-P Public-Private Partnership Pilot Program

PI Public Information/Involvement

PNRS Projects of National and Regional Significance

QoL Quality of Life

RAQC Regional Air Quality Council

RFP Request for Proposal

RFQ Request for Qualifications

ROD Record of Decision

ROW Right-of-Way

RRIF Railroad Rehabilitation & Improvement Financing

RTP Regional Transportation Plan

SB Senate Bill

SEA Supplemental Environmental Assessment

T3 Transformation through Transportation

TIF Tax Increment Financing

TIFIA Transportation Infrastructure Finance and Innovation Act of 1998

TIGER Transportation Investment Generating Economic Recovery

TIGGER Transit Investments in Greenhouse Gas and Energy Reduction

TIP Transportation Improvement Program

TOD Transit-Oriented Development

TOFC Trailer On Freight Car

Page 8: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

TOC vi

UPRR Union Pacific Railroad

USA Union Station Alliance

USACE US Army Corps of Engineers

USNC Union Station Neighborhood Company

WIN Workforce Initiative Now

YOE Year-of-Expenditure

Page 9: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

TOC vii

Page left intentionally blank

Page 10: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

TOC viii

Page left intentionally blank

Page 11: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

1 April 3, 2012

EXECUTIVE SUMMARY The 2011 Annual Report to DRCOG on FasTracks was prepared pursuant to Senate Bill 208 (SB 208), which was passed by the Colorado legislature in 1990. SB 208 requires Metropolitan Planning Organization (MPO) approval of the financing and technology for all fixed guideway projects. The original report on FasTracks was prepared and approved by Denver Regional Council of Governments (DRCOG) in 2004. In the resolution approving the original report, the requirement for RTD to submit a report annually to DRCOG was a condition of approval. Since that time, reports have been submitted each year. This report represents the seventh annual report to DRCOG on FasTracks. This report further documents progress on FasTracks projects; presents information on additional FasTracks efforts; and includes a summary and discussion of the approved 2012 FasTracks Financial Plan. Project Definition and Scope The FasTracks Plan consists of nine rail lines (new or extended); two bus rapid transit (BRT) lines; redevelopment of Denver Union Station (DUS); a new Commuter Rail Maintenance Facility (CRMF) and an expanded light rail maintenance facility. By the 2022 opening day, the Plan will add approximately 64 miles of commuter rail (East Rail, Gold Line, North Metro Rail, and Northwest Rail – Phase 1 and 2); approximately 28 miles of light rail (Southeast Rail and Southwest Rail Line Extensions, Central Rail Line Extension, I-225, and West Rail Line); Park-n-Ride improvements and/or relocations at existing Park-n-Ride lots along US 36 (US 36 BRT – Phase 1), and up to 80 miles of BRT (US 36 BRT – Phase 2 and Northwest BRT).

Page 12: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

2 April 3, 2012

FasTracks Plan – Rapid Transit Lines

Page 13: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

3 April 3, 2012

Status of FasTracks Lines Below is a description and status of each line. Central Line Extension The Central Line Extension is 0.8-miles in length and extends light rail from the 30th and Downing Station to the 38th/Blake Station where it will facilitate transfers to the East Rail Line. The Environmental Evaluation (EE) was completed in February 2010. Of the $305 million available due to the lower-than-expected Eagle Project bid price, $0.5 million is being used on this Extension for additional technical analysis including the use of a streetcar vehicle as well as the feasibility of other alignments. Denver Union Station Denver Union Station is a multimodal transportation hub that will include light rail, commuter rail, and bus connections, as well as pedestrian access to downtown businesses and the 16th Street Mall Shuttle system. In October 2008, the Federal Transit Administration (FTA) signed the Record of Decision (ROD), and a contract for early construction was signed in May 2009. The Denver Union Station Project Authority (DUSPA) was created in 2008 to provide oversight; distribute project funding; and to contract with the design-builder for all transit infrastructure. Eagle Project The Eagle Project consists of the East Rail Line, the Gold Line, and a portion of the Northwest Rail Line known as the Northwest Rail Electrified Segment (from DUS to the Westminster Station) as well as the CRMF, the commuter rail cars, and other ancillary improvements. In July 2010, RTD entered into a Concession Agreement with Denver Transit Partners (DTP) to design, build, finance, operate, and maintain the Eagle Project. The final Eagle Project cost estimate from DTP was $305 million under RTD’s internal estimates. These funds were allocated to seven unfunded FasTracks projects.

East Rail Line The East Rail Line is a commuter rail line, using Electric Multiple Unit (EMU) vehicles that is 22.8-miles in length and extends from DUS to Denver International Airport (DIA). The FTA signed the ROD in November 2009. On August 31, 2011, FTA granted this project a Full Funding Grant Agreement (FFGA). Gold Line The Gold Line is a commuter rail line, using EMU vehicles, that is 11.2-miles in length and extends from DUS to Ward Road in Wheat Ridge. It shares 3.6 miles from DUS to Pecos with Northwest Rail. FTA signed the ROD in November 2009. On August 31, 2011, FTA granted this project a Full Funding Grant Agreement (FFGA). Northwest Rail Line – Phase 1 Phase 1 of the Northwest Rail Line is the 5.5 mile portion of the Northwest Rail commuter rail line that extends to Downtown Longmont. This commuter rail segment originates at DUS and extends to the Westminster Station and is shared with the Gold Line between DUS and the Pecos Station (3.6 miles). This segment received environmental clearance in both the Northwest Rail EE, which was adopted by the RTD Board of Directors in May 2010 and released to the public in June 2010, as well as the Gold Line Final Environmental Impact Statement (FEIS).

Page 14: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

4 April 3, 2012

Commuter Rail Maintenance Facility (CRMF) This project includes a maintenance shop for commuter rail vehicles, a commuter rail control center, employee facilities, administrative offices, parking, and a building and laydown areas for maintenance-of-way (MOW) equipment and materials. In early 2009, the Fox North (48th & Fox) site was selected as the preferred location in the Supplemental Environmental Assessment (SEA), which was completed in April 2009. The environmental analysis was incorporated into and cleared through the East Rail Line, Gold Line, and North Metro Rail Line EISs.

I-225 Rail Line I-225 is a 10.5-mile light rail line that extends along I-225 from the existing Nine Mile Station, north and east to a station that will be constructed at Peoria/Smith. This station will serve as a transfer point to the East Rail Line. RTD’s current plan is for the I-225 Rail Line to be built in two segments with two different procurement delivery methods. Segment 1 is the segment of the line from the end of line immediately north of the Nine Mile Station to the Iliff Station. Segment 2, the remainder of the line, will continue north from the Iliff Station to the Peoria/Smith Station, which is shared with the East Rail Line. The Draft EE was released in July 2009 and the RTD Board adopted the Final EE in October 2009. Of the $305 million available due to the lower-than-expected Eagle Project bid price, $90 million will be used on this Line to pay for completion of Segment 1. Light Rail Maintenance Facilities This project includes the expansion of existing light rail maintenance facilities at Elati and Mariposa. It essentially doubled the maintenance and operational capacity for light rail. Construction on Elati began in May 2009 and was completed in 2010. Construction on Mariposa began in 2010 and was completed in 2011. North Metro Rail Line North Metro is a commuter rail line, using EMU vehicles, which is 18.4-miles in length and extends from DUS north to 162nd Avenue. In 2009, additional analysis was done on alignment refinements in the southern portion of the line. The Draft Environmental Impact Statement (DEIS) was released in November 2009. The FEIS was released in January 2011 and a ROD was signed on April 22, 2011. Of the $305 million available due to the lower-than-expected Eagle Project bid price, $90 million will be used on this Line to complete the segment from DUS to the National Western Stock Show Station. Northwest Rail Line – Phase 2 Phase 2 of the Northwest Rail Line is comprised of a section of commuter rail using Diesel Multiple Unit (DMU) rail vehicles that is approximately six miles in length that extends from Westminster Station to Church Ranch Station. Of the $305 million available due to the lower-than-expected Eagle Project bid price, $17 million will be used on this Line to complete the Downtown Longmont Station, which will be constructed early and open in 2015. Construction of Phase 2 is scheduled for completion in 2022. The Final EE was adopted by the RTD Board of Directors in May 2010 and released to the public in June 2010.

Page 15: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

5 April 3, 2012

Northwest Rail Line – Phase 3 The remainder of the Northwest Rail Line, 29 miles of DMU commuter rail, will be completed from Church Ranch Station to Downtown Longmont Station as funding becomes available from the original 0.4% sales and use tax. Funding is anticipated to be available during the period of 2026 – 2032.

Northwest BRT Northwest BRT, together with US 36 BRT, will serve the Northwest Corridor area from DUS to Longmont and will consist of up to 80 miles of BRT. The exact BRT alignment and other project elements will be finalized subsequent to environmental clearance and final design. This project is anticipated to be completed in 2020. Southeast Rail Line Extension The Southeast Rail Line Extension is a 2.3-mile light rail extension from the current Southeast Line end-of-line station at Lincoln Avenue and I-25, south to the RidgeGate Parkway/I-25 interchange. The EE for this project was initiated in July 2008 and the Final EE was adopted by the RTD Board of Directors in February 2010. Of the $305 million available due to the lower-than-expected Eagle Project bid price, $9 million will be used on this Line to complete final design and undertake a federal environmental process to prepare for a federal grant application. Southwest Rail Line Extension The Southwest Rail Line Extension is a 2.5-mile light rail extension from the current Southwest Line end-of-line station at Mineral Avenue and Santa Fe Drive (US-85), south and east to the southwest corner of the C470/Lucent Boulevard interchange. The EE for this project was initiated in July 2008 and the Final EE was adopted by the RTD Board of Directors in February 2010. Of the $305 million available due to the lower-than-expected Eagle Project bid price, $8.5 million will be used on this Line to relocate Union Pacific Railroad (UPRR) track. US 36 BRT - Phase 1 This project includes Park-n-Ride improvements, improved pedestrian access to the bus stations, and the construction of bus loading areas along US 36. All improvements associated with Phase I were completed in spring 2010. US 36 BRT - Phase 2 The US 36 BRT-Phase 2 includes funding for RTD’s proportionate share of 18 miles of managed lanes (high-occupancy toll and vehicle and BRT) on US 36. Also included is construction of a pedestrian bridge at the Table Mesa Park-n-Ride and a new eastbound bus pull-out ramp on the south side of US 36. The ROD for the EIS prepared jointly by RTD with Colorado Department of Transportation (CDOT) was signed in December 2009. Of the $305 million available due to the lower-than-expected Eagle Project bid price, $90 million is committed to complete the managed lanes on US 36 to Interlocken. This, and an additional $30 million previously allocated to this project, is being used to partner with the CDOT to extend the managed lanes past Interlocken to 88th Street in a contract that was awarded on February 29, 2012. West Rail Line The West Rail Line originates at DUS and extends for 12.1-miles ending at the Jefferson County Government Center. On January 16, 2009, an FFGA with FTA was executed for $308.68 million to help fund the line. A full Notice to Proceed (NTP) was issued on June

Page 16: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

6 April 3, 2012

16, 2009. Significant construction on this light rail line has been accomplished since construction began in 2008. As of October 2011, a total of 15 bridges, flyovers, and tunnels have been substantially completed and overall construction progress is at 84%. Opening day is scheduled for May 2013. Summary of Environmental Process In 2011, the North Metro EIS, was completed and the ROD was signed on April 22, 2011. In order to be eligible for federal funding, additional environmental studies were undertaken in 2011 for the I-225 Rail Line and for the Southeast Rail Extension. The I-225 EA was completed in September 2011 and the Southeast Rail Extension AA/EA was initiated in October 2011. Current Plan and Line Costs An Annual Program Evaluation (APE) was conducted in late 2011/early 2012 to determine changes in FasTracks project costs and to further evaluate these costs against projected revenues. Overall, it shows an increase in costs from 2004 ($4.7 billion to $7.4 billion), through 2022, and a decrease in projections of sales and use tax receipts for the period 2005 through 2035 ($13.7 billion to $8.0 billion) from 2004 forecasts. The 2012 APE serves as the cost basis for the approved 2012 FasTracks Financial Plan. Annual Program Evaluation Since 2007, RTD has conducted an APE to update both the costs and projected revenues of the FasTracks Program. This information is then used to prepare the FasTracks Financial Plan. This Annual Report includes results of the 2012 APE. Following voter approval of the FasTracks Plan in 2004, commodity prices began an unprecedented rise. In 2008, a drop in prices was observed; however, through 2009, 2010, and 2011 commodity prices have continued an upward trend. Raw materials costs remain well above original 2004 project estimates. Overall, there has been an increase in capital costs from the 2011 APE. This increase is primarily the result of extending the Program schedule out to 2022 and to an increase in the costs for the Northwest Rail line to Church Ranch Station (based on the most recent information from negotiations with Burlington Northern Santa Fe Railroad). Capital costs increased from $6.8 billion (2011 APE) to $7.4 billion (2012 APE). Further, sales and use tax revenues through 2035 are projected at $8.0 billion, which remains below those projected in 2004. FasTracks Program Capital costs and revenue projections for 2004 and 2007-2012 are shown in the two figures below.

Page 17: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

7 April 3, 2012

FasTracks Program Capital Cost Summary

Historical Perspective of Tax Revenue Forecasts 2005-2035

Sales and Use Tax Forecast Change To address the challenges of long-term sales and use tax revenue projections, RTD decided in 2010 to engage a contractor to develop sales and use tax revenue projections for 2011 and beyond. The Leeds School of Business at the University of Colorado at Boulder was selected as the contractor. Leeds developed short-term, medium-term, and long-term sales and use tax revenue forecast models. The Sales and Use Tax Forecasting Working Group which was originally convened in 2009 and consists of a group of state and local government economic advisors, was reconvened twice in 2011 to review progress from Leeds. The group agreed that the long-term models developed by Leeds would be used in the FasTracks 2012 Financial Plan, in the 2012 APE, and going forward. Using the methodology developed by Leeds, average annual growth rates were determined. The medium growth rate scenario of 3.39% per year for the period 2005-2035 was recommended for use in the 2012 Financial Plan. The average annual growth

$4.7 $6.1

$7.9 $6.9 $6.7 $6.8 $7.4

$0.0

$2.0

$4.0

$6.0

$8.0

$10.0

2004FasTracks

2007 APE

2008 APE

2009 APE

2010 APE

2011 APE

2012 APE

Billio

ns

Page 18: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

8 April 3, 2012

rate for the period 2012-2035, or the future years of the Financial Plan, is 3.89% in the medium scenario. FasTracks Construction Inflation Workshop A FasTracks Construction Inflation Workshop was held on November 1, 2011, to discuss and evaluate the construction cost inflation rate that is applied to FasTracks capital cost estimates. Participants included RTD staff, senior transit consultants, representatives from local government and regional agencies, and Ken Simonson, Chief Economist for The Association of General Contractors. In the workshop, RTD’s current cost-estimating methodology and current method for analyzing, forecasting, and estimating construction cost inflation and sales tax revenue were presented. Construction Inflation Workshop participants generally agreed that RTD’s current methodology (and forecast values) for estimating Construction Cost Inflation is conservative, considering the current market trends, expert forecasts, and averages for other similar transit agencies. Financial Plan Alternatives Considered RTD continues to work closely with elected officials, local governments, corridor stakeholders, and the public to identify how to move the FasTracks Program forward. On December 6, 2011, staff presented the RTD Board of Directors with updated cost estimates for the Northwest Rail Line (based on inputs from BNSF). The cost estimate for the Northwest Rail Line represents a significant increase compared to costs assumed last year, and staff indicated at that time that completion of the Northwest Rail Line would likely have to be delayed to 2023 – 2025 to match RTD’s cash flow constraints. Staff identified the following options for RTD Board consideration:

Option 1 (Base Case): Delay completion of Northwest Rail to 2024 to match RTD’s cash flow requirements;

Option 2: Delay completion of Northwest Rail to 2024 to match RTD’s cash flow requirements, but accelerate select capital projects and increase funding for bus service for Northwest Rail and US 36 BRT Service Areas. This option would require a six-month delay for the remaining partially-funded lines;

Option 3: Remove Northwest Rail from the FasTracks plan and commit remaining Northwest Rail project funds, capped at $894.6 million (YOE), for expanded/enhanced BRT in the Northwest Corridor area to be completed by 2020.

Subsequently, based on RTD Guiding Principles and discussions with RTD’s stakeholders, on March 20, 2012, RTD proposed a hybrid option that includes the following:

Extending the Northwest Commuter Rail Line from Westminster Station to the Church Ranch Station with revenue service commencing at a point between 2020 - 2022 to provide bi-directional peak service for commuters connecting to/from DUS;

Completing the Northwest Rail Line incrementally or in its entirety from Church Ranch to Longmont, pending future action by the RTD Board of Directors, as funding becomes available from the original 0.4% sales and use tax. Funding is anticipated to be available to initiate construction and begin revenue service during the period of 2026 – 2032;

Page 19: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

9 April 3, 2012

Building a BRT system by 2020 that will provide cost effective, immediate relief/ mobility improvements for the Northwest Corridor area.

RTD Financial Plan Selection On March 27, 2012 the RTD Board of Directors adopted a Financial Plan that incorporated the staff recommendation for the Northwest Rail Corridor area. This Financial Plan assumes an election in 2012 with an additional 0.4% sales and use tax increase commencing in January 2013. The Financial Plan also assumes opening day for the FasTracks Program by 2022. The remainder of the Northwest Rail Line from Church Ranch Station to Downtown Longmont Station will be completed pending future action by the RTD Board of Directors and as funding becomes available from the original 0.4% sales and use tax. Project costs determined from the 2012 APE and included in the FasTracks Financial Plan are shown in the table below.

FasTracks Projected Costs by Project (In Millions of YOE Dollars)

Bus Service Levels Background bus service levels in the financial plan have changed due to an RTD Board of Directors initiative to ensure long-term fiscal sustainability of RTD’s services that are funded through the original 0.6% sales and use tax. In October 2011, the Board of Directors approved service reductions designed to maximize ridership in a cost-effective manner, or “right-sizing” the level of service to meet current and projected future revenue streams. This resulted in a decrease of 3.5% between 2011 and 2012 bus service hours, including fixed route, call-n-Ride, and ADA services. RTD is committed to funding rubber tire service increases through the FasTracks Program. In 2012, the FasTracks Program is funding approximately 7% of the fixed-route rubber tire service. Without this financial commitment through FasTracks, RTD would be forced to make deeper cuts in rubber tire service to balance its budget. Future year projected service increases range between

Project 2012 APE

West Rail Line $684.3

Total Eagle Project Costs $2,185.0

I-225 Rail Line $748.5

Northwest Rail Corridor (Phase 2 to Church Ranch) $396.0

Northwest BRT $894.6

North Metro Rail Line $978.7

Central Rail Extension $60.3

Southeast Rail Extension $209.1

Southwest Rail Extension $182.2

U.S. 36 BRT – Phase 1 $19.0

U.S. 36 BRT – Phase 2 $220.4

Denver Union Station $287.3

Light Rail Maintenance Facility $18.2

Downtown Denver Circulator $17.3

Other FasTracks Project Costs $482.5

Total FasTracks Program Costs $7,383.4

Page 20: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

10 April 3, 2012

0.7% and 1.1% from 2013 through 2022 and approximately 1.9% annually from 2023 through 2035. Operating Characteristics Since the DRCOG approval of the FasTracks Plan in 2004, the planning horizon for the Regional Transportation Plan (RTP) has been extended to 2035 for most projects. There have been minor changes to the transit operating characteristics, including travel times and speeds, for some of the FasTracks lines, based on changes in technology and alignment refinements. The two most significant changes to the FasTracks operating plan are related to light rail operations and the Northwest Rail Line. The FasTracks light rail operating plan has been updated due to signal timing changes in downtown Denver and the implementation of four-car train platforms. The Northwest Rail Line is now phased. Phase 2 will travel from DUS to Church Ranch Station, Phase 3 will extend the line to the Downtown Longmont Station, and BRT will be implemented to the Downtown Longmont Station. Conclusion Though the unprecedented rise in costs of labor and materials observed after 2004 has moderated, costs have continued to fluctuate. Likewise, sales and use tax revenue projections remain below those originally projected in 2004. The result is the continuation of a funding gap that was first observed during the 2008 APE. Throughout 2011, RTD evaluated different options for completing the FasTracks Plan including various options for future sales and use tax increases. Additionally, to more accurately forecast revenue and determine costs, RTD reconvened a Sales and Use Tax Forecasting Working Group and conducted a Construction Inflation Workshop. These efforts have included recognized experts and stakeholders and have yielded results that were used in preparation of this year’s APE (2012) as well as the 2012 FasTracks Financial Plan. In particular, the Sales and Use Tax Forecasting Working Group utilized the Leeds School of Business at the University of Colorado to develop sales and use tax revenue projections for 2011 and beyond. On March 27, 2012 the RTD Board of Directors adopted a Financial Plan that incorporated the staff recommendation for the Northwest Rail Corridor area. This Financial Plan assumes an election in 2012 with an additional 0.4% sales and use tax increase commencing in January 2013, and would result in opening day for the FasTracks Program by 2022, with Northwest Rail completion to Longmont, incrementally or in its entirety, in the 2026-2032 timeframe.

Page 21: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

11 April 3, 2012

Page left intentionally blank

Page 22: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

12 April 3, 2012

Page left intentionally blank

Page 23: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

13 April 3, 2012

INTRODUCTION In May 2011, RTD prepared and submitted its annual report to the Denver Regional Council of governments (DRCOG) titled RTD 2010 Annual Report to DRCOG on FasTracks. This 2011 Annual Report provides DRCOG with an update on the FasTracks Program (Program) and addresses notable Program changes that have occurred since the RTD 2010 Annual Report to DRCOG on FasTracks. The Financial Plan has also been updated to reflect current forecasting assumptions.

1.0 PROJECT DEFINITION: SCOPE AND COSTS In 2004, the FasTracks Plan (Plan) was approved by the voters. Since Plan approval, annual reports have been prepared and submitted to DRCOG documenting work progress, issues facing the Plan, and the current Financial Plan. The original report prepared pursuant to Senate Bill (SB) 208 was completed in February 2004, prior to voter approval of FasTracks in November 2004. DRCOG reviewed the original report and documented its findings in an April 2004 report. In approving the original report, the DRCOG Board of Directors approved eighteen resolutions that included an annual report as a condition of approval (Appendix A). To date, there have been seven reports submitted and approved by DRCOG. These include the original 2004 report and subsequent reports for 2005 through 2010. This report, the RTD 2011 Annual Report to DRCOG on FasTracks, further documents progress on FasTracks projects; presents information on additional FasTracks efforts; and includes a summary and discussion of the 2012 FasTracks Financial Plan.

1.1 9BProject Definition and Scope The FasTracks Plan (XFigure 1X) consists of nine rail lines (new or extended); two bus rapid transit (BRT) lines; redevelopment of Denver Union Station (DUS); a new Commuter Rail Maintenance Facility (CRMF) and an expanded light rail maintenance facility. By opening day, the Plan will add approximately 64 miles of commuter rail (East Rail, Gold Line, North Metro Rail, and Northwest Rail – Phase 1 and 2); approximately 28 miles of light rail (Southeast Rail and Southwest Rail Line Extensions, Central Rail Line Extension, I-225, and West Rail Line); Park-n-Ride improvements and/or relocations at existing Park-n-Ride lots along US 36 (US 36 BRT – Phase 1), and up to 80 miles of BRT (US 36 BRT – Phase 2 and Northwest BRT). The Financial Plan included in this report incorporates the results of the Annual Program Evaluation (APE) for 2012. The 2012 APE results are discussed in Section 1.3.2 and the corridor descriptions are discussed in Section 1.4. A summary of the 2012 FasTracks Financial Plan is presented in Section 2, with the full Financial Plan description presented in Appendix B.

Page 24: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

14 April 3, 2012

Figure 1: FasTracks Plan - Rapid Transit Lines

Page 25: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

15 April 3, 2012

1.2 10BCurrent Plan and Costs The FasTracks Plan characteristics for all FasTracks lines and major components, such as maintenance facilities, are summarized in XTable 1X. This table highlights changes from the 2010 Annual Report. Information presented in the RTD 2010 Annual Report to DRCOG on FasTracks is shown in yellow and 2011 Annual Report information is shown in blue. Changes from 2010 are identified by bolded type. XTable 2X is a companion to Table 1 and provides additional parking information for opening day for each line. Parking has been updated to reflect the changes in the Northwest Rail phasing as well as the addition of Northwest BRT (see Sections 1.4.7 – 1.4.9). X

Page 26: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

16 April 3, 2012

Page left intentionally blank

Page 27: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

17 April 3, 2012

Table 1: Comparison of 2010 & 2011 FasTracks Capital Cost Characteristics

Total Existing

New:

With

Parking

New:

Without

Parking

2010Central Rail Line

Extension

Light

Rail/Streetcar6

Build single track in each traffic lane between 38th and Blake and 30th/Downing, rather than exclusive ROW; use existing light rail

alignment to 20th/Welton Station, then through downtown loop. Two stations are included along Downing St: 33rd & Downing and

35th & Downing.

Use Denver Downing St ROW. 2 2,4 0 0 2 n/a 18 0 0.8

2010

Central Rail Line

Existing Facility

Enhancements

n/aInstall CBD signal software; and build second pair of tracks from Broadway Station to Alameda Station and from 10th/Osage Station

to Colfax (CPV/CBD split). n/a n/a n/a n/a n/a n/a n/a n/a n/a

2011Central Rail Line

Extension

Light

Rail/Streetcar6

Build single track in each traffic lane between 38th and Blake and 30th/Downing, rather than exclusive ROW; use existing light rail

alignment to 20th/Welton Station, then through downtown loop. Two stations are included along Downing St: 33rd & Downing and

35th & Downing.

Use Denver Downing St ROW. 3 2,4 0 1 2 0 2 18 0 0.8

2011

Central Rail Line

Existing Facility

Enhancements

n/aInstall CBD signal software (completed); Upgrade to 4-car platforms from I-25/Broadway Station to 18th/Stout &

18th/California Stations (with substation capacity improvements (completed);n/a n/a n/a n/a n/a n/a n/a n/a n/a

2010Denver Union

Station (DUS)

Light Rail,

Commuter Rail

& Bus

Light rail station will be located at grade along the CML; the commuter rail station will be located at grade; the Mall Shuttle will be

extended along 16th Street from DUS to the light rail station; RTD Express and Regional bus terminal will be located underground

below 17th Street.

Use RTD ROW (already acquired) and RR ROW (purchased). 1 1 n/a n/a n/a n/a n/a n/a

2011Denver Union

Station (DUS)

Light Rail,

Commuter Rail

& Bus

Light rail station will be located at grade along the CML; the commuter rail station will be located at grade; the Mall Shuttle will be

extended along 16th Street from DUS to the light rail station; RTD Express and Regional bus terminal will be located underground

below 17th Street. The light rail portion of the project was completed in 2011.

Use RTD ROW (already acquired) and RR ROW (purchased). 1 1 n/a n/a n/a n/a n/a n/a

2010 East Rail LineCommuter

Rail/EMU

The alignment follows the UPRR corridor between DUS and Airport Blvd and then heads north and east to DIA. The alignment will

have 16.8 miles of double track and 6 miles of single track. The new track will not be shared with existing or planned freight rail

operations. East Rail Line will use the shared alignment north of DUS to access the CRMF with the FasTracks Gold Line, North

Metro, and Northwest commuter rail lines. The line includes 6 stations: 38th & Blake, Colorado, Central Park Blvd (existing

Stapleton PnR), Peoria/Smith, Airport Blvd/40th (existing), DIA.

Use a combination of UPRR ROW, private property, and shared City and County of

Denver and City of Aurora ROW. 6 2, 5 2 3 1 3,529 7 15

13 (Broadway, 38th Ave, BNSF Market Lead, Quebec, Sand Creek, UPRR-

Airport Blvd-31st Ave-32nd Place-I70, 56th Ave, First Creek, E-470, Pena

Blvd, New Castle, Airport Entrance Rd, Airport Exit Rd)

22.8

2011 East Rail LineCommuter

Rail/EMU

The alignment follows the UPRR corridor between DUS and Airport Blvd and then heads north and east to DIA. The alignment will

have 16.8 miles of double track and 6 miles of single track (additional segments will be reinstated to double track pending an

IGA in 2012). The new track will not be shared with existing or planned freight rail operations. East Rail Line will use the shared

alignment north of DUS to access the CRMF with the FasTracks Gold Line, North Metro, and Northwest commuter rail Lines. The

line includes 6 stations: 38th & Blake, 40th/Colorado, Central Park Blvd (existing Stapleton PnR), Peoria/Smith, Airport Blvd/40th

(existing), DIA.

Use a combination of UPRR ROW, private property, and shared City and

County of Denver and City of Aurora ROW. 6 2, 5 2 3 1 3,529 7 15

13 (Broadway, 38th Ave, BNSF Market Lead, Quebec, Sand Creek, UPRR-

Airport Blvd-31st Ave-32nd Place-I70, 56th Ave, First Creek, E-470, Pena

Blvd, New Castle, Airport Entrance Rd, Airport Exit Rd)

22.8

2010 Gold LineCommuter

Rail/EMU

The Gold Line will operate between DUS and Ward Road in Wheat Ridge primarily on a double track system (with the exception of

one single track segment of approximately 1.5 miles from Ralston Road to Carr St in Arvada) dedicated to commuter rail with no

track shared with freight rail operations. Gold Line will use the shared alignment north of DUS to access the CRMF with the

FasTracks East, North Metro, and Northwest commuter rail lines. Gold Line will share track with Northwest Rail from the CRMF to

Pecos Station. The project includes 7 stations: 41st Ave, Pecos, Federal, Sheridan, Olde Town (existing), Arvada Ridge and Ward

Rd (existing).

Purchase RR ROW and additional private land. 7 2 5 0 2,300 186 (Federal Blvd, Clear Creek, Moffat Line Flyover, Ralston Creek,

Wadsworth Bypass, Kipling)11.2 8

2011 Gold LineCommuter

Rail/EMU

The Gold Line will operate between DUS and Ward Road in Wheat Ridge primarily on a double track system (with the exception of

one single track segment of approximately 1.5 miles from Ralston Road to Carr St in Arvada) dedicated to commuter rail with no

track shared with freight rail operations. Gold Line will use the shared alignment north of DUS to access the CRMF with the

FasTracks East, North Metro, and Northwest commuter rail lines. Gold Line will share track with Northwest Rail from the CRMF to

Pecos Station. The project includes 7 stations: 41st Ave, Pecos, Federal, Sheridan, Olde Town (existing), Arvada Ridge and Ward

Rd (existing).

Purchase RR ROW and additional private land. 7 2 5 0 2,300 186 (Federal Blvd, Clear Creek, Moffat Line Flyover, Ralston Creek,

Wadsworth Bypass, Kipling)11.2 8

2010 I-225 Rail Line Light Rail

Build new double tracks for entire length; the project will travel through the City of Aurora and through one small section of the City

and County of Denver. It will extend from the existing Nine Mile Station to the proposed terminus at Peoria St and Smith Rd. Will

operate on the east side of I-225 from Nine Mile to Florida Station. The alignment crosses over to the west side of I-225 at 13the Ave

to serve the Fitzsimons Medical Campus and remains on the west side to the Peoria/Smith station. The project includes 8 stations:

Iliff, Florida, City Center, 2nd/Abilene, 13th Ave, Colfax, Montview, and Peoria/Smith.

No RR ROW required; Use CDOT I-225 ROW, Aurora ROW, and RTD ROW.

For stations/PnRs acquire private property. 8 2,3 0 5 3 1,800 7 31

8 (I-225 Mainline NB lanes only, Yale, Iliff/Abilene/I-225 NB off-ramp

intersection, NB I-225 to Mississippi Ave off-ramp-Mississippi-Mississippi

Ave to NB I-225 on-ramp, 6th Ave/I-225 NB ramps intersection, I-225 NB &

SB mainline, Colfax, Sand Creek)

10.5

2011 I-225 Rail Line Light Rail

Build new double tracks for entire length; the project will travel through the City of Aurora and through one small section of the City

and County of Denver. It will extend from the existing Nine Mile Station to the proposed terminus at Peoria St and Smith Rd. Will

operate on the east side of I-225 from Nine Mile to Florida Station. The alignment crosses over to the west side of I-225 at 13the Ave

to serve the Fitzsimons Medical Campus and remains on the west side to the Peoria/Smith station. The project includes 8 stations:

Iliff, Florida, City Center, 2nd/Abilene, 13th Ave, Colfax, Montview, and Peoria/Smith.

No RR ROW required; Use CDOT I-225 ROW, Aurora ROW, and RTD ROW.

For stations/PnRs acquire private property. 8 2,3 0 5 3 1,800 7 31

8 (I-225 Mainline NB lanes only, Yale, Iliff/Abilene/I-225 NB off-ramp

intersection, NB I-225 to Mississippi Ave off-ramp-Mississippi-Mississippi

Ave to NB I-225 on-ramp, 6th Ave/I-225 NB ramps intersection, I-225 NB &

SB mainline, Colfax, Sand Creek)

10.5

Notes:

13. Shifted from "Other Items" budget

Changes from 2010 Annual Report are shown in Bold.

10. For additional corridor-specifc information please see the Status of FasTracks Corridors (Section 1.4).

11. Represents only new construction.

12. A bus maintenance facility for the Northwest Corridor BRT is included with that project.

4. The Central Rail Extension terminates at the 38th/Blake Station and creates a transfer point between Commuter Rail (East Rail Line) and Light Rail (Central Rail Extension).

5. Two "design option" stations (East Rail Line) to be privately funded include 62nd/Pena Boulevard and 72nd/Dunkirk. These are not shown in the station total.

6. The Central Rail Extension will utilize a single light rail vehicle in a streetcar function.

7. 550 parking spaces at the Peoria Station (East Rail Line) are shared with the I-225 Rail Line.

8. Gold Line and NW Rail Line share 3.6 miles of track from DUS to Pecos.

9. US 36 & Church Ranch and US 36 & E. Flatiron Circle (NW Rail Line - Flatiron Station; US 36 BRT - Flatiron/96th St. Station) are existing PnRs with 396 spaces and 264 spaces respectively. These will be shared stations by both the US 36 BRT Corridor and the NW Rail Corridor. The existing spaces are accounted for in the Existing and Total Opening Day columns for both US 36 BRT and NW Rail.

3. I-225 Rail Line also includes Nine Mile Station, which is existing, and is not included in the number of stations listed.

Annual

Report

YearCorridor 10 Mode Track, Facilities, and Stations ROW

Stations in New Corridors Total Number

of Parking

Spaces

(opening day) 1

At-Grade

Crossings -

New Transit

Lines

Grade Separations: Structures and Tunnels 11

New Rapid

Transit

Alignment

Length

(miles)

SB 208

Finding

Require-

ment

1. Parking is summarized by corridor in Table 2. Parking in this Table represents parking built by each project.

2. The East Rail Line shares stations with the I-225 Rail Line, where commuter rail and light rail meet, and with the Central Rail Extension (parking to be built by the East Rail Line).

Page 28: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

18 April 3, 2012

Page left intentionally blank

Page 29: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

19 April 3, 2012

Table 1: Comparison of 2010 & 2011 FasTracks Capital Cost Characteristics (continued)

Total Existing

New:

With

Parking

New:

Without

Parking

2010Maintenance

Facilities 12

Light Rail and

Commuter Rail

New commuter rail maintenance facility with buildings and vehicle storage areas. Expansion of the Elati and Mariposa facilities for

light rail maintenance.Purchase private ROW. n/a n/a n/a n/a n/a n/a n/a n/a

2011Maintenance

Facilities 12

Light Rail and

Commuter Rail

New commuter rail maintenance facility with buildings and vehicle storage areas. Expansion of the Elati and Mariposa facilities for

light rail maintenance. All completed in 2011.Purchase private ROW. n/a n/a n/a n/a n/a n/a n/a n/a

2010North Metro Rail

Line

Commuter

Rail/EMU

(pending ROD)

Approximately 13 miles of the alignment is single-track, with passing track segments in five locations from DUS to 38th Street; from

south of 72nd Avenue to just north of I-76; from north of Thornton Parkway to just north of 104th Avenue; from south of 124th Avenue

to south of York Street; and from SH 7 to the end of line, approximately 162nd Avenue. Eight stations proposed: National Western

Stock Show, 72nd Ave (will replace existing Commerce City PnR); 88th Ave; 104th Ave; 112th Ave; Eastlake/124th Ave; 144th Ave

West; and SH 7/162nd Ave. The alignment is proposed to be adjacent to the BNSF Brush Subdivision freight ROW from DUS to

58th Ave and within the UPRR Boulder Branch ROW between the 72nd Ave Station and the SH 7/162nd Ave area.

Purchased UPRR ROW Boulder Branch and additional RR ROW; Purchase

private ROW. Share UP Boulder Branch with one UP train per week. 8 1 7 0 4,020 18

12 (Delgany Wye Track, South Platte River [3], Washington St, 47th Ave,

Marion St, Race Ct, York-BNSF-Brighton-UPRR-O'Brian Canal-Sand

Creek-I270, O'Brian Canal, 104th, 120th)

18.4

2011North Metro Rail

Line

Commuter

Rail/EMU

Approximately 13 miles of the alignment is single-track, with passing track segments in five locations from DUS to 38th Street; from

south of 72nd Avenue to just north of I-76; from north of Thornton Parkway to just north of 104th Avenue; from south of 124th Avenue

to south of York Street; and from SH 7 to the end of line, approximately 162nd Avenue. Eight stations proposed: National Western

Stock Show, 72nd Ave (will replace existing Commerce City PnR); 88th Ave; 104th Ave; 112th Ave; Eastlake/124th Ave; 144th Ave

West; and SH 7/162nd Ave. The alignment is proposed to be adjacent to the BNSF Brush Subdivision freight ROW from DUS to

58th Ave and within the UPRR Boulder Branch ROW between the 72nd Ave Station and the SH 7/162nd Ave area.

Purchased UPRR ROW Boulder Branch and additional RR ROW; Purchase

private ROW. Share UP Boulder Branch with one UP train per week. 8 1 7 0 4,020 18

12 (Delgany Wye Track, South Platte River [3], Washington St, 47th Ave,

Marion St, Race Ct, York-BNSF-Brighton-UPRR-O'Brian Canal-Sand

Creek-I270, O'Brian Canal, 104th, 120th)

18.4

2010Northwest Rail Line:

Phase 1

Commuter

Rail/EMU

This Phase is a 5.5-mile portion of the Northwest Rail commuter rail corridor. This EMU commuter rail segment originates at DUS

and extends to the South Westminster/71st Avenue Station and is shared with the Gold Line between DUS and the Pecos Station.

