Top Banner

of 59

System Formwork by Rachna

Apr 03, 2018

Download

Documents

gabuchia
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 7/28/2019 System Formwork by Rachna

    1/59

    7/9/2013 1

    SYSTEM FORMWORKLarsen and toubro limited

    Presentation by:Rachna Rajput

    (1030227)

  • 7/28/2019 System Formwork by Rachna

    2/59

    7/9/2013 2

    LARSEN & TOUBRO LIMITED

    ECC DIVISION

    LUDHIANA CITY CENTRE

    CONSTRUCTION OF RCC BASEMENT STRUCTURE

    By : A.K. Mishra

  • 7/28/2019 System Formwork by Rachna

    3/59

    7/9/2013 3

    THE CLIENT: TODAYHOMES AND INFRASTRUCTUR

    JOINT VENTURE WITH LUDHIANAIMPROVEMENT TRUST

    ARCHITECT: CP KUKREJA AND ASSOCIATES

    CONTRACTOR : LARSEN AND TOUBRO LIMITED

  • 7/28/2019 System Formwork by Rachna

    4/59

    7/9/2013 4

    LUDHIANA CITYCENTRE

    LOCATED IN HEART OF LUDHIANABUILT ON 25 ACRES OF LAND4 SIDE OPEN PLOTMAXIMUM NUMBER OF CAR PARKS UNDERONE ROOFONLY DEVELOPMENT OF INDIA WITH 5 STARHOTEL,SHOPPING MALL,IT/OFFICESPACE,HEALTH CARE,LIBRARY,MUESEAMUNDER 1 ROOFBIGGEST ATRIUM:2 LAKH SQUARE FEET

  • 7/28/2019 System Formwork by Rachna

    5/59

    7/9/2013 5

    LUDHIANA CITY CENTRECONSTRUCTION OF RCC BASEMENT STRUCTUREProject Highlights

    JOB VALUE : 12400 lacsDATE OF LOI: 30:1:2006DATE OF COMMENCEMENT: 15:02:2006

    DATE OF COMPLETION: 14:02:2007DURATION OFPROJECT : 12 months

  • 7/28/2019 System Formwork by Rachna

    6/59

  • 7/28/2019 System Formwork by Rachna

    7/59

    7/9/2013 7

    WHAT IS FORMWORK?FORMWORK IS A MOULD USED TO SHAPECONCRETE UNTIL IT ATTAINS SUFFICIENTSTRENGTH TO CARRY ITS OWN WEIGHTCAN BE ASSEMBLED BY UNSKILLED

    LABOUR

    CONSTITUTES 30% OF THE COST AND60% OF THE TIME IN CONCRETECONSTRUCTION

    GOOD FORMWORK RESULTS IN

    SPEED,QUALITY,ECONOMY AND SAFETY

  • 7/28/2019 System Formwork by Rachna

    8/59

    7/9/2013 8

    TRADITIONALAPPROACH

    BALLIES USED AS SUPPORT FORSHUTTERING

    UNSAFE AND UNRELIABLE

    LOW REUSE VALUE

    DOES NOT PRODUCE GOOD QUALITYCONCRETE

  • 7/28/2019 System Formwork by Rachna

    9/59

    7/9/2013 9

    CHOICE OF RIGHT TYPE OFFORMWORK

    FORMWORK SHOULD BE ABLE TO BEDESHUTTERED AND DISMANTLED FASTSAFETY TO BE IMPROVED BY SITEPERSONNELOVERALL COST SAVINGSGOOD SURFACE FINISH TO BE ACHIEVEDOPTIMUM STOCK OF FORMWORK FOR SIZEOF WORKFORCE AND SPECIFIED TIMESCHEDULE

  • 7/28/2019 System Formwork by Rachna

    10/59

    7/9/2013 10

    SYSTEM FORMWORK-

    L&TEARLIER CALLED DOKAFORMWORK

    INVERSIBLEFAST ERECTIONMORE STABLESAFE IN USE

  • 7/28/2019 System Formwork by Rachna

    11/59

    7/9/2013 11

    FORMWORK PLANNINGSTEP1.)

    CONFIRMING HQ ON THE NEW JOBS BAGGEDIDENTIFYING TIME AND MATERIALS FORCONSTRUCTION PROJECT

    STEP2.)

    FINALIZING FORMWORK MATERIALSREQUIREMENTS FOR THE PROJECTCOLLATE THE REPORTS FROM RUNNING SITES

    AND CHECK SEPARABILITY FROM OTHER

    SITES WITHIN THE REGIONSENDING REQUEST FOR TRANSFER OFRESOURCES IF AVAILIBILIY IS CONFIRMED

  • 7/28/2019 System Formwork by Rachna

    12/59

    7/9/2013 12

    CONTD.