It includes one station: South Westminster/71st Ave Station.

Purchase private property as well as share RR ROW with BNSF. 1 0 1 0 350 26 (South Platte River, 38th Ave, Jersey Cutoff, BNSF TOFC/UPRR, UPRR

& relocated BNSF flyover at Utah Junction, Clear Creek)5.5 8

2010Northwest Rail Line:

Phase 2

Commuter

Rail/DMU

Phase 2 comprises the remainder of the NW Rail Line from the Westminster Station to Downtown Longmont. Between the

Westminster Station and Longmont, the existing BNSF track would be rehabilitated/replaced, and one new track adjacent to the

existing BNSF track would be constructed. Both tracks would be utilized by freight and commuter rail vehicles. Between the South

Westminster/71st Ave Station and DUS, the track would be in exclusive transit ROW, owned by RTD. The project includes 6

stations: Walnut Creek (existing US 36 & Church Ranch PnR), Flatiron (existing US 36 & E. Flatiron Circle PnR ), Downtown

Louisville, Boulder Transit Village, Gunbarrel, and Downtown Longmont (existing). Northwest Rail Corridor will use the shared

alignment north of DUS to access the CRMF with the FasTracks Gold Line, North Metro, and East Commuter Rail Lines.

Purchase private property as well as share RR ROW with BNSF. 6 3 3 0 3,010 9 407 (Church Ranch Blvd, Old Wadsworth, 75th St, SH 7/Arapahoe Rd, South

Boulder Creek, Boulder Creek, St. Vrain Creek)35.5

2011Northwest Rail Line:

Phase 1

Commuter

Rail/EMU

This Phase is a 5.5-mile portion of the Northwest Rail commuter rail corridor. This EMU commuter rail segment originates at DUS

and extends to the Westminster Station and is shared with the Gold Line between DUS and the Pecos Station. It includes one

station: Westminster Station. Between the Westminster Ave Station and DUS, the track would be in exclusive transit

ROW, owned by RTD.

Purchase private property as well as share RR ROW with BNSF. 1 0 1 0 350 2

7 (23rd st Flyover13 South Platte River, 38th Ave, Jersey Cutoff, BNSF

TOFC/UPRR, UPRR & relocated BNSF flyover at Utah Junction, Clear

Creek)

5.5 8

2011Northwest Rail Line:

Phase 2

Commuter

Rail/DMU

Phase 2 comprises the portion of the NW Rail Line from Westminster Station to Church Ranch Station. The existing

BNSF track would be rehabilitated/replaced, and one new track adjacent to the existing BNSF track would be

constructed. Both tracks would be utilized by freight and commuter rail vehicles. The project includes one station

Church Ranch (existing PnR). Northwest Rail Corridor will use an exclusive DMU maintenance facility at a location to-be-

determined.

Purchase private property as well as share RR ROW with BNSF. 1 1 0 0 636 10 1 (Church Ranch Blvd) 6.0

2011Northwest Rail

Line: Phase 3

Commuter

Rail/DMU

Phase 3 comprises the remainder of the NW Rail Line from the Church Ranch Station to Downtown Longmont Station.

Between the Church Ranch Station and Longmont, the existing BNSF track would be rehabilitated/replaced, and one

new track adjacent to the existing BNSF track would be constructed. Both tracks would be utilized by freight and

commuter rail vehicles. The project includes adding rail platforms to 4 PnRs (Flatiron - existing US 36 & E. Flatiron

Circle PnR; Downtown Louisville; Gunbarrel; Downtown Longmont - existing) and constructing the Boulder Transit

Village Station. Northwest Rail Corridor will use an exclusive DMU maintenance facility at a location to-be-determined.

Purchase private property as well as share RR ROW with BNSF. 1 1 0 0 575 306 (Old Wadsworth, 75th St, SH 7/Arapahoe Rd, South Boulder Creek,

Boulder Creek, St. Vrain Creek)35.0

2011Northwest

Corridor BRTBRT

Freeway BRT portion of the project includes: Exclusive guideway on SH 119 (buffer separated), transit signal priority

upgrades at existing signalized intersctions. Buses will utilize existing infrastructure on US 36 as completed with the US

36 managed lanes project. The project constructs parking and/or upgrades to include BRT station elements at the

Gunbarrel and Flatiron Stations.

Arterial BRT portion of the project includes transit signal priority and queue jumps at existing signalized intersections

along SH 7, SH 42, US 287, and S. Boulder Rd. The project constructs parking and/or upgrades to include BRT station

elements at the following stations: Downtown Louisville, Lafayette (existing PnR to be relocated), Hwy 119/Niwot

(existing PnR, and US 287/Niwot (existing PnR).

New, specially branded BRT vehicles will be purchased and a new BRT maintenance facility will be constructed along

the corridor.

Primarily CDOT ROW along state highways. Some purchase of private

property will be required.6 3 3 0 2,003 0 0 80.0

Notes:

13. Shifted from "Other Items" budget

Changes from 2010 Annual Report are shown in Bold.

3. I-225 Rail Line also includes Nine Mile Station, which is existing, and is not included in the number of stations listed.

Annual

Report

YearCorridor 10 Mode Track, Facilities, and Stations ROW

Stations in New Corridors Total Number

of Parking

Spaces

(opening day) 1

At-Grade

Crossings -

New Transit

Lines

Grade Separations: Structures and Tunnels 11

New Rapid

Transit

Alignment

Length

(miles)

SB 208

Finding

Require-

ment

1. Parking is summarized by corridor in Table 2. Parking in this Table represents parking built by each project.

2. The East Rail Line shares stations with the I-225 Rail Line, where commuter rail and light rail meet, and with the Central Rail Extension (parking to be built by the East Rail Line).

10. For additional corridor-specifc information please see the Status of FasTracks Corridors (Section 1.4).

11. Represents only new construction.

12. A bus maintenance facility for the Northwest Corridor BRT is included with that project.

4. The Central Rail Extension terminates at the 38th/Blake Station and creates a transfer point between Commuter Rail (East Rail Line) and Light Rail (Central Rail Extension).

5. Two "design option" stations (East Rail Line) to be privately funded include 62nd/Pena Boulevard and 72nd/Dunkirk. These are not shown in the station total.

6. The Central Rail Extension will utilize a single light rail vehicle in a streetcar function.

7. 550 parking spaces at the Peoria Station (East Rail Line) are shared with the I-225 Rail Line.

8. Gold Line and NW Rail Line share 3.6 miles of track from DUS to Pecos.

9. US 36 & Church Ranch and US 36 & E. Flatiron Circle (NW Rail Line - Flatiron Station; US 36 BRT - Flatiron/96th St. Station) are existing PnRs with 396 spaces and 264 spaces respectively. These will be shared stations by both the US 36 BRT Corridor and the NW Rail Corridor. The existing spaces are accounted for in the Existing and Total Opening Day columns for both US 36 BRT and NW Rail.

Page 30: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

20 April 3, 2012

Page left intentionally blank

Page 31: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

21 April 3, 2012

Table 1: Comparison of 2010 & 2011 FasTracks Capital Cost Characteristics (continued)

Total Existing

New:

With

Parking

New:

Without

Parking

2010SE Rail Line

ExtensionLight Rail

Build new double track for entire extension. The extension runs along the west side of I-25 from existing Lincoln Station to Sky

Ridge Ave, crosses over I-25, and proceeds south along the east side of I-25 past RidgeGate Parkway. Three stations proposed:

Sky Ridge, Lone Tree City Center, and RidgeGate end-of-line station.

Use mostly developer donated ROW (pending) and purchase private ROW. 3 12 0 1 2 2,000 2 3 (Lincoln, I-25, RidgeGate Parkway) 2.3

2010

SE Rail Line

Existing Facility

Enhancements

Light RailBuild bicycle and pedestrian improvements at Belleview and Arapahoe stations; Build 520 parking spaces at Lincoln Station and

upgrade all platforms to 4-car platforms. n/a 1 1 0 0 520 n/a n/a n/a

2011SE Rail Line

ExtensionLight Rail

Build new double track for entire extension. The extension runs along the west side of I-25 from existing Lincoln Station to Sky

Ridge Ave, crosses over I-25, and proceeds south along the east side of I-25 past RidgeGate Parkway. Three stations proposed:

Sky Ridge, Lone Tree City Center, and RidgeGate end-of-Line Station.

Use mostly developer donated ROW (pending) and purchase private ROW. 3 12 0 1 2 2,000 2 3 (Lincoln, I-25, RidgeGate Parkway) 2.3

2011

SE Rail Line

Existing Facility

Enhancements

Light RailBuild bicycle and pedestrian improvements at Belleview and Arapahoe stations; Build 520 parking spaces at Lincoln Station and

upgrade all platforms to 4-car platforms. All elements completed.n/a 1 1 0 0 520 n/a n/a n/a

2010SW Rail Line:

ExtensionLight Rail

Build new double track for entire extension. The extension runs south from the existing Mineral Station along the west side of the

UPRR and BNSF lines. One station proposed at C-470/Lucent Blvd.

Use existing RTD ROW; use RR ROW (already use agreement); use CDOT

C-470 ROW, use Englewood ROW and purchase private ROW.1 0 1 0 1,000 0 2 (County Line-C470, Erickson Blvd) 2.5

2010

SW Rail Line

Existing Facility

Enhancements

Light RailEnhancements include additional parking at the Englewood Station, coordination with the City of Englewood for a potential Bates

Station, and improving all existing stations so they can accommodate 4-car trains. n/a 1 1 0 0 440 n/a n/a n/a

2011SW Rail Line:

ExtensionLight Rail

Build new double track for entire extension. The extension runs south from the existing Mineral Station along the west side of the

UPRR and BNSF lines. One station proposed at C-470/Lucent Blvd.

Use existing RTD ROW; use RR ROW (already use agreement); use CDOT

C-470 ROW, use Englewood ROW and purchase private ROW.1 0 1 0 1,000 0 2 (County Line-C470, Erickson Blvd) 2.5

2011

SW Rail Line

Existing Facility

Enhancements

Light RailEnhancements include additional parking at the Englewood Station, coordination with the City of Englewood for a potential Bates

Station, and improving all existing stations so they can accommodate 4-car trains. n/a 1 1 0 0 440 n/a n/a n/a

2010US-36 BRT:

Phase 1Bus

Improvements to Westminster and Flatiron PnRs. Bus pull-outs at Church Ranch PnR. Bus pull-outs and a pedestrian bridge at

both Broomfield and McCaslin PnRs. Bus superstops on 28th St built by the City of Boulder. Project includes 5 stations (all

existing): US 36 & McCaslin, Flatiron & 96th, Broomfield, US 36 & Church Ranch, and Westminster Center.

Use CDOT ROW (US 36); purchase private ROW for pnR expansion. 5 5 0 0 3,376 9 0 n/a n/a

2011US-36 BRT:

Phase 1Bus

Improvements to Westminster and Flatiron PnRs. Bus pull-outs at Church Ranch PnR. Bus pull-outs and a pedestrian bridge at

both Broomfield and McCaslin PnRs. Bus superstops on 28th St built by the City of Boulder. Project includes 5 stations (all

existing): US 36 & McCaslin, Flatiron & 96th, Broomfield, US 36 & Church Ranch, and Westminster Center. All completed in 2010.

Use CDOT ROW (US 36); purchase private ROW for pnR expansion. 5 5 0 0 3,376 9 0 n/a n/a

2010US-36 BRT:

Phase 2HOV/BRT

Eighteen miles of new managed lanes (BRT/HOV/HOT) from Table Mesa PnR to existing managed lanes in the vicinity of Pecos St.

Service continues to DUS. Pedestrian bridge and ramp pull-outs at the existing Table Mesa PnR.Use CDOT ROW. 1 1 0 0 824 0 0 18.0

2011US-36 BRT:

Phase 2HOV/BRT

Eighteen miles of new managed lanes (BRT/HOV/HOT) from Table Mesa PnR to existing managed lanes in the vicinity of Pecos St.

Service continues to DUS. Pedestrian bridge and ramp pull-outs at the existing Table Mesa PnR.Use CDOT ROW. 1 1 0 0 824 0 0 18.0

2010 West Rail Line Light Rail

Build new double track from Auraria West Station and existing CPV connection to Denver Federal Center Station and single track

westward to Jefferson County Government Center Station. Project includes 11 stations: Jefferson County Government Center, Red

Rocks Community College, Federal Center (existing Cold Spring PnR), Oak, Garrison, Wadsworth, Lamar, Sheridan, Perry, Knox

and Federal.

Use RTD ROW; use CDOT US-6 ROW; use City and County of Denver ROW;

use Lakewood ROW; and purchase private ROW. Will operate in a separate

ROW, US 6 ROW and city streets.

11 1 5 5 5,605 20

11 (Burnham Lead/Shoshone Street-CML-Umatilla, Platte River, Federal,

Sheridan, Wadsworth, Kipling, West 6th & Frontage Road, Union, West

6th-Indiana, I-70, West Colfax)

12.1

2011 West Rail Line Light Rail

Build new double track from Auraria West Station and existing CPV connection to Denver Federal Center Station and single track

westward to Jefferson County Government Center-Golden Station. Project includes 11 stations: Jefferson County Government

Center-Golden, Red Rocks Community College, Federal Center (formerly the existing Cold Spring PnR), Oak, Garrison,

Lakewood-Wadsworth, Lamar, Sheridan, Perry, Knox and Decatur-Federal.

Use RTD ROW; use CDOT US-6 ROW; use City and County of Denver ROW;

use Lakewood ROW; and purchase private ROW. Will operate in a separate

ROW, US 6 ROW and city streets.

11 1 5 5 5,605 20

11 (Burnham Lead/Shoshone Street-CML-Umatilla, Platte River, Federal,

Sheridan, Wadsworth, Kipling, West 6th & Frontage Road, Union, West

6th-Indiana, I-70, West Colfax)

12.1

2010 Other ItemsCommuter Rail

& other

Build 23rd Street Flyover bridge over the CML for both the Gold Line and the Northwest Corridor Commuter Rail, which consists of a

bridge structure near Park Ave and southeast of the South Platte River; and overall project management. Purchase ROW options in

northeast (US-85/I-76) corridor. Install new downtown circulator (not defined).

n/a n/a n/a n/a n/a n/a n/a n/a

2011 Other ItemsCommuter Rail

& other

Build 23rd Street Flyover bridge over the CML for both the Gold Line and the Northwest Corridor Commuter Rail, which consists of a

bridge structure near Park Ave and southeast of the South Platte River; and overall project management. Purchase ROW options in

northeast (US-85/I-76) corridor. Install new downtown circulator (see Section 7.0 for project definition).

n/a n/a n/a n/a n/a n/a n/a n/a

Notes:

13. Shifted from "Other Items" budget

Changes from 2010 Annual Report are shown in Bold.

3. I-225 Rail Line also includes Nine Mile Station, which is existing, and is not included in the number of stations listed.

1. Parking is summarized by corridor in Table 2. Parking in this Table represents parking built by each project.

2. The East Rail Line shares stations with the I-225 Rail Line, where commuter rail and light rail meet, and with the Central Rail Extension (parking to be built by the East Rail Line).

10. For additional corridor-specifc information please see the Status of FasTracks Corridors (Section 1.4).

11. Represents only new construction.

12. A bus maintenance facility for the Northwest Corridor BRT is included with that project.

4. The Central Rail Extension terminates at the 38th/Blake Station and creates a transfer point between Commuter Rail (East Rail Line) and Light Rail (Central Rail Extension).

5. Two "design option" stations (East Rail Line) to be privately funded include 62nd/Pena Boulevard and 72nd/Dunkirk. These are not shown in the station total.

6. The Central Rail Extension will utilize a single light rail vehicle in a streetcar function.

7. 550 parking spaces at the Peoria Station (East Rail Line) are shared with the I-225 Rail Line.

8. Gold Line and NW Rail Line share 3.6 miles of track from DUS to Pecos.

9. US 36 & Church Ranch and US 36 & E. Flatiron Circle (NW Rail Line - Flatiron Station; US 36 BRT - Flatiron/96th St. Station) are existing PnRs with 396 spaces and 264 spaces respectively. These will be shared stations by both the US 36 BRT Corridor and the NW Rail Corridor. The existing spaces are accounted for in the Existing and Total Opening Day columns for both US 36 BRT and NW Rail.

Annual

Report

YearCorridor 10 Mode Track, Facilities, and Stations ROW

Stations in New Corridors Total Number

of Parking

Spaces

(opening day) 1

At-Grade

Crossings -

New Transit

Lines

Grade Separations: Structures and Tunnels 11

New Rapid

Transit

Alignment

Length

(miles)

SB 208

Finding

Require-

ment

Page 32: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

22 April 3, 2012

Page left intentionally blank

Page 33: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

23 March 2012

Table 2: Opening Day Parking by Line

Corridor Existing SpacesExisting PnR:

Spaces Subtracted1

Existing PnR:

Spaces Added

New PnR:

Spaces Added

Total Opening Day

Spaces

Central Rail Extension 0 0 0 0 0

East Rail Line 3 2,848 -1,769 0 2,450 3,529

Gold Line 691 -491 200 1,900 2,300

I-225 Rail Line3 0 0 0 1,800 1,800

North Metro Rail Line 83 -83 0 4,020 4,020

Northwest Rail Line: Phase 1 0 0 0 350 350

Northwest Rail Line: Phase 2 396 0 240 0 636

Northwest Rail Line: Phase 3 0 0 0 575 575

Northwest BRT2,4 569 -237 0 1,671 2,003

Southeast Rail Extension 0 0 0 2,000 2,000

Southeast Rail Enhancements 0 0 520 0 520

Southwest Rail Extension 0 0 0 1,000 1,000

Southwest Rail Enhancements 0 0 440 0 440

US 36 BRT Line 2 3,826 0 374 0 4,200

West Corridor Line 646 0 354 4,605 5,605

Total 9,059 -2,580 2,128 20,371 28,978

2. US 36 & Church Ranch and US 36 & E. Flatiron Circle (NW BRT - Flatiron Station; US 36 BRT - Flatiron/96th St. Station) are existing PnRs with 396 spaces and 264

spaces respectively. These will be shared stations by both the US 36 BRT Corridor and the NW Rail Corridor. The existing spaces are accounted for in the Existing and

Total Opening Day columns for both US 36 BRT and NW BRT.

3. East Rail Line and I-225 share the 550 spaces at the Peoria/Smith Station. Those spaces are counted in the Total Opening Day Spaces for both corridors.

1. In most cases subtraction of spaces is due to relocating an existing PnR that becomes a rapid transit station.

4. Northwest BRT includes parking at existing Hwy 119/Niwot and US 287/Niwot PnRs that will be BRT stations.

Page 34: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

24 April 3, 2012

Table 3: FasTracks Projected Costs by Project

(In Millions of YOE Dollars)

In identifying the scope for a potential sales and use tax election in 2012, RTD established a fiscally responsible approach that balances the immediate mobility needs of the region with the long-term affordability of building out the entire system. The new tax would complete North Metro, I-225, the Central, Southeast and Southwest Extensions, the Downtown Denver Circulator and Northwest BRT by 2020 and an extension of the Northwest Rail Line to the Church Ranch station by 2022. Assuming a successful sales and use tax election in 2012, this approach will allow RTD to address mobility needs across the region by opening day (2022), and will allow RTD to completely sunset the new sales and use tax earlier. Additionally, RTD remains committed to completing the Northwest Rail Line to Longmont, as included in the original 2004 plan, when funding becomes available from the original 0.4% sales and use tax. Completing the Northwest Rail Line when it is affordable will fulfill the voter approved 2004 FasTracks Plan. The 2012 FasTracks Financial Plan currently assumes funding will be available to complete the Northwest Rail Line to Longmont starting in 2026 and completing in 2032. It is difficult to quantify the exact cost of the remainder of this corridor given the need to complete various negotiations and the uncertainties involved with projecting project costs this far into the future. However, to be consistent with RTD’s strategic approach of the past few years to use a conservative methodology for projecting costs and revenues, the agency is currently and conservatively projecting a cost of $830 million (Base Year costs)/$1.8 billion (Year of Expenditure costs) to complete the Northwest Rail Line from Church Ranch to Longmont by 2032.

Project 2012 APE

West Rail Line $684.3

Total Eagle Project Costs $2,185.0

I-225 Rail Line $748.5

Northwest Rail Corridor (Phase 2 to Church Ranch) $396.0

Northwest BRT $894.6

North Metro Rail Line $978.7

Central Rail Extension $60.3

Southeast Rail Extension $209.1

Southwest Rail Extension $182.2

U.S. 36 BRT – Phase 1 $19.0

U.S. 36 BRT – Phase 2 $220.4

Denver Union Station $287.3

Light Rail Maintenance Facility $18.2

Downtown Denver Circulator $17.3

Other FasTracks Project Costs $482.5

Total FasTracks Program Costs $7,383.4

Page 35: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

25 April 3, 2012

1.3 11B2012 Annual Program Evaluation (APE) Since 2007, RTD has conducted an APE, which includes updating the FasTracks Financial Plan with current capital costs, operating costs and revenue estimates, reflecting ever-changing economic conditions. During the 2008 APE, RTD identified a funding gap for the FasTracks Program. The gap was a result of extraordinary escalation of costs for commodities and materials, combined with an economic slowdown and the corresponding downward impact on current and forecast sales and use tax revenues. Since the 2008 APE, RTD has been working with stakeholders, elected officials and DRCOG to determine how to implement the FasTracks Program given the gap in funding for the Program. The following sections further discuss these challenges and other risk factors for the FasTracks Program. The 2012 Financial Plan included in this report incorporates the results of the 2012 APE. 1.3.1 23BCost and Revenue Challenges, Risk Factors, and Opportunities In 2010, RTD reached a major milestone in the FasTracks Program with the award of the contract for the Eagle Project to Denver Transit Partners (DTP). In 2011, RTD received a Full Funding Grant Agreement (FFGA) from the Federal Transit Administration (FTA) in the amount of $1.03 billion for this project. The Eagle Project, which includes the East and Gold Line Lines, a Commuter Rail Maintenance Facility (CRMF), and Northwest Rail Line – Phase 1, is the largest public-private partnership transit project in the United States. RTD has contracted with DTP to design, build, and finance the initial construction of the projects, and to operate and maintain all project assets through the year 2044. Through this contract, RTD realized savings over its internally estimated construction costs, and established its operating and maintenance costs for the first 30 years of line operations. The DTP bid came in $305 million lower than RTD’s internal estimate. Those funds have been allocated to seven unfunded FasTracks projects. Additionally, RTD has signed right-of-way (ROW) agreements with the railroads for all lines, and continues negotiating with Burlington Northern Santa Fe (BNSF) railroad for an operating agreement for the Northwest Line. Ongoing railroad negotiations and the Eagle Project are discussed in more detail in Sections 1.3.1.4 and 1.4.3. Despite its success with the Eagle Project award and receipt of a $1.03 billion FFGA, implementation of the FasTracks Plan continues to present challenges to RTD. The current Financial Plan, assuming a successful sales and use tax election in 2012, identifies an opening day (2022) program cost of $7.4 billion, representing an increase of $2.7 billion over the original projected cost of the Program. At the same time, the continued challenges of the regional economy resulted in a decrease in projected sales and use tax collections through 2035. In late 2011, RTD reconvened a working group of local government economists and financial experts to review its long-term sales and use tax forecasts and a group with experience on both national transit construction projects and local public works projects to review its construction escalation assumptions. Those processes resulted in a FasTracks Financial Plan that relies on conservative tax projections and construction costs, which will set the stage for the successful completion of the FasTracks Program. Since the last Annual Report to DRCOG, RTD hired the Business Research Division of CU Leeds School of Business to develop a third party methodology for projecting sales and use tax growth. This resulted in a very slight decrease in annual growth rate assumptions for sales and use tax as part of the 2012 financial plan. The new

Page 36: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

26 April 3, 2012

methodology was reviewed with the Regional Sales and Use Tax Working Group on October 27, 2011, who determined that the methodology represented a reasonable approach for forecasting long-term growth in sales and use tax (see Section 1.3.3.2). RTD’s annual Construction Inflation Workshop was held on November 1, 2011. Results of the Construction Inflation Workshop are generally consistent with the assumptions and methodologies used and approved by DRCOG as part of last year’s APE (see Section 1.3.3.3). 41B1.3.1.1 Construction Costs and Variability Building the FasTracks Program requires a significant amount of raw materials. As such, project cost estimates fluctuate depending on the market price for project commodities. Following voter approval of the FasTracks Plan in 2004 commodity prices began an unprecedented rise. In 2008, a drop in prices was observed; however, through 2009, 2010, and 2011 commodity prices have generally continued an upward trend. Raw materials costs remain well above original 2004 project estimates. For more information on cost estimating methodologies see Appendix C. To illustrate this trend, the following figures identify prices for copper and crude oil for the past nine years. The increase in prices for both copper and crude oil from 2009 through 2011 is expected to continue. These materials are critical in the construction of the FasTracks Program and are generally representative of the commodities market. The results are summarized in XFigure 2X and XFigure 3X.

Figure 2: Historical Copper Prices

$0.00

$0.50

$1.00

$1.50

$2.00

$2.50

$3.00

$3.50

$4.00

$4.50

$5.00

2003 2004 2005 2006 2007 2008 2009 2010 2011

Copper (LB)

Page 37: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

27 April 3, 2012

Figure 3: Historical Crude Oil Barrel Prices

Since 2008, the cost for copper and crude oil has significantly increased. However, increases in raw materials have not translated to similar increases in the cost of finished goods such as running rail and reinforcing steel. As an example, the cost of running rail and reinforcing steel has remained relatively constant. In the case of running rail, the cost has fallen since 2008 and 2009. See XFigure 4X and XFigure 5X for a summary in the price of running rail and reinforcing steel, respectively.

Figure 4: Unit Costs for Running Rail (per ton)

$0.00

$20.00

$40.00

$60.00

$80.00

$100.00

$120.00

2003 2004 2005 2006 2007 2008 2009 2010 2011

NYMEX Crude Oil (Barrel)

$0.00

$200.00

$400.00

$600.00

$800.00

$1,000.00

$1,200.00

$1,400.00

$1,600.00

2003 2004 2005 2006 2007 2008 2009 2010 2011

115# Running Rail (Ton)

Page 38: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

28 April 3, 2012

Figure 5: Unit Costs for Reinforcing Steel (Cwt)

42B1.3.1.2 Sales And Use Tax Forecast Change Implementation of the FasTracks Program depends on a variety of financial assumptions and projections. Projected revenue received through sales and use tax is one critical financial assumption that is used to forecast and implement the FasTracks Program. Sales and use taxes, which are RTD’s primary local funding sources, have been affected by changing and challenging economic circumstances. Average annual sales and use tax growth from 1980 – 2002 was 6.3%. To be conservative, and based on input from DRCOG and their financial consultants, in the original 2004 FasTracks Financial Plan, RTD used a projected growth rate of 6.06%, which was below this historic average. However, as a result of the recent economic environment, sales and use tax growth declined below this historic average in 2001, 2004, 2006, and 2007, and even includes years of contraction in 2002, 2003, 2008, and 2009. Growth was above this historic average in 2010. XTable 4X shows historical sales and use tax growth for the years 1992-2011.

$0.00

$10.00

$20.00

$30.00

$40.00

$50.00

$60.00

$70.00

2003 2004 2005 2006 2007 2008 2009 2010 2011

Reinforcing Steel (Cwt)

Page 39: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

29 April 3, 2012

Table 4: Growth in Sales and Use Tax Revenues 1992 – 2011 (Dollars in Thousands)

To address the challenges of long-term sales and use tax revenue projections, RTD decided in 2011 to engage a contractor to develop sales and use tax revenue projections in 2012 and beyond. The Working Group was reconvened in 2011 to review forecasts made in 2010, and discuss the upcoming contractor procurement for future forecasts. The Leeds School of Business at the University of Colorado at Boulder was selected as the contractor. Leeds developed short-term, medium-term, and long-term sales and use tax revenue forecast models. The Sales and Use Tax Forecasting Working Group, which was originally convened in 2009 and consists of a group of state and local government economic advisors, was reconvened twice in 2011 to review progress from Leeds. The group agreed that the long-term models developed by Leeds would be used in the FasTracks 2012 Financial Plan, in the 2012 APE, and going forward. Using the methodology developed by Leeds, average annual growth rates were determined. The medium growth rate scenario of 3.39% for the period 2005-2035 per year was recommended for use in the Financial Plan. The average annual growth rate for the period 2012-2035, or the future years of the Financial Plan, is 3.89% in the medium scenario. Forecasted rates of increase vary by year, and the forecasted annual growth rates by year for the period 2005-2035 are shown in Figure 6.

Fiscal Year Tax Rate Sales and Use Tax Revenues

Percentage Growth

1992 0.6% $108,389

1993 0.6% 121,611 12.20%

1994 0.6% 134,431 10.54%

1995 0.6% 142,214 5.79%

1996 0.6% 153,807 8.15%

1997 0.6% 164,565 6.99%

1998 0.6% 179,990 9.37%

1999 0.6% 202,303 12.40%

2000 0.6% 224,182 10.81%

2001 0.6% 224,648 0.21%

2002 0.6% 213,668 (4.89%)

2003 0.6% 210,447 (1.51%)

2004 0.6% 221,276 5.15%

2005 1.0% 386,427 74.64%

2006 1.0% 399,558 3.40%

2007

1.0% 418,407 4.72%

2008

1.0% 412,824 (1.33%)

2009

1.0% 371,405 (10.03%)

2010 1.0% 397,669 7.07%

2011 1.0% 415,137 4.42%

Page 40: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

30 April 3, 2012

Figure 6: Projected Sales and Use Tax Growth 2005-2035, 2011 vs. 2012 APE

1.3.1.3 Management Reserve Fund 43B

In order to provide greater assurance that the Program will be able to stay on schedule if there is an additional downturn in the economy or rapid escalation in commodities or construction costs, a Management Reserve Fund has been added to the adopted FasTracks Plan. Use of the Management Reserve would be subject to approval of the RTD Board of Directors, and no corridor or project would be allowed to access the Management Reserve until all project contingency has been expended. Potential uses for the Management Reserve include covering capital cost increases caused by unexpected construction cost escalation, changes in regulatory requirements (i.e., new FTA rules) or unknown site conditions, or to meet debt service requirements in the event of a decrease in sales and use tax receipts. The current $30 million FasTracks Contingency Reserve will be reclassified into the Management Reserve in 2013 and the balance in the Management Reserve will increase by approximately $30 million per year until it reaches 3% of the projected remaining cost of the FasTracks Program as of January 2012, or $166 million. This reserve will be maintained for four years after completion of the opening day program. At that time, RTD will work with stakeholders to develop a recommendation concerning the use of any funds remaining after the entire program is complete. Options for use of remaining funds could include fulfilling outstanding commitments allowed by the original FasTracks Plan or paying down the existing bonds so that the additional 0.4% sales and use tax would be able to sunset earlier than anticipated.

Page 41: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

31 April 3, 2012

1.3.1.4 Railroad Negotiations Through 2010 RTD and the railroads had entered into agreements for the Gold Line, East Rail Line, West Rail Line, North Metro Rail Line (Boulder Industrial Lead) and Northwest Rail – Phase 1. RTD closed on the UPRR ROW transaction for the Gold Line in January 2012. With this transaction, RTD will have the entire railroad ROW needed to build the Gold Line. RTD closed on the Burnham Yard Lead section of UPRR ROW for the West Rail Line on April 26, 2011. RTD acquired an additional easement from the BNSF for the West Rail Line in 2011. Both BNSF and UPRR relocated the Burnham Yard Lead this year and ROW was made available for the West Rail Line to tie-into the existing system. Tie-in was completed August 2011. The East Rail Line ROW closing will occur when UPRR infrastructure has been relocated to its final location (estimated closing 2014). RTD entered into an agreement with BNSF in early 2011 to study the required operating easements necessary for a shared track commuter rail on the Northwest Rail Line – Phase 2 and Phase 3, from Westminster Station to Downtown Longmont Station. Engineering work and operational estimates were completed late in 2011. Primary activities between the railroads and RTD have been to ensure the compliance to the agreements. Both railroads are currently reviewing RTD’s plans for capital improvements on the Gold Line, East Rail Line and the Northwest Rail – Phase 1. Construction has started for the UPRR relocation work, including fiber optic relocation and several utility modifications on the East Line. UPRR and BNSF have also completed their at grade road crossing improvements on the Gold Line (Tennyson and Lowell). 2012 should see the design approval for all RTD capital improvements by BNSF and UPRR for the Gold Line, East Rail Line and Northwest Rail – Phase 1. Construction is also anticipated on all three of the lines throughout 2012. 44B1.3.1.5 Grant Opportunities In 2011, RTD continued to apply for Federal grant dollars. As a result, RTD received $7.02 million in Federal competitive grants in 2011. RTD has applied across a wide spectrum of federal grant programs with diverse and competitive projects for both the FasTracks Program as well as RTD’s base system. All of the $7.02 million in grant funding received came from the Department of Transportation (DOT) Bus and Bus Facilities (State of Good Repair) Program, which will be used to fund repairs at the Civic Center Station and to help complete an Asset Management Database. RTD will make permanent repairs to several large springs underneath the bus way at the Civic Center Station as well as repair leaks in the roof. Throughout 2011, RTD also pursued Federal grant funding for several other projects. These applications, however, were not selected for grant funding. These applications included the following projects:

Nine Mile Park-n-Ride Repairs

Intercity Bus Replacement

Deferred Maintenance Projects

Page 42: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

32 April 3, 2012

Downtown Denver Circulator Project

16th Street Mall Reconstruction

16th Street Mall Shuttle Replacement

Eagle Project Energy Conservation Initiative

I-225 Rail Line between Parker Road and Iliff

14th/Walnut Bus Transfer Facility Enhancements

Senior Resource Center

Special Transit In addition to the $7.02 million, on August 31, 2011, U.S. Transportation Secretary Ray LaHood and FTA Administrator Peter Rogoff officially awarded RTD a $1.03 billion FFGA to help build two FasTracks rail lines, the East Rail Line and the Gold Line. 1.3.2 24BResults of the 2012 APE Since 2008, there have been significant fluctuations in commodity prices as a result of the current recession; however, these prices still remain higher than original forecasts. At the same time there have been significant additional decreases in projected sales and use tax revenues. 45B1.3.2.1 Major Changes from 2011 APE The 2012 FasTracks Program opening day capital costs in XFigure 7X (expressed in YOE dollars) are approximately $600 million (8.8%) higher than 2011 forecasts. This increase is primarily the result of extending the opening day Program schedule out to 2022 and proposing a FasTracks Plan amendment that will include extending Northwest Rail to Church Ranch and building out a BRT system in the Northwest Corridor Area (see Sections 1.4.7 and 1.4.9). The 2012 costs are approximately $2.7 billion (57%) higher than those in the original FasTracks Financial Plan presented to the voters in April 2004. The 2012 capital cost estimates were updated based on most current information on alignments, railroad issues, stations, facilities and planning/engineering progress. The key factors for the increase in capital costs since 2004 include: (1) material, labor and ROW escalation which increased at a rate higher than the 2003-2008 Consumer Price Index (CPI) that was used as the FasTracks escalation factor; (2) changes with respect to stations and Park-n-Rides; (3) changes resulting from negotiations with the railroads for the Program; and (4) scope clarifications/changes. The 2012 Financial Plan, as with the 2011 Financial Plan, assumes a 0.4% sales and use tax increase commencing in 2013 following voter approval in 2012. This results in a delay in the projected completion of the FasTracks Program to 2022.

Page 43: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

33 April 3, 2012

Figure 7: FasTracks Program Capital Cost Summary (YOE$)

Economic conditions have also required a reevaluation of how RTD projects future sales and use tax revenue growth. In 2011, RTD contracted with the Business Research Division of CU Leeds School of Business to develop a new methodology for forecasting sales and use tax growth. This new methodology resulted in a very slight decrease in annual growth rate assumptions for sales and use tax as part of the 2012 financial plan. Using this new methodology, the sales and use tax forecast for 2005 – 2035 is currently $7.992 billion. Previous 2004 forecasts projected $13.7 billion over the same time period. This represents a 42% reduction from the 2004 forecast. RTD reconvened a working group of local government economists to review the new methodology for forecasting sales and use tax growth on October 27, 2011 (see Section 1.3.3.2). The group determined that the methodology represented a reasonable approach for forecasting long-term growth in sales and use tax. See Figure 8 for a summary of tax revenue forecasts.

Figure 8: Historical Perspective of Tax Revenue Forecasts 2005-2035

RTD also reconvened a group with experience on both national transit construction projects and local public works projects to review its construction escalation assumptions

Page 44: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

34 April 3, 2012

on November 1, 2011 (see Section 1.3.3.3). Results of the Construction Inflation Workshop are generally consistent with the assumptions and methodologies used and approved by DRCOG as part of last year’s Annual Report on FasTracks. 47B1.3.2.2 Financial Plan Alternatives Considered

RTD continues to work closely with elected officials, local governments, corridor stakeholders, and the public to identify how to move the FasTracks Program forward. On December 6, 2011, staff presented the RTD Board of Directors with updated cost estimates for the Northwest Rail Line (based on inputs from BNSF). The cost estimate for the Northwest Rail Line represents a significant increase compared to costs assumed last year, and staff indicated at that time that completion of the Northwest Rail Line would likely have to be delayed to 2023 – 2025 to match RTD’s cash flow constraints. Since December 6, 2011, RTD stakeholders have raised concerns about the increased costs and schedule risk for the Northwest Rail Line. In response to stakeholder concerns, staff identified the following options for RTD Board consideration:

Option 1 (Base Case): Delay completion of Northwest Rail to 2024 to match RTD’s cash flow requirements;

Option 2: Delay completion of Northwest Rail to 2024 to match RTD’s cash flow requirements, but accelerate select capital projects and increase funding for bus service for Northwest Rail and US 36 BRT Service Areas. This option would require a six-month delay for the remaining partially-funded projects;

Option 3: Remove Northwest Rail from the FasTracks plan and commit remaining Northwest Rail project funds, capped at $894.6 million (YOE), for expanded/enhanced BRT in the Northwest Corridor area to be completed by 2020.

RTD staff presented the technical and financial results of Option 1 to the RTD Board of Directors on January 17, 2012. On January 24, 2012 the RTD Board directed staff to conduct additional technical and financial analyses on Options 2 and 3 prior to the RTD Board of Directors finalizing their decision on the 2012 APE. The Board also directed staff to continue working with regional stakeholders and elected officials to determine a path forward. From January – March of 2012, RTD met with elected officials, local governments, line stakeholders and the public to discuss these options. RTD also held two half-day charrettes with line stakeholders to further refine these options, and held a public education meeting on February 22, 2012 with national subject matter experts in commuter rail transit and BRT to explain how either of these transit modes could operate in the Northwest Corridor Area. As determined through staff discussions, and formal feedback received from RTD’s stakeholders, there was no consensus around any of the three options proposed. Therefore, RTD relied heavily upon the following FasTracks Guiding Principles, presented to the RTD Board of Directors in 2010, to develop the staff recommendation to the RTD Board of Directors:

Ensure every step contributes to the full vision

Focus money available to the greatest good

Spend public money wisely

Maximize outside funding before going to taxpayers

Page 45: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

35 April 3, 2012

Deliver key investments in all corridors. Subsequently, based on these Guiding Principles, and discussions with RTD’s stakeholders, on March 20, 2012, RTD staff proposed a hybrid option that includes the following:

No schedule or cost impacts for any other partially-funded corridor projects

Completing the Northwest Rail Line incrementally from Church Ranch to Longmont as rail becomes more cost effective and funding becomes available from the original 0.4% FasTracks sales tax

A combination of an incremental segment of diesel-multiple unit (DMU) commuter rail in the Northwest Corridor area during the period of 2020 - 2022 and a BRT system by 2020 that will provide comprehensive, cost effective mobility improvements for the region

o Including funding for an EA or EIS that will be required prior to finalizing an exact BRT alignment, etc.

o When and if the RTD Board of Directors selects this option, RTD would begin working immediately with stakeholders to develop a formal Request for Proposals (RFP) for the remaining environmental work that would be advertised in early 2013 if there is a successful sales and use tax election in November of 2012

Extension of the Northwest Commuter Rail Line from Westminster Station to the Church Ranch Station to provide bi-directional peak service for commuters connecting into/from DUS. Extending rail to Church Ranch would provide approximately 12 of the 41 miles of commuter rail for the Northwest Corridor (30% of the complete corridor length), and will allow RTD to continue moving forward with our ultimate vision of building rail to Longmont.

o Based on conservative estimates of cost, it is currently anticipated that funding would be available to complete the rail extension during the period of 2020 – 2022

RTD’s remaining financial commitment to Phase 2 of the US 36 BRT project, $82 million (YOE), would be available in 2014 and 2015

In addition to the $82 million (YOE) remaining for the US 36 BRT project, $894.6 million (YOE) would be provided to expand the BRT system in the Northwest Corridor area by 2020. This financial cap (including prior expenditures) was based on last year’s APE and was chosen to reflect the level of capital funding available to complete the FasTracks program by 2020

Consistent BRT service levels, as identified through the SB 208 process and subsequent environmental analyses, until five years after opening of the full BRT system – after which time all routes would be required to meet service standards. RTD will also increase service during or after this five year period, according to service criteria, if ridership levels increase to such levels where they dictate more BRT service in the corridor.

RTD staff chose this hybrid option over the other options considered for two main reasons:

Page 46: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

36 April 3, 2012

This approach allows the entirety of the Northwest Rail Line to remain in the FasTracks plan, completing the Northwest Rail Line incrementally from Church Ranch to Longmont as rail becomes more cost effective and funding becomes available from the original 0.4% FasTracks sales tax

As RTD incrementally builds the Northwest Rail Line, BRT will provide a cost effective solution to effectively address mobility needs sooner in the Northwest Corridor Area.

48B1.3.2.3 RTD Board Financial Plan Selection On March 27, 2012 the RTD Board of Directors adopted a Financial Plan that incorporated the staff recommendation for the Northwest Rail Corridor area. This Financial Plan assumes an election in 2012 with an additional 0.4% sales and use tax increase commencing in January 2013. The Financial Plan also assumes opening day for the FasTracks Program by 2022. The remainder of the Northwest Rail Line from Church Ranch Station to Downtown Longmont Station will be completed in the timeframe between 2026-2032 pending future action by the RTD Board of Directors and as funding becomes available from the original 0.4% sales and use tax. 1.3.3 25BCollaborative Efforts In 2011, key stakeholders and RTD staff evaluated the FasTracks Program’s financial assumptions and provided recommendations on the Program’s direction. This was accomplished through the Metro Mayors Task Force, Sales and Use Tax Forecast Working Group, the FasTracks Construction Review Council, and the FasTracks Construction Inflation Workshop. 49B1.3.3.1 Metro Mayors FasTracks Task Force The Metro Mayors FasTracks Task Force was convened in 2008 to explore options for delivering the full FasTracks Program. The Task Force is comprised of elected officials, RTD Board members, and key stakeholders from the business and environmental communities. The Task Force has continued to meet as needed to promote stakeholder input to the FasTracks Program. In 2011, RTD staff worked extensively with the Task Force to validate RTD’s financial assumptions through third-party reviews of capital costs, sales and use tax forecasts, construction inflation, etc. During this time, staff also worked with the Metro Mayors and other FasTracks stakeholders to gain consensus on the amount of the sales tax to pursue and the timing of a future election. As part of these efforts, the mayors requested that RTD and the Metro Mayors Caucus (MMC) develop and agree upon an “Accountability Agreement” that addresses the following two broad issues:

Clear definition of how the proposed tax increase will be used;

Specific ballot language to be used for a future election. On March 1, 2011, RTD staff presented detailed financial information to the RTD Board of Directors that outlined the financial constraints RTD faces in developing an Accountability Agreement that provides the stakeholders the assurances they need, while maintaining enough financial flexibility to complete the program on time, and to successfully issue new bonds.

Page 47: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

37 April 3, 2012

In this presentation, RTD agreed that a reasonable financial construct would be for the proceeds of debt payable from the new sales and use tax to be used only for the remaining FasTracks lines and projects and that the new sales and use tax can fully sunset. However, to provide adequate coverage to both issue the new debt and to be able to operate and maintain the remaining lines, revenues from the new tax must be combined with existing available revenues for debt coverage purposes. RTD presented the results of two analyses to illustrate why these constraints exist:

If revenues from the new sales and use tax cannot be combined with existing revenues, RTD could not issue bonds in the timeframe needed to complete the remaining lines and projects on schedule at a 2.00x Additional Bonds Test (ABT). RTD could issue debt at less than 2.00x ABT, however, this could result in:

o Lower credit rating o Higher interest rates o Reduced pool of potential investors o More risk for completing the program if revenues do not meet

expectations.

If revenues can be blended together for debt coverage purposes, but cannot be used to fund operations and maintenance on the new lines, the existing sales and use tax would not be able to fund operation and maintenance on all the remaining lines and projects until after 2035.

On March 8, 2011, RTD met with members of the Metro Mayors Task Force to discuss these challenges in more detail. During this meeting, the mayor’s asked whether all of the revenue from the new sales and use tax is assumed to be used on the remaining partially-funded lines. RTD responded that under all financial plan analyses conducted by RTD staff, no proceeds of the new 0.4% sales and use tax are applied to the construction of the currently funded lines. The proceeds of the new 0.4% sales and use tax are assumed to be used only to (a) finance construction of the new lines, and (b) operate and maintain both the new and the currently funded lines. While it is assumed that the new 0.4% sales and use tax is available to operate and maintain both the new and currently funded lines, the existing 0.4% sales and use tax is sufficient to operate and maintain all of the currently funded lines. However, as stated above, to maintain the program schedule, RTD needs to combine the receipts of the existing and new sales and use tax for debt service coverage purposes and to provide for operation and maintenance of all lines. Combining the existing and new sales and use taxes on this basis provides benefits to the remaining partially-funded lines by:

Achieving a higher credit rating on the bonds issued to finance construction of the new lines than can be achieved absent the existing sales and use taxes. This results in reduced interest expense and increased cash flow to ensure the remaining lines get built on time.

Providing more financial flexibility to structure debt service to accommodate the increased operations and maintenance expense associated with the completion of all lines.

Page 48: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

38 April 3, 2012

Providing for an earlier sunset of the new sales and use tax due to the improved cash flow, resulting in enhanced debt service coverage and an increased cash flow cushion.

On March 8, 2011, the MMC formally provided the following list of recommendations to the RTD Board of Directors (several of which relate to the proposed Accountability Agreement):

The MMC will negotiate an agreement with the RTD Board of Directors to formally commit to building each line’s specific list of line improvements as described in the FasTracks Plan and if possible such a commitment should be embedded in ballot language for any tax increase.

RTD should accelerate construction wherever this is possible and will result in savings.

All possible revenue strategies must be employed to close the funding gap and shorten the life of any new tax.

The MMC supports an election for a sales tax increase of 0.4% to take effect as soon as feasible and with enforceable sunset provisions, provided that the SB 208 review of the 2011 APE by DRCOG confirms the cost and revenue estimates that RTD has used to ensure that 0.4% is adequate to complete the entire system by 2020.

All revenues raised by a voter approved sales tax increase must be used exclusively for construction and operation of the improvements described in the FasTracks plan and not for any other purpose.

Should a sales tax increase of less than 0.4% be approved, necessitating additional funding sources to complete the FasTracks plan, the MMC will join RTD in lobbying Congress and FTA for New Starts and Small Starts funding on qualifying lines.

The Metro Mayors FasTracks Task Force should remain active to provide ongoing input into RTD decision making regarding FasTracks funding and line construction priorities.

In addition, discussions with the Task Force indicated a continuing interest from select members to establish a clear firewall to ensure that the new revenues are only applied to the FasTracks partially-funded lines. The Metro Mayors FasTracks Taskforce has indicated understanding and support for how RTD intends to use a proposed tax increase to fund the remaining portions of the FasTracks Program. Conversations concerning the Accountability Agreement and specific ballot language are on-going and are anticipated to continue into 2012. 50B1.3.3.2 Sales and Use Tax Forecast Working Group To address the challenges of making longer-term sales and use tax revenue projections, RTD convened a group of state and local government economic and financial advisors in 2009 to review RTD’s current forecasting methodology; evaluate potential forecasting methodologies; and obtain consensus on a future forecasting method. Information gained from the work sessions was used to forecast sales and use tax revenue for input into RTD’s 2010 and 2011 Financial Plans. Based on discussions throughout the sessions regarding source data and model input, a final recommendation was made that the group reconvene on an annual basis, change model parameters as

Page 49: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

39 April 3, 2012

dictated by changing economic conditions, and revise sales and use tax revenue forecasts based on updated forecasts for the independent variables. During 2010, RTD staff updated sales and use tax revenue projections quarterly and updated input data as they became available. RTD decided in 2010 to engage a contractor to develop sales and use tax revenue projections in 2011 and beyond. The Leeds School of Business at the University of Colorado at Boulder was selected as the contractor. Leeds developed short-term, medium-term, and long-term sales and use tax revenue forecast models. The Working Group reconvened twice in 2011 to review progress from Leeds. The group agreed that the long-term models developed by Leeds will be used in the FasTracks Financial Plan, for the 2012 APE, and going forward. 51B1.3.3.3 FasTracks Construction Inflation Workshop A FasTracks Construction Inflation Workshop was held on November 1, 2011, to discuss and evaluate the construction cost inflation rate that is applied to FasTracks capital cost estimates. Participants included RTD staff, senior transit consultants, representatives from local government and regional agencies, and Ken Simonson, Chief Economist for The Association of General Contractors. In the workshop, RTD’s current cost-estimating methodology and current method for analyzing, forecasting, and estimating construction cost inflation and sales tax revenue were presented. Construction Inflation Workshop participants generally agreed that RTD’s current methodology (and forecast values) for estimating Construction Cost Inflation is conservative, considering the current market trends, expert forecasts, and averages for other similar transit agencies. The following recommendations from the Construction Inflation Workshop were incorporated into the 2012 APE:

Materials cost escalation of 5.1% per year from 2012-2020

Escalation assumptions for other cost elements such as operations and maintenance, labor, fuel, and others were updated based on the most current CPI forecasts from Moody’s Economy.com

1.3.3.4 FasTracks Construction Review Council In 2011, RTD instituted a FasTracks Construction Review Council (FCRC). The Council consists of 15 members from the construction industry including representatives of major construction firms, engineering companies, small and disadvantaged businesses, labor organizations and public agencies that perform major construction projects. Specifically, RTD worked with the Colorado Contractors Association (CCA), the American Consulting Engineers Council (ACEC), the Hispanic Contractors of Colorado (HCC), the Conference of Minority Transportation Organization (COMTO), the International Brotherhood of Electrical Workers (IBEW), Front Range Executive Service Corps (FRESC), CDOT, CCD and the City of Aurora to provide members. Key RTD staff from the Capital Programs Department participates in the meetings. RTD reviews its construction program, planned contracts, assumptions and approaches with the Council. It has proven to be an excellent process to gain outside feedback and input from experienced construction professionals with a diverse background. The FCRC meetings are held quarterly and are open to the public.

Page 50: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

40 April 3, 2012

Page left intentionally blank

Page 51: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

41 April 3, 2012

Page left intentionally blank

Page 52: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

42 April 3, 2012

1.4 12BStatus of FasTracks Lines The descriptions below provide new information on each of the FasTracks elements that have changed since the 2010 Annual Report to DRCOG on FasTracks. Included is a summary of the project, notable milestones or events that have occurred, description of the current status, and current cost estimates (in YOE dollars). 1.4.1 26BCentral Rail Extension The Central Rail Extension begins at the 30th and Downing Station and extends north approximately 0.8 miles to the 38th/Blake Station. This station will serve as the terminus for the Central Rail, as well as a transfer hub to the East Line. The alignment will operate within a traffic lane in each direction along Downing Street from 30th and Downing to 36th. The alignment will continue along 36th from Downing to the new proposed end of line station at 38th Avenue and Blake Street, shared with the East Line (Figure 9X). The alignment does not connect with the North Metro Rail Line. The Final Environmental Evaluation (EE) was completed in February 2010. The recommended alternative for the Central Rail Extension is in-street rail transit with single light rail vehicles operating as a streetcar operation. This is preferred because it does not require acquisition of buildings, minimizes community impacts, and can be built within the proposed budget. There are two stations recommended along Downing Street: 33rd and Downing, and 35th and Downing. As a result of $305 million being available due to the lower-than-expected Eagle Project bid price, $0.5 million is being used on this Extension for additional technical analysis including the potential use of a streetcar vehicle as well as the feasibility of other alignments. This is due in large part to CCD changing the traffic signal timing in downtown Denver in May 2011. The downtown traffic signals went from a 75-second cycle length to a 90-second cycle length. This reduced the number of trains that could operate through the downtown light rail loop. As such, the operating plan proposed in the EE is no longer feasible. The 2011 cost estimate for the Central Rail was $70.6 million YOE$. The current cost estimate is $60.3 million YOE$. Central Rail Extension Summary Length: 0.8 miles (approximate) Mode: Light Rail Costs: The $60.3 million-2012, YOE$; $70.6 million-2011, YOE$ Method of Delivery: Design-Bid-Build Status: Additional study underway Tasks Remaining: Final Design and Construction; Operation and Maintenance Scheduled Completion: 2017 Notable Changes:

None. Additional FasTracks improvements were programmed for the Central Rail. These upgrades include 4-car platforms from I-25/Broadway to 18th/Stout & 18th/California, substation capacity improvements, and downtown traffic signal software. All of these projects were completed in 2010.

Page 53: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

43 April 3, 2012

Figure 9: Central Rail Extension

Page 54: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

44 April 3, 2012

1.4.2 27BDenver Union Station Denver Union Station is a multimodal transportation hub that will include light rail transit, commuter rail transit, bus connections, as well as pedestrian and bicycle access to downtown businesses and the mall shuttle system (Figure 10X). It will serve as the catalyst for redeveloping and preserving Denver's historic Union Station and 19.5 acres of surrounding land. Union Station will be transformed into a transportation hub serving the needs of residents, tourists, and commuters (XFigure 11X).

Figure 10: Denver Union Station Transit Improvements In 2008, the City and County of Denver (CCD) created the Denver Union Station Project Authority (DUSPA), which is a board made up of the following stakeholders: RTD, CCD, the Colorado Department of Transportation (CDOT), DRCOG, and the Union Station Neighborhood Company (USNC) (the master developer). The group is responsible for receipt and distribution of project funding and for contracting with the Design-Builder for all transit infrastructure. In February 2010, DUSPA issued a full Notice to Proceed (NTP) to the Design-Builder. In July 2010, the DUS project became a fully funded project with the loan approval for $155 million under the Railroad Rehabilitation & Improvement Financing (RRIF) Program. At the same time, DUSPA received a Federal Transportation Infrastructure Finance and Innovation Act of 1998 (TIFIA) Loan for $146.6 million. Other funding sources include, in net contributed dollars, CDOT’s SB1 grants ($17.4 million) and Projects of National and Regional Significance (PNRS) grants ($45.3 million), DRCOG Transportation Improvement Program (TIP) grant ($2.5 million), various FTA grants ($9.5 million), proceeds of land sales and other non-FasTracks local funds ($39.5 million), and RTD’s local FasTracks funds. The loan closings guarantee the completion of the public transportation infrastructure of the redevelopment including a 22-bay

Page 55: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

45 April 3, 2012

underground bus facility, a light rail station for current and future light rail routes, a commuter rail station that will serve Amtrak and the East, Gold, North Metro, and Northwest Rail commuter rail lines, extension of the 16th Street Mall Shuttle, streets and public plazas to integrate transit service with adjacent neighborhoods.

Figure 11: Denver Union Station

Now that full construction is underway, the schedule has been set with key milestones, which will meet the RTD’s commitments to hand over the project area to the Eagle Project Concessionaire to install systems in May 2014. The light rail station was opened August 15, 2011 and approximately 50% of the bus facility has been constructed. The bus facility is generally considered the critical path with the facility opening to operations in 2014. Excavation of the commuter rail platforms is underway and it is expected that commuter rail operations will commence in 2016 (operated by the Eagle Project Concessionaire). Substantial completion of all transit facilities design packages were completed by the end of 2011. The 2011 cost estimate for RTD funding at DUS was $283.3 million YOE$. The current cost estimate is $287.3 million YOE$.

Page 56: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

46 April 3, 2012

Denver Union Station Summary Length: NA Mode: NA RTD Costs: $287.3 million-2012, YOE$; $283.3 million-2011, YOE$ Method of Delivery: Design-Build; Eagle Project (systems) Status: In construction Tasks Remaining: Bus Facility and Commuter Rail Construction; Operation and Maintenance Scheduled Completion: 2014 (for civil construction of bus facility and commuter rail); 2014 (for systems components required for project turnover to Eagle Project Concessionaire); 2016 (overall systems completion) Notable Changes:

None.

Page 57: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

47 April 3, 2012

Page left intentionally blank

Page 58: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

48 April 3, 2012

1.4.3 28BEagle Project The Eagle Project consists of the East Line, the Gold Line, and a portion of the Northwest Rail Line (Phase 1) (from DUS to the Westminster Station) as well as the CRMF, the commuter rail cars, and other ancillary improvements (Figure 12X). Northwest Rail – Phase 1 will be built as part of the Eagle Project but will be funded locally (i.e. not using Federal funding). In September 2009, RTD issued the Eagle Project RFP to the pre-qualified teams. Final proposals were received in April 2010. In July 2010, RTD entered into a Concession Agreement with DTP to design, build, finance, operate, and maintain the Eagle Project. The Eagle Project is being advanced in two phases. Phase 1 comprises the design, construction and operation of the East Rail Line, the CRMF, and purchase of the commuter rail vehicles, as well as final design of the entire project. Phase 2 comprises the balance of the work including the Gold Line and Northwest Rail – Phase 1. The NTP issued in August 2010 authorized Phase 1. The Phase 2 NTP was issued after the receipt of the FFGA, in August 2011. Funding for the Eagle Project comes from three sources. Approximately $1.03 billion is secured from the FTA in the form of an FFGA. RTD is also utilizing funds from the FasTracks Program to pay for ROW, project budget contingencies, and design-build oversight. The remainder of the project funding will include debt and equity from the Concessionaire to assist in funding the capital improvements. During the operations and maintenance phase, RTD will make service payments to the Concessionaire. Payment amounts will consider how the Concessionaire performs against the performance metrics defined in the Concession Agreement. The metrics are designed to provide strong financial incentives to maintain quality service. DTP originally proposed a single track section on the East Rail Line from I-70 to the north. Due to cooperative efforts between RTD and CCD, a portion of the double track from the EIS will be reinstated. This section of double track will be added back into the project, in part, to facilitate the addition of stations in the future. Additionally, CCD will add two grade separations to the project (at Green Valley Ranch and Tower Road). These grade separations will be locally funded (to be paid for jointly by RTD and CCD). These changes in scope will occur once an IGA is completed between RTD and CCD (anticipated in spring of 2012). Since the project elements are being built as one project costs are increasingly difficult to separate. Eagle Project costs for all elements are provided below. Individual costs for the project elements are not broken out in subsequent sub-sections. This section includes updates for the FasTracks lines and major elements that comprise the Eagle Project. The 2011 cost estimate for RTD funding for the Eagle Project was $2,185.0 million YOE$. The current cost estimate is $2,185.0 million YOE$.

Page 59: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

49 April 3, 2012

Eagle Project Summary Length: 35.9 miles Mode: Commuter Rail/Electric Multiple Unit (EMU) RTD Costs: $2,185.0 million-2012, YOE$; $2,185.0 million-2011, YOE$ Method of Delivery: DBFOM Status: In Final Design; Major construction began in the Fall of 2011. Tasks Remaining: Complete Final Design; Construction; Operation and Maintenance Scheduled Completion: East Rail Line January 2016; Gold Line July 2016; NWES March 2016; CRMF May 2014 Notable Changes:

Sections of double track reinstated on the East Rail Line.

Figure 12: Eagle Project

Page 60: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

50 April 3, 2012

53B1.4.3.1 East Rail Line The East Rail Line is a commuter rail service utilizing electric multiple unit (EMU) vehicles from DUS to Denver International Airport (DIA). The Line serves the Denver communities of Five Points, Cole, Elyria/Swansea, Northeast Park Hill, Stapleton, Gateway, and DIA, as well as northwest Aurora. It also serves to transport passengers arriving and departing from DIA (XXFigure 13). The Final Environmental Impact Statement (FEIS) was released in September 2009 and the Record of Decision (ROD) was signed by FTA on November 6, 2009. The FTA granted an FFGA for this project on August 31, 2011. As described in Section 1.4.3, the East Rail Line will be built in the first phase of the Eagle Project. In July 2010, DTP was selected as the Concessionaire for the Eagle Project. The groundbreaking for the East Rail Line occurred in August 2010. The current DTP plan indicates that the East Rail Line will begin revenue service in January 2016. DTP originally proposed a single track section on the East Rail Line from I-70 to the north. Due to cooperative efforts between RTD and CCD, a portion of the double track from the EIS will be reinstated. This section of double track will be added back into the project, in part, to facilitate the addition of stations in the future. Additionally, CCD will add two grade separations to the project (at Green Valley Ranch and Tower Road). These grade separations will be locally funded. These changes in scope will occur once an IGA is completed between RTD and CCD (anticipated in spring of 2012) Aurora and CCD have initiated the environmental work for a grade separation over the East Rail Line and the UPRR at Peoria. RTD is working with the stakeholders to coordinate this project with the East Rail Line. The grade separation is planned to be open by/before testing begins on the East Rail Line. This grade separation will not be funded as part of the Eagle Project. Since the project elements, including the East Rail Line, are being built as one project, costs are increasingly difficult to separate. Individual costs for the project elements are not broken out. Eagle Project costs for all elements are provided in Section 1.4.3. East Rail Line Summary Length: 22.8 miles Mode: Commuter Rail/EMU Method of Delivery: DBFOM; Eagle Project Status: FEIS released September 2009; ROD signed November 2009; Construction began August 2010. Tasks Remaining: DBFOM Scheduled Completion: January 2016 Notable Changes:

Sections of double track to be reinstated pending an IGA between RTD and CCD.

Page 61: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

51 April 3, 2012

Figure 13: East Rail Line

Page 62: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

52 April 3, 2012

54B1.4.3.2 Gold Line The Gold Line is commuter rail service, utilizing EMU vehicles, from DUS to Ward Road in Wheat Ridge (Figure 14XX). The project is 11.2 miles from the DUS platform to Ward Road. The alignment from DUS to Pecos is shared with Northwest Rail Line (3.6 miles). This section will be constructed as part of the Northwest Rail - Phase 1 through the Eagle Project. There is a single track section of the Gold Line from Ralston Road to Carr Street in Arvada, a distance of approximately 1.5 miles. This single track section was designed during the Environmental Impact Statement (EIS) process to minimize environmental impacts. The FEIS was released in August 2009 and a ROD was signed by FTA in November 2009. The FTA granted an FFGA for this project on August 31, 2011. As described in Section 1.4.3, the Gold Line will be built in the second phase of the Eagle Project. In July 2010, DTP was selected as the Concessionaire for the Eagle Project. RTD broke ground on this project in August 2011. The current DTP plan indicates that the Gold Line is scheduled for completion by July 2016. Since the project elements, including the Gold Line, are being built as one project, costs are increasingly difficult to separate. Individual costs for the project elements are not broken out. Eagle Project costs for all elements are provided in Section 1.4.3. Gold Line Summary Length: 11.2 miles (3.6 miles from DUS to Pecos are shared with Northwest Rail – Phase 1) Mode: Commuter Rail/EMU Method of Delivery: DBFOM; Eagle Project Status: FEIS released August 2009; ROD signed November 2009; Construction began August 2011 Tasks Remaining: DBFOM Scheduled Completion: July 2016 Notable Changes:

None.

Page 63: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

53 April 3, 2012

Figure 14: Gold Line

Page 64: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

54 April 3, 2012

55B1.4.3.3 Northwest Rail Line – Phase 1 The Northwest Rail Line – Phase 1 is the 5.5 mile portion of the 41-mile Northwest Rail commuter rail project that will extend to Downtown Longmont. This segment (Phase 1) originates at DUS and extends to the Westminster Station (XFigure 15X) and is shared with the Gold Line between DUS and the Pecos Station (3.6 miles). This phase underwent environmental study in both the Northwest Rail EE, which was released to the public in June 2010, as well as the Gold Line FEIS. The Northwest Rail project will be built in three phases. Phase 1 will be built as part of the Eagle Project, but will be funded locally. Construction began on Phase 1 in August 2011. Phase 2 of the Northwest Rail project builds DMU from DUS to the Church Ranch Station and will also be funded locally. Refer to Section 1.4.7 for information on Phase 2 of the Northwest Rail Line project. Phase 3 of the project will be built incrementally from Church Ranch Station to Downtown Longmont Station as funding becomes available from the original 0.4% FasTracks sales tax. Since the Eagle Project elements, including the Northwest Rail Line – Phase 1, are being built as one project, costs are increasingly difficult to separate. Individual costs for the project elements are not broken out. Eagle Project costs for all elements are provided in Section 1.4.3. Northwest Rail Line – Phase 1 Summary Length: 5.5 miles (3.6 miles from DUS to Pecos are shared with the Gold Line) Mode: Commuter Rail/EMU Method of Delivery: DBFOM; Eagle Project Status: EE completed; Construction began August 2011 Tasks Remaining: DBFOM Scheduled Completion: March 2016 Notable Changes:

South Westminster/71st Avenue Station was renamed to Westminster Station.

Page 65: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

55 April 3, 2012

Figure 15: Northwest Rail Line

Page 66: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

56 April 3, 2012

56B1.4.3.4 Commuter Rail Maintenance Facility The Fox North site (48th Ave and Fox St) has been selected as the preferred location for the CRMF. The Fox North site encompasses approximately 31 acres and is generally bounded by 48th Avenue on the south, 54th Avenue on the north, Fox Street on the east, and the BNSF Trailer On Freight Car (TOFC) Yard and UPRR North Yard on the west. The CRMF will include facilities to repair, maintain, clean, fuel, and store the FasTracks commuter rail vehicles and maintain the commuter rail network. The facility will include a maintenance shop, commuter rail control center employee facilities, administrative offices, employee parking facilities, and a building and laydown area for maintenance-of-way (MOW) equipment and materials. The CRMF site includes space for offices, storage of equipment, storage for spare parts, and parking. The MOW building is no longer needed as its function was incorporated into the CRMF and yard. XFigure 16X displays the proposed location. The CRMF is part of the Eagle Project, which is separated into two phases. The East Rail Line and CRMF will be built in the first phase. The Concessionaire, DTP, plans to open the East Rail Line by January 2016. To achieve opening in this timeframe, DTP has scheduled completion of the CRMF by December 2014. Delivery of the first commuter rail vehicles is planned for November 2013 and will likely be stored in the CRMF yard. Since the project elements, including the CRMF, are being built as one project, costs are increasingly difficult to separate. Individual costs for the project elements are not broken out. Eagle Project costs for all elements are provided in Section 1.4.3. Commuter Rail Facility Summary Length: NA Mode: Commuter Rail Method of Delivery: DBFOM (part of Eagle Project) Status: SEA completed April 2009. Tasks Remaining: Design and Construction; Operation and Maintenance Scheduled Completion: May 2014 Notable Changes:

None.

Page 67: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

57 April 3, 2012

Figure 16: CRMF Site Location

CRMFBuilding

Page 68: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

58 April 3, 2012

1.4.4 29BI-225 Rail Line The FasTracks I-225 Rail Line project will extend RTD’s light rail 10.5 miles within the I-225 corridor, while not precluding a future eight-lane highway widening within the CDOT ROW. The light rail extension will begin at the existing Nine Mile Station, serve the Aurora City Center, the Anschutz/Fitzsimons Medical Campus and provide a transfer to the planned East Rail Line commuter rail at a shared station near the intersection of Peoria Street and Smith Road ( XFigure 17X). The Draft EE was released in July 2009 for agency and public review. The Final EE was adopted by the RTD Board in October 2009. The I-225 Rail Line has been divided into two segments. Segment 1 is the segment from the end of line immediately north of the Nine Mile Station to the Iliff Station. Segment 2, the remainder of the Line, will continue north from the Iliff Station to the Peoria/Smith Station, which is shared with the East Rail Line. The design of Segment 1 was completed to 100% design in January 2011. In 2010, $305 million became available due to the lower-than-expected Eagle Project bid price. Of that $305 million, $90 million will be used to pay for completion of Segment 1. The current program delivery plan for Segment 1 of the I-225 Rail Line is to partner with CDOT to construct the structural and civil elements of the 1.5 mile light rail extension from Nine Mile Station to the Iliff Station and expand the highway from Parker Road to Mississippi Ave. A separate project will be procured through RTD including construction of the transit elements (track, electrical systems, the station and the Park-n-Ride). In order to meet the federal environmental clearance requirement for the combined project, RTD conducted an Environmental Assessment (EA) exclusively for the Segment 1 of the I-225 Rail Line. On August 20, 2011, the I-225 Light Rail minimal operable segment EA completed the public review and comment period. Responses to comments were summarized in the report documenting the Finding of No Significant Impact (FONSI), which was signed by the FTA on September 22, 2011. The I-225 FasTracks team prepared an application for a TIGER III discretionary grant for Segment 1 of the I-225 rail line. The application, which was submitted on October 31, 2011, emphasized the multimodal project and partnership with CDOT for the widening of the I-225 highway and the extension of the light rail from Nine Mile Station to Iliff Station. The application was ultimately unsuccessful. The 2011 cost estimate was $750.8 million YOE$. The current cost estimate is $748.5 million YOE$.

Page 69: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

59 April 3, 2012

I-225 Rail Line Summary Length: 10.5 miles Mode: Light Rail Costs: $748.5 million-2012, YOE$; $750.8 million-2011, YOE$ Method of Delivery: Design-Bid-Build for Segment 1 and Design-Build for Segment 2 Status: EE and PE completed Tasks Remaining: Design and Construction; Operation and Maintenance Scheduled Completion: Segment 1 completion scheduled for 2014; entire project will be completed in 2020. Notable Changes:

None.

Figure 17: I-225 Rail Line

Page 70: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

60 April 3, 2012

1.4.5 30BMaintenance Facilities This section includes facilities for light rail and bus. The CRMF is being built as part of the Eagle Project and is included in Section 1.4.3.4. The light rail maintenance is accommodated by an expansion of the existing Elati and Mariposa Facilities. As noted in previous Annual Reports, evaluation of the need for an additional bus maintenance facility determined that it is not needed until after 2035. 57B1.4.5.1 Light Rail Maintenance Facility The Elati Maintenance Facility opened in 2004 with the capacity to maintain and store 100 vehicles. In 2006, RTD completed the construction of additional storage tracks and catenary systems to accommodate the West Rail Line fleet at the Elati facility. The change of the Gold Line technology from light rail to commuter rail resulted in a decrease in light rail fleet requirements. It was determined that an expanded Elati facility could accommodate the entire FasTracks light rail fleet. RTD made the decision to expand the Elati facility eliminating the need for a second light rail maintenance facility. Construction for the expansion of the Elati facility started in May 2009 following RTD’s Board approval of the construction contract. The work was phased to accommodate the ongoing operational requirements of the facility. The Elati facility work was completed in 2011. XFigure 18X below shows the site plan for the Elati Light Rail Maintenance Facility Expansion. The scope of work for the extension of the light rail maintenance facility includes a new vehicle wash bay, additional parts storage capacity, additional power supply into and for the system elements for the added light rail vehicles to be stored at the site, modifications to the drainage system, added tracks, yard lighting, walks, and access drive improvements. Associated with the expansion of the Elati Facility is the expansion of the Mariposa Facility where RTD conducts heavy maintenance on the light rail vehicles. This Program doubles the maintenance and operational light rail capacity. The construction Program for the light rail facility improvements (including Elati and Mariposa) was completed in 2011.

Figure 18: Light Rail Maintenance Facility

The 2011 cost estimate for the light rail maintenance facility was $20.9 million YOE$. The final cost estimate is $18.2 million YOE$.

LEGEND:

Improvement Boundary

Railroad Track

Surface Improvements/

Drainage

Page 71: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

61 April 3, 2012

Light Rail Maintenance Facility Summary Length: NA Mode: Light Rail Costs: $18.2 million-2012, YOE$; $20.9 million-2011, YOE$ Method of Delivery: Design-Bid-Build Status: Design and construction complete Tasks Remaining: Operation and Maintenance Scheduled Completion: Elati Facility completed in 2010; Mariposa Facility completed in 2011 Notable Changes:

None.

Page 72: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

62 April 3, 2012

1.4.6 31BNorth Metro Rail Line The North Metro Rail Line begins at DUS and extends north 18.4 miles to SH 7/162nd Avenue traversing the jurisdictions of Denver, Commerce City, Adams County, Northglenn, and Thornton. In 2008, as a result of the UPRR negotiations, the alignment was revised in order to avoid the 36th Street Yard owned by UPRR. The alignment now follows the BNSF rail alignment to near 54th Avenue, then further north it joins the UPRR Boulder Branch ROW (XFigure 19X). The five areas of the alignment that are double tracked (passing track) are: from DUS to 38th Street; from south of 72nd Avenue to just north of I-76; from north of Thornton Parkway to just north of 104th Avenue; from south of 124th Avenue to south of York Street; and from SH 7 to the end of line, approximately 162nd Avenue. The FEIS was released for public review in January 2011. The ROD was signed on April 22, 2011. As a result of $305 million being available due to the lower-than-expected Eagle Project bid price, $90 million of that amount is being used on this rail line to complete the segment from DUS to the National Western Stock Show Station. Construction on this segment is scheduled to begin in 2014. The 2011 cost estimate for North Line was $904.3 million YOE$. The current cost is $978.7 million YOE$. North Metro Rail Line Summary Length: 18.4 miles Mode: Commuter Rail/EMU Costs: $978.7 million-2012, YOE$; $904.3 million-2011, YOE$ Method of Delivery: Design-Bid-Build Status: ROD signed April 2011 Tasks Remaining: Final Design; Construction; Operation and Maintenance Scheduled Completion: Segment 1 (DUS to National Western Stock Show Station) 2017; Entire project 2020. Notable Changes:

Contract changed from design-build to design-bid-build.

Segment 1 completion date changed from 2015 to 2017 due to changing from design-build to design-bid-build contract methodology and ROW requirements.

Page 73: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

63 April 3, 2012

Figure 19: North Metro Rail Line

Page 74: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

64 April 3, 2012

1.4.7 32BNorthwest Rail Line – Phase 2 The Northwest Rail Line is a 41-mile commuter rail line that originates at DUS and extends northwest to Downtown Longmont. Jurisdictions served include northwest Denver, Adams County, Westminster, Broomfield, Louisville, City of Boulder, Boulder County, and Longmont (Figure 20X). Phase 2 will operate along a six-mile commuter rail segment, using diesel multiple unit (DMU) rail vehicles, between Westminster Station and the Church Ranch Station. The Northwest Rail project will be built in three phases. Phase 1 will be the 5.5-mile, locally-funded, portion of the alignment from DUS to the Westminster Station and will be built as part of the Eagle Project (see Section1.4.3.3). Construction began on Phase 1 in August 2011. Phase 2 of the Northwest Rail project extends the alignment from the Phase 1 end-of-line at Westminster Station an additional six miles to the Church Ranch Station and will also be funded locally. Phase 3 of the project will be built incrementally from Church Ranch Station to Downtown Longmont Station as funding becomes available from the original 0.4% FasTracks sales and use tax (see Section 1.4.8). Included in Phase 2 is a DMU maintenance facility to be used exclusively by the Northwest Rail Line at a location to-be-determined. Construction of Phase 2 is scheduled for completion in 2022. The Final EE was adopted by the RTD Board of Directors in May 2010 and released to the public in June 2010. As a result of a lower-than-expected Eagle Project bid price, $305 million was available for other lines. Of that amount $17 million will be used on the Northwest Rail project to complete the Downtown Longmont Station, which will be constructed early and open in 2015. Longmont Station’s design is currently on hold, pending the completion of the Longmont Station Area Master Plan (STAMP). The STAMP is expected to be completed in early 2012. The completed STAMP will influence the final design and layout of the station Park-n-Ride. The current cost estimate is $396.0 million YOE$. Northwest Rail Line – Phase 2 Summary Length: 6 miles (3.6 miles from DUS to Pecos are shared with the Gold Line) Mode: Commuter Rail/DMU Costs: $396.0 million-2012 YOE$ Method of Delivery: Line infrastructure to be built by BNSF Railway. Design-Bid-Build will be used to construct the Park-n-Ride. Status: EE and PE completed Tasks Remaining: Final Design and Construction; Operation and Maintenance Scheduled Completion: 2022 Notable Changes:

Phase 2 was previously the segment from Westminster Station to Downtown Longmont Station. Based on an RTD Board action on March 27, 2012, the Northwest Rail Line is now being constructed in three phases and Phase 2 terminates at the Church Ranch Station.