    RECEIVING NEW TARGETS ONPRODUCTIVITY FROM HQ

    COMPARING THE RUNNINGLMP COST FROM THE ACTUAL

    IDENTIFYING TRAINING NEEDSOF STAFF

  • 7/28/2019 System Formwork by Rachna

    13/59

  • 7/28/2019 System Formwork by Rachna

    14/59

    7/9/2013 14

    FOUNDATION FORMWORK

    STEEL PANELS OF STANDERED SIZESMINIMIZE MAKING AT SITEUSE OF VERSATILE COMPONENTS LIKE

    STEEL WALERS(2 ISMC BACK 2BACK) AND ALIGNMENT PROPSEASY ASSEMBLY WITH DIMENSIONAL

    ACCURACY

  • 7/28/2019 System Formwork by Rachna

    15/59

    7/9/2013 15

  • 7/28/2019 System Formwork by Rachna

    16/59

  • 7/28/2019 System Formwork by Rachna

    17/59

    7/9/2013 17

    CONTD

  • 7/28/2019 System Formwork by Rachna

    18/59

    7/9/2013 18

    CONTD.

  • 7/28/2019 System Formwork by Rachna

    19/59

    7/9/2013 19

    AFTER ERECTIONSteel panel

    Pipe waler

    Alignmentprop

    welar

    Pipe waler clamp

  • 7/28/2019 System Formwork by Rachna

    20/59

    7/9/2013 20

    HDT TOWERBASIC FRAMEHORIZONTAL BRACEDIAGNOL BRACE

    TAKES LOAD OF 250KNHIEGHT ADJUSTMENTS UPTO 800MMPOSSIBLE

    TRANSPORT DEVICES CAN BE ATTATCHED

  • 7/28/2019 System Formwork by Rachna

    21/59

    7/9/2013 21

    COMPONENT DETAILING

  • 7/28/2019 System Formwork by Rachna

    22/59

    7/9/2013 22

    CONTD.

  • 7/28/2019 System Formwork by Rachna

    23/59

    7/9/2013 23

    AFTER ERECTION

    Coupler andspring lock pin

    Foot plate

    Tower

    spindle

  • 7/28/2019 System Formwork by Rachna

    24/59

    7/9/2013 24

    WALL/COLUMN FORMWORK

    SHOP MADE SHUTTER

    ACCORDING TO THE HIEGHT OF WALL ORCOLUMN SPLICING CAN BE DONE

    ISMC WALERS ARE USED FOR BEARING

  • 7/28/2019 System Formwork by Rachna

    25/59

    7/9/2013 25

    COMPONENTDETAILING

  • 7/28/2019 System Formwork by Rachna

    26/59

    7/9/2013 26

    CONTD.

  • 7/28/2019 System Formwork by Rachna

    27/59

  • 7/28/2019 System Formwork by Rachna

    28/59

    7/9/2013 28

    COLUMN FORMWORK WORKINAT 4.8M HIEGHT

  • 7/28/2019 System Formwork by Rachna

    29/59

    7/9/2013 29

    COLUMN FORMWORK

  • 7/28/2019 System Formwork by Rachna

    30/59

    7/9/2013 30

    WALL FORMWORK 1.8M HIEGHT

  • 7/28/2019 System Formwork by Rachna

    31/59

    7/9/2013 31

    SLAB/BEAM FORMWORK

    SHEATHING MEMBER

    H-BEAM(SECONDARY MEMBER)

    WELAR(PRIMARY MEMBER)

    HDT TOWER

  • 7/28/2019 System Formwork by Rachna

    32/59

    7/9/2013 32

    AFTER ERECTION

    tower

    H-beam

    Sheathing

    welar

  • 7/28/2019 System Formwork by Rachna

    33/59

    7/9/2013 33

    DESIGN OF FORMWORKFORMWORK MUST SUPPORT ALL THEVERTICAL AND LATERAL LOADS

    ALL LOADS ARE ASSUMED TO BE

    UNIFORMLY DISTRIBUTEDBEAMS SUPPORTED OVER 3 OR MORESPANS ARE TAKEN AS CONTINUOUS

    APPROXIMATE FORMULAE ARE USED

  • 7/28/2019 System Formwork by Rachna

    34/59

    7/9/2013 34

    AN IMPORTANT POINT

    SHEATHING SPAN DECIDES H-BEAM SPACING

    H-BEAM SPAN DECIDES WALER SPACING

    WELAR SPAN DECIDES TOWER SPACING

    SPAN HERE MEANS THE DISTANCE BETWEEN

    TWO REACTION POINTS

  • 7/28/2019 System Formwork by Rachna

    35/59

    7/9/2013 35

    DESIGN PROCEDUREEXAMPLE

    LOADS TO BE TAKEN

    DEAD LOAD(1)(THICKNESS OF MEMBER*DENSITY OF

    CONCRETE)

    LIVE LOAD(2)

    SELF WEIGHT(3)

    DESIGN LOAD,W=(1)+(2)+(3)

  • 7/28/2019 System Formwork by Rachna

    36/59

    7/9/2013 36

    DESIGN PROCEDURECHECKS TO BE APPLIED

    BENDING MOMENT CONDITIONSHEAR FORCE CONDITIONDEFLECTION CONDITION

    THE MINIMUM OF ALL 3 SPANS ISTAKEN AS SPAN FOR THE MEMBER

    ACCORDING TO HEIGHT OF WALL ORCOLUMN THE REQUIRED LENGTH OFH-BEAM(AN I SECTION )HIGH