13B

1.4.8 Northwest Rail Line – Phase 3 The remainder of the Northwest Rail Line, 29 miles of DMU commuter rail, will be completed from Church Ranch Station to Downtown Longmont Station as funding becomes available from the original 0.4% sales and use tax. Phase 3 may be built in

Page 75: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

65 April 3, 2012

segments or all at once depending on funding. Funding is anticipated to be available to initiate construction and begin revenue service during the period of 2026 – 2032.

Phase 3 has been addressed environmentally under the Northwest Rail EE which was adopted by the RTD Board of Directors in May 2010 and released to the public in June 2010.

Phase 3 includes upgrading four Park-n-Rides to include commuter rail station platforms and associated elements: Flatiron, Louisville, Gunbarrel, Downtown Longmont. Park-n-Ride improvements for these stations will be built with the Northwest BRT (see Section 1.4.9). Phase 3 also includes construction of parking and station platforms at the station near the Boulder Transit Village, as well as adding up to 575 spaces at Westminster Station (350 spaces are to be built with Phase 1).

Figure 20: Northwest Rail Line

Page 76: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

66 April 3, 2012

1.4.9 Northwest BRT Northwest BRT, together with US 36 BRT, will serve the Northwest Corridor area from DUS to Longmont and will consist of up to 80 miles of BRT. It is anticipated that BRT service will be provided between DUS and Longmont along US 36 and Hwy 119. Additionally, BRT will serve Louisville and other existing park-n-rides along US 287. The exact BRT alignment and other project elements will be finalized subsequent to environmental clearance and final design. Northwest BRT will build parking and/or upgrade Park-n-Rides to include BRT station elements at the following locations: Flatiron (existing), Louisville, Gunbarrel, Lafayette (existing but to be relocated), Hwy 119/Niwot (existing), US 287/Niwot (existing). New BRT vehicles will be purchased and a new BRT maintenance facility will be constructed along the corridor at a location to-be-determined. This project is anticipated to be completed in 2020. This project will be capped at a total cost, including prior expenditures, not to exceed $894.6 million YOE$. Northwest BRT Summary Length: up to 80 miles Mode: BRT Costs: $894.6 million-2012 YOE$ Method of Delivery: TBD Status: Environmental process pending Tasks Remaining: Completion of environmental process; design and construction; operation and maintenance Scheduled Completion: 2020 Notable Changes:

This is a new element of the FasTracks Program that will be included in a Plan Amendment and referenced in the 2012 ballot language. If the election is not successful, then this element will not be included in the Program moving forward.

Page 77: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

67 April 3, 2012

Figure 21: Northwest BRT

Page 78: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

68 April 3, 2012

1.4.10 33BSoutheast Rail Extension The Southeast Rail Extension is 2.3 miles in length and extends from the existing Lincoln Station south to RidgeGate Parkway. There are three proposed stations: Sky Ridge, Lone Tree City Center and a new end-of-line station immediately south of RidgeGate Parkway ( XFigure 22X). The Final EE was adopted by the RTD Board in February 2010, which finalized the environmental phase of the project. The project team is currently evaluating options for moving forward with advanced design. As a result of $305 million being available due to the lower-than-expected Eagle Project bid price, $9 million of that amount will be used on this Line to complete final design and undertake a federal environmental process. In 2011, the RTD Board of Directors approved a financial plan that assumed federal funding in the form of a Small Starts grant for the Southeast Rail Extension project. To be eligible for Small Starts funding, an Alternatives Analysis (AA)/EA was initiated in October 2011. The AA is scheduled for completion in early 2012 and the EA in late 2012. The 2011 cost estimate for the Southeast Rail Extension was $209.1 million YOE$. The current cost is $209.1 million YOE$. Southeast Rail Extension Summary Length: 2.3 miles Mode: Light Rail Costs: $209.1 million-2012, YOE$; $209.1 million-2011, YOE$ Method of Delivery: Design-Build Status: Basic Engineering (BE) and Final EE complete; AA and EA underway Tasks Remaining: Design and Construction; Operation and Maintenance Scheduled Completion: 2017 Notable Changes:

None. Additional FasTracks improvements were programmed for the Southeast Line. These upgrades include the addition of 520 parking spaces at Lincoln Station and upgrading all Southeast Rail Extension stations to accommodate 4-car trains. Bicycle and pedestrian improvements at Arapahoe and Belleview are also included. All of these elements have been completed.

Page 79: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

69 April 3, 2012

Figure 22: Southeast Line

Page 80: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

70 April 3, 2012

1.4.11 34BSouthwest Rail Extension The Southwest Rail Extension is 2.5 miles in length and extends from the existing Mineral Station south and east to C-470/Lucent Boulevard, where a new end-of-line station is planned (XFigure 23X). The Final EE was adopted by the RTD Board in February 2010, which finalized the environmental phase of the project. The project team is currently evaluating options for moving forward with advanced design. As a result of $305 million being available due to the lower-than-expected Eagle Project bid price, $8.5 million of that amount will be used on this Line to relocate UPRR track. Relocation of the UPRR track addresses a key schedule risk area for the project, and will facilitate efficient project completion once the remainder of the funding is identified. The 2011 cost estimate for the Southwest Rail Extension was $185.1 million YOE$. The current cost estimate is $182.2 million YOE$. Southwest Rail Extension Summary Length: 2.5 miles Mode: Light Rail Costs: $182.2 million-2012, YOE$; $185.1 million-2011, YOE$ Method of Delivery: Design-Bid-Build Status: BE and Final EE complete Tasks Remaining: Design and Construction; Operation and Maintenance Scheduled Completion: 2020 Notable Changes:

None. Additional FasTracks improvements are programmed for the Southwest Line. These upgrades include additional parking at the Englewood Station, coordination with the City of Englewood for a potential Bates Station, and improving existing stations so they can accommodate 4-car trains. Four-car train platform improvements at existing stations have been completed.

Page 81: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

71 April 3, 2012

Figure 23: Southwest Rail Line

Page 82: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

72 April 3, 2012

Page left intentionally blank

Page 83: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

73 April 3, 2012

1.4.12 35BUS 36 Bus Rapid Transit (BRT) Line - Phase 1 The US 36 BRT – Phase 1 project provides for modifications and/or relocations to the existing Park-n-Ride lots along US 36, improved pedestrian access to the bus stations, and the construction of bus loading areas. Phase I projects include Park-n-Ride improvements and/or relocations at the Church Ranch, Broomfield, and McCaslin Park-n-Rides. These three FasTracks-funded projects include the location of bus loading areas adjacent to US 36 on/off ramps. Completion of these projects, together with the existing Westminster Center and Flatiron Crossing Park-n-Rides, mark the completion of Phase 1 projects. In 2010, RTD completed the remaining elements of the US 36 BRT – Phase 1 project. The Broomfield Park-n-Ride, which was relocated from Wadsworth Boulevard to 116th Avenue and US 36, adjacent to the 1stBank Center, and bus-only slip ramps opened in May 2010. The final cost to complete the project was $19.0 million YOE$, which was $2.3 million less than the budget of $21.3 million. This remaining $2.3 million was transferred to the US 36 BRT – Phase 2 project. US 36 BRT – Phase 1 Summary Length: Not Applicable Mode: BRT Costs: $19.0 million-2012, YOE$; $21.3 million-2011, YOE$; Method of Delivery: Design-Bid-Build Status: Construction complete Tasks Remaining: None Scheduled Completion: Completed Spring 2010 Notable Changes:

None. 1.4.13 36BUS 36 Bus Rapid Transit (BRT) Line - Phase 2 The US 36 BRT – Phase 2 project includes FasTracks funding for RTD’s proportional share of building 18 miles of managed lanes (BRT/high-occupancy toll/high-occupancy vehicle) on US 36. As part of the FasTracks Plan, RTD has a set financial commitment to this project. Additional funding from other sources will be required to complete the entire project. The lanes will extend from the existing managed lanes in the vicinity of Pecos to the Table Mesa Park-n-Ride. RTD will provide BRT service from DUS to the Table Mesa Park-n-Ride. Construction of a pedestrian bridge at the Table Mesa Park-n-Ride and a new eastbound bus ramp pull-out on the south side of US 36 are a separately-funded part of the project improvements (XFigure 24X). The US 36 Project FEIS, jointly funded by CDOT and RTD, which includes the elements of Phase 2, was signed on October 20, 2009. A ROD for the EIS prepared jointly by RTD with CDOT was signed in December 2009. The Table Mesa pedestrian bridge design is completed and construction began in late 2011. Additionally, construction of bus-only queue jumps/ramp improvements at four locations (Sheridan Boulevard, Church Ranch Boulevard, Flatiron/96th Street and McCaslin Boulevard) has received Categorical Exclusion (CE) approval and final design is proceeding. Construction of a portion of these improvements at Church Ranch and

Page 84: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

74 April 3, 2012

McCaslin is expected to begin in early 2012. Additional construction at Sheridan, Church Ranch and Flatiron/96th Street will be included as part of the managed lanes project (see below for more details). Funding for the Table Mesa Park-n-Ride and a new eastbound bus ramp pull-out on the south side of US 36 includes Senate Bill 1 funds in the amount of $3.5 million for construction of the pedestrian bridge. RTD will provide the match for these funds from the US 36 - Phase 2 BRT budget. In addition, $7.6-million of the RTD apportionment of ARRA funds will be used for the US 36 queue jumps that are a component of the US 36 - Phase 2 BRT project. As a result of $305 million being available due to the lower-than-expected Eagle Project bid price, $90 million of that amount is committed to complete the managed lanes on US 36 to Interlocken. This, and an additional $30 million previously allocated to this project, is being used to partner with CDOT to extend the managed lanes. CDOT was awarded a TIFIA loan of $54 million in 2011. Together with RTD’s contribution, the TIFIA loan will provide the funding to construct the managed lanes past Interlocken/96th Street to 88th Street in a contract that was awarded on February 29, 2012. Construction of the Managed Lanes Project is expected to begin in July 2012. The 2011 cost estimate was $218.1 million YOE$. The current cost estimate is $220.4 million YOE$. US 36 BRT – Phase 2 Summary Length: 18 miles Mode: BRT Costs: $220.4 million-2012, YOE$; $218.1 million-2011, YOE$ Method of Delivery: TBD Status: Environmental process complete/ROD signed in December 2009. Tasks: Final Design and Construction (to be implemented in phases); Operation and Maintenance Scheduled Completion: Managed lanes to Interlocken/96th Street expected to be completed in 2015. Segment to Table Mesa to be determined based on availability of funding from CDOT. Notable Changes:

None.

Page 85: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

75 April 3, 2012

*The managed lanes will extend from the existing managed lanes in the vicinity of Pecos to the Table Mesa Park-n-Ride. RTD will provide BRT service from DUS to the Table Mesa Park-n-Ride.

Figure 24: US 36 BRT Line

Page 86: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

76 April 3, 2012

1.4.14 West Rail Line The West Rail Line extends from DUS to the Jefferson County Government Center including the existing CPV spur, and 12.1 miles of new light rail. The areas served include the Auraria Campus, west Denver, Lakewood, Lakewood Industrial Park, Denver Federal Center, Red Rocks Community College, and the Jefferson County Government Center in the City of Golden (XFigure 25X). This line is furthest along in the development and construction process, with completion of civil construction scheduled for June 2012, systems construction scheduled for December 2012, and Wadsworth and Sheridan parking structure construction scheduled for May 2013. The entire line is scheduled to open in May 2013. Construction has been on-going for three years and six months (since early construction and utility work began in April 2008). As of October 2011, a total of 15 bridges, flyovers, and tunnels have been substantially completed. Overall construction progress is at 84%. Overall wall and underground work is 98% complete. Trackwork is 79% complete and stations are 70% complete, with all stations in varying states of completion, including the newly relocated Auraria West Station which opened to the public in October 2011. Systems construction is 70% complete and contracts were recently awarded for the design and construction of the final two parking structures (at Wadsworth and Sheridan). The alignment is double-tracked between Auraria West Station in downtown Denver and the Federal Center Station. There will be single track from the Federal Center Station to the Jefferson County Government Center-Golden Station. West Rail Line Summary Length: 12.1 miles Mode: Light Rail Costs: $709.8 million-2012 YOE$ (Federal Project Only); $709.8 million-2011, YOE$ Method of Delivery: Construction Manager/General Contractor (CM/GC) Status: Under construction Tasks Remaining: Construction; Operation and Maintenance Scheduled Completion: December 2012 (construction complete); May 2013 (opening) Notable Changes:

None.

Page 87: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

77 April 3, 2012

Figure 25: West Rail Line

Page 88: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

78 April 3, 2012

2.0 2BSUMMARY OF FINANCIAL PLAN

The current $7.4 billion cost is a revision from the originally estimated $4.7 billion (2004), and previously estimated $6.8 billion (2011) costs following updates to material, ROW, financing, and labor cost estimates. The ability to implement the FasTracks Plan depends on a variety of financial assumptions and projections which have been developed using the best available current estimates of costs, reasonably anticipated federal funding based on current federal law and regulations, and revenues from other sources including RTD sales tax and fare collections. Over the anticipated remaining build-out, specific cost items, federal and other contributions, and RTD revenues may vary from this Financial Plan. Based on the extensive analysis behind the financial assumptions used, RTD expects to deliver the major transit corridors and related improvements within the time frames set forth. RTD cannot guarantee that each separate assumption will be met, and expects that over a multi-year time-frame, certain adjustments and modifications will be required. On an annual basis, through the APE process, RTD updates the FasTracks Financial Plan with new revenue and cost projections, reflecting ever-changing economic conditions. Each APE update to the Financial Plan projects capital, financing and operating costs for each of the lines and projects in YOE dollars, and reflects the currently adopted FasTracks implementation schedule for each of the lines. The current 2012 APE Financial Plan extends to the year 2035, and covers both the FasTracks Program and the base public transit system and services provided by RTD. During the 2008 APE, RTD identified a funding gap for the FasTracks Program as a result of rapidly escalating costs for commodities and materials on the world market, combined with the economic slowdown and the corresponding downward impact on current and forecast sales and use tax revenues. Over the past four years, RTD has worked closely with elected officials, local governments, corridor stakeholders and the public to identify how to move the FasTracks Program forward, addressing these challenges. During this period, there have been significant fluctuations in commodity prices as a result of the current recession; however, these prices still remain higher than original forecasts. Additionally, there have been concurrent significant additional decreases in projected sales and use tax revenues. On March 27, 2012, the RTD Board of Directors adopted a financial plan scenario for the 2012 FasTracks APE that assumes the passage of 0.4% sales and use tax increase commencing in January 2013 and a FasTracks Plan amendment that will include extending the Northwest Rail Line to Church Ranch and building out a BRT system in the Northwest Corridor Area (see Sections 1.4.7 and 1.4.9). This scenario results in an opening day for the FasTracks Program of 2022 (excluding Phase 3 of the Northwest Rail Line), assuming current cost escalation and revenue growth forecasts. The remainder of the Northwest Rail Line (Phase 3), 29 miles of DMU commuter rail, will be completed from Church Ranch Station to Downtown Longmont Station, as funding becomes available from the original 0.4% sales and use tax. Funding is anticipated to be available during the period of 2026 – 2032. If a tax increase initiative is not approved by the voters, a revised, updated Financial Plan would be adopted by the Board at that time, recognizing the new opportunities and constraints that would exist.

Page 89: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

79 April 3, 2012

The FasTracks Program is currently financed in part through a 0.4% regional sales and use tax approved by voters in November of 2004. If the initiative is placed on the ballot in 2012 and it passes, the total transit tax rate for RTD will increase to 1.4% (i.e., 0.6% for the base system, 0.8% for FasTracks). The Plan also includes $1.3 billion in Federal New Start Grant funding in conjunction with $277.6 million in other Federal grant funding. Contributions from local jurisdictions benefiting from transit in an amount equal to 2.5% of eligible project costs are expected to yield 2.0% of total program costs or $144.5 million system-wide. In addition to Federal grants, the Plan includes a loan from the US DOT under the TIFIA program in the amount of $280.0 million. Table 5 summarizes the sources of funds expected to pay for the Plan’s $7.4 billion of project expenditures: Table 5: FasTracks Estimated Capital Sources of Funds Through 2022 (Millions of

Dollars)

3.0 3BIMPLEMENTATION SCHEDULE The following section identifies the current schedule for FasTracks, discusses modifications since the 2011 Financial Plan and provides a status of the environmental processes for all the projects.

3.1 14BModifications to Line/Project Schedules RTD has revised the FasTracks Plan schedule submitted to DRCOG in this 2011 Annual Report. The updated FasTracks schedule is shown in XFigure 25X and XFigure 26X. Figure 25 contrasts the current schedule with the original 2004 FasTracks schedule and Figure 26 contrasts the current schedule with the schedule in the 2010 Annual Report. Based on the 2012 Financial Plan, the current implementation schedule assumes a tax vote would occur in November 2012. This has affected the timing of when final design and construction contracts can be awarded as well as when other activities, like purchasing ROW, could occur. The impact of the financial gap on the overall FasTracks Program and the assumption of a vote in 2012 are reflected in the schedule delays for

Revenue Bond Proceeds $2,551.8 34.6%

COPs Proceeds $251.5 3.4%

TIFIA Loan Proceeds $280.0 3.8%

Denver Union Station Note Proceeds $168.0 2.3%

Pay-as-you-go Capital $1,857.0 25.2%

Federal New Start Grants $1,339.1 18.1%

Federal Small Start Grants $75.0 1.0%

Other Federal Grants $202.6 2.7%

Local Match Funding $144.5 2.0%

Other Local Funding¹ $26.1 0.4%

Public-Private Partnerships $487.8 6.6%

Total FasTracks Program Funding $7,383.4 100.0%

Page 90: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

80 April 3, 2012

some elements of the FasTracks Program. FasTracks projects with delays are summarized below. Light Rail Projects:

The Southeast Line Extension project schedule is now projected for completion in mid 2017. Final design is scheduled to occur concurrently with an application for federal funding.

Commuter Rail Projects:

The North Metro overall schedule is consistent with last year’s schedule. However due to changing from design/build to design-bid-build contract methodology and ROW requirements, segment 1 (DUS to the National Western Stock Show) has moved out to mid 2017.

The Northwest Rail Line now has a rail component (Westminster Station to Church Ranch Station), and an overall BRT component. The overall schedule has been adjusted to match this revised scope. The BRT portion of the Northwest corridor is currently scheduled to be complete in 2020, with the rail portion to Church Ranch Station completed in 2022. The remainder of the Northwest Rail Line (Phase 3) will be completed in the 2026-2032 time period once funding is available from the original 0.4% sales and use tax.

Page 91: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

81 April 3, 2012

Figure 26: FasTracks SB 208 Original Schedule (2004) & 2012 Financial Plan Schedule

Corridor

Denver Union Station2004 SB208 Construction

P Design / Construction

Commuter Rail - EAGLE ProjectsEast Corridor

2004 SB208 P Construction / Test

P Design / Construction / Test

Gold Line

2004 SB208 Construction / Test

EIS / AE

P Design / Construction / Test

Northwest Rail - Pecos to Westminster (Phase 1)

2004 SB208 Construction / Test

Current Design / Construction / Test (Pecos to Westminster - Phase 1)

Commuter Rail Maintenance Facility

P Design / Construction

Light Rail ProjectsWest Corridor

2004 SB208 Construction / Test

Construction / Test

I-225 Corridor

2004 SB208 P Construction / Test

Fnl Dsn-Nine Mile to Iliff P Construction / Test - Nine Mile to Iliff

Southeast Corridor Extension

2004 SB208 P Final Design

Final Design

EA/PE New Starts / NEPA P

Southwest Corridor Extension

2004 SB208 EA/PE Final Design

EA/PE

Light Rail Maintenance Facility

Design - Elati P

Design - Mariposa P

Central Corridor Extension

2004 SB208 Final Design

Current

Commuter Rail ProjectsNorth Metro Corridor

2004 SB208 Final Design Construction / Test

EIS / AE P - DUS to Stockshow

Northwest Rail - Westminster to Church Ranch (Phase 2)

2004 SB208 Construction / Test

P Design - Longmont Station

Bus ProjectsUS 36 BRT - Phase1

2004 SB208 Station and HOV Lane Construction - BRT2

Current

US 36 BRT - Phase 2

2004 SB208 Station and HOV Lane Construction - BRT2

Current RTD Funding Available

Corridor

BRT1

EE/PE

P

PDesign-DUS to Stockshow Construction / Test - DUS to Stockshow

P Constr - Longmont Sta

Final Design

2020

2020

Design / Construction / Test - Stockshow to EOL P - Stockshow to EOL

2019

2019

Design / Construction / Test - Iliff to EOL

20172016

CR

Current

Current

Fnl Dsn - RR Relo P

P

Construction / Test

Current

Construction / Test

Final Design

P - Iliff to EOL

P Final Dsn Construction / Test

Construction / Test

Constr - RR Relo

P

Current

Final Design

2010

P

2018

P

P

Current

Current

2007 2008

P

EE / PE

Final Design

Final Design

P

Design and Construction

2005

BRT1

P

Final Design

P

2011 20122007

EIS/PE Final Design

EIS/PE

Construction - Mariposa

2005 2006

ROW

2009

PEIS/PE Final Design P

2009

EIS/PE

ROW

P

EIS/PE

ROW

Construction - Elati

2006 2012 2013 2014 20152010 2011

Current

EIS

Current

EIS/PE

P

EA/PE

EIS/PE

Final Design

EIS / AE

Current

Final Design

ROW

EIS/PE

EIS/PE

Current

Current

EE

P

ROW

EIS/PE

P

P

P

2017

ROW

P

Final Design

2008

CR

P

P

2018

ROW-Prep-FD-BD

P

P

Final Design

20162014 2015

P

Construction / Test

Construction / Test

2013

LRT

EIS/PE

P

P

P

P

EIS/PE ROW P

EA/PEP

2021 2022

2021 2022

Final Design P

P

P

P

LRT

P Construction / Test (Westminster to Church Ranch - Phase 2)

Design / Construction / Test - BRT

Final Design - to Church Ranch P

P

Page 92: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

82 April 3, 2012

Page left intentionally blank

Page 93: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

83 April 3, 2012

Figure 27: FasTracks SB 208 2010 Report Schedule & 2012 Financial Plan Schedule

Corridor

Denver Union Station

P Design / Construction

P Design / Construction

Commuter Rail - EAGLE ProjectsEast Corridor

P Design / Construction / Test

P Design / Construction / Test

Gold LineEIS / AE

P Design / Construction / Test

EIS / AE

P Design / Construction / Test

Northwest Rail - Pecos to Westminster (Phase 1)2010 SB208 Design / Construction / Test (Pecos to Westminster - Phase 1)

Current Design / Construction / Test (Pecos to Westminster - Phase 1)

Commuter Rail Maintenance Facility

P Design / Construction

P Design / Construction

Light Rail ProjectsWest Corridor

Construction / Test

Construction / Test

I-225 CorridorFnl Dsn-Nine Mile to Iliff Construction / Test - Nine Mile to Iliff

Fnl Dsn-Nine Mile to Iliff P Construction / Test - Nine Mile to Iliff

Southeast Corridor Extension

Final Design

EA/PE New Starts / NEPA P

Final Design

EA/PE New Starts / NEPA P

Southwest Corridor Extension

EA/PE

EA/PE

Light Rail Maintenance FacilityDesign - Elati P Construction - Elati

Design - Mariposa P Construction - Mariposa

Design - Elati P

Design - Mariposa P

Central Corridor Extension2010 SB208

Current

Commuter Rail ProjectsNorth Metro Corridor

EIS / AE P - DUS to Stockshow

EIS / AE P - DUS to Stockshow

Northwest Rail - Westminster to Church Ranch (Phase 2) P P

Final Design - Longmont Station P BNSF - Guideway Design / Construction / Test

P Design - Longmont Station

Bus ProjectsUS 36 BRT - Phase1

2010 SB208

Current

US 36 BRT - Phase 22010 SB208 RTD Funding Available

Current RTD Funding Available

Corridor

Constr - Longmont Sta

Construction / Test

P - Stockshow to EOL

2019

Design-DUS to Stockshow

PFinal Dsn Construction / Test

2019

Design / Construction / Test - Iliff to EOL

20172016

Construction / Test

P Construction / Test - DUS to Stockshow

Construction / Test

RTD Station Fnl Dsn RTD Station Construction / Test

2020

2020

Design / Construction / Test - Stockshow to EOL

Constr - RR Relo

P

Current

CurrentFnl Dsn - RR Relo P

2010

2018

P

Current

Current

Current

Construction / Test

Final Design

P - Stockshow to EOL Design / Construction / Test - Stockshow to EOL

2005

P

2009 2013

P

2005 2006 2009

P

P

2011 20122007

Construction - Mariposa

Final Design

Construction - Elati

2006

EE EE/PE

EE/PE

20122007 2008

EE / PE

Design and Construction

2010 SB208

2010 SB208

2014 20152010 2011

Current

EIS/PE

EE / PE

2010 SB208

Fnl Dsn - RR Relo

Current

CurrentEE

P

2010 SB208

EIS

Current

2018

P

Constr - RR Relo

P

P

P

20172008 20162014 20152013

EA/PE

Final Design

CR

EIS/PE

EIS / AE

2010 SB208

P

P - Iliff to EOL

Final Design - to Church Ranch P

P

P

P Final Dsn

P

2021 2022

2021 2022

Design / Construction / Test - Iliff to EOL

Design / Construction / Test - DUS to Stockshow

CR

P Construction / Test

P

P - Iliff to EOL

LRTCurrent

Current

2010 SB208 P

EIS/PE

Final Design

2010 SB208EIS/PE

LRT

2010 SB208EIS / AE

2010 SB208 P

Construction / Test (Westminster to Church Ranch - Phase 2)

Design / Construction / Test - BRT

2010 SB208EIS

Constr - Longmont Sta

Design and Construction

2010 SB208P EA/PE P

Page 94: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

84 April 3, 2012

Page left intentionally blank

Page 95: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

85 April 3, 2012

3.2 15BStatus of Environmental Process In 2011, the North Metro EIS, was completed and the ROD was received on April 22, 2011. Proactive coordination with reviewing agencies such as FTA and Environmental Protection Agency (EPA), including preparation of an anticipated review schedule for all FasTracks Program documents, has helped to expedite the completion of environmental processes. In order to be eligible for federal funding, additional environmental studies were undertaken in 2011 for the I-225 Rail Line and for the Southeast Rail Extension. The I-225 EA was completed in September 2011 and the Southeast Rail Extension AA/EA was initiated in October 2011. The progress and status of the environmental documentation for each of the FasTracks projects is discussed below. Central Rail Extension The Draft EE was released in December 2009 and the Final EE was completed in February 2010. The recommended alternative for the Central Rail Extension is in-street rail transit with single light rail vehicles operating as a streetcar operation. Denver Union Station In 2006, a master developer, USNC, was selected and in March 2006, the DEIS was issued. In 2008, the Denver City Council created the DUSPA, which is the primary financing entity for the DUS project and will be the contracting entity for the construction contracts. The FEIS was released in August 2008 and a ROD was issued on October 17, 2008. Construction has started on this project. East Rail Line The DEIS was released in January 2009 and the FEIS was released in September 2009. The ROD from FTA was obtained on November 6, 2009 signifying the completion of the environmental process for the line. Construction has started on this project. Gold Line The DEIS was released on July 18, 2008 and the FEIS was released on August 21, 2009. A ROD from FTA was obtained on November 2, 2009 signifying the completion of the environmental process for the line. Construction has started on this project. I-225 Rail Line The I-225 Rail Line EE was initiated in August 2007. In July 2009, the Draft EE was released for public and agency comment. The RTD Board of Directors adopted the Final EE in October 2009. In February 2011, an EA for the I-225 Minimum Operable Segment (MOS) from the current end-of-line station at Nine Mile to the proposed new end-of-line station at Iliff was initiated. This EA was necessary to permit use of Congestion Mitigation and Air Quality Improvement (CMAQ) Program funds for the Iliff Station. The EA also provides the environmental clearance necessary for eligibility for other federal funding opportunities that might become available. The EA was completed and a Finding of No Significant Impact (FONSI) obtained on September 22, 2011. Maintenance Facilities Light Rail Maintenance Facility This project consists of the expansion of the existing Elati Facility and the Mariposa Facility. Because these are being expanded within the existing footprint, an environmental process was

Page 96: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

86 April 3, 2012

not required. Both were included in the Southeast Rail FEIS. The construction program for the light rail facility improvements (including Elati and Mariposa) was completed in the second quarter of 2011. Commuter Rail Maintenance Facility The environmental process for the CRMF was a SEA to the Gold Line, North Metro and East Rail Line EISs. This document was released for public review on April 15, 2009. The Gold Line and East Rail Line RODs, which were received in November 2009, provided the environmental clearance for the CRMF. North Metro The North Metro environmental process was initiated in August 2006. The DEIS was released in November 2009. The FEIS was released in January 2011, and the ROD was signed in April 2011. Northwest Rail The Final EE was adopted by the RTD Board of Directors in May 2010 and released to the public in June 2010. The EE addresses all phases of the Northwest Rail project. Northwest BRT The Northwest BRT project will be cleared environmentally either through and EA or EIS, which would begin in the first quarter of 2013 and be complete by the second quarter of 2016. Southeast Rail Extension The Southeast Rail Extension EE was initiated in July 2008. The Draft EE was released in November 2009 and the RTD Board of Directors adopted the Final EE in February 2010. A CE for portions of the alignment that will utilize CDOT ROW will also be necessary. The CE will be timed so that it is completed prior to the projected construction start date. Beginning in October 2011, an AA/EA for the Southeast Rail Extension was begun and scoping meetings were held in November 2011. The AA is scheduled for completion in the first quarter 2012 and the EA will be completed in late 2012. It is necessary to complete an environmental process, such as an EA, in order for the Southeast Rail Extension to be eligible for Federal funding. Southwest Line Extension The Southwest Line EE was initiated in July 2008. The Draft EE was released in November 2009 and the RTD Board of Directors adopted the Final EE in February 2010. A CE for portions of the alignment that will utilize CDOT ROW will also be necessary. The CE will be timed so that it is completed prior to the projected construction start date. US 36 BRT – Phase 1 All necessary environmental clearances have been obtained and this project is completed. US 36 BRT – Phase 2 The DEIS for US 36 BRT was released in August 2007 and the FEIS was released in October 2009. A ROD was obtained in December 2009 signifying the completion of the environmental work for this line.

Page 97: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

87 April 3, 2012

West Rail Line A ROD was received for the West Rail Line project on April 19, 2004. Construction on the West Rail Line began in early 2008 and Final Design was completed in late 2008. An FFGA was received in January 2009 and a full NTP was issued in June 2009.

Page 98: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

88 April 3, 2012

4.0 4BBUS SERVICE LEVELS

Background bus service levels in the 2012 financial plan have changed due to an RTD Board of Directors initiative to ensure long-term fiscal sustainability of its services that are funded through the original 0.6% sales and use tax. In October 2011, the Board of Directors approved service reductions designed to maximize ridership in a cost-effective manner, or “right-sizing” the level of service to meet current and projected future revenue streams. This resulted in a decrease of 3.5% between 2011 and 2012 bus service hours, including fixed route, Call-n-Ride, and ADA services. RTD is committed to funding rubber tire service increases through the FasTracks Program. In 2012, the FasTracks Program is funding approximately 7% of the fixed-route rubber tire service. Without this financial commitment through FasTracks, RTD would be forced to make deeper cuts in rubber tire service to balance its budget. Future year projected service increases range between 0.7% and 1.1% from 2013 through 2022 and approximately 1.9% annually from 2023 through 2035 (Table 6).

Table 6: FasTracks Plan Bus Service Levels

5.0 BOPERATING CHARACTERISTICS Since the DRCOG approval of the FasTracks Plan in 2004, the planning horizon for the Regional Transportation Plan (RTP) has been extended to 2035 and most of the FasTracks environmental documents have individually assumed a 2035 horizon year. However, to be consistent with final federal funding applications, three lines have not changed to a 2035 planning horizon: East Rail Line, Gold Line, and West Rail Line. There have been minor changes to the transit operating characteristics, including travel times and speeds, for some of the FasTracks lines, based on changes in technology and alignment refinements. In addition, there have been more substantial changes to the Northwest corridor operating characteristics as well as the light rail operating plan. These changes are described below.

All Bus Hours (Fixed,

call-n-Ride, ADA)

% Change from Prior

Year

Actual

2006 3.78 N/A

2007 3.88 2.60%

2008 3.9 0.47%

2009 3.85 -1.19%

2010 3.86 0.27%

2011 Budget 3.88 0.50%

Programmed

2012 3.74 -3.54%

Future Planned

2017 3.94 1.06%

2023 4.15 1.90%

2035 5.22 1.94%

Total Service Hours (millions)

Year

Page 99: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

89 April 3, 2012

The FasTracks light rail operating plan has been updated due to two recent changes that impact the existing RTD light rail system. First, RTD updated the existing platforms and systems to accommodate four-car light rail trains. This was done to better accommodate the ridership demand for special events and during peak hours. Second, CCD changed the timing of the traffic signals in downtown Denver. The change in signal timing reduced the number of light rail trains per hour that can travel through the downtown Denver light rail loop. Prior to the change in signal timing, there were 24 slots per hour available for light rail trains. The change in signal timing reduced the number of slots to 20 per hour. The existing light rail operations utilize 18 of the 20 slots during the peak periods. As such, the system is operating near capacity with only two slots available for recovery time. The resultant decrease in the capacity of the light rail system to carry additional light rail trains required changes to be made to the original FasTracks operating plan. The original FasTracks operating plan included increased frequencies on three of the existing light rail lines in the future. These increased frequencies were planned to be implemented after the opening of all other FasTracks lines. The existing C and E Lines were planned to increase from 30 minute peak headways to 15 minute peak headways and the existing F Line was planned to increase from the existing 15 minute peak headway to a 10 minute peak headway. Given the reduction in the number of available light rail slots from the change in the downtown Denver signal timing, these increased frequencies cannot be accommodated. As such, the FasTracks operating plan no longer includes these frequency increases. However, the total corridor passenger capacities have not been reduced from the original FasTracks plan due to the increase in consist sizes from a combination of two- and three-car trains to a combination of three- and four-car trains. The change in the downtown Denver signal timing also requires a change in the operating plan for the Central Rail Extension. This is described in detail below. Table 7 lists the approximate peak hour capacity and maximum peak hour passenger line loads and Figure 28 displays the updated operating plan and peak hour capacities for FasTracks lines in 2035. Figure 29 shows the peak hour capacities for the US 36 and Northwest BRT lines. RTD has committed to operating at least these BRT service levels until five years after opening of the full BRT lines – after which time all BRT routes would be subject to service reductions if they are not meeting RTD service standards. RTD will increase service, according to service criteria, if ridership levels increase to such levels where they dictate more BRT service in the corridor. Service increases could occur anytime after the opening of the BRT lines if ridership criteria are met. The capacities shown in Figure 29 assumes a seated capacity of 60 passengers per bus on US 36 and 40 passengers per bus north of Boulder (SH 119, US 287, Arapahoe Rd). These capacities are subject to change based on the final BRT vehicle selected for the corridors. For BRT routes operating on freeways, the maximum capacity is assumed to be the same as the seated capacity. For arterial BRT routes, the maximum capacity is assumed to be 1.25 times the seated capacity.

Page 100: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

90 April 3, 2012

Table 7: FasTracks Rail Line Capacity and Year 2035 Maximum Line Loads

Peak Hour CapacityPeak Hour Max Line

LoadPeak Hour Capacity

Peak Hour Max Line

Load

Central 7,625 7,479 9,145 6,261

CPV 6,500 6,424 5,425 2,999

East 1 2,160 1,742 3,344 2,107

Gold 1 3,000 2,228 1,672 1,193

I-225 2,500 1,424 4,340 2,797

North Metro 1,620 1,689 3,344 2,901

Northwest - Phase 2 1,080 416 764 373

Southeast 4,375 3,225 5,270 3,138

Southwest 3,250 3,068 3,875 3,132

West 1 4,500 4,248 3,720 2,763

Corridor

Original Plan (2025) Current Plan (2035)

1. Max Load numbers for the federally funded corridors (East, Gold, West) are based on the approved 2030 travel model outputs that

were used in the final federal funding applications. The 2030 maximum loads have been extrapolated to 2035 using an 8.9% growth

rate based on regional population change between the 2030 and 2035 models. The peak hour capacities are based on these results

and are only valid for this report.

Page 101: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

91 April 3, 2012

Figure 28: Updated Rail Operating Plan and Peak Hour Capacities for FasTracks Lines in 2035

Page 102: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

92 April 3, 2012

Figure 29: BRT Peak Hour Capacities (Opening Day)

Page 103: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

93 April 3, 2012

58BCentral Rail Extension The Central Rail Extension was originally planned to be interlined with the train from I-225; however, the EE for the Central Rail Extension suggested that an operating plan with an independent line between downtown Denver and 38th/Blake Station would better match the modeled demand for this line, which is one light rail vehicle every 15-minutes during peak hours. Therefore, the plan for the Central Rail Extension was subsequently updated to operate single-car trains around the downtown loop to the 38th/Blake Station. However, CCD changed the traffic signal timing in downtown Denver in May 2011. The downtown traffic signals went from a 75-second cycle length to a 90-second cycle length. This reduced the number of trains that could operate through the downtown light rail loop. As such, the operating plan proposed in the EE is no longer feasible. RTD is in the process of completing a planning study looking at other operating plans for this line including the feasibility of changing the technology to streetcar. The operations plan included in this report assumes that a three-car D Line train will continue to serve the Welton corridor to the 30th/Downing Station every 15 minutes. The segment from 30th/Downing Station to 38th/Blake Station is tentatively planned to be a one-car light rail or streetcar vehicle operating every 15 minutes. However, this operating plan is subject to change based on the outcome of the study. In addition to looking at the feasibility of streetcar, the primary objective of the study will be to determine the best southern terminus for the extension to tie into the existing light rail system.

59BEast Rail Line The East Rail Line has always been planned as 15 minute peak and off-peak service between DUS and DIA. Denver Transit Partners is constructing and will operate the East Rail Line as part of the EAGLE Project. The East Rail Line will open in 2016 with 15 minute all day service. Two-car EMU commuter rail trains will be utilized for opening day and expanded to four-car trains when ridership demand warrants the increased capacity.

60BGold Line In the original FasTracks Plan, the Gold Line was originally planned as a light rail line with 7.5 minute peak service and 15 minute off-peak service. During the environmental planning process the technology for the Gold Line was changed to EMU commuter rail and the service was changed to 15 minute peak and off-peak headways. The Gold Line was combined with the East Rail Line as part of the Eagle Project and it is being constructed and will be operated by DTP with an opening day of 2016. Two-car commuter rail trains will meet the forecasted ridership demand for the Gold Line through 2035. 61BI-225 Rail Line The service plan for the I-225 Rail Line has been refined since the FasTracks Plan was completed. The FasTracks Plan indicated that the I-225 Rail Line would have 7.5 minute peak service and 10 minute off-peak service between Nine Mile Station and the Peoria/Smith Station. The operating plan has been refined to include the H-Line terminating at Florida Station and the Z Line serving the entire I-225 Line (originating at the RidgeGate Parkway Station on the Southeast Rail Line and terminating at the Peoria/Smith Station). The H Line headways are planned to remain at 15 minutes peak and off-peak. The Z Line is planned to open with 10 minute peak and 15 minute off-peak headways. By 2035 the Z Line peak period service will be increased to 7.5 minutes. This will result in the section between Nine Mile Station and Florida Station having better service than was originally planned. The H Line will continue to operate with a combination of three- and four-car light rail trains as it does today. The Z Line will be served by a combination of one- and two-car light rail trains.

Page 104: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

94 April 3, 2012

An extension of the H Line from Nine Mile Station to Iliff Station (Segment 1) is planned to be completed in 2014 in advance of the build-out of the full I-225 Rail Line. Segment 1 will be served with 15 minute peak and off-peak service from the H Line. The Z Line will be implemented with the completion of the full I-225 Rail Line.

62BNorth Metro Rail Line The original FasTracks Plan included 30 minute peak and 60 minute off-peak service for the North Metro Rail Line between DUS and SH 7/162nd Avenue Station. The project also included double-track to 124th Avenue with short turn trains providing 15 minute peak service and 30 minute off-peak service between DUS and 124th Avenue Station. Since originally planned, the short turn at 124th Avenue Station was eliminated and all trains were defined to operate between DUS and 162nd Avenue Station with 15 minute peak and 30 minute off-peak headways. The North Metro Rail Line will open with two-car EMU trains and expand to four-car trains as ridership warrants increased capacity. The first segment of the North Metro Rail Line from DUS to the National Western Stock Show Station is planned to be completed in 2016. The service on this segment will be 30 minute peak and off-peak headways until the entire line is completed, at which time 15 minute peak service will be introduced.

63BNorthwest Rail Line The Northwest Rail Line was included in the FasTracks Plan as a commuter rail line with 30 minute peak and off-peak service between DUS and Longmont. In addition, short turn trains would be utilized during the peak period to provide 15 minute peak service between the Boulder Transit Village and DUS. The opening day service level was planned to be 30 minute peak, 60 minute off-peak for the entire line. The Northwest Rail Line is planned to operate in a shared right-of-way with the BNSF. RTD and BNSF have begun negotiations for an operating agreement for the corridor. The completion of this rail line is now planned as a phased approach as described below.

63BNorthwest Rail Line – Phase 1 The first segment of the Northwest Rail Line between DUS and Westminster Station and has been combined with the EAGLE Project and will open in 2016 with two-car EMU commuter rail trains. Phase 1 will operate as an independent segment with 30 minute peak and 60 minute off-peak frequencies. Denver Transit Partners is building and will operate Phase 1 from 2016 until 2022 when the next Phase of the Northwest Rail Line is scheduled to be completed. Once Phase 2 is constructed this segment will switch from operating with EMU trains to DMU trains.

63BNorthwest Rail Line – Phase 2 Phase 2 of the Northwest Rail Line includes the completion of the DMU commuter rail line from DUS to Church Ranch Station. Phase 2 will operate with a minimum of 30 minute bi-direction peak period and 60 minute off-peak service. The BNSF has indicated that RTD will be able to operate a maximum of 55 trips per day in their ROW. BNSF is currently evaluating a proposal that would allow RTD to operate Phase 2 with more frequent peak period service within the 55 trip per day limit. An increase in peak period service would likely result in a reduction in the total hours of operation for the rail line.

63BNorthwest Rail Line – Phase 3 Phase 3 consists of completing the Northwest DMU commuter rail line from Church Ranch Station to Downtown Longmont Station. The original operating plan for the full rail line is described above. However, RTD has begun negotiations with BNSF for operations on this

Page 105: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

95 April 3, 2012

corridor and learned that operating more than 55 trips per day will likely not be possible. Therefore, RTD is considering a modified operating plan for the full build out of the line. RTD is evaluating the distribution of the 55 trains per day limit with 30 minute bi-drectional service between DUS and Longmont with short-turn trains providing 15 minute bi-directional peak hour service between Boulder Transit Village and DUS. Off-peak service will be hourly for the entire line. Due to the 55 trains per day limit, the hours of operation for the line will be reduced from the original span of service assumptions. The modified operating plan is shown to have a minimal impact on forecast ridership. This modified operating plan for the full rail line is subject to BNSF approval.

63BNorthwest BRT The Northwest BRT, in conjunction with the US 36 BRT, will provide rapid transit service between DUS and Longmont. The exact BRT alignments, routes, vehicles and operating characteristics will be finalized through an environmental process and final design. However, for purposes of defining the Northwest BRT project and this report the following assumptions were made about the BRT operations. Three types of BRT routes would be included in the Northwest BRT project:

All-Stop Freeway – routes that operate on a freeway and stop at all BRT stations.

Express Freeway – routes that operate on a freeway and only stop at select stations providing faster travel times between key origin-destination pairs.

Arterial – routes that connect destinations on arterial roads with fewer stops and faster travel times than local bus routes.

The BRT routes will operate in a combination of running ways to ensure buses have priority over automobiles traveling along the same roadways. The freeway BRT routes will utilize a combination of center running Bus/HOV lanes and the outside shoulder. In general, the express freeway routes will utilize the Bus/HOV lanes and the all-stop freeway routes would use the shoulder instead of merging from the ramp stations into the center Bus/HOV lane. The arterial routes will utilize a combination of signal priority and queue bypass lanes to ensure faster travel times along the corridor. The preliminary BRT routing and service frequencies are summarized in Table 8.

Page 106: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

96 April 3, 2012

Table 8: Northwest BRT and US 36 BRT Routes

Southeast Rail Extension The FasTracks Plan included the extension of the E, F and Z Lines from Lincoln Station to RidgeGate Station. The plan included increased service on the E, F and Z Lines to combine to four minute peak and six minute off-peak service for the Southeast Rail Extension. However due to the change in the downtown Denver traffic signal timing, the Southeast Rail Extension service plan has changed to maintain the existing frequencies on the E and F Lines. Increased capacity will be provided on the Southeast Rail Line with longer trains. The service frequencies for the E and F Lines combine for 10 minute peak and 15 minute off-peak service. The E and F Lines are served by a combination of two-, three- and four-car trains. The original FasTracks service levels will be achieved on the Southeast Rail Extension with the addition of the Z Line that will be implemented with the completion of the I-225 Rail Line. The Z Line will open with 10 minute peak and 15 minute off-peak service with a combination of one- and two-car light rail trains. By 2035, the Z Line will operate with 7.5 minute peak service. With the addition of the 2035 Z Line service the Southeast Rail Extension will operate with the originally planned four minute peak and six minute off-peak headways. Southwest Rail Extension The FasTracks Plan included the extension of the existing C and D Lines from Mineral Station to C-470/Lucent Boulevard Station with increased peak service on the C Line to combine for 6 minute peak and 7.5 minute off-peak service. Due to the change in the downtown Denver traffic signal timing, the Southwest Rail Extension service plan has changed to maintain the existing

Route Description Type of BRT Peak Hour Service

BF Denver Union Station - US 36 & Broomfield via US 36

Express 10 min

BV Denver Union Station - Boulder Transit Center via US 36 and Broadway in Boulder

All-Stop 30 min

BV-Long Denver Union Station - Longmont (1st & Main) via US 36, Broadway & SH 119

All-Stop 30 min

BX Denver Union Station - Boulder Transit Center via US 36 and Broadway in Boulder

Express 10 min

HV Denver Civic Center Station - Boulder Junction via US 36 and 28th St in Boulder

All-Stop 15 min

HV-Long

Denver Civic Center Station - Longmont (1st & Main) via US 36, Foothills Pkwy & SH 119

All-Stop 30 min

HX Denver Civic Center Station - Boulder Junction via US 36 and 28th St in Boulder

Express 10 min

L Denver Union Station - Longmont (1st & Main) via US 36, SH 42/96th St, S Boulder Rd, SH 287

All-Stop 30 min

LX Denver Union Station - Longmont (1st & Main) via US 36, SH 42/96th St, S Boulder Rd, SH 287

Express 20 min

LoX Denver Union Station - Louisville via US 36, SH 42/96th St

Express 20 min

LBX Louisville - Boulder Junction via Arapahoe Rd or S Boulder Rd

Arterial 10 min

Page 107: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

97 April 3, 2012

service level on the C Line. Increased capacity will be provided with longer trains. The C and D Lines provide 7.5 minute peak and 10 minute off-peak service with a combination of two-, three- and four-car light rail trains. US 36 BRT The FasTracks Plan has always included 18 miles of BRT for a Bus/HOV lane on US 36 between I-25 and the Table Mesa park-n-ride. Through the EIS process, it was determined that the US 36 BRT project would include a center running Bus/HOV lane and side ramp stations. The BRT service would include a combination of express and all-stop routes between Boulder and Denver. In Boulder, the BRT routes would serve both the Boulder Transit Center and Boulder Transit Village Station. In Denver, the BRT routes would serve both DUS and Civic Center Station. FasTracks has completed several station enhancements including slip ramps and pedestrian access improvements along the corridor. The opening of the new US 36 & Broomfield park-n-ride in May 2010 is the first full project to be completed as part of FasTracks. This was the first step in upgrading the existing US 36 bus service to BRT as the opening of the new park-n-ride with slip ramps saves up to 15 minutes of travel time between Denver and Boulder. RTD has partnered with CDOT to fund the extension of the US 36 managed lanes from Federal Boulevard to Interlocken/96th Street. The extension of the managed lanes to Interlocken will be completed in 2015. The completion of the managed lanes project will coincide with the official opening of US 36 BRT as it will result in significant travel time savings and improved reliability over the existing bus service. The US 36 BRT routes are all of the B and H routes shown in Table 8. The service levels and routing associated with the US 36 BRT service are summarized in the table. West Rail Line The West Rail Line was included in the FasTracks Plan as a light rail line with 5 minute peak and 15 minute off-peak service. In 2007, as one of the cost containment strategies for the West Rail Line, double track between the Denver Federal Center and the Jefferson County Government Center-Golden Stations was changed to single track. This modification changed the operating plan. Under this revised operating plan approved by FTA, peak period trains to downtown Denver will operate every 15 minutes from the Jefferson County Government Center-Golden Station and every 5 minutes from the Federal Center Station. Two-car light rail trains will be utilized to serve this corridor and are forecasted to meet the 2030 ridership demand.

Page 108: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

98 April 3, 2012

6.0 6BTRANSIT ORIENTED DEVELOPMENT (TOD)

64BStation Area Planning In 2011, RTD staff collaborated with local government jurisdictions on 13 station area and station-related plans. The affected stations are listed by line below.

West Rail Line: Decatur-Federal (Denver), Federal Center (Lakewood)

Northwest Rail Line: Boulder Transit Village, Louisville, Downtown Longmont

Gold Line: Olde Town (Arvada)

I-225 Rail Line: Colfax/Fitzsimons (Aurora), Florida (Aurora)

East Rail Line: 38th/Blake (Denver), Central Park Blvd (Denver)

North Metro Rail Line: National Western Stock Show (Denver)

Central/CPV: 10th/Osage (Denver), Welton Stations (Denver)

UResearch and Reporting

RTD’s 2011 TOD Status Report is anticipated to be released in early 2012. The report details new real estate development and changes in the status of existing real estate projects within a half-mile of existing and planned stations and transfer centers. Combining the data for the existing RTD system and planned FasTracks expansion, the following development has either already been built or is currently under construction:

22,406 housing units

5,909 hotel rooms

5.65 million square feet of office space

5.28 million square feet of retail

2.4 million square feet of governmental space

5.81 million square feet of medical-related space

160,000 square feet of cultural space

1.94 million square feet of educational space

2.62 million square feet of convention/sports space.

Additionally, the following levels of development have been proposed: 6,804 housing units, 1,585 hotel rooms, 857,206 square feet of retail, 2.95 million square feet of office space, and 4.3 million square feet of medical-related space.

In developing the 2011 TOD Status Report, RTD looked at the changes that have occurred since 2010 and found that there continues to be slow real estate growth. Economic recovery remains elusive, and although Denver’s market appears stronger than many other parts of the country, new development is projected to come online much more slowly than during the peak years between 2006 and 2009. Residential for-rent apartment development is poised to recover most quickly according to our projections and should reverse the declining trend of the last two years

Page 109: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

99 April 3, 2012

with increasing levels of production in 2012 and 2013. In contrast, office and retail development are projected to continue their downward trend over the next couple of years.

TOD Pilot Program

In 2010, RTD made a significant change to its TOD policy, with a decision to take a more prominent role in the planning and execution of mixed-use development around transit centers. This decision, based on the new federal livability guidelines and local interests, with the support of the RTD Board of Directors, places greater emphasis on the creation of affordable housing in relation to transit centers through:

Strategic management of parking

Being more flexible with the use of RTD land in public private partnerships that are consistent with FTA guidelines

Seeking grant funding for TOD that has an emphasis on community growth

Forming partnerships with other government agencies

To implement this new policy, RTD has initiated a TOD Pilot Program to test new approaches. Four sites have been selected for the Program, which RTD believes have the greatest chance of successful TOD implementation. The Program will serve as a model for the rest of the region. The TOD Pilot Program was launched to test this expanded role with a focus on stations considered to have the greatest opportunity for success within a 3- to 5-year timeframe. Criteria for “success” was determined to consist of a station’s presence on an existing or funded corridor, commitment by both public and private sector interests, market potential, a TOD plan in place, and RTD’s ability to advance development through actions such as offering land as equity with other partners and accelerating certain project elements (e.g., initial structured rather than surface parking). The TOD Pilot Program progressed this year with continued focus on the four pilot projects: Alameda Station, The Federal Center Station in Lakewood, the Welton corridor, and Olde Town Station in Arvada. The most significant TOD Pilot Program accomplishments:

Reported on Lessons Learned with the TOD Pilot Program in November 2011

Completed ULI Technical Advisory Panels for the Federal Center Station and Welton Corridor TOD Pilots

Developed a draft MOU with the General Services Administration (GSA) and Lakewood to move forward with a development framework at the Federal Center Station

Established draft design criteria to address optimizing transit operations with implementation of joint development

Advanced discussions on the Alameda Station and Olde Town Station pilots to the point where substantive agreements for joint development implementation will be required in 2012

In addition, the TOD team worked on a number of other key projects throughout 2011:

Actively participated in the development of ULI’s TOD Marketplace program

Successful approval of design-build contract for Boulder Transit Village joint development

QoL 2010 detailed reports completed and results presented at the National Performance Measures Conference

Page 110: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

100 April 3, 2012

Release of Request for Qualifications (RFQ) and RFP for DUS Historic Building reuse and successful selection of a development partner

Assisted with solidifying the preliminary design for the Sheridan Station parking garage in support of community goals for TOD

RTD’s TOD work also included facilitating the process to determine a developer of the historic building at DUS. After public input meetings and consultations with stakeholders, historic preservation, and development experts, RTD staff took a final recommendation for the historic building reuse process to the RTD Board of Directors in early April, 2011. That process called for the release of a RFQ and a subsequent request for a business plan proposal. RTD received two final proposals on October 5th. The first, from USNC, proposed retail and restaurant uses on the bottom floor that included a market concept that incorporated local vendors. USNC proposed office and creative entrepreneurial office space in conjunction with “Create Denver.” The second, from the Union Station Alliance (USA) - made up of Urban Neighborhoods, Sage Hospitality, Milender White Construction, and Tryba Architects, among others – proposed a boutique hotel on the upper floors with retail and restaurant uses on the main floor. USA’s proposal also called for expanding what has been traditionally thought of as usable space in the station by repurposing the attic on the third floor and adding a mezzanine level on the part of the first floor wing buildings. The Historic Building Evaluation Panel took up deliberations and the two development groups offered their visions for the reuse to a well-attended (over 550 people) public meeting on November 3rd. The Evaluation Panel took its recommendation to the RTD Board of Directors on November 22nd, and after several weeks of deliberating, the Board voted to approve the USA proposal on December 20th. RTD staff will now begin working with the USA team on signing an exclusive negotiation agreement. If USA’s initial timeline remains consistent, the historic building redevelopment should be complete in 2014.

Transit Oriented Communities

Understanding transit’s impact beyond simply moving people from point A to point B, RTD’s thinking around transit-oriented development has shifted in recent years. Instead of simply serving as the “T” in “TOD,” RTD is looking at other ways to encourage transit-supportive development around existing and planned rail stations. The launch of the revised Strategic Plan for TOD in 2010 marked the first step in this new direction, when RTD redefined its measures of success for TOD. Instead of simply considering ridership and revenue impacts of TOD, the revised strategic plan incorporated livability benefits represented by the Federal HUD-DOT-EPA Partnership for Sustainable Communities. Also incorporated in the 2010 revision is a mixed-income housing policy that guides the incorporation of an affordability goal when issuing RFPs for development on RTD property. Proactive engagement (such as the TOD Pilot program and the WIN program) has allowed RTD to take a more holistic approach to moving beyond acting as just the “T” in “TOD.” Instead of simply encouraging the construction of a transit-supportive building, RTD is developing transit-supportive communities by fostering jobs and affordable housing in transit accessible neighborhoods. This philosophy at RTD is why the agency is moving beyond the term “transit-oriented development” and thinking instead of an entire “transit-oriented community.”

Page 111: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

101 April 3, 2012

Page left intentionally blank

Page 112: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

102 April 3, 2012

7.0 7BDOWNTOWN DENVER CIRCULATOR

The Downtown Denver Circulator is a planned shuttle route that is designed to complement the 16th Street Mall Shuttle and local bus network. The Circulator is intended to connect DUS, where all of the FasTracks lines will tie into downtown, with the employment centers throughout downtown Denver. The Circulator was defined in the Denver Multimodal Access Plan (DMAP), which was led by the CCD, with participation from RTD. The DMAP study addressed mobility needs for vehicles, freight, pedestrians, bicycles, and transit for downtown Denver. Funding for the Downtown Denver Circulator rolling stock and operations have always been and remain part of the FasTracks Financial Plan. Capital costs are also represented in Table 3 of this report. The project was previously assumed to be part of the ongoing bus service cost and now it includes a mix of buses and capital improvements along the alignment. Since the project is moving into preliminary engineering, RTD is presenting the project separately for tracking purposes. In March 2010 a draft of the Proposed Downtown Denver Circulator/Distributor plan was published. The Plan includes several recommendations for the final design and implementation of the Circulator. These recommendations include the following elements:

Type of buses to be used

Stop locations

Routing

Schedule

Unique stop design with bus bulbs The proposed route starts at DUS and travels down 19th Street and Broadway to 12th Ave & Acoma St (just south of the Denver Art Museum), where it will then turn around and return to DUS along Lincoln and 18th Street. The proposed route is shown in XFigure 30. Traffic analysis and PE are currently underway to provide a better understanding of the feasibility and impacts of adding bus bulbs. Upon completion of PE, traffic analysis, and coordination with the CCD, the final number of stops and locations will be determined. The overall plan for the Circulator will be presented to the RTD Board for approval in 2012 and it is anticipated that the Circulator will begin operating in 2014 concurrent with the opening of the DUS bus facility.

Page 113: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

103 April 3, 2012

Figure 30: Downtown Denver Circulator Proposed Route

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

BR

OA

DW

AY L

INC

OLN

ST

GLE

NAR

M P

L

15TH ST

STOUT

ST

BR

OA

DW

AY

WELT

ON S

T

SP

EE

R B

LVD

CHAM

PA S

T

CURTIS

ST

17TH ST

14TH ST

LARIM

ER S

T

W COLFAX AVE

18TH ST

19TH ST

BLAKE

ST

LIN

CO

LN

ST

ARAPA

HOE S

T

CALI

FORNIA

ST

LAW

RENCE S

T

E 11TH AVE

E 18TH AVE

E 17TH AVE

E 16TH AVE

E 14TH AVE

E 13TH AVE

E 12TH AVE

E 10TH AVE

MAR

KET

ST

7TH

ST

E 20TH AVE

LIP

AN

ST

E 19TH AVE

WAZE

E S

T16TH

ST

OS

AG

E S

T

KA

LA

MA

TH

ST

E COLFAX AVE

AURAR

IA P

KWY

GLE

NAR

M P

L

SA

NTA

FE

DR

BA

NN

OC

K S

T

EL

AT

I S

T

MA

RIP

OS

A S

T

W 10TH AVE

10TH

ST

CH

ER

OK

EE

ST

TREM

ONT

PL

WEW

ATTA S

T

RIO

CT

DE

LA

WA

RE

ST

AC

OM

A S

T

WYNKO

OP S

T

9TH

ST

COURT P

L

28TH ST

8TH

ST

CHESTN

UT

PL

LITTLE

RAV

EN S

T

12TH

ST

QU

IVA

S S

T

11TH

ST

PE

CO

S S

T

CLE

VELA

ND P

L

11TH

ST

19TH ST

WA

SH

ING

TO

N S

T

Legend

!( Light Rail Station

Downtown Denver Circulator Proposed Alignment

DUS Bus Box Proposed Circulator Route

16th St. FREE MallRide

RTD Light Rail

Downtown Denver Circulator Proposed Stop

±

CivicCenter

StateCapitol

DenverPublicLibrary

Denver

ArtMuseum

City and

County ofDenver

Colorado Convention

Center

DenverPavilions

Denver

Performing Arts

Complex

University of

ColoradoDenver

Auraria

Campus

Skylin

e Par

k

Coors Field

Den

ver U

nion

Sta

tion

Lawson Park

BenedictFountain

Park

Com

mon

s Par

k

Connection to

Commuter Rail

Connection to Light Rail and

16th Street FREE MallRide

CivicCenterStation

November 2011

Page 114: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

104 April 3, 2012

8.0 8BOTHER FASTRACKS PLAN ELEMENTS

8.1 16BLegislative Update The 2011 First Regular Session of the 68th Colorado General Assembly convened on January 12, 2011, and adjourned on May 11, 2011. The following bill of relevance to RTD and FasTracks was passed in the 2011 session: 8.1.1 38BSenate Bill 11-223, concerning state sales tax revenues retained by a vendor as

compensation for expenses incurred by the vendor in the collection and remittance of such tax revenues to the state, and making an appropriation therefore.

The Governor signed this bill into law on May 5, 2011. This bill temporarily reduces the fee that vendors can retain for compensation of sales tax collection expenses between July 1, 2011 and June 30, 2014, from the current amount of 3.33% of the sales tax they collect to 2.22%. (In 2009, Senate Bill 09-212 and SB 09-275 temporarily repealed the vendor fee from July 1, 2009 through July 1, 2011. This bill will reinstate a vendor fee of 2.22% for FY 2011-12, FY 2012-13, and FY 2013-14.) RTD will see a slight increase in the amount of sales tax it receives.

8.2 7BQuality Management Oversight RTD’s quality philosophy is to place primary responsibility for quality assurance on the contractors who are performing the work; including environmental planning, design, construction, manufacturing, and installation services and products. To that end, every contractor or consultant performing work on the RTD FasTracks Program must submit a Quality Management Plan to RTD that meets the criteria found in the international standard ISO 9001, Quality Management Systems – Requirements; as well as U.S. Department of Transportation FTA-IT-90-50001-02.1, Quality Assurance and Quality Control Guidelines. By meeting these two related quality management standards, RTD can be assured that its contractors and consultants are adequately reviewing RTD’s requirements, planning their work, checking their work, and resolving non-conforming work to RTD’s satisfaction. RTD ensures contractor quality assurance programs are functioning satisfactorily through a robust quality oversight program that assesses the work products on a sampling basis, and the quality processes of each contractor/consultant. By looking at the processes, RTD can proactively prevent nonconforming work from occurring. The RTD Quality Management Oversight team focuses on providing program-wide procedures, tools, training, and support to the project teams so that consistent quality oversight processes can be applied from the planning stage through commissioning. RTD’s Quality Oversight Program is ISO 9001 registered, and includes:

Planning Reviews (ensuring that EIS/EA/EE documentation meets the requirements of RTD’s Environmental Policies and Procedures Manual).

Design Reviews (ensuring that BE, PE and final design plans and specifications meet the requirements found in RTD’s design criteria, environmental documentation, system safety criteria, and other required industry standards).

Management Audits (ensuring contractors and consultants are effectively implementing their approved management plans, such as the Quality Management Plan, Health and Safety Plan, etc. Management Audits are a macro view of the management system.)

Page 115: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

105 April 3, 2012

Process Audits (ensuring contractors and consultants are properly following their management and production procedures. Whereas management audits are a macro view of the management system, process audits are narrowly focused on a particular procedure, and are conducted more frequently.)

Construction Verification Inspections (ensuring the constructed or fabricated product complies with the requirements in the design plans and specifications).

Construction Verification Testing (ensuring that the contractor is providing accurate test results of construction materials that are incorporated into the project).

Internal Audits (ensuring that RTD is following its own management procedures and processes, and implementing continuous improvement).

8.3 18BQuality of Life (QoL) The QoL Study is a multiyear monitoring Program intended to identify, track and measure how the FasTracks Program is achieving the goals adopted in the April 2004 FasTracks Plan. In doing this, the study measures how the region changes as transit lines are planned, constructed and opened for service. This study focuses on “quality of life” in the context of those areas most affected by transit improvements: mobility, environment, economic activity, and development/land use. Data collection for the QoL Study has been underway since 2006. Five reports have been published and the latest report is scheduled for release in early 2012.

8.4 19BFasTracks Public Information/Public Outreach Program The mission of the FasTracks Public Information/Public Outreach Program is to support the implementation of the FasTracks Plan by creating and maintaining a comprehensive and proactive internal and external communications Program. The Program Public Information Team has established a “big picture” approach to communicating to the entire region about FasTracks. To establish coordination and consistency of messaging with the rail and BRT line/project public information teams, the FasTracks Public Information (PI) Team has assigned staff members to serve as project liaisons. These PI liaisons work as part of the rail line and BRT line/project teams and closely with the contractor PI teams to provide a consistent information “bridge” through each phase of FasTracks implementation, (environmental, design and construction). The PI liaison concept ensures a convenient and streamlined flow of communication between the FasTracks PI Team and the rail and BRT line/project PI teams. The FasTracks Public Information (PI) team focuses on two major elements, Public Information Strategic Planning and Communications Implementation.

Public Information Planning. A Strategic Public Information Plan serves as the overarching approach to program-wide public information and outreach. The team develops an Annual Public Information Plan to define the anticipated tasks and approaches necessary for the coming year. Each quarter, the team then further defines the work plan into a Quarterly Plan of specific tasks and activities for the upcoming quarter, which also includes a progress report of activities from the previous quarter.

Communications Program Implementation. The FasTracks PI Team communicates and engages internal and external stakeholders through seven strategic communication

Page 116: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

106 April 3, 2012

Programs: Internal Relations, Public Involvement, Public Outreach, Government Relations, Media Relations, Issues Management and Crisis Communications.

PI Team primary activities during 2011 included:

Public Education Campaign. The PI team developed two FasTracks public education campaigns in 2011. The first campaign was the first one developed with the new RTD brand. Much of the campaign focused on the destinations of FasTracks and where people could eventually take transit through this program. The campaign used a variety of communication tools including community newspaper ads, bus and light rail ads, banners in high profile RTD facilities and social media.

The second 2011 FasTracks public education campaign was based on feedback received in the Annual FasTracks Public Opinion Survey, which was conducted in October 2011, as well as focus groups that were conducted in summer 2011. The messages that resonated most with people were reducing traffic congestion, providing choice, reducing air pollution, and offering convenience. To capture commuters, FasTracks used primarily outdoor advertising – billboards, exterior signage on buses and the FREE Mall Ride, as well as banners and LCD displays at various RTD stations. Relying on these outdoor tools, the message was created to be quick, relevant and compelling through a simple message using everyday language that speaks to how people feel when they’re stuck in traffic. Thus, the campaign phrase, “because traffic s#©!s.”

The “Call to the People”. In April, RTD General Manager Phil Washington encouraged members of the public to let the agency know whether it should pursue a sales tax increase vote in 2011 to complete the FasTracks Program sooner rather than later, or perhaps sometime in the future. The two-week mini-campaign utilized community newspaper advertising, social media elements, a video along with an online survey.

North Metro RODeo. RTD FasTracks celebrated the signing of the ROD by the FTA for the North Metro Rail Line on Thursday, May 19, 2011. The ROD signified the end of environmental planning and the beginning of final design and construction. The event commemorated the milestone with a western-themed “RODeo” ceremony at the National Western Stock Show, the first stop of the North Metro Rail Line. This marked the end of more than four years of in-depth project development, evaluation, refinement and extensive public involvement, which RTD began in September 2006.

Full Funding Grant Agreement Signing Ceremony and Gold Line Groundbreaking. On August 31, U.S. Transportation Secretary Ray LaHood and FTA Administrator Peter Rogoff officially awarded RTD a $1.03 billion FFGA to help build two FasTracks rail lines, the East Rail Line and the Gold Line. A special signing ceremony was followed by the groundbreaking for the Gold Line at the site of the future Olde Town Arvada Station. Actors dressed as gold prospectors used pick axes to “break ground” near where real gold miners struck gold in the 1850s as a symbolic tribute to the history of the Gold Line. An estimated 600 people attended the event that drew regional, national and international attention in the transportation world.

T3 Industry Forum. RTD’s call for innovations enticed many high-level executives from a cross-section of large and small firms to the T3 industry forum. More than 200 people attended the forum, representing numerous engineering, construction, financial, technology and other major corporate firms. They came to learn more about RTD and the

Page 117: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

107 April 3, 2012

types of innovative solutions RTD is looking for in the areas of capital programs, operations and maintenance along with technology. The intent of the forum was to spur innovative proposals on how to complete the FasTracks transit expansion program as soon as possible, enhance the overall RTD customer experience and reduce the cost of the agency’s operations.

RTD’s New Commuter Rail Car Model. For five weeks in May and June, RTD displayed its new rail car model for public viewing at DUS, drawing more than 7,800 visitors. The 10,700-pound unit gave the public opportunity to tour the model and provide feedback on its interior design. Feedback on surveys filled out by visitors were evaluated by the project team and rail car manufacturer Hyundai Rotem USA resulting in some changes to the features of the rail cars. The display, which depicted the front third of an actual 85-foot commuter rail car, showed how a commuter rail car is designed for longer lines, faster speeds and more passengers.

Final FasTracks Light Rail Car. RTD received its final light rail vehicle to complete the fleet needed to accommodate the additional service that will be provided through the FasTracks Program on October 5, 2011. The car is the final of 55 vehicles ordered for RTD’s future light rail service planned for the West Rail Line, I-225 Rail Line and the Southwest and Southeast Rail Extensions. This final light rail car brings RTD’s total light rail fleet up to 172 vehicles.

Telephone Town Halls. RTD Directors started a new method of public outreach on November 28, 2011, through telephone town hall meetings. A series of 15 town halls – one in each director district – were conducted through December 2011. Through the series, RTD randomly called more than 400,000 people across the eight-county district. This allowed board members to reach out in a more direct and interactive way to far more constituents than through traditional public meetings or newsletters.

Opening of the Federal Center Station. The West Rail Line was the first project in RTD’s FasTracks Program to start construction and will be the first to open in May 2013. July 28 marked the official opening of the Federal Center Station on the line and the closing of the Cold Spring Park-n-Ride. This action was taken to assist with existing RTD bus service and parking as well as to prepare commuters for future rail service.

Annual FasTracks Public Opinion Survey. The 2011 FasTracks Public Opinion Survey provided RTD and the FasTracks PI Team with helpful insights on public perception about RTD, FasTracks, and how the PI program should craft its communications in the coming year. Seven years into RTD’s multi-billion FasTracks transit expansion program, 80 percent of metro-area residents say that approving FasTracks funding in 2004 was a good decision. Not surprisingly, jobs/employment/economy continued to be seen as the top issue facing the Denver metro area, as cited by 47% of survey participants.

Annual Program Evaluation Outreach. In an effort to keep internal and external stakeholders informed about the goals and progress of the APE, the PI Team implemented a communication plan to share information through a number of communication channels, including the FasTracks website, Inside FasTracks e-newsletter, Director District newsletters, and community and stakeholder presentations.

Growth of Facebook and Twitter. The PI team and RTD Public Relations and Marketing continued to grow their presence on social media. The FasTracks PI team also looked at

Page 118: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

108 April 3, 2012

different ways of using social media to promote the public education campaign and events, and has received significant results by doing so. For instance, in the weeks leading up to the FFGA event, a photo of a gold nugget at a location along the project alignment was posted every day. The first person to guess the correct location each day won a prize. The photo contest received more than 28,000 impressions on Facebook in the two-week period.

Inside FasTracks e-newsletter. A monthly e-newsletter called Inside FasTracks is distributed the last Monday of each month to elected officials, their staff, and other key stakeholders to keep them informed and engaged about FasTracks progress, timely news, and facts.

Information Materials. The PI Team develops and distributes a number of collateral materials to inform and educate the public about FasTracks. The materials produced throughout the year include a general FasTracks brochure, the final issue of the quarterly Transit Times District Newsletters, corridor and project fact sheets, and Program brochures on specific topic areas.

Media Relations. The PI Team continues to foster a good working relationship with local and national media organizations, many of whom inquire about FasTracks on a regular basis. The PI Team conducts annual media visits with the major local media organizations and community newspapers to provide an update on FasTracks and give the media an opportunity to ask questions about various aspects of the program. This year, the team also kicked off a FasTracks Media Working Group with representatives of local media entities to get feedback on the elements of FasTracks of most interest to them, their readers, viewers and listeners, and how the PI Team can best serve them as our media partners.

Photo/Video Documentation. An ongoing effort is capturing periodic still-photo and video documentation of the progress on FasTracks. Photos and video are compiled of construction, public meetings, special events, and other visual opportunities to show the progress of FasTracks. The photos and video are utilized throughout the year in information materials on the FasTracks and RTD websites, in videos, in public education campaigns, in community presentations, and in outside publications to accompany stories on FasTracks. The photos and video also help to document the projects before, during and after construction.

Video Education. As part of the annual public information campaign, the PI Team produces a short video to help educate the public about the progress of FasTracks and the benefits of the program. The 2011 video focuses on the various ways FasTracks benefits and connects communities across the region. An e-mail with a link to the video was sent to elected officials and key stakeholders in the region. The video was also distributed to the local Channel 8 station for inclusion in their programming when possible, and is available on the FasTracks website as well as on YouTube.

Website Maintenance. Regular updates of the FasTracks website occur to keep information fresh and easy to navigate. Three news features on the home page are changed out frequently to share the latest information that is of interest to the community at large.

Page 119: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

109 April 3, 2012

Speakers Bureau. The PI Team documents the community presentations that RTD Board Members and members of the FasTracks team deliver in an effort to keep stakeholders informed and updated about FasTracks. The process also tracks the collective number of attendees the team is reaching each year. Through December 2011, RTD reached about 6,481 people around the region through community presentations.

8.5 20BCitizens Advisory Committee (CAC) The FasTracks CAC completed its sixth full year serving in an advisory capacity to the RTD Board of Directors and the FasTracks Team on the implementation of the Program. The 17-member committee holds regular meetings each quarter and work sessions on the off months. During 2011, the CAC held three quarterly meetings at locations around the District - in Louisville, Greenwood Village, and Lakewood - to enhance outreach efforts to the community. Some of the issues the CAC focused on during 2011 include:

Review and input to the 2010 SB 208 Annual Report to DRCOG.

Review and input on timing and level of future sales tax election.

Review and input on RTD’s DUS historic building reuse review process.

Review Public Education Plan and RTD re-branding efforts.

Review updated FasTracks Public Involvement Plans.

Review TOD Report, proposed revisions to TOD Policy and Station Pilot Project.

Review Public Information Survey results.

Review progress for each Line; toured East Rail Line and DUS.

Review the 2011 APE process, financial modeling and schedules.

Review short-term and long-term options for completing FasTracks.

Participated on RTD’s Fiscal Sustainability Task Force.

Review and input on DUS historic building redevelopment proposals.

8.6 21BSustainability Program On October 17, 2006, the Board of Directors adopted a Sustainability Policy and Guidelines for existing and new transit systems and facilities throughout the District. The Policy objectives include: (1) Environmental Sustainability, (2) Travel choices and Accessibility, and (3) Livable Cities and Communities. RTD has established two sustainability committees to implement this policy. The Interdepartmental Committee consists of representatives from each of the nine RTD departments. The FasTracks Sustainability Committee meets monthly to check on sustainability progress, to educate on innovation and to evaluate the program’s sustainability initiatives. In 2011, the FasTracks Sustainability Committee revised its areas of focus for sustainability and they are now grouped into the following three categories:

Business Practices. RTD implements sustainable business practices with a number of measures, which include reviewing processes that eliminate, reduce or recycle waste, increasing the number of purchased recyclable products, and curbing the use of nonrenewable resources by increasing the use of alternatives energies. RTD determines what products are harmful to the environment and disposes of them properly if no green alternatives are available. RTD takes into account the life cycle costs for inputs of items purchased. Input costs must be considered in regards to regulations, energy use, storage, and disposal. RTD recycles metals, construction debris, printer cartridges, cardboard,

Page 120: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

110 April 3, 2012

paper, and developed electronic fiche systems. RTD supports the use of locally available products to reduce shipping costs and transportation, and promotes the use of ultra-low sulfur diesel fuel in off-road vehicles.

Resource Efficiency. RTD has implemented measures that help reduce the use of fuel, increased the efficiency and effectiveness of its transit system, maintained the use of renewable energy for light rail operations above 11%, recycled tires, lubricants, batteries, refrigerant and filters, and upgraded building systems throughout the district.

Knowledge Exchange. As the dialogue on societal, economical and environmental sustainability continues, RTD looks at its impact on this “Triple Bottom Line” in order to improve efficiency and effectiveness, to reduce expenses and to keep the public informed. RTD knowledge exchange explores options for using renewable resources, sustainability certifications for professionals and consultants, products and their reliability, and tax or other incentives. RTD focuses on three areas:

1. Informing RTD staff about sustainable practices, 2. Engaging the public on the practice of sustainability 3. Collaborating, sharing, discussing and presenting with and to academia,

businesses and other agencies. Some FasTracks line-specific accomplishments include:

Denver Union Station: The Station redevelopment area officially applied for LEED Certification in 2009 and continues to develop to LEED Silver standard, including utilizing materials with a total of 20% post-consumer recycled content. New lighting standards include the utilization of efficient lighting design and equipment such as LED and T8 fluorescent lamps.

Eagle Project: Project offices are located in a LEED Certified building. Included sustainability language within the Eagle Project contract, including using renewable energy for traction power and sustainable practices. Planning for various LEED elements within the project design, including the requirement to provide a renewable electrical energy source. Employees are required to contribute to VMT reduction by commuting on public transit.

I-225 Rail Line: Project specifications include using recycled asphalt and concrete within pavement sub-base.

North Metro Rail Line: Required that the consultant team include sustainable measures in the line design.

Northwest Rail Line: Plan to procure vehicles that have the flexibility to accommodate future advancements in alternative fuel engines through upgrades and retrofits.

US 36 BRT Line: Monitoring LED test area at Westminster Center parking structure. Design for queue jumps at several locations intended to reduce congestion, minimize wait times and emissions. Developed a pedestrian bridge at Broomfield Park-n-Ride that serves mixed-use development, improves regional transit efficiency and reduces congestion.

West Rail Line: New parking structures are specified to be ready for solar photovoltaic retrofitting. Obtained a variance to the parking structure design to optimize lighting.

Page 121: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

111 April 3, 2012

Allocated 49,000 tons of concrete to be recycled. Utilized shredded tires as a vibration mitigation measure.

8.7 22BFastConnects The FastConnects program is designed to improve transit service by improving the experience for transferring passengers. FastConnects uses timed transfers, where certain transit services are specifically scheduled in order to minimize the time passengers must wait for connecting service. The basic components of FastConnects are the transit services and facilities themselves ( XFigure 31). Related components are important to the design of the FastConnects system; these are land development and transit priority. FasTracks introduces six new rapid transit lines and three extensions, and FastConnects will help link them and all supporting bus services together. Prior to the FasTracks vote, RTD had already completed a preliminary study of the FastConnects concept with the report Network Developed Timed Transfer Sketch Plan, February 2003. In June 2010, RTD completed a detailed FastConnects Service Development Report. Two types of connections are envisioned as part of the FastConnects program: grid transfer and timed transfer. Grid transfer refers to locations where intersecting routes offer a high frequency of service (many at 15 minutes or better) and, therefore, simultaneous timing of vehicle schedules is not required for a convenient transfer. For timed transfer, schedules need to be written on clock-face headways (for RTD, multiples of 15 minutes) and transfer centers carefully selected so that bus, Call-n-Ride and rapid transit lines all have vehicles timed to arrive at the same time, minimizing the time a passenger has to wait. Critical factors in design of timed transfers include:

Bus route schedules designed to provide efficient clock-face headway

Call-n-Ride service area and circuit designed to provide efficient clock-face headway

Reliable running times

Efficient transfer window

A suitable site for vehicles to wait and passengers to make their connections With these FastConnects factors considered, investments can be directed towards making the bus routes as productive as possible as the FasTracks rapid transit lines begin to open in the coming years. The primary FastConnects location along the West Rail Line, opening in 2013, is the Federal Center Station which opened for bus access in July 2011.

Page 122: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

112 April 3, 2012

Figure 31: FastConnects

Page 123: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

113 April 3, 2012

8.8 Workforce Initiative Now (WIN) RTD has received a $486,465 grant from the FTA for the Workforce Initiative Now (WIN), a partnership between RTD, Community College of Denver, Urban League of Metropolitan Denver, and Denver Transit Partners. WIN is a sector workforce partnership that strives to meet the hiring and training needs of local employers by helping to create and retain living wage careers in the transit and construction industries, as well as providing local residents with skills development training, jobs and career pathways to work in these industries. This funding represents the largest grant awarded through FTA’s Innovative Workforce Development Grants program. WIN will use this funding to provide enhanced access to training equipment and materials for WIN network partners, hire support staff, and increase available funds to support foundational and skilled training. Training and supportive services are provided through the WIN Network, a collaborative of over 30 community-based organizations, community and technical colleges, industry training providers, and workforce development regions. By awarding the full amount requested, FTA has once again acknowledged the value of this initiative and the innovative thinking and planning in the RTD FasTracks program. The WIN partners are encouraged that this level of financial commitment from FTA may indicate that this collaborative workforce partnership will be used as a model for future transit projects.

8.9 Transformation through Transportation (T3) Industry Forum RTD held its first transit “industry forum” in September 2011, which brought the private sector together with RTD and other public partners to seek out innovations for the FasTracks Program, enhance the RTD customer experience, and reduce the cost of RTD operations. Nearly 240 high-level executives attended the forum, known as Transformation through Transportation (T3). Representatives from dozens of national and international firms attended, such as AT&T, Balfour Beatty Rail, CenturyLink, CH2M Hill, General Electric, Goldman Sachs, Herzog, IBM, Panasonic, RNL Design, Sprint, and Xerox. RTD’s main goal of the T3 process was to receive unsolicited proposals for various components of either the FasTracks Program or enhancements to RTD’s base system. To better familiarize attendees with its process, RTD presented, among other things, its unsolicited proposal methodology should they choose to move forward. RTD also described the base system, profiled progress made through the FasTracks program, and described RTD’s financial situation. As a result of RTD’s efforts to evaluate and investigate innovative proposals to help complete the FasTracks Program sooner and enhance its base system, RTD received an unsolicited proposal for the North Metro project. North Metro Constructors, a joint venture led by Fluor Enterprises Inc., Balfour Beatty Rail Inc., and Ames Construction submitted the proposal to RTD in October 2011. RTD evaluated the proposal after declaring it had initial merits; however, financial restrictions prevented RTD from moving forward on the proposal. RTD remains open to any proposals and will evaluate each for both technical and financial merits.

Page 124: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

April 3, 2012

Page left intentionally blank

Page 125: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

April 3, 2012

Appendix A:

SB 208 Legislations and DRCOG Resolutions (2004, 2008, 2009, and 2010)

Page 126: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers
Page 127: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers
Page 128: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Authority for MPO Review of FasTracks Annual Report

Colorado Revised Statutes

32-9-107.7. Regional fixed guideway mass transit systems - construction -

authorization.

(1) Any action of the board relating to the authorization of the construction of aregional fixed guideway mass transit system in any corridor shall require the affirmativevote of a two-thirds majority of the board membership. The board shall take no actionrelating to the construction of a regional fixed guideway mass transit system until aftersuch system has been approved by the designated metropolitan planning organization.Each component part or corridor of such system shall be separately approved by themetropolitan planning organization. Such action shall include approval of the method offinancing and the technology selected for such projects.

Page 129: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers
Page 130: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers
Page 131: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 7 , 2009

A RESOLUTION TO APPROVE MODIFICATIONS OF THE FASTRACKS SYSTEM.

WHEREAS, Senate Bill 90-208 (32-9-107.7 CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization (MPO) to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District (RTD) before any action relatingto construction may take place; and

WHEREAS, the Denver Regional Council of Governments (DRCOG) is theMetropolitan Planning Organization for the Denver region and is responsible for theoperation and maintenance of a continuing, comprehensive transportation planningprocess, including the preparation and adoption of transportation plans and programs; and

WHEREAS, the Board of Directors, on April 21, 2004, approved each componentpart and corridor of the FasTracks Plan, as well as the system as a whole in resolutionnumber 18, 2004, pursuant to section 32-9-107.7 CRS; and

WHEREAS, the DRCOG Board of Directors last approved an annual review of theupdated FasTracks Plan on May 21, 2008; and

WHEREAS, the Board of Director’s approval of the RTD FasTracks Plan onApril 21, 2004 was subject to a number of understandings, which include the conduct ofan annual review through the MPO process to identify any substantial changes in variouselements of the FasTracks Plan and determine if further SB-208 action is required; and

WHEREAS, the RTD has described further progress on the FasTracks Plan andhas proposed certain changes in the document RTD 2008 FasTracks Update InterimReport to DRCQG (January 2009>, which it submftted to DRCOG for review; and

WHEREAS, the changes identified in the RTD 2008 Interim Annual Report, werereviewed pursuant to the established process, and presented in the DRCOG 2008 InterimAnnual FasTracks Review and Determination Report. The review concurs with theidentification of several minor system changes to station locations and planned parkingspaces and concludes that the changes are not substantial enough to require furtherSB-208 action by the DRCOG Board of Directors; and

WHEREAS, the FasTracks system remains consistent with the intent of the MetroVision 2035 Plan, including its transportation element; and

WHEREAS, the Regional Transportation Committee has recommended theDRCOG 2008 Interim Annual Fas Tracks Review and Determination Report andacceptance of the changes presented by RTD.

Page 132: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE MODIFICATIONS OF THE FASTRACKS SYSTEM.Resolution No. 7 , 2009Page 2

NOW, THEREFORE, BE IT RESOLVED that the Board of Directors of the DenverRegional Council of Governments hereby accepts the findings of the DRCQG 2008 InterimAnnual Fas Tracks Review and Determination Report and approves modification of theFasTracks system.

BE IT FURTHER RESOLVED that the other understandings of resolutions number14, 2008 are not modified by this action, and remain in effect.

RESOLVED, PASSED AND ADOPTED this I~day of tVIc.~ r~c2k , 2009at Denver, Colorado.

ATTEST:

Jennif r h ufele, Exe4~ve Director

Denver Regional Council of Governments

Page 133: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers
Page 134: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers
Page 135: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers
Page 136: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DiRECTORS RESOLUTION NO. /0 , 2008

A RESOLUTION TO APPROVE THE MODIFIED GOLD LINE TRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-107.7 CRS), enacted by the Colorado GeneralAssembly, requires the Metropolitan Planning Organization (MPO) to approve the specifictechnology and method of financing of regional fixed guideway mass transit projectsproposed by the Regional Transportation District (RTD) before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments (DRCOG) is theMetropolitan Planning Organization for the Denver region and is responsible for theoperation and maintenance of a continuing, comprehensive transportation planningprocess, including the preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District submitted the FasTracks Plansystem, which includes the Gold Line corridor transit project, to DRCOG for its review andapproval pursuant to section 32-9-107.7 CRS; and

WHEREAS, the Board of Directors, on April 21, 2004, approved each componentpart and corridor of the FasTracks Plan in accordance with section 32-9-107.7 CRS,including the Gold Line corridor transit project in resolution number 10, 2004; and

WHEREAS, the Board of Director’s approval of the RTD FasTracks Plan onApril 21, 2004 was subject to a number of understandings, which include the conduct of anannual review through the MPO process to identify any substantial changes in variouselements of the FasTracks Plan and determine if further SB-208 action is required; and

WHEREAS, the RTD has described progress thus far on the FasTracks Plan andhas proposed certain changes in the document RTD 2007 Annual Report to DRCOG onFas Tracks (December 2007, with Addenda and Errata dated May 1, 2008), which itsubmitted to DRCOG for review; and

WHEREAS, a public hearing was held March 19, 2008 to receive public comment onthe RTD 2007 Annual Report, including the Gold Line corridor; and

WHEREAS, the RTD 2007 Annual Report identified a modification of the technologyin the Gold Line corridor developed through the National Environmental Policy Act (NEPA)process from light rail transit to commuter rail (specifically, electric multiple unit); and

Page 137: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE MODIFIED GOLD LINE TRANSIT PROJECTResolution No. /O , 2008Page 2

WHEREAS, the RTD 2007 Annual Report included an updated Financial Plan thatmodifies the specific method of financing the Gold Line corridor to be a design/build/finance/operate/maintain public-private partnership; and

WHEREAS, review of the modifications identified in the RTD 2007 Annual Report,pursuant to the established process and public hearing, as presented in the DRCOG 2007Annual FasTracks Review and Determination Report, categorizes the proposed changes tothe Financial Plan as substantial and requiring new SB-208 action; and

WHEREAS, the review finds the modifications of the technology proposed for theGold Line—commuter rail—appropriate for the corridor, given the requirements of therailroad company and the insignificant increase in corridor travel times, and consistent withthe intent of the Metro Vision 2035 Plan, including its transportation element; and

WHEREAS, the review finds the updated Financial Plan, including the method offinancing the Gold Line corridor, acceptable subject to the concerns noted in thecompanion Systems resolution; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe modification of the Gold Line project.

NOW. THEREFORE, BE IT RESOLVED that, pursuant to authority granted throughsection 32-9-1 07.7 CRS, the Board of Directors of the Denver Regional Council ofGovernments hereby approves the modified Gold Line corridor transit project, including themethod of financing and technology, as submitted by the Regional Transportation District.

BE IT FURTHER RESOLVED that the other understandings of resolution number10, 2004 are not modified by this action and remain in effect.

RESOLVED, PASSED AND ADOPTED this p/st day of ,2008at Denver, Colorado.

ATTEST:

~Director

BDenver Regional Council of Governments

Page 138: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. ~) 1 , 2008

A RESOLUTION TO APPROVE THE MODIFIED NORTHWEST RAIL TRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-1077 CRS), enacted by the Colorado GeneralAssembly, requires the Metropolitan Planning Organization (MPO) to approve the specifictechnology and method of financing of regional fixed guideway mass transit projectsproposed by the Regional Transportation District (RTD) before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments (DRCOG) is theMetropolitan Planning Organization for the Denver region and is responsible for theoperation and maintenance of a continuing, comprehensive transportation planningprocess, including the preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District submitted the FasTracks Plansystem, which included the US-36 Corridor/Longmont Extension transit project, to DRCOGfor its review and approval pursuant to section 32-9-107.7 CRS; and

WHEREAS, the Board of Directors, on April 21, 2004, approved each componentpart and corridor of the FasTracks Plan in accordance with section 32-9-107.7 CRS,including the US-36 Corridor/Longmont Extension transit project in resolution number 9,2004; and

WHEREAS, the Board of Director’s approval of the RTD FasTracks Plan onApril 21, 2004 was subject to a number of understandings, which include the conduct of anannual review through the MPO process to identify any substantial changes in variouselements of the FasTracks Plan and determine if further SB-208 action is required; and

WHEREAS, the RTD has described progress thus far on the FasTracks Plan andhas proposed certain changes in the document RTD 2007 Annual Report to DRCOG onFas Tracks (December 2007, with Addenda and Errata dated May 1, 2008), which itsubmitted to DRCOG for review; and

WHEREAS, the RTD 2007 Annual Report separated the original US-36 Corridor!Longmont Extension transit project into the US-36 corridor project and the Northwest Railcorridor project; and

WHEREAS, a public hearing was held March 19, 2008 to receive public comment onthe RTD 2007 Annual Report, including the US-36 corridor and Northwest Rail corridor; and

Page 139: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE MODIFIED NORTHWEST RAIL TRANSIT PROJECT

Resolution No. /) , 2008Page 2

WHEREAS, the RTD 2007 Annual Report identified a modification of the renamedNorthwest Rail corridor, developed through the Environmental Evaluation process,extending it approximately 2.3 miles north and east from SH-1 19/Hover Road to 1~Avenue/Terry Street in downtown Longmont; and

WHEREAS, review of the modifications identified in the RTD 2007 Annual Report,pursuant to the established process and public hearing, as presented in the DRCOG 2007Annual FasTracks Review and Determination Report, categorizes the proposed changes inthe Northwest Rail corridor as substantial and requiring new SB-208 action; and

WHEREAS, the RTD 2007 Annual Report identifies that this extension is cost-neutral and, while rail travel time to the new end-of-line station is projected to increase 2 to2.5 minutes, the higher density land uses in downtown Longmont provide somewhat betterridership, arid the review concurred with the assessment and the proposed extension; and

WHEREAS, the commuter rail technology finding for the Northwest Rail corridorremains; and

WHEREAS, the review categorizes the changes in the US-36 corridor as notsubstantial and requiring no further SB-208 action; and

WHEREAS, the review finds the Financial Plan acceptable, subject to the concernsnoted in the companion Systems resolution; and

WHEREAS, the Regional Transportation Committee has recommended no furtherSB-208 action on the US-36 corridor and has recommended approval of the modificationsto the Northwest Rail corridor.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted throughsection 32-9-1 07.7 CRS, the Board of Directors of the Denver Regional Council ofGovernments hereby approves the modified Northwest Rail corridor project, as submittedby the Regional Transportation District.

BE IT FURTHER RESOLVED that resolution number 9, 2004 ‘remains in effect asthe SB-208 approval of the US-36 corridor and that findings for the Longmont Extensionproject in that resolution are superseded by the findings for the Northwest Rail corridor ofthis action.

BE IT FURTHER RESOLVED that the other understandings of resolution number 9,2004 are not modified by this action, and remain in effect in that resolution for the US-36corridor and are incorporated by reference herein for the Northwest Rail corridor.

Page 140: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE MODIFIED NORTHWEST RAIL TRANSIT PROJECT

Resolution No. IL 2008Page 3

RESOLVED, PASSED AND ADOPTED this ~ /st day of _____ 2008at Denver, Colorado.

oard of DirectorsDenver Regional Council of Governments

ATTEST:

~Director

Page 141: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCiL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. l~ , 2008

A RESOLUTION TO APPROVE THE MODIFIED EAST CORRIDOR TRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-1 07.7 CRS), enacted by the Colorado GeneralAssembly, requires the Metropolitan Planning Organization (MPO) to approve the specifictechnology and method of financing of regional fixed guideway mass transit projectsproposed by the Regional Transportation District (RTD) before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments (DRCOG) is theMetropolitan Planning Organization for the Denver region and is responsible for theoperation and maintenance of a continuing, comprehensive transportation planningprocess, including the preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District submitted the FasTracks Plansystem, which includes the East Corridor transit project, to DRCOG for its review andapproval pursuant to section 32-9-107.7 CRS; and

WHEREAS, the Board of Directors, on April 21, 2004, approved each componentpart and corridor of the FasTracks Plan in accordance with section 32-9-107.7 CRS,including the East Corridor transit project in resolution number 11, 2004; and

WHEREAS, the Board of Director’s approval of the RTD FasTracks Plan onApril 211 2004 was subject to a number of understandings, which include the conduct of anannual review through the MPO process to identify any substantial changes in variouselements of the FasTracks Plan and determine if further SB-208 action is required; and

WHEREAS, the RTD has described progress thus far on the FasTracks Plan andhas proposed certain changes in the document RTD 2007 Annual Report to DRCOG onFas Tracks (December 2007. with Addenda and Errata dated May 1, 2008), which itsubmitted to DRCOG for review; and

WHEREAS, a public hearing was held March 19, 2008 to receive public comment onthe RTD 2007 Annual Report, including the East Corridor; and

WHEREAS, the RTD 2007 Annual Report included an updated Financial Plan that modifiesthe specific method of financing the East Corridor to be a designfbuild/finance/operate/maintain public-private partnership; and

Page 142: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE MODIFIED EAST CORRIDOR TRANSIT PROJECTResolution No. _J~?, , 2008Page 2

WHEREAS, review of the modifications identified in the RTD 2007 Annual Report,pursuant to the established process and public hearing, as presented in the DF?COG 2007Annual FasTracks Review and Determination Report, categorizes the proposed changes tothe Financial Plan as substantial and requiring new SB-208 action; and

WHEREAS, the review finds the updated Financial Plan, including the method offinancing the East Corridor, acceptable subject to the concerns noted in the companionSystems resolution; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe modification of the East Corridor project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted throughsection 32-9-107.7 CRS, the Board of Directors of the Denver Regional Council ofGovernments hereby approves the modified method of financing the East Corridor projectas submitted by the Regional Transportation District.

BE IT FURTHER RESOLVED that the technology finding and other understandingsof resolution number 11, 2004 are not modified by this action and remain in effect.

RESOLVED, PASSED AND ADOPTED this /~ day of , 2008at Denver, Colorado.

(~~jncy McNally, ChairOBoard of Directors

Denver Regional Council of Governments

ATTEST:

utive Director

Page 143: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. , 2008

A RESOLUTION TO APPROVE THE MODIFICATION OF OTHER FASTRACKSCOMPONENTS.

WHEREAS, Senate Bill 90-208 (32-9-1 07.7 CRS), enacted by the Colorado GeneralAssembly, requires the Metropolitan Planning Organization (MPO) to approve the specifictechnology and method of financing of regional fixed guideway mass transit projectsproposed by the Regional Transportation District (RTD) before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments (DRCOG) is theMetropolitan Planning Organization for the Denver region and is responsible for theoperation and maintenance of a continuing, comprehensive transportation planningprocess, including the preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District submitted the FasTracks Plansystem, which includes the Denver Union Station improvements, maintenance facilities,and accessory items which serve the entire transit system as component parts, to DRCOGfor its review and approval pursuant to section 32-9-1 07.7 CRS; and

WHEREAS, the Board of Directors, on April 21, 2004, approved each componentpart and corridor of the FasTracks Plan in accordance with section 32-9-107.7 CRS,including these facilities and items in resolution number 17, 2004; and

WHEREAS, the Board of Director’s approval of the RTD FasTracks Plan onApril 21, 2004 was subject to a number of understandings, which include the conduct of anannual review through the MPO process to identify any substantial changes in variouselements of the FasTracks Plan and determine if further SB-208 action is required; and

WHEREAS, the RTD has described progress thus far on the FasTracks Plan andhas proposed certain changes in the document RTD 2007 Annual Report to DRCOG onFasTracks (December 2007, with Addenda and Errata dated May 1, 2008), which itsubmitted to DRCOG for review; and

WHEREAS, a public hearing was held March 19, 2008 to receive public comment onthe RTD 2007 Annual Report, including the other FasTracks components; and

Page 144: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE MODIFICATION OF THE OTHER FASTRACKSCOMPONENTSResolution No. 13 , 2008Page 2

WHEREAS, the RTD 2007 Annual Report included an updated Financial Plan that modifiesthe specific method of financing the commuter rail maintenance facility to be adesign/build/finance/operate/maintain public-private partnership; and

WHEREAS, review of the modifications identified in the RTD 2007 Annual Report,pursuant to the established process and public hearing, as presented in the DRCOG 2007Annual Fas Tracks Review and Determination Report, categorizes the proposed changes tothe Financial Plan as substantial and requiring new SB-208 action; and

WHEREAS, the review finds the updated Financial Plan, including the method offinancing the commuter rail maintenance facility, acceptable subject to the concerns notedin the companion Systems resolution; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe modification of the commuter rail maintenance facility project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted throughsection 32-9-107.7 CRS, the Board of Directors of the Denver Regional Council ofGovernments hereby approves the modified method of financing the commuter rail facilityproject as submitted by the Regional Transportation District.

BE IT FURTHER RESOLVED that the other findings and other understandings ofresolution number 17, 2004 are not modified by this action and remain in effect.

RESOLVED, PASSED AND ADOPTED this ~ 1 s1 day of , 2008at Denver, Colorado.

McNally, Ch~irBoard of Directors

Denver Regional Council of Governments

ATTEST:

Director

Page 145: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. j~/ , 2008

A RESOLUTION TO APPROVE MODIFICATIONS OF THE FASTRACKS SYSTEM.

WHEREAS, Senate Bill 90-208 (32~9-107.7 CRS), enacted by the Colorado GeneralAssembly, requires the Metropolitan Planning Organization (MPO) to approve the specifictechnology and method of financing of regional fixed guideway mass transit projectsproposed by the Regional Transportation District (RTD) before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments (DRCOG) is theMetropolitan Planning Organization for the Denver region and is responsible for theoperation and maintenance of a continuing, comprehensive transportation planningprocess, including the preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Govemments Board of Directors(hereafter “Board of Directors”) established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District submitted the FasTracks Plansystem to DRCOG for its review and approval pursuant to section 32-9-107.7 CRS; and

WHEREAS, the Board of Directors, on April ?1, 2004, approved each componentpart and corridor of the FasTracks Plan, as well as the system as a whole in resolutionnumber 18, 2004, pursuant to section 32-9-107.7 CRS; and

WHEREAS, the Board of Director’s approval of the RTD FasTracks Plan onApril 21, 2004 was subject to a number of understandings, which include the conduct of anannual review through the MPO process to identify any substantial changes in variouselements of the FasTracks Plan and determine if further SB-208 action is required; and

WHEREAS, the RTD has described progress thus far on the FasTracks Plan andhas proposed certain changes in the document RTD 2007 Annual Report to DRCOG onFas Tracks (December 2007, with Addenda and Errata dated May 1, 2008), which itsubmitted to DRCOG for review; and

WHEREAS, a public hearing was held March 19, 2008 to receive public comment onthe RTD 2007 Annual Report, including individual corridors and the system as a whole; and

WHEREAS, the RTD 2007 Annual Report included an updated Financial Plan thatincluded significant alternation of costs and revenues and also added a design/build!

• • finance/operate/maintain public-private partnership as a method of financing two corridors

and one maintenance facility; and

Page 146: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE MODIFICATiONS OF THE FASTRACKS SYSTEM.Resolution No. .J4[ , 2008Page 2

WHEREAS, review of the modifications identified in the RTD 2007 Annual Report.pursuant to the established process and public hearing, as presented in the DRCOG 2007Annual FasTracks Review and Determination Report, categorizes modifications in twocorridors and the updated Financial Plan as substantial and requiring new SB-208 action;and

WHEREAS, the Board of Directors has separately approved the two corridormodifications; and

WHEREAS, the review finds the Financial Plan acceptable, subject to the concernsspecified in the Report, and accepts the design/build/finance/operate/maintain publicprivate partnership as the method of financing for the East and Gold Line corridors and thecommuter rail maintenance facility; and

WHEREAS, the FasTracks system remains consistent with the intent of the MetroVision 2035 Plan, including its transportation element; and

WHEREAS, the Regional Transportation Committee has recommended theDRCOG 2007 Annual FasTracks Review and Determination Report and approval of theproposals requiring new SB-208 action.

NOW, THEREFORE, BE IT RESOLVED that the Board of Directors of the DenverRegional Council of Governments hereby accepts the findings of the DRCOG 2007Annual FasTracks Review and Determination Report.

BE IT FURTHER RESOLVED that, pursuant to authority granted through section32-9-107.7 CRS, the Board of Directors approves modification of the FasTracks system.

• BE IT FURTHER RESOLVED that the other understandings of resolution number18, 2004 are not modified by this action, and remain in effect.

• BE IT FURTHER RESOLVED that because there is a high degree of uncertainty in• the updated Financial Plan, this determination is made subject to the next Financial Plan

that RTD submits in the next annual report include less optimistic, more conservativeassumptions, unless actual FasTracks implementation bears out RTD’s assumptions.This specifically includes capital costs, New Starts revenues, sales and use tax estimates,

• • and cost and revenue benefits of public-private partnerships.

BE IT’ FURTHER RESOLVED that this determination is made subject to the nextannual report that RTD submits showing demonstrable progress on completingenvironmental studies and negotiating with the railroads.

Page 147: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE MODIFICATIONS OF THE FASTRACKS SYSTEM.Resolution No. 14 , 2008Page 3

RESOLVED, PASSED AND ADOPTED this ?/sl day of h4n~ , 2008at Denver, Colorado.

~a~. -

C..- ~Ø~cy McNally, Chair~‘≤oard of Directors

Denver Regional Council of Governments

ATTEST:

irector

Page 148: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 8 , 2004

A RESOLUTION TO APPROVE THE CENTRAL AND CENTRAL PLATTE VALLEYCORRIDOR ENHANCEMENTS TRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-107.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating to•construction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem, which includes the Central and Central Platte Valley Corridor Enhancementstransit project as a component part, to the Denver Regional Council of Governments for itsreview and approval pursuant to section 32-9-107.7 CRS; and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including the Central and Central Platte Valley CorridorEnhancements transit project; and

WHEREAS; following review of the proposed project pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found the Centraland Central Platte Valley Corridor Enhancements transit project (light rail improvementsand signal software as described in Table 1 of the DRCOG report Review of the RTDFasTracks Plan Final Report, dated April 21, 2004) to be consistent with the Metro Vision2020 Plan, including its transportation element; that the proposed technology, light railtransit, is appropriate for the corridor; that the FasTracks financial plan, which includes thisproject, is reasonable provided approval of a 0.4 percent increase in sales tax and TABORexemption; that all established criteria for regional fixed guideway transit projects have beenmet; and that no significant adverse environmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe Central and Central Platte Valley Corridor Enhancements transit project.

Page 149: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE CENTRAL AND CENTRAL PLATTE VALLEYCORRIDOR ENHANCEMENTS TRANSIT PROJECTResolution No. 8 , 2004Page 2

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governmentshereby approves the Central and Central Platte Valley Corridor Enhancements transitproject (light rail improvements and signal software as described in Table 1 of the DRCOGreport Review of the RTD FasTracks Plan Final Reijort, dated April 21, 2004), includingthe method of financing and technology, as submitted by the Regional TransportationDistrict.

BE IT FURTHER RESOLVED that this approval is made subject to the followingunderstandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(NEPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final Report, dated April 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmission and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomp~shed in all corridors will be adjusted according!y and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Report, dated April 21, 2004),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);

Page 150: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE CENTRAL AND CENTRAL PLATTE VALLEYCORRIDOR ENHANCEMENTS TRANSIT PROJECTResolution No. ~ , 2004Page 3

level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks PlanFinal Report. dated Arril 21, 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of theFasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the Central and Central Platte Valley Corridor Enhancements transit projectdoes not commit such funding.

RESOLVED, PASSED AND ADOPTED this 21st day of_ ______,2004at Denver, Colorado.

• __

Lorraine Anderson, ChairmanBoard of Directors

Denver Regional Council of Governments

ATTEST:

Betty McC~ty, Acting Exe utive Director

Page 151: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 9 , 2004

A RESOLUTION TO APPROVE THE US-36 CORRIDOR/LONGMONT EXTENSIONTRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-1 07.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem, which includes the US-36 Corridor/Longmont Extension transit project, to theDenver Regional Council of Governments for its review and approval pursuant to section32-9-107.7 CRS; and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including the US-36 Corridor/Longmont Extensionproject; and

WHEREAS, following review of the proposed project pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found the US-36Corridor/LongmOnt Extension transit project to be consistent with the Metro Vision 2020Plan, including its transportation element; that the proposed technologies, commuter railand Phase 1 bus improvements, are appropriate for the corridor; that the FasTracksfinancial plan, which includes this project, is reasonable provided approval of a 0.4 percentincrease in sales tax and TABOR exemption; that all established criteria for regional fixedguideway transit projects have been met; and that no significant adverse environmentalimpacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe US-36 Corridor/Longmont Extension transit project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governments

Page 152: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE US-36 CORRIDOR/LONGMONT EXTENSIONTRANSIT PROJECTResolution No. 0 , 2004Page 2

hereby approves the US-36 Corridor/Longmont Extension transit project (commuter railand Phase 1 bus improvements as described in Table 1 of the DRCOG report Review ofthe RTD FasTracks Plan Final ReDort, dated April 21. 2004) including the method offinancing and technology, as submitted by the Regional Transportation District.

BE IT FURTHER RESOLVED that funds for Phase 2 construction of stations andstation access improvements and partial funds for construction of bus lanes and bicycleimprovements are identified in the financing component of the FasTracks Plan and thatimplementation of bus rapid transit will be subsequently defined in the federalenvironmental process and approved as required by 32-9.107.7 CRS.

BE IT FURTHER RESOLVED that the above approvals are made subject to thefollowing understandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(NEPA) process, and that the revisions be presented through the MetropolitanPlanning Organization CM P0) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final Reiort dated April 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requirerQ,hm~c~nr~ ~nH r~nnrnv~! thrnnnh +hp MPQ oro~~ss ~nd• ~-,. • • l~ I~ - - — - - •

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Report dated April 21, 2004),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),

Page 153: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE US-36 CORRIDORILONGMONT EXTENSIONTRANSIT PROJECTResolution No. ~ , 2004Page 3

• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);• level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks PlanFinal Re~jorL dated AiriI 21, 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of theFasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the US-36 Corridor/Longmont Extension transit project does not commit suchfunding.

RESOLVED, PASSED AND ADOPTED this 21 st of April , 2004at Denver, Colorado.

/~j//~~

~_—~ I Lorraine Anderson, ChairmanBoard of Directors

Denver Regional Council of Governments

ATTEST:

Betty Director

Page 154: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 10 , 2004

A RESOLUTION TO APPROVE THE GOLD LINE TRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-107.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem, which includes the Gold Line as a corridor, to the Denver Regional Council ofGovernments for its review and approval pursuant to section 32-9-107.7 CRS; and

WHEREAS, a public hearing’was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including the Gold Line project; and

WHEREAS, following review of the proposed project pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found the GoldLine transit project to be consistent with the Ivietro Vision 2020 Plan, including rLstransportation element; that the proposed technology, light rail transit, is appropriate forthe corridor; that the FasTracks financial plan, which includes this project, is reasonableprovided approval of a 0.4 percent increase in sales tax and TABOR exemption; that allestablished criteria for regional fixed guideway transit projects have been met; and that nosignificant adverse environmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe Gold Line project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governmentshereby approves the Gold Line transit project, including the method of financing andtechnology, as submitted by the Regional Transportation District.

Page 155: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE GOLD LINE TRANSIT PROJECTResolution No. 1 p , 2004Page 2

BE IT FURTHER RESOLVED that this approva is made subject to the followingunderstandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(NEPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final Reøort. dated ADril 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmission and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Rejjort, dated April 21, 2004),plan and corridor costs (a-s defined in Tables 1 and 13),

• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);• level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks PlanFinal Re~jort, dated April 21, 2004, or that DRCOG. be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of theFasTracks Plan and preserves the ability to pursue planned highway improvements in

Page 156: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE GOLD LINE TRANSIT PROJECTResolution No. 1 0 , 2004Page 3

corridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the Gold Line transit project does not commit such funding.

RESOLVED, PASSED AND ADOPTED this 21 st day of ~-i 1 , 2004at Denver, Colorado.

orraine Anderson, ChairmanBoard of Directors

Denver Regional Council of Governments

ATTEST:

Betty utive Director

Page 157: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. — 11 , 2004

A RESOLUTION TO APPROVE THE EAST CORRIDOR TRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-1 07.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem, which includes the East Corridor transit project, to the Denver Regional Council ofGovernments for its review and approval pursuant to section 32-9-107.7 CRS; and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including the East Corridor transit project; and

WHEREAS, following review of the proposed project pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found the EastCorridor transit project to be consistent with the Metro Vision 2020 Plan, including itstransportation element; that the proposed technology, commuter rail, is appropriate for thecorridor; that the FasTracks financial plan, which includes this project, is reasonableprovided approval of a 0.4 percent increase in sales tax and TABOR exemption; that allestablished criteria for regional fixed guideway transit projects have been met; and that nosignificant adverse environmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe East Corridor transit project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governmentshereby approves the East Corridor transit project, including the method of financing andtechnology, as submitted by the Regional Transportation District.

Page 158: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE EAST CORRIDOR TRANSIT PROJECTResolution No. 11 , 2004Page 2

BE IT FURTHER RESOLVED that this approval is made subject to the followingunderstandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(NEPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final Report, dated April 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmissiOn and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Report, dated April 21, 2004),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);• level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks PlanFinal Report, dated April 21, 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of the

Page 159: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE EAST CORRIDOR TRANSIT PROJECTResolution No. ji , 2004Page 3

FasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the East Corridor transit project does not commit such funding.

RESOLVED, PASSED AND ADOPTED this 71 ~i- day of ~-~i i , 2004at Denver, Colorado~

ATTEST:

Lorraine Anderson, ChairmanBoard of Directors

Denver Regional Council of Governments

Betty McCqrtY~ Acting Ex~cutive Director

Page 160: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 12 , 2004

A RESOLUTION TO APPROVE THE WEST CORRIDOR TRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-107.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem, which includes the West Corridor transit project, to the Denver Regional Councilof Governments for its review and approval pursuant to section 32-9-107.7 CRS; and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including the West Corridor transit project; and

WHEREAS, following review of the proposed, project pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found the WestCorridor project to be consistent with the Metro Vision 2020 Plan, including itstransportation element; that the proposed technology, light rail transit, is appropriate forthe corridor; that the FasTracks fihancial plan, which includes this project, is reasonableprovided approval of a 0.4 percent increase in sales tax and TABOR exemption; that all

• established criteria for regional fixed guideway transit projects have been met; and that nosignificant adverse environmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe ‘West Corridor transit project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governmentshereby approves the West Corridor transit project, including the method of financing andtechnology, as submitted by the Regional Transportation District.

Page 161: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE WEST CORRIDOR TRANSIT PROJECTResolution No. 12 , 2004Page 2

BE IT FURTHER RESOLVED that this approval is made subject to the followingunderstandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(N EPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final Report, dated Airil 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmissiOn and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in the following items and that the DRCOG Board of Directorsrnake~a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Report, dated Anril 21, 2004),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);• level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks PlanFinal Re~~ort, dated ArriI 21, 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of the

Page 162: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE WEST CORRIDOR TRANSIT PROJECTResolution No. 12 , 2004Page3

FasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the West Corridor transit project does not commit such funding.

RESOLVED, PASSED AND ADOPTED this 21 stday of April , 2004at Denver, Colorado.

Lorraine Anderson, ChairmanBoard of Directors

Denver Regional Council of Governments

ATTEST:

Betty Director

Page 163: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 13 , 2004

A RESOLUTION TO APPROVE THE NORTH METRO CORRIDOR TRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-107.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transit•projects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem, which includes the North Metro Corridor transit project, to the Denver RegionalCouncil of Governments for its review and approval pursuant to section 32-9-107.7 CRS;and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including the North Metro Corridor transit project; and

WHEREAS, following review of the proposed project pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found the NorthMetro Corridor transit project to be consistent with the Metro Vision 2020 Plan, includingits transportation element; that the proposed technology, commuter rail, is acceptable forthe corridor; that the FasTracks financial plan, which includes this project, is reasonableprovided approval of a 0.4 percent increase in sales tax and TABOR exemption by thepublic; that all established criteria for regional fixed guideway transit projects have beenmet; and that no significant adverse environmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe North Metro Corridor transit project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governmentshereby approves the North Metro Corridor transit project, including the method of financingand technology, as submitted by the Regional Transportation District.

Page 164: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE NORTH METRO CORRIDOR TRANSIT PROJECTResolution No. 1 ~ , 2004Page 2

BE IT FURTHER RESOLVED that this approval is made subject to the followingunderstandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(NEPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final Report dated Alril 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmission and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that, prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes. in the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Report dated ADril 21, 2004),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);• level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks PlanFinal Report dated Arril 21, 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of the

Page 165: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE NORTH METRO CORRIDOR TRANSIT PROJECTResolution No. 1 3 , 2004Page 3

FasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the North Metro Corridor transit project does not commit such funding.

RESOLVED, PASSED AND ADOPTED this 21 stday of April , 2004at Denver, Colorado.

Lorraine Anderson, ChairmanBoard of Directors

Denver Regional Council of Governments

ATTEST:

Betty McCarI~’, Acting Exec~/~tive Director

Page 166: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 14 , 2004

A RESOLUTION TO APPROVE THE SOUTHWEST CORRIDOR ENHANCEMENTSTRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-107.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem, which includes the Southwest Corridor Enhancements transit project as acomponent part, to the Denver Regional Council of Governments for its review andapproval pursuant to section 32-9-107.7 CRS; and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including the Southwest Corridor Enhancements transitproject; and

WHEREAS, following review of the proposed project pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found theSouthwest Corridor Enhancements transit project to be consistent with the Metro Vision2020 Plan, including its transportation element; that the proposed technology, light railtransit, is appropriate for the corridor; that the FasTracks financial plan, which includes thisproject, is reasonable provided approval of a 0.4 percent increase in sales tax and TABORexemption; that all established criteria for regional fixed guideway transit projects havebeen met; and that no significant adverse environmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe Southwest Corridor Enhancements transit project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governmentshereby approves the Southwest Corridor Enhancements transit project (light rail extension

Page 167: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE SOUTHWEST CORRIDOR ENHANCEMENTSTRANSIT PROJECTResolution No. 1 4 , 2004D~ri

and upgrades as described in Table 1 of the DRCOG report Review of the RTD FasTracksPlan Final Report dated April 21, 2004) including the method of financing and technology,as submitted by the Regional Transportation District.

BE IT FURTHER RESOLVED that this approval is made subject to the followingunderstandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(NEPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final Report dated April 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmission and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Reiort dated Airil 21, 2004),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);• level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks Plan

Page 168: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE SOUTHWEST CORRIDOR ENHANCEMENTSLRANSIT PROJECTResOlution No. 1 ~ 2004Page 3

Final Report dated April 21, 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of theFasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the Southwest Corridor Enhancements transit project does not commit suchfunding.

RESOLVED, PASSED AND ADOPTED this 21 ~tday of ~-~i i , 2004at Denver, Colorado.

Lorraine Anderson, ChairmanBoard of Directors

Denver Regional Council of Governments

ATTEST:

Betty McCart~, Acting Execu~ive Director

Page 169: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 15 , 2004

A RESOLUTION TO APPROVE THE SOUTHEAST CORRIDOR ENHANCEMENTSTRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-107.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submiffed the FasTracks Plansystem, which includes the Southeast Corridor Enhancements transit project as acomponent part, to the Denver Regional Council of Governments for its review andapproval pursuant to section 32-9-107.7 CRS; and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including the Southeast Corridor Enhancements transitproject; and

WHEREAS, following review of the proposed project pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found theSoutheast Corridor Enhancements transit project to be consistent with the Metro Vision2020 Plan, including its transportation element; that the proposed technology, light railtransit, is appropriate for the corridor; that the FasTracks financial plan, which includes thisproject, is reasonable provided approval of a 0.4 percent increase in sales tax and TABORexemption; that all established criteria for regional fixed .guideway transit projects havebeen met; and that no significant adverse environmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommendedapproval ofthe Southeast Corridor Enhancements transit project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governmentshereby approves the Southeast Corridor Enhancements transit project (light rail extension

Page 170: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE SOUTHEAST CORRIDOR ENHANCEMENTSTRANSIT PROJECTResolution No. 1 5 , 2004Page2

and upgrades as described in Table 1 of the DRCOG Report Review of the RTDFasTracks Plan Final Report dated April 21, 2004), including the method of financing andtechnology, as submitted by the Regional Transportation District.

BE IT FURTHER RESOLVED that this approval is made subject to the followingunderstandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(NEPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final Report dated Arril 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmission and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Report dated Arril 21, 2004),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);• level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks Plan

Page 171: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE SOUTHEAST CORRIDOR ENHANCEMENTSTRANSIT PROJECTResolution No. 1 ~ , 2004Page3

Final Report dated April 21, 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of theFasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the Southeast Corridor Enhancements transit project does not commit suchfunding.

RESOLVED, PASSED AND ADOPTED this 21 st day of April , 2004at Denver, Colorado.

4~~raineAnderson,chai~r~Board of Directors

Denver Regional Council of Governments

ATTEST:

,jj~ 24(4~

Betty McCa[ty, Acting Exe~~utive Director

Page 172: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

~r F-’ r- F- /~ I F-~ I~ A ~~ I P~ I t ~jr LMLJ’~J

BOARD OF DIRECTORS RESOLUTION NO. 16 , 2004

A RESOLUTION TO APPROVE THE 1-225 CORRIDOR TRANSIT PROJECT.

WHEREAS, Senate Bill 90-208 (32-9-107.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem, which includes the 1-225 Corridor transit project (from Parker Road to the EastCorridor), to the Denver Regional Council of Governments for its review and approvalpursuant to section 32-9-107.7 CRS; and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including the 1-225 Corridor transit project; and

WHEREAS, following review of the proposed project pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found the i-225Corridor transit project to be consistent with the Metro Vision 2020 Plan, including itstransportation element; that the proposed technology, light rail transit, is appropriate forthe corridor; that the FasTracks financial plan, which includes this project, is reasonableprovided approval of a 0.4 percent increase in sales tax and TABOR exemption; that allestablished criteria for regional fixed guideway transit projects have been met; and that nosignificant adverse environmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe 1-225 Corridor transit project.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governmentshereby approves the 1-225 Corridor transit project (from Parker Road to the East Corridor),including the method of financing and technology, as submitted by the RegionalTransportation District.

Page 173: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE 1-225 CORRIDOR TRANSIT PROJECTResolution No. _j~_, 2004Page 2

BE IT FURTHER RESOLVED that this approval is made subject to the followingunderstandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(NEPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTrackS Plan Final Reiort. dated AIriI 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmissiOfl and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in. the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definitiOn/SCOPe (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Report, dated ADril 21, 20Q4),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);• level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks PlanFinal Report, dated April 21, 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

Page 174: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE 1-225 CORRIDOR TRANSIT PROJECTResolution No. 1 6 , 2004Page 3

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of theFasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the 1-225 Corridor transit project does not commit such funding.

RESOL~~’, PASSED AND ADOPTED this 21st day of Aprilat Denver, Colorado.

ATTEST:

2004

Betty McCart7, Acting Exec~ttive Director

ierson, ChairmanBoard of Directors

Denver Regionai Council of Governments

Page 175: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 17 , 2004

A RESOLUTION TO APPROVE THE OTHER FASTRACKS COMPONENTS.

WHEREAS, Senate Bill 90-208 (32-9-107.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit projects including specific criteria to be used in evaluating suchprojects; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem, which includes Denver Union Station improvements, maintenance facilities, andaccessory items which serve the entire transit system as component parts, to the DenverRegional Council of Governments for its review and approval pursuant to section 32-9-107.7 CRS; and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan, including these items and facilities; and

WHEREAS, following review of the proposed project pursuant to its establishedprocess and a public hearing on the project, the Board of Drectors has found these itemsand facilities to be consistent with the Metro Vision 2020 Plan, including its transportationelement; that they serve and support appropriate technologies; that the FasTracksfinancial plan, which includes these items and facilities, is reasonable provided approval ofa 0.4 percent increase in sales tax and TABOR exemption; that all established criteria forregional fixed guideway transit projects have been met; and that no significant adverseenvironmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthese items and facilities in its recommendation of the FasTracks Plan.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governmentshereby approves the Denver Union Station improvements, maintenance facilities and

Page 176: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE OTHER FASTRACKS COMPONENTSResolution No. 17 , 2004Page 2

other items as described in Table 1 of the DRCOG report A Review of the RTD FasTracksPlan Final Report dated April 21, 2004, including the method of financing andtechnologies, as submitted by the Regional Transportation District.

BE IT FURTHER RESOLVED that this approval is made subject to the followingunderstandings:

1. that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(N EPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final Report, dated April 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmission and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for cost overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTD~~i4 ~ ~

~4 ~ •,

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Report, dated April 21, 2004),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);. level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks Plan

Page 177: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE OTHER FASTRACKS COMPONENTSResolution No. 1 7 , 2004Page 3

Final Rerort. dated Arril 21. 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of theFasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of these facilities and items does not commit such funding.

RESOLVED, PASSED AND ADOPTED this 21 st day of April , 2004at Denver, Colorado.

Lorraine Anderson, ChairmanBoard of Directors

Denver Regional Council of Governments

ATTEST:

Betty McCarfr~ Acung Exe4utive Director

Page 178: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

DENVER REGIONAL COUNCIL OF GOVERNMENTS

STATE OF COLORADO

BOARD OF DIRECTORS RESOLUTION NO. 18 , 2004

A RESOLUTION TO APPROVE THE FASTRACKS SYSTEM.

WHEREAS, Senate Bill 90-208 (32-9-107.7, CRS), enacted by the ColoradoGeneral Assembly, requires the Metropolitan Planning Organization to approve thespecific technology and method of financing of regional fixed guideway mass transitprojects proposed by the Regional Transportation District before any action relating toconstruction may take place; and

WHEREAS, the Denver Regional Council of Governments is the MetropolitanPlanning Organization for the Denver region and is responsible for the operation andmaintenance of a continuing, comprehensive transportation planning process, includingthe preparation and adoption of transportation plans and programs; and

WHEREAS, the Denver Regional Council of Governments Board of Directors(hereafter “Board of Directors”) has established a process for the review of regional fixedguideway mass transit system proposals including specific criteria to be used in evaluatingsuch proposals; and

WHEREAS, the Regional Transportation District has submitted the FasTracks Plansystem to the Denver Regional Council of Governments for its review and approvalpursuant to section 32-9-107.7 CRS; and

WHEREAS, a public hearing was held on January 21, 2004 to receive publiccomment on the FasTracks Plan; and

WHEREAS, the Board of Directors has separately approved each component partand corridor of the FasTracks system in accordance with section 32-9-107.7 CRS; and

WHEREAS, following review of the FasTracks system pursuant to its establishedprocess and a public hearing on the project, the Board of Directors has found theFasTracks system to be consistent with the Metro Vision 2020 Plan, including itstransportation element; that the proposed technologies included in the system areacceptable or appropriate; that the FasTracks financial plan is reasonable providedapproval of a 0.4 percent increase in sales tax and TABOR exemption; that all establishedcriteria for a regional fixed guideway system have been met; and that no significantadverse environmental impacts are anticipated; and

WHEREAS, the Regional Transportation Committee has recommended approval ofthe FasTracks system.

NOW, THEREFORE, BE IT RESOLVED that, pursuant to authority granted through32-9-107.7, CRS, the Board of Directors of the Denver Regional Council of Governments

Page 179: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE FASTRACKS SYSTEM.Resolution No. 1 8 , 2004Page2

hereby approves the FasTracks system, including the method of financing and technology,as submitted by the Regional Transportation District.

BE IT FURTHER RESOLVED that this approval is made. subject to the followingunderstandings:

1 that the approval of the technology to be constructed for each individual corridor maybe modified only as required by the results of the National Environmental Policy Act(NEPA) process, and that the revisions be presented through the MetropolitanPlanning Organization (MPO) Process for approval prior to construction; and

2. that the final corridor improvements and operational plans should not significantlyincrease transit travel times without producing ridership gains; and

3. that this approval is limited to the financing plan submitted and scenarios as modeledand considered through this process which include a ballot measure for the 0.4% salestax increase and TABOR Exemption to be approved by the voters and federal fundingis received substantially consistent with the plan as submitted by RTD and reviewedthrough this process; (the scenarios further defined in Table 20 of the Review of theRTD FasTracks Plan Final ReDort, dated Arril 21, 2004); and that any significantfinancial alteration in the plan from the scenarios evaluated, would requireresubmission and reapproval through the MPO process; and

4. that if revenues are better or worse than expected, the construction to beaccomplished in all corridors will be adjusted accordingly and that prior to construction,a corridor risk assessment and value engineering will be conducted to optimizeopportunities for cost efficiencies and schedule acceleration and to minimize thepotential for co~t overruns and schedule delays; that this information shall be includedin the annual report to the MPO planning process described below, prior to any RTDBoard action; and

5. that an annual review will be conducted through the MPO process to identify anysubstantial changes in the following items and that the DRCOG Board of Directorsmake a determination if the changes are substantial and require further SB-208 action:• project definition/scope (defined in Table 1 of the Review of the RTD FasTracks

Plan Final Report, dated Airil 21, 2004),• plan and corridor costs (as defined in Tables 1 and 13),• revenue projections (as defined in Tables 18 and 19),• implementation schedule (as defined in Figure 4),• operating characteristics (as defined in Table 2 and Figure 3 for the year 2025, and

similarly as defined in the RTD submittal for the opening year);• level of bus service (as defined in Chapter VI); and

6. that RTD continue to maintain and increase bus service in the district as defined in theRTD submittal and summarized in Chapter VI of Review of the RTD FasTracks PlanFinal Rerort, dated ADril 21, 2004, or that DRCOG be notified of any significant changethat will deviate from this plan, prior to bus service plan changes being implemented,and

Page 180: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

A RESOLUTION TO APPROVE THE FASTRACKS SYSTEM.Resolution No. 1 8 , 2004Page 3

7. that RTD and CDOT implement the Master Intergovernmental Agreement (IGA)establishing a coordinated process which facilitates the implementation of theFasTracks Plan and preserves the ability to pursue planned highway improvements incorridors where both transit and highway improvements are identified in the regionalplan as likely to occur, and

8. that this action is taken solely pursuant to SB 90-208 and does not constitute anendorsement of a FasTracks ballot initiative.

BE IT FURTHER RESOLVED that, although potential federal funding provided byfunds made available to DRCOG for allocation is mentioned in the FasTracks Plan, theapproval of the FasTracks system does not commit such funding.

RESOLVED, PASSED AND ADOPTED this 21st day of April , 2004at Denver, Colorado.

Lorraine Anderson, ChairmanBoard of Directors

Denver Regional Council of Governments

ATTEST:

Betty McCa~/1Y~ Acting Ex~cutive Director

Page 181: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

April 3, 2012

Appendix B: 2011 Financial Plan Summary

Page 182: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

FASTRACKS\Models\GS Model - Deal\GS Model\31.0 - Revised APE 2009 For Board Adoption\2009 Financial Plan Documentation v3_GS2.doc Cohen, Susan 3 Apr 2012 14:22 1/26

Regional Transportation District FasTracks Financial Plan Update April 3, 2012

Page 183: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 1

Executive Summary

The Regional Transportation District (the “District” or “RTD”), has developed a comprehensive $7.4 billion plan (the Plan), known as “FasTracks,” which addresses mobility needs in the metropolitan Denver region. The $7.4 billion opening day cost is a revision from the originally estimated $4.7 billion (2004) opening day cost following updates to material, right-of-way, financing and labor cost estimates. The ability to implement the FasTracks plan depends on a variety of financial assumptions and projections which have been developed using the best available estimates of costs, reasonably anticipated federal funding based on current federal law and regulations, and revenues from other sources including RTD sales tax and fare collections. Over the anticipated remaining time-period until opening day (2022), specific cost items, federal and other contributions, and RTD revenues may vary from this financial plan. Based on the extensive analysis behind the financial assumptions used, RTD expects to deliver the major transit corridors and related improvements within the time frames set forth herein. RTD cannot guarantee that each separate assumption will be met, and expects that certain adjustments and modifications will be required prior to the expected opening day date of 2022. However, RTD is confident that we can complete the FasTracks program in accordance with our 2012 financial plan due to RTD’s efforts to reduce construction risk and manage future cost and revenue risk exposures, namely:

• 5 out of 12 FasTracks projects already under contract, with fixed budgets negotiated with contractors

• Most complex transit procurement in the country (Eagle Project) came in $305 million below internal cost estimates

• West Corridor is being completed on time and within budget • Engineering advanced to at least 30%, and “bottoms up” estimates complete for all rail

corridors • RTD uses conservative cost estimates and inflation rates • RTD conducts sensitivity analyses on sales and use tax forecasts to ensure the program can

still be completed on schedule. This report details the assumptions used and provides further explanation as to how RTD expects to pay for the FasTracks Plan. Unlike typical transit development strategies, which are pursued one corridor at a time and can take decades to accomplish, the FasTracks plan offers a comprehensive, region-wide approach to transit development. The FasTracks Plan consists of nine rail lines (new or extended); two bus rapid transit (BRT) lines; redevelopment of Denver Union Station (DUS); a new Commuter Rail Maintenance Facility (CRMF) and an expanded light rail maintenance facility. At opening day, the Plan will add approximately 64 miles of commuter rail (East Rail, Gold Line, North Metro Rail, and Northwest Rail – Phase 1 and 2); approximately 28 miles of light rail (Southeast Rail and Southwest Rail Line Extensions, Central Rail Line Extension, I-225, and West Rail Line); Park-n-Ride improvements and/or relocations at existing Park-n-Ride lots along US 36 (US 36 BRT – Phase 1), and up to 80 miles of BRT (US 36 BRT – Phase 2 and Northwest Corridor BRT). For all FasTracks corridors, future RTD Board of Directors action would be required prior to initiating construction. FasTracks rubber-tire service increases (bus and ADA) were determined based on forecasted demand and senior/ADA needs that were identified through the Eagle project Full Funding Grant Agreement (FFGA) process. The remainder of the Northwest Rail Line, 29 miles of DMU commuter rail, will be completed from Church Ranch Station to Downtown Longmont Station, as funding becomes available from the original 0.4% sales and use tax.

On an annual basis, through the Annual Program Evaluation (APE) process, RTD updates the FasTracks financial plan with new revenue and cost projections, reflecting ever-changing economic conditions. Each APE update to the financial plan projects capital, financing and operating costs for each of the corridors and projects in year of expenditure (YOE) dollars, and reflects the currently

Page 184: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 2

adopted FasTracks implementation schedule for each of the corridors. The current 2012 APE financial plan extends to the year 2035, and covers both the FasTracks program and the base public transit system and services provided by RTD. During the 2008 APE, RTD identified a funding gap for the FasTracks program as a result of rapidly escalating costs for commodities and materials on the world market, combined with the economic slowdown and the corresponding downward impact on current and forecast sales and use tax revenues. Over the past four years, RTD has worked closely with elected officials, local governments, corridor stakeholders and the public to identify how to move the FasTracks program forward, addressing these challenges. During this period, there have been significant fluctuations in commodity prices as a result of the current recession; however, these prices still remain higher than original forecasts. Additionally, there have been concurrent significant additional decreases in projected sales and use tax revenues. On December 6, 2011, staff presented the RTD Board of Directors with updated cost estimates for the Northwest Rail Line. The cost estimate represented a significant increase compared to costs assumed last year, and staff indicated at that time that completion of the Northwest Rail Line would likely have to be delayed to 2023 – 2025 to match RTD’s cash flow constraints. Subsequently, based on discussions with RTD’s stakeholders, on March 27, 2012, the RTD Board of Directors approved the following financial plan assumptions:

• Extending the Northwest Commuter Rail Line from DUS to the Church Ranch Station with revenue service commencing at a point between 2020 - 2022 to provide bi-directional peak service for commuters connecting to/from DUS;

• Completing the Northwest Rail Line incrementally or in its entirety from Church Ranch to Longmont, pending future action by the RTD Board of Directors, as funding becomes available from the original 0.4% sales and use tax. Funding is anticipated to be available to initiate construction and begin revenue service during the period of 2026 – 2032;

• Building up to 80 miles of BRT by 2020 that will provide cost effective, immediate relief/mobility improvements for the Northwest Corridor.

The 2012 FasTracks financial plan assumes the passage of 0.4% sales and use tax increase commencing in January 2013. This scenario results in an opening day for the FasTracks program of 2022, assuming current cost escalation and revenue growth forecasts. Should the Board choose not to seek a tax increase, or if a tax increase initiative is not approved by the voters, a revised, updated financial plan would be adopted by the Board at that time, recognizing the new opportunities and constraints that would exist. The FasTracks program is currently financed in part through a 0.4% regional sales and use tax approved by voters in November of 2004. If the initiative is placed on the ballot in 2012 and it passes, the total transit tax rate in the District will increase to 1.4% (i.e., 0.6% for the base system, 0.8% for FasTracks). The Plan anticipates a total of $1.3 billion in Federal New Start Grant funding, a Small Starts grant of $75M for the Southeast Corridor, and $202.6 million in other federal grant funding. Contributions from local jurisdictions benefiting from transit in an amount equal to 2.5% of eligible project costs are expected to yield 2.0% of total program costs or $144.5 million system-wide.

In an effort to reduce costs and risks and improve delivery of FasTracks, RTD is delivering a portion of its commuter rail projects (the Eagle Project) through a long-term Public-Private Partnership (PPP) agreement in which a private party will design, build, finance, operate and maintain projects on behalf of RTD. The Eagle Project, which includes the East and Gold Line Corridors, a commuter rail maintenance facility, and a short electrified segment of the Northwest Rail Corridor, is the largest PPP transit project in the United States. RTD has contracted with Denver Transit Partners (DTP) to design, build, and finance the initial construction of the projects, and to operate and maintain all project assets through the year 2044. Through this contract, RTD realized savings over its internally

Page 185: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 3

estimated construction costs, and established the basis for its operating and maintenance costs for the first 28 years of corridor operations. In 2010, RTD awarded the contract for the Eagle Project to DTP, and began construction of the project. In 2011, RTD received a Full Funding Grant Agreement (FFGA) from the Federal Transit Administration (FTA) in the amount of $1.03 billion for this project.

Table 1 summarizes the sources of funds expected to pay for the Plan’s $7.4 billion of project expenditures:

Table 1 FasTracks Estimated Capital Sources of Funds Through 2022

(Millions of Year of Expenditure Dollars)

Source Amount Percentage of

Total Cost Revenue Bond Proceeds $2,551.8 34.6% COPs Proceeds 251.5 3.4% TIFIA Loan Proceeds 280.0 3.8% Denver Union Station Note Proceeds 168.0 2.3% Pay-as-you-go Capital 1,857.0 25.2% Federal New Start Grants 1,339.1 18.1% Federal Small Starts Grants 75.0 1.0% Other Federal Grants 202.6 2.7% Local Match Funding 144.5 2.0% Other Local Funding¹ 26.1 0.4% Public-Private Partnerships 487.8 6.6% Total FasTracks Program Funding $7,383.4 100.0% ¹Other local funding includes state Senate Bill 1 and FASTER funding, City and County of Denver construction of the platform at the DIA station and outside reimbursements for other items outside the scope of the original FasTracks plan.

In order to accomplish the Plan, a voter-approved Taxpayer Bill of Rights (TABOR), authorization of $3.477 billion in principal and $7.129 billion in total debt service was requested and received in November, 2004. This initiative was passed by 58% of the voting population.

The current financial plan assumes the passage of an additional 0.4% sales and use tax increase commencing in January 2013 to fund the balance of the FasTracks program. As required by TABOR, the RTD Board of Directors would need a vote to place the question in front of the voters at a general election, and the voters would need to pass the ballot initiative. At that time, the Board would review the authorized debt limits and determine the additional debt authorization request to include in the ballot issue.

Page 186: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 4

The Financial Plan

1. Projected Capital Costs

RTD has proposed a $7.4 billion Plan designed to improve mobility and travel options in the metropolitan Denver region by 2022. Unlike the traditional corridor-by-corridor approach, RTD’s Plan allows local policy makers and voters to direct the agenda in terms of project delivery and funding options. The Plan responds to the projected increase in regional population to 4.4 million in 2035 from 2.8 million in 2010. The Plan will not only improve mobility and livability in the region, but will provide a needed economic stimulus.

The Plan includes nine rail lines (new or extended); two bus rapid transit (BRT) lines; redevelopment of Denver Union Station (DUS); a new Commuter Rail Maintenance Facility (CRMF) and an expanded light rail maintenance facility. At opening day, the Plan will add approximately 64 miles of commuter rail (East Rail, Gold Line, North Metro Rail, and Northwest Rail – Phase 1 and 2); approximately 28 miles of light rail (Southeast Rail and Southwest Rail Line Extensions, Central Rail Line Extension, I-225, and West Rail Line); Park-n-Ride improvements and/or relocations at existing Park-n-Ride lots along US 36 (US 36 BRT – Phase 1), and up to 80 miles of BRT (US 36 BRT – Phase 2 and Northwest Corridor BRT). For all FasTracks corridors, future RTD Board of Directors action would be required prior to initiating construction. FasTracks rubber-tire service increases (bus and ADA) were determined based on forecasted demand and senior/ADA needs that were identified through the Eagle project Full Funding Grant Agreement (FFGA) process. The 2012 project opening day costs in Table 2, expressed in year of expenditure (YOE) dollars, are approximately $2.7 billion (57%) higher than those in the original FasTracks financial plan presented to the voters in April 2004. The 2012 capital cost estimates were updated based on the most current information available on alignments, railroad issues, stations, facilities and planning/engineering progress. In addition, the costs reflect new unit rates based on current bid prices (metro area and nationally), and updated ROW estimates where applicable. On December 6, 2011, staff presented the RTD Board of Directors with updated cost estimates for the Northwest Rail Line. The cost estimate represented a significant increase compared to costs assumed last year, and staff indicated at that time that completion of the Northwest Rail Line would likely have to be delayed to 2023 – 2025 to match RTD’s cash flow constraints. Subsequently, based on discussions with RTD’s stakeholders, on March 27, 2012, the RTD Board of Directors approved the following financial plan assumptions:

• Extending the Northwest Commuter Rail Line from DUS to the Church Ranch Station with revenue service commencing at a point between 2020 - 2022 to provide bi-directional peak service for commuters connecting to/from DUS;

• Completing the Northwest Rail Line incrementally or in its entirety from Church Ranch to Longmont, pending future action by the RTD Board of Directors, as funding becomes available from the original 0.4% sales and use tax;

• Building up to 80 miles of BRT by 2020 that will provide cost effective, immediate relief/mobility improvements for the Northwest Corridor.

Other key factors for the overall increase in capital costs since 2004 include: (1) material, labor and ROW escalation which increased at a rate higher than the 2003-2008 Consumer Price Index (CPI) that was used as the FasTracks escalation factor; (2) changes with respect to stations and park-n-Rides; and (3) scope clarifications/changes.

Page 187: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 5

In order to obtain additional review of the key assumptions in the financial plan, RTD reconvened a working group of local government economists and financial experts to review its long-term sales and use tax forecasts and a group with experience on both national transit construction projects and local public works projects to review its construction escalation assumptions.

In 2011, RTD hired the Business Research Division of CU Leeds School of Business to develop third party sales and use tax forecasts. This resulted in a lower average annual growth rate assumptions for sales and use tax as part of the 2012 financial plan. The new methodology was reviewed with the Regional Sales and Use Tax Working Group on October 27, 2011, who determined that the methodology represented a reasonable approach for forecasting long-term growth in sales and use tax.

The Construction Inflation Workshop was held on November 1, 2011. Results of the Construction Inflation Workshop are generally consistent with the assumptions and methodologies used and approved by DRCOG as part of last year’s APE.

Table 2 summarizes the projected costs of the Plan by corridor:

Table 2 FasTracks Projected Costs by Project

(In Millions of Year of Expenditure Dollars)

Corridor 2012 APE West Corridor $684.3 Total Eagle Project Costs $2,185.0 I-225 Corridor $748.5 Northwest Rail Corridor (Phase 2 to Church Ranch) $396.0 Northwest Corridor BRT $894.6 North Metro Corridor $978.7 Central Corridor Extension $60.3 Southeast Corridor Extension $209.1 Southwest Corridor Extension $182.2 U.S. 36 BRT – Phase 1 $19.0 U.S. 36 BRT – Phase 2 $220.4 Denver Union Station $287.3 Light Rail Maintenance Facility $18.2 Downtown Denver Circulator $17.3 Other FasTracks Project Costs $482.5

Total FasTracks Program Costs $7,383.4

In identifying the scope for a potential sales and use tax election in 2012, RTD established a fiscally responsible approach that balances the immediate mobility needs of the region with the long-term affordability of building out the entire system. The new tax would complete North Metro, I-225, the Central, Southeast and Southwest Extensions, the Downtown Denver Circulator and Northwest BRT by 2020 and an extension of the Northwest Rail Line to the Church Ranch station by 2022. Assuming a successful sales and use tax election in 2012, this approach will allow RTD to address mobility needs across the region by opening day (2022), and will allow RTD to completely sunset the new sales and use tax earlier.

Page 188: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 6

Additionally, RTD remains committed to completing the Northwest Rail Line to Longmont, as included in the original 2004 plan, when funding becomes available from the original 0.4% sales and use tax. Completing the Northwest Rail Line when it is affordable will fulfill the voter approved 2004 FasTracks Plan.

The 2012 FasTracks Financial Plan currently assumes funding will be available to complete the Northwest Rail Line to Longmont starting in 2026 and completing in 2032. It is difficult to quantify the exact cost of the remainder of this corridor given the need to complete various negotiations and the uncertainties involved with projecting project costs this far into the future. However, to be consistent with RTD’s strategic approach of the past few years to use a conservative methodology for projecting costs and revenues, the agency is currently and conservatively projecting a cost of $830 million (Base Year costs)/$1.8 billion (Year of Expenditure costs) to complete the Northwest Rail Line from Church Ranch to Longmont by 2032.

Page 189: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 7

2. Non-Operating Revenues

Sales and Use Tax

Since inception, the primary funding source for RTD has been a sales and use tax imposed on transactions within RTD boundaries. Major events in the tax history are as follows:

• January 1, 1974: 0.5% sales and use tax established • May 1, 1983: tax was increased by 0.1% to 0.6% • January 1, 2005: tax was increased by 0.4%, to 1.0%.

The current tax generated revenues of $415.1 million in 2011.

Average annual sales and use tax growth from 1980 – 2002 was 6.3%. However, due to recent economic conditions, sales and use tax growth has declined significantly below this historic average, including negative growth in 2008 and 2009. In 2004, RTD projected sales and use tax revenues for the FasTracks program of $13.7 billion from 2005 – 2035. Current projections included in this financial plan reduce this projection from $13.7 billion to $8.0 billion. This decrease in projected revenues over time has a significant impact on the FasTracks plan.

Table 3 Growth in Sales and Use Tax Revenues

1992 – 2011 (Dollars in Thousands)

Fiscal Year Tax Rate Sales and Use Tax Revenues

Percentage Growth

1992 0.6% $108,389 1993 0.6% 121,611 12.20% 1994 0.6% 134,431 10.54% 1995 0.6% 142,214 5.79% 1996 0.6% 153,807 8.15% 1997 0.6% 164,565 6.99% 1998 0.6% 179,990 9.37% 1999 0.6% 202,303 12.40% 2000 0.6% 224,182 10.81% 2001 0.6% 224,648 0.21% 2002 0.6% 213,668 (4.89%) 2003 0.6% 210,447 (1.51%) 2004 0.6% 221,276 5.15% 2005 1.0% 386,427 74.64% 2006 1.0% 399,558 3.40% 2007 1.0% 418,407 4.72% 2008 1.0% 412,824 (1.33%) 2009 1.0% 371,405 (10.03%) 2010 1.0% 397,669 7.07% 2011 1.0% 415,137 4.42%

Page 190: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 8

The RTD Board of Directors has adopted a financial plan scenario for the 2012 FasTracks Annual Program Evaluation that assumes the passage of 0.4% sales and use tax increase effective on January 1, 2013. This scenario results in the completion of all corridors in the FasTracks program except Northwest Rail by 2020, and completion of Northwest Rail to Church Ranch by 2022, assuming current cost escalation and revenue growth forecasts. Figure 1 demonstrates the projected cash flow for the FasTracks program assuming an additional 0.4% sales tax increase:

Figure 1

Projected FasTracks Cash Flow 2005-2035

(Dollars in Thousands)

The FasTracks program is currently financed in part through a 0.4% increase in the regional sales and use tax approved by voters in November of 2004. If a second initiative is placed on the ballot, and it passes, the total transit tax rate in the District will increase to 1.4% (i.e., 0.6% for the base system, 0.8% for FasTracks). RTD has contracted with the Business Research Division (BRD) of the Leeds School of Business at the University of Colorado to provide sales and use tax forecasts. The Leeds models use variable autoregression techniques to address short-term, medium-term, and long-term planning horizons, which are one-year, six-year, and thirty-year forecasts.

All three models consist of dynamic equations that link RTD district retail sales and sales and use tax revenues to underlying national and state economic indicators. The long-term model also incorporates age shares of the population as a key factor influencing the rate of growth in real output. Forecasts of the national indicators that are needed to drive the state and district forecasts come from Moody’s Analytics. Population projections that enter the equations of the long-term model come from the U.S. Bureau of the Census and the Colorado Demography Office. Colorado economy forecasts are derived from the Colorado Economy Model that was developed by members of the BRD team for the Colorado Office of State Planning and Budget (OSPB).

Starting in late 2009, RTD has convened a group of State and local government economic advisors and financial experts to review RTD’s current forecasting methodology; evaluate potential forecasting

Page 191: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 9

methodologies; and obtain consensus on a future forecasting method. A representative of this group participated in the selection of BRD to perform RTD’s sales tax forecasts, and the group as a whole reviewed the BRD forecasts in October 2011.

The BRD forecasts project an average annual growth rate of 3.39% in sales and use tax collections for the financial plan period 2005-2035. The average annual growth rate for the period 2012-2035, or the future years of the financial plan, is projected at 3.89%. Forecasted rates of increase vary by year, and the forecasted annual growth rates by year for the period 2005-2035 are shown in Figure 2 below. Between October 2009 and June 2011, the State of Colorado waived the 3 1/3% allowance paid to vendors to collect RTD sales tax. This resulted in a boost to RTD sales tax revenues over that period. This was reduced to a waiver of 1/3 of the allowance between July 2011 and June 2014, with the full vendor allowance being restored in July 2014.

Figure 2 Projected Sales and Use Tax Growth

2005-2035

Local Contributions

Beginning with the Central Platte Valley and the Southeast Corridor project, RTD has established a policy of requiring a portion of major project costs to be paid by local jurisdictions.

Page 192: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 10

This Plan assumes that this policy will continue and that RTD’s jurisdictions will contribute an amount in aggregate equal to 2.5% of the eligible corridor capital costs, which equates to 2.0% of total project capital costs. On a plan-wide basis, the amount of this contribution is estimated to total $144.5 million.

The source of funding for the local contribution is at the discretion of each local jurisdiction. Local contributions can consist of right-of-way dedications, permit fee waivers, cash contributions, corridor utility relocations as well as any other direct, project-related corridor contributions. Generally throughout the system, the financial benefit to the jurisdiction comes from increases in the real property assessed valuations, enhanced development potential, reduced travel times and improved congestion that accrue to the local communities.

On February 17, 2004, the RTD Board of Directors approved a resolution entitled “Regarding Board Commitments for FasTracks (Hold Harmless)”. This action confirmed RTD’s commitment to build each corridor’s specific list of corridor improvements consistent with and as described in the FasTracks Plan and within the fiscal constraints and schedule of the Plan subject to the completion of the environmental process and conformity with any federal Record of Decision for a corridor. The Hold Harmless resolution formalizes RTD’s commitment to analyze the Plan annually to determine current revenue projections from both local and federal sources. The resolution states, “If RTD revenues are better or worse than expected then all the corridors will be adjusted accordingly.”

Additionally, the Hold Harmless resolution commits "that prior to construction, a corridor cost risk assessment and value engineering (will) be conducted to minimize the potential for cost overruns and schedule delays.” Based on honoring both key tenets of the Hold Harmless resolution, modifications to individual corridor project elements, service plans, and schedules may be necessary for all FasTracks corridors. This may be necessary so as to not impact the scheduled construction and operation of the remaining FasTracks corridors, thereby "holding harmless" those corridors. This information will be reported annually to the general public.

Lastly, the Hold Harmless resolution includes: “Construction of FasTracks committed improvements within a corridor will not start until there is a firm commitment of all required funding sources, be they private, local-match or federal monies and intergovernmental agreements are in place with local governments concerning permits, design and plan review process for timely implementation.”

Over the past three years, RTD has worked closely with elected officials, local governments, corridor stakeholders and the public to identify how to move the FasTracks program forward in a manner that is consistent with the Hold Harmless resolution. Consensus from the stakeholders is that building the entire program as soon as possible, and finding additional revenues to fill the gap (as assumed in this financial plan) is consistent with the Hold Harmless resolution.

Federal Funding

The existing Southwest and the Southeast corridor projects were completed with assistance from the Federal Transit Administration in the form of New Start Grant funds. Under federal procedures, once a project is qualified for funding, the FTA enters into a “Full Funding Grant Agreement” (FFGA). The FFGA sets a maximum federal contribution and the percentage of federal funding. For the Southwest Corridor, the federal New Start percentage was 68% and for the Southeast the federal percentage was 60% of the project costs.

In January of 2009, RTD received a FFGA for the West Corridor project in the amount of $308.7 million. As of 2011, the full FFGA amount of $308.7 million in New Starts funds has been appropriated for the West Corridor.

In August 2011, RTD received a FFGA for the Eagle project in the amount of $1.03 billion. As of 2011, a total of $84.5 million had been appropriated for the Eagle project. The projected 2012 appropriation for the Eagle project is $140.9 million. Future appropriations for the Eagle project are expected to extend through 2018.

Page 193: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 11

The total amount of Federal funding in the Plan assumes $1.3 billion in Federal New Start Grant funds, $75 million in Small Starts funds, and $202.6 million of other federal grant revenues. The Plan includes the existing FFGAs for the West Corridor and the Eagle Project. Additionally, the plan assumes that one corridor, the Southeast Corridor Extension, will receive a federal Small Starts grant. Of the $202.6 million of other federal grants, the Plan assumes approximately $10 million in Future Surface Transportation Reauthorization grants, $83.5 million in federal flexible (CMAQ) dollars, and $61.3 million in SAFETEA-LU earmarked funds between years 2008 and 2018, consistent with the DRCOG 2008-2013 TIP allocation, and with current conservative RTD projections of reductions in the level of future discretionary grant programs. The Plan also assumes $0.4 million in Homeland Security grants.

The Plan also includes $47.4 million in American Recovery and Reinvestment Act (ARRA) funds, which includes $28.4 for DUS, $7.6 million for US 36 BRT Phase 2, $8.8 million for West Corridor CNPA, and $2.6 million for corridor enhancements. These funds were appropriated in 2009 and will be spent in full by 2014.

In the future, RTD has the option to request federal participation in other FasTracks corridors. Future transportation funding reauthorizations are subject to Congressional discretion. Historically the minimum statutory local match has been 20%; recently, the practical match for New Starts projects has been 40 – 50%.

Interest Earnings

RTD issued $600 million in sales tax revenue bonds and $379.1 million in sales tax revenue bonds in 2006 and 2010, respectively. The Plan calls for additional debt issuances in 2016 and 2021. The Plan assumes investment income on bond proceeds until they are spent down, as well as on debt service reserves and other unspent cash balances. The annual rate of return on future RTD investments is assumed to be range between 1.50% and 3%.

Between 2005 and 2022, investment earnings are projected to total $363.5 million.

3. Operating Revenues

Farebox Revenues: Base System

Base system farebox revenues were based on the forecast contained in RTD’s 2012 Adopted Budget, which includes a fare increase that was implemented on January 1, 2011. Farebox revenue forecasts for the base system for the years 2012-2035 assumed growth based on population growth, service growth and the change in the consumer price index (CPI). Farebox revenues were assumed to increase with improvements in productivity of base system bus service between the years 2020 and 2035, consistent with the regional travel forecasts. Additional increases were tied to increases in service, with farebox revenue assumed to increase at 75% of the system wide average revenue per service hour with each increased hour of bus service provided. These adjustments were initially applied in constant 2012 dollars.

RTD fiscal policies state that RTD’s six-year Strategic Business Plan (SBP) includes periodic fare increases to permit fare revenues to keep pace with cost increases, as measured by the Denver-Boulder Consumer Price Index (CPI-U). RTD’s most recent fare increase was implemented on January 1, 2011. The farebox revenue forecasts in the Plan assume that the next fare increase will be implemented in 2014, and that CPI-based fare increases will be implemented every third year after 2014. Table 4 shows the projected RTD fare increase percentages from 2014 – 2035:

Page 194: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 12

Table 4 RTD Fare Increase Percentage

2012-2035 Year Fare Increase 2014 10.80% 2017 9.20% 2020 8.50% 2023 8.60% 2026 8.40% 2029 8.00% 2032 7.50% 2035 6.90%

Farebox Revenues: FasTracks System For the FasTracks corridors, RTD prepares travel forecasts for the horizon years 2020 and 2035. These forecasts are provided at the station level and assume the full build-out of the FasTracks rapid transit system. RTD combined the construction schedule with the forecasts; with passenger fare revenues starting at the time the corridors are assumed to open to revenue service per the construction schedule.

Existing average fares paid by class of service are applied to the ridership forecasts for each corridor in constant 2010 dollars. Based upon the forecast boardings by station, RTD can estimate the percentages of riders on each corridor that are expected to be paying local, express, regional, and skyRide fares. Table 5 shows the 2010 average fare paid by class of service.

Table 5 RTD Average Fare by Service Class

(2010 Dollars) Service Class Average Fare Paid

Local $0.96 Express 2.53 Regional 3.28 skyRide 4.61

Light Rail 0.83

Applying the average fare paid by service class to the forecast boardings by station and distance from downtown Denver, average fares per boarding were generated for each corridor as shown in Table 6:

Page 195: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 13

Table 6 FasTracks

Average Fare Paid by Corridor Segment (2010 Dollars)

Corridor Segment Average Fare Per

Boarding Central $0.43 Southwest 0.84 Southwest Extension 1.16 Central Platte Valley 0.43 Southeast 1.09 Southeast Extension 1.51 West 0.68 Northwest Rail 0.43 U.S. 36 BRT 1.51 East 1.05 Central Corridor Extension 0.43 I-225 0.83 North Metro 1.20 Gold Line 0.61

The travel forecasting model produces daily ridership estimates. The fare recovery rates were applied, and then the daily fare totals annualized to produce annual fare revenue forecasts for each corridor. The annualization factors of 307 for rail and 257 for bus are based on RTD actual operating statistics and fare revenues.

The initial farebox revenue projections were developed in constant year dollars, and adjusted to incorporate fare increases to keep pace with inflation. Fare increases for the FasTracks system are assumed to occur on the same schedule as those for the base system, with future fare increases in every third year starting in 2014. The average fare paid for FasTracks corridors also is assumed to increase at the same rate as for the base system, with fare increases ranging from 6.9% to 10.8%.

Parking Revenues

In 2006 and 2007, the Colorado General Assembly passed legislation allowing RTD to charge for parking at its park-n-Ride lots. According to the legislation, RTD is allowed to allocate a fixed percentage of spaces in each park-n-Ride lot to be reserved for fee-paying users. Fees are charged to patrons who park at park-n-Ride lots for over 24 hours or non-residents of RTD. The legislation also allows different parking rates for District residents and non-residents.

RTD developed a parking revenue model incorporating the provisions of the legislation, as well as reasonable assumptions on parking demand and administrative costs. The model assumes that:

• Residents of RTD are not charged a fee for parking on a daily basis for first-come-first-served spaces.

• 12-13% of residents would opt to pay into a program that offers reserved spaces close to boarding areas and that the price for this would be $20 per month (per 22 working days).

Page 196: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 14

• Non-residents will be charged $4.00 per day for first-come-first-served spaces and $40 to $50 per month for reserved spaces, depending on circumstances (location, demand, etc.).

• Charges for overnight parking for the East Corridor at a rate of $2.00 per 24 hours for residents and $4.00 for 24 hours for non-residents.

RTD implemented the Parking Management Program in stages over the first half of 2009. Forecast revenues in the 2010 Amended Budget were $411,000 for the first full year of operation. By 2035, the Parking Management Program is forecasted to generate a total of $8.7 million annually; $1.0 million allocated to FasTracks and $7.7 million allocated to the base system.

4. Operating Expenditures

Operating and non-operating revenues were applied to the payment of operating and capital expenditures. Operating expenditures are a major component of the Plan, which ensures that adequate funding is available to cover the cost of operating and maintaining the base and FasTracks systems once initial construction is complete. RTD developed operating expenditure projections based on past experience and expectations of future ridership, schedules, renewal and replacement, labor and general maintenance, all adjusted for inflation. RTD’s 2010 operating expenditures totaled $389.3 million and the Plan projects operating expenditures to increase to $1.164 billion by 2035 after full implementation of FasTracks.

RTD’s estimated operating expenditures are illustrated in the following figure. Included in these estimates are the operating portion of the service payment the District will make under the Concession Agreement with Denver Transit Partners relating to private operating expenditures for the Eagle Project, as discussed in greater detail in Section 6.

Figure 3 Projected Operating Expenditures

2005-2035 (Dollars in Millions)

¹ FasTracks O&M Includes the operating portion of the service payment the District will make under the Concession Agreement with Denver Transit Partners for the Eagle Project

Page 197: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 15

5. Debt Financing

Financing a major project over a relatively short construction period requires significant expense to service debt and lease purchase financing. Historically, RTD has utilized two primary financing techniques: Sales Tax Revenue Bonds and Certificates of Participation (COPs).

As of December 31, 2010, RTD had $261.1 million in sales tax bonds outstanding for the base system and $977.6 million in sales tax bonds outstanding for the FasTracks program. In August 2001, a commercial paper program secured by sales tax revenues on a junior lien to the fixed rate sales tax bonds was implemented in the amount of $118.5 million to provide bridge financing for the T-REX project. Commercial paper in the amount of $92.5 million was actually issued, and was repaid in full as of November, 2010.

Sales Tax Revenue Bonds

Sales tax revenue bonds are the “backbone” of RTD’s financing program. This is because senior lien sales tax bonds provide the strongest security, and thus lowest long-term borrowing costs to RTD.

To date, RTD has issued $979.1 million in sales tax revenue bonds to fund capital investments in the FasTracks program. Additional sales tax revenue bond issues totaling $1.84 billion are projected to be issued in accordance with the schedule in Table 7:

Table 7 FasTracks Senior Lien Sales Tax Bond

Issuances Through 2022 (Dollars in Thousands)

Year Par Amount 2006A $600,000 20101 379,140 2015 (Future) 768,470 2018 (Future) 1,066,920 Total for FasTracks $2,814,530

Prior Issues 979,140 Future Issues 1,835,390

1 These bonds were issued as Build America Bonds.

Bonds are assumed to be issued on a fixed rate basis, but this is not required. A TIC (True Interest Cost) of 5.85% is assumed for future issuances, which reflects an interest rate of 125 basis points over the 10-year historical estimated financing cost for RTD. The 10-year historical estimated financing cost for RTD is based upon the average of the 30-year MMD Index (4.60%), which is roughly 146 basis points higher than the current 30-year MMD Index (3.14% as of January 31, 2012). For Plan purposes, all bonds are assumed to be issued on June 1 of their respective years of issuance. The Series 2015 and 2018 issuances each have 30-year final maturities. The bonds are amortized to comply with all required bond covenants and TABOR requirements as well as RTD’s minimum net 1.20x debt service coverage policy.

In addition to the bonds required to meet the initial obligations under the plan, it is anticipated that RTD would issue an additional $1.38 billion in sales tax bonds in 2030 to finance the completion of

Page 198: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 16

the Northwest Rail line to Longmont. These bonds would be backed by the original 04% FasTracks sales and use tax. At the same time, RTD would use available accumulated revenues over expenditures to call the Series 2015 and Series 2018 issuances prior to maturity, after 10 years outstanding. All calls are assumed to be made at 101% of principal, with the longest-maturity bonds eligible for call being called first.

Table 8 shows the debt service requirements for the existing bonds, and estimated debt service requirements through 2035 for the future projected bonds, assuming that bonds are called when cash flow permits. Table 9 shows the debt service requirements for all bonds, assuming no calls.

Table 8 Sales Tax Revenue Bonds

Existing and Projected Debt Service Requirements – Assuming Calls (Dollars in Thousands)

Year

Existing Bonds Future Debt Service (Estimated)

Total Debt Service

Base System

FasTracks System

Existing and New

Tax

Existing Tax Only Bond Calls

2011 $35,444 $48,206 $- $- $- $83,650 2012 35,443 49,515 - - - 84,958 2013 28,772 49,515 - - - 78,287 2014 28,773 49,515 - - - 78,288 2015 28,772 49,519 18,731 - - 97,022 2016 28,769 49,516 44,955 - - 123,240 2017 28,627 49,517 44,955 - - 123,099 2018 28,381 49,518 70,962 - - 148,861 2019 28,385 49,517 107,370 - - 185,272 2020 28,384 49,516 107,370 - - 185,270 2021 22,896 49,518 107,370 - - 179,784 2022 9,584 49,517 107,370 - - 166,471 2023 9,582 49,515 107,370 - - 166,467 2024 9,588 49,516 107,370 - - 166,474 2025 - 49,516 107,370 - - 156,886 2026 - 49,519 107,370 - 776,155 933,044 2027 - 97,330 80,960 - - 178,290 2028 - 97,329 80,960 - - 178,289 2029 - 97,332 80,957 - - 178,289 2030 - 97,332 80,956 33,705 - 211,993 2031 - 97,335 80,955 80,891 145,344 404,525 2032 - 97,335 72,535 80,891 137,395 388,156 2033 - 97,331 64,586 80,891 241,688 484,496 2034 - 97,332 50,581 80,891 145,586 374,390 2035 - 97,334 42,149 80,891 193,698 414,072 Total $351,400 $1,666,945 $1,673,202 $438,160 $1,639,866 $5,769,573

Page 199: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 17

Table 9 Sales Tax Revenue Bonds

Existing and Projected Debt Service Requirements (Dollars in Thousands)

Year

Existing Bonds Future D/S(Estimated)

Total Debt Service

Base System

FasTracksSystem

Existing and New

Tax Existing Tax Only

2011 $35,444 $48,206 $- $- $83,650 2012 35,443 49,515 - - 84,958 2013 28,772 49,515 - - 78,287 2014 28,773 49,515 - - 78,288 2015 28,772 49,519 18,731 - 97,022 2016 28,769 49,516 44,955 - 123,240 2017 28,627 49,517 44,955 - 123,099 2018 28,381 49,518 70,962 - 148,861 2019 28,385 49,517 107,370 - 185,272 2020 28,384 49,516 107,370 - 185,270 2021 22,896 49,518 107,370 - 179,784 2022 9,584 49,517 107,370 - 166,471 2023 9,582 49,515 107,370 - 166,467 2024 9,588 49,516 107,370 - 166,474 2025 - 49,516 107,370 - 156,886 2026 - 49,519 107,370 - 156,889 2027 - 97,330 125,915 - 223,245 2028 - 97,329 125,915 - 223,244 2029 - 97,332 125,912 - 223,244 2030 - 97,332 125,912 33,705 256,949 2031 - 97,335 125,910 80,891 304,136 2032 - 97,335 125,909 80,891 304,135 2033 - 97,331 125,918 80,891 304,140 2034 - 97,332 125,912 80,891 304,135 2035 - 97,334 125,912 80,891 304,137 Total $351,400 $1,666,945 $2,171,778 $438,160 $4,628,283

Denver Union Station Bond

In July 2010, RTD issued a $168 million, 30-year, subordinate lien bond to the Denver Union Station Project Authority (DUSPA) to finance a portion of the RTD contribution to the Denver Union Station project. Under this bond agreement, RTD will provide DUSPA with a 30-year cash flow of $12 million per year, structured as a fixed-rate bond with an interest rate of 5.85% on the RTD funds. This bond is amortized to comply with all required bond covenants and TABOR requirements as well as RTD’s minimum net 1.20x debt service coverage policy.

Page 200: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 18

As of December 31, 2010, $166.8 million in principal was outstanding. Table 10 shows the debt service by year on the DUSPA bond through 2035.

Table 10 DUSPA Bond Debt Service

(Dollars in Thousands) Year Total Debt Service

2011 12,006 2012 12,006 2013 12,006 2014 12,006 2015 12,006

2016 12,006 2017 12,006 2018 12,006 2019 12,006 2020 12,006

2021 12,006 2022 12,006 2023 12,006 2024 12,006 2025 12,006

2026 12,006 2027 12,006 2028 12,006 2029 12,006 2030 12,006

2031 12,006 2032 12,006 2033 12,006 2034 12,006 2035 12,006

Total $300,162

Certificates of Participation (COPs)

RTD has used COP financing, which is a form of lease purchase transactions for financing buses and rail vehicles. COPs are not secured by sales tax revenues, but are secured by the underlying leased asset and backed by RTD’s commitment to appropriate payments in future annual budgets. As of December 31, 2010, RTD had $274.9 million in outstanding COPs for the base system and $282 million in COPs outstanding for the FasTracks program.

RTD issued the Series 2005A COPs totaling $81.0 million in par amount to finance initial FasTracks expenditures related to the West Corridor. In November 2010, RTD issued $312.9 million in COPs to fund capital investments on both the base and FasTracks systems. FasTracks investments funded

Page 201: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 19

from the Series 2010 COPs issue included the purchase of light rail vehicles and the construction of station parking facilities. In addition to the COPs issued for the FasTracks program, the Plan assumes the issuance of approximately $947 million in COPs to fund base system capital expenditures. COP lease payments are not covered by TABOR restrictions.

Future COP issuances related to the Plan are shown in Table 11:

Table 11 RTD Future COP Issuances

(Dollars in Thousands)

Year Base

System FasTracks

System Total

2011 $- $- $- 2012 28,530 - 28,530 2013 68,460 - 68,460 2014 89,240 - 89,240 2015 86,225 - 86,225 2016 14,990 - 14,990 2017 - - - 2018 68,825 - 68,825 2019 76,795 - 76,795 2020 31,135 - 31,135 2021 - - - 2022 - - - 2023 20,340 - 20,340 2024 72,740 - 72,740 2025 104,550 - 104,550 2026 124,460 - 124,460 2027 - - - 2028 - - - 2029 - - - 2030 160,290 - 160,290 2031 - - - 2032 - - - 2033 - - - 2034 - - - 2035 - - - Total $946,580 $- $946,580

Table 12 shows the lease payment requirements for RTD’s outstanding COPs, and estimated lease payment requirements through 2035 for the future projected COPs:

Page 202: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 20

Table 12 Certificates of Participation

Existing and Projected Lease Payment Requirements (Dollars in Thousands)

Year Existing

COPs

Future COPs

(Estimated) Total Lease

Payment

2011 $54,928 $- $54,928 2012 57,025 749 57,774 2013 52,932 3,589 56,521 2014 54,498 8,267 62,765 2015 45,249 13,117 58,366 2016 45,245 18,252 63,497 2017 40,341 18,649 58,990 2018 44,874 27,553 72,427 2019 44,869 41,152 86,021 2020 52,066 54,749 106,815 2021 52,062 60,665 112,727 2022 48,550 66,073 114,623 2023 34,492 68,779 103,271 2024 34,487 72,632 107,119 2025 34,489 75,572 110,061 2026 21,215 77,472 98,687 2027 21,213 67,131 88,344 2028 21,216 62,032 83,248 2029 21,216 59,946 81,162 2030 21,212 64,138 85,350 2031 21,216 68,540 89,756 2032 21,178 58,011 79,189 2033 21,187 53,720 74,907 2034 21,196 53,723 74,919 2035 21,208 53,725 74,933 Total $908,164 $1,148,236 $2,056,400

Commercial Paper

The Commercial Paper (CP) Market allows RTD to provide short-term, interim financing to provide a bridge for federal appropriations and thus keep the project on schedule. Of the $118.5 million authorized CP, $92.5 million was actually issued. The full amount was retired as of November, 2010, and RTD has no outstanding CP at this time. Currently the Plan does not include future use of the Commercial Paper Market.

Page 203: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 21

TIFIA

TIFIA, or the Transportation Infrastructure Finance and Innovation Act of 1998, provides a source of project financing to eligible projects. Under the provisions of TIFIA, the U.S. DOT can provide direct loans, credit enhancement or lines of credit. Eligible projects must meet the following federal criteria:

Project cost must be at least $50 million

TIFIA support is limited to 33% of project costs

Project adheres to federal project requirements (labor, civil rights, etc.)

Repayment must be from project revenues or non-federal sources

Project senior debt must be investment grade

The Denver Union Station Project Authority has secured a $155 million loan from TIFIA to finance a portion of the Denver Union Station project. This TIFIA loan is not an RTD obligation, and is therefore not represented in the 2011 financial plan.

On December 1, 2011, RTD closed on a TIFIA loan for up to $280 million of the local share of the Eagle Project, at a locked-in interest rate of 3.14%. The terms of the loan allow RTD to draw funds and begin accruing interest when the funds are needed to meet the construction schedule, and to defer repayment until five years after the project is open for operations. RTD also has the option to refinance the loan at any time, or to prepay any or all of the outstanding principal amount at par at any time. Based on the projected construction draw and repayment schedule, it is estimated that RTD saved $164 million on a present value basis over the cost of executing the same financing in the current bond market at the time of closing.

Table 13 shows the projected construction draw schedule for the TIFIA loan, and Table 14 shows the debt service by year on the TIFIA loan through 2035. The TIFIA loan is projected to be repaid in full by 2045.

Table 13 EAGLE TIFIA Loan Construction Draws

(Dollars in Thousands) Year Total Draw

2013 $125,000 2014 80,000 2015 75,000

Total $280,000

Page 204: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 22

Table 14 EAGLE TIFIA Loan Debt Service

(Dollars in Thousands) Year Total Debt Service

2021 $10,888 2022 10,888 2023 10,888 2024 10,888 2025 19,484

2026 19,481 2027 11,305 2028 11,305 2029 11,305 2030 11,305

2031 11,305 2032 11,305 2033 11,305 2034 11,305 2035 11,305

Total $184,261

6. Public-Private Partnerships (PPP)

A Public-Private Partnership (PPP) is a contracting arrangement where the public entity partners with a private contractor or consortium on the development of a public project. In return for the private participation, the public agency pays annually appropriated availability payments to the private partner thereby spreading out large upfront costs of a project over time and preserving cash in the early years.

The Eagle Project, which includes the East and Gold Line Corridors, a commuter rail maintenance facility, and a short electrified segment of the Northwest Rail Corridor, is the largest PPP transit project in the United States. RTD has contracted with Denver Transit Partners (DTP) to design, build, and finance the initial construction of the projects, and to operate and maintain all project assets through the year 2044. Through this contract, RTD realized savings over its internally estimated construction costs, and established the basis for its operating and maintenance costs for the first 28 years of corridor operations. In 2010, RTD awarded the contract for the Eagle Project to DTP, and began construction of the project. In 2011, RTD received a Full Funding Grant Agreement (FFGA) from the Federal Transit Administration (FTA) in the amount of $1.03 billion for this project.

As part of the financial plan in the concession agreement, DTP will provide debt and equity to cover $486.9 million of the initial capital cost of the Eagle project. In August, 2010, RTD acted as the conduit issuer for the issuance of $397.8 million in tax-exempt Private Activity Bonds for DTP to cover the debt portion of its financial commitment to the project. RTD will do cash flow borrowings, expected to be secured by the FasTracks sales and use tax, to bridge future receipts of Federal New Starts Grants, as described below.

Under the concession agreement, RTD will make annual availability payments (service payments) to DTP once the project is open for revenue service, which will cover operations, maintenance, and capital repayment. These payments are segmented into two pieces. The capital portion of the

Page 205: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 23

service payment is structured as a fixed annual debt subject to TABOR, secured on a subordinate basis to existing FasTracks revenue bonds. The outstanding principal amount of the TABOR portion of the service payment as of December 31, 2010 was $589.9 million. The operating portion of the service payment includes all costs to operate and maintain the line. The operating portion of the service payment is assumed to adjust according to a formula that includes inflation-based increases and performance-related reductions. The operating portion of the service payment is subject to annual appropriation and is not covered by TABOR restrictions. Table 15 shows the schedule of projected annual service payments to DTP.

Under the concession agreement, DTP is responsible for delivering and operating the project according to the District’s policy goals and standards and paying all project and finance costs from these service payments, while the District will own the project. The concession agreement includes various protections for RTD to ensure adequate control and remedies. Performance standards, periodic reviews, corrective measures, penalty assessments, cure periods, payment reductions, sharing of certain upside benefits and various other measures are provided in the terms of the contract to protect RTD. Ultimately, if DTP does not adequately perform under the contract, all or parts of the contract may be terminated.

Cashflow Borrowing for PPP

RTD will do cash flow borrowings, expected to be secured by the FasTracks sales and use tax, to bridge future receipts of Federal New Starts Grants. The plan anticipates RTD issuing a total of $240 million of cashflow bonds in 2013 and 2014 to bridge receipts of Federal New Starts Grants. The assumed interest rate for the cashflow borrowing is 3.95% which is lower than the assumed long-term sales tax bond borrowing rate due to the short tenor of the cashflow borrowings. The cash flow borrowings would be repaid in full by 2018, at a total repayment cost of $280.1 million and would be subject to TABOR.

Page 206: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 24

Table 15 Service Payment Schedule

TABOR Portion of the Service Payment and Operating Portion of the Service Payment¹

(Thousands of Year of Expenditure Dollars)

Year TABOR Portion of Service Payment

Operating Portion of Service Payment Total

2011 - - - 2012 - - - 2013 - - - 2014 - - - 2015 - - - 2016 - 49,064 49,064 2017 40,954 40,974 81,927 2018 34,437 51,233 85,670 2019 45,388 64,333 109,721 2020 45,813 72,894 118,708 2021 46,264 59,961 106,225 2022 44,618 62,425 107,044 2023 45,790 66,233 112,023 2024 47,210 78,938 126,149 2025 49,812 103,721 153,533 2026 44,524 73,001 117,525 2027 45,475 72,723 118,198 2028 46,679 79,754 126,433 2029 48,154 91,495 139,649 2030 61,423 125,832 187,255 2031 49,261 81,418 130,679 2032 55,465 80,521 135,986 2033 67,957 83,362 151,319 2034 84,464 101,959 186,422 2035 97,323 131,689 229,012 2036 43,848 106,349 150,197 2037 49,295 101,307 150,602 2038 57,226 107,149 164,375 2039 73,605 124,989 198,595 2040 82,267 138,929 221,196 2041 77,751 117,664 195,415 2042 13,006 105,611 118,617 2043 15,090 152,590 167,680 2044 25,134 149,916 175,050 Total $1,438,234 $2,676,034 $4,114,268

¹TABOR Portion of the Service payment is considered a multi-year fiscal obligation of the District, and counts against RTD’s 2004 FasTracks TABOR Authorization and is secured on a lien below the existing FasTracks sales tax bonds. The Operating Portion of the Service Payment is subject to annual appropriation and may be adjusted for desired service levels. The Operating Portion of the Service Payment shown in the table reflects nominal figures per the Concession and Lease Agreement with DTP inflated using RTD’s inflation assumptions.

Page 207: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

Regional Transportation District – FasTracks 2012 Financial Plan 25

7. TABOR Requirements

The Taxpayer’s Bill of Rights (TABOR), or Article X, Section 20 of the Colorado Constitution, approved by Colorado voters in November 1992, restricts the ability of RTD to enter into a multi-year fiscal obligation without voter approval unless there are adequate present cash reserves. TABOR also requires voter approval in advance for: (i) any increase in RTD’s revenues and spending from one year to the next in excess of a specified growth rate (CPI plus a growth factor based on net increase in the value of new taxable property); or (ii) any new tax or tax increase.

In November 2004, the voters of RTD approved a ballot measure under TABOR that increased the RTD tax rate and provided a debt authorization to build the FasTracks program. The ballot measure authorized RTD to increase the tax rate by 0.4%, from 0.6% to 1.0%, and to use the revenue generated by the tax to build and operate the FasTracks program, and repay all debt issued to build the projects. The measure also authorized RTD to keep a portion of the tax increase after the FasTracks system is built and all debt is repaid, in order to cover the operating costs for the expanded system.

While the increase in the authorized tax rate is fairly straightforward, authorization for debt in Colorado must define the maximum principal amount of debt to be issued and the maximum total debt service costs for such borrowings. Four elements of the financial plan are subject to the TABOR requirements: sales tax revenue bonds, the TABOR Portion of the Service Payment, the DUSPA bond, and cashflow borrowings for the Eagle Project. Any potential TIFIA loan or commercial paper would be subject to TABOR if these are added to the plan at a future date. All of the estimated principal and interest for these items are included in the voted authorization. However, the allocation of principal and interest among these various financing mechanisms is subject to change. The total amount of principal and debt service the voters authorized in 2004 is shown in Table 16.

Table 16 TABOR Authorization

Revenue Bonds, Commercial Paper and TIFIA Issuances (Dollars in Thousands)

Principal $3,476,872 Total Debt Service $7,129,398

As with any long range capital improvement plan, the actual implementation of the Plan is dependent on project costs, inflation factors, revenue trends, and the interest rate environment in the future. These factors can never be predicted over a ten year horizon with exact precision. For this reason, the Plan reflects contingencies, both in interest rates and project costs.

The Plan also assumes that Federal grants will be received approximately two years in arrears of project expenditures. To the extent Federal funding is provided on a timelier basis, some of the debt assumed in the Plan may become unnecessary.

The current financial plan assumes the passage of an additional 0.4% sales and use tax increase commencing in January 2013 to fund the balance of the FasTracks program. As required by TABOR, the RTD Board of Directors would need a vote to place the question in front of the voters at a general election, and the voters would need to pass the ballot initiative. At that time, the Board would review the authorized debt limits and determine the additional debt authorization request to include in the ballot issue.

Page 208: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

April 3, 2012

Page left intentionally blank

Page 209: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2011 Annual Report to DRCOG on FasTracks

April 3, 2012

Appendix C: Cost Estimating Methodologies

Page 210: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2010 Annual Report to DRCOG on FasTracks

May 2011

During the FasTracks 2010 Annual Program Evaluation (APE), the majority of the estimates that were prepared followed the “Bottoms Up Estimating” procedure.

Top Down Estimating Procedure for the RTD-FasTracks Program

1. Top Down or parametric estimates are used on the FasTracks program when the

corridor/project is less than 30% complete with design. Top Down estimates utilize standard unit rates developed internally by RTD.

2. A unit rate development team is assembled at the very start of the APE. This team is comprised of staff from all major disciplines i.e. track, civil, stations, bridges, systems, etc.

3. For each discipline, a lead is identified and has responsibility for all unit rates within that discipline.

4. Each discipline lead is given a unit rate template in the FTA Standard Cost Categories for Capital Projects (SCC) format to populate.

5. Bi-monthly status meetings are held to assist in keeping the process on schedule and to resolve issues.

6. RTD’s estimating group publishes material and labor cost and submits them to the discipline

leads for their use. This process makes sure all unit rates use consistent pricing. Markup Guidelines 7. In order to provide consistency to the development of the APE unit rates, the following is a

guideline used to markup the APE unit rates. The unit rate needs to include contractor’s profit and home office overhead (15%). The Contractor’s field office overhead and other direct costs (ODCs) is 17% and is accounted for in a separate line item within the estimates under SCC 40.08. Unit rates are developed by one of the following approaches:

Bottom’s up Estimate If the unit rate is developed from the “bottoms up”, the contractor’s profit and home office overhead of 15% must be added. Colorado Department of Transportation (CDOT) Estimate CDOT unit rates include all markups. When using the CDOT unit rates the contractor’s indirect costs of 20% should be removed. Contractors Quote A contractor’s quote includes all markups. When using a contractor’s quote the contractor’s indirect costs of 20% should be removed. Means Estimate When Means unit rates are considered, the “Total” amount and not the “Total incl O&P” values are used. The 15% for the contractor’s home office overhead is added to the “Total” Means values. The contractor’s field overhead and ODCs are included in the SCC 40.08 line.

Page 211: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2010 Annual Report to DRCOG on FasTracks

May 2011

Other Estimate Any alternative method used for unit rate development is evaluated by RTD’s FasTracks Chief Capital Cost Estimator before it is used on any FasTracks APE estimates.

8. Once the initial unit rates are developed they are sent to out to the project team for review and comment. After the comments are incorporated the unit rates are published and used by the Project Managers (PMs). The PMs populate the project estimate with the approved unit rates.

9. The Engineer of Record design plan quantities shall be used as the official takeoff quantities. The quantities can be generated traditionally by using either dimensions shown on the drawings, or by scaled measurements when necessary. In addition, some linear and area measurements can be made on the electronic copies of the plan sheets in portable document format (PDF) by utilizing on-screen measuring tools.

10. The takeoff quantities are loaded into the individual project cost estimates. 11. The following must be carefully taken into consideration when estimating “big ticket” items:

• Major items of cost will require “bottoms up” estimating by selecting and possibly modifying the preprogrammed standard crews. In addition, the production rates used will require careful consideration of the uniqueness of the project.

• Material suppliers are contacted to obtain permanent and expendable material costs. • Contact subcontractors to get input and prices for specialty work. • Research appropriate websites to obtain general information, especially regarding

various expendable materials such as forming supplies, form rentals, sheet piling, shoring, etc. Also, research the capabilities of the various specialty equipment to be used as related to the specific project requirements

12. Using information from the estimate, as well as the FasTracks program schedules,

determine the total time required for each phase of the project (i.e., design, construction, commissioning/testing). This duration, usually designated in months, is used in the calculation of the jobsite indirect costs.

Page 212: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2010 Annual Report to DRCOG on FasTracks

May 2011

Estimating Procedure for the RTD-FasTracks Program (Bottoms Up)

1. “Heavy Bid” by HCSS, Inc. is the standard estimating software that is utilized for producing all RTD-FasTracks program estimates and includes the following capabilities:

• Preprogrammed material and subcontract costs that are pertinent to the RTD-FasTracks

program. These will be updated for each major estimate, especially for those materials and subcontracts that comprise the largest costs (rail, ties, MSE wall panels, MSE wall select backfill, embankment borrow material, concrete, reinforcing steel, structural steel, prestressed concrete bridge girders, etc.).

• Preprogrammed labor rates for the various classifications (i.e., laborer, carpenters, semi-skilled, bulldozer operator, etc.). The Estimating Group continually monitors the latest Davis-Bacon decisions and updates the labor rates accordingly.

• Preprogrammed equipment rates for most types of equipment. These rates periodically revised whenever there are any major changes to either the ownership or operating costs with yearly updates to the Rental Rate Blue Book for Construction Equipment.

• Preprogrammed crew assemblies for the most common heavy/highway/transit/rail types of work.

• The ability to customize the labor rates, equipment rates, crews, etc. to fulfill job-specific requirements.

• The ability to modify the labor burden categories (payroll taxes, workman’s comp rates, fringe benefits, hours greater than 40 per workweek factor, etc.).

• Preprogrammed typical heavy/highway/transit/rail pay items that have built-in unit prices.

• Preprogrammed activities from past estimates, which contain a checklist of indirect costs (supervision, engineering, quality control inspection and testing, survey, field office, equipment maintenance and mechanic, etc.) typically encountered on heavy/highway/ transit/rail types of projects.

2. The FasTracks Standard Production Rates have been developed for most of the work

activities that are typically encountered on FasTracks projects. For the majority of the individual work activities, there are “low,” “medium,” and “high” production rates listed, depending upon jobsite conditions and the quantities of work to be performed.

3. Monitor the anticipated design plan submittal dates as reflected on the FasTracks Master

Program Schedule to establish time frames required for producing the major program corridor estimates. In addition, Heavy Bid is used to perform check estimates on contract changes/contract directives or any other estimating services as required. Estimating subconsultants are employed on an as-needed basis when the estimating workload is anticipated to exceed the available resources.

4. Consult with experts in the field (people who have “first-hand” knowledge of field operations)

of transit/rail construction to obtain their input related to crew assemblies (labor and equipment), along with typical production rates that the crews are capable of obtaining in various scenarios (tight ROW, limited work areas, large work areas, interfaces with third parties, typical things to “watch out for”, etc.). Heavily utilize the information obtained from these sources to adjust the standard preprogrammed crews in Heavy Bid or add custom and/or specialty crews to the database.

Page 213: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2010 Annual Report to DRCOG on FasTracks

May 2011

5. Study the plans to gain an understanding of the work which comprises the majority of the project cost. Roughly identify the 20% of the project elements which comprise 80% of the project cost. Partition the time allotted to produce the cost estimate between the 20% “big ticket” items, according to the level of effort required. For instance, earthwork, drainage and various structures components will usually require more time than rail installation.

6. Perform the detailed quantity takeoff, particularly for all of the “big ticket” items. The

designer’s plan quantities, if provided, should be used as a “rough check” of the takeoff quantities. The quantities can be generated traditionally by using either dimensions shown on the drawings, or by scaled measurements when necessary. In addition, some linear and area measurements can be made on the electronic copies of the plan sheets in portable document format (PDF) by utilizing on-screen measuring tools.

7. Input the takeoff quantities into the individual cost activities set up in the Heavy Bid

estimating software. 8. The following must be carefully taken into consideration when estimating “big ticket” items:

• Major items of cost will require “bottoms up” estimating by selecting and possibly modifying the preprogrammed standard crews. In addition, the production rates used will require careful consideration of the uniqueness of the project.

• Material suppliers are contacted to obtain permanent and expendable material costs. • Contact subcontractors to get input and prices for specialty work. • Research appropriate websites to obtain general information, especially regarding

various expendable materials such as forming supplies, form rentals, sheet piling, shoring, etc. Also, research the capabilities of the various specialty equipment to be used as related to the specific project requirements

9. Using information from the estimate, as well as the FasTracks program schedules,

determine the total time required for each phase of the project (i.e., design, construction, commissioning/testing). This duration, usually designated in months, is used in the calculation of the jobsite indirect costs.

10. Utilizing the indirect activities from past estimates as a template, determine the applicable

items comprising the jobsite indirect costs. Base the individual activity costs on the estimated times determined in the above step.

11. Next, use the “Spread” tool in Heavy Bid to spread the markup amounts for the contractor’s

home office overhead and profit (usually 15%) to all of the activities of cost. This will generate the “bid prices” for each of the bid items comprising the estimate.

12. When the estimate has been completed in Heavy Bid, usually the estimate will need to be

compared to either the Design Engineer’s or the Contractor’s cost estimate. As such, produce a spreadsheet that compares these costs. Usually the designer will already have put his estimate in Excel spreadsheet format, with a separate workbook sheet being used for each of the SCC codes. There should also be a separate summary sheet in the workbook that summarizes the costs by the SCC codes.

13. Estimates generated within the FasTracks Estimating Group are reviewed by a qualified

estimator within the group to confirm the estimates are accurate and free of error.

Page 214: Table of Contents - FasTracks · DBFOM Design-Build-Finance-Operate-Maintain ... RRIF Railroad Rehabilitation & Improvement Financing ... USACE US Army Corps of Engineers

2010 Annual Report to DRCOG on FasTracks

May 2011

14. The estimates are reviewed with the Corridor Project Manager to confirm all project elements have been included. Appropriate adjustments are made and the estimate is finalized. The estimate is then coded with the Work Breakdown Structure (WBS) cost accounts and an Excel spreadsheet export file generated. The resulting export file can be input into PRISM Project Manager, the FasTracks Cost Control System, for estimate-to-complete calculations and cost control purposes.

15. When the subsequent design submittal are received for review, the previous design

submittal estimate is version controlled before any estimate updates are completed as a result of any changes to the design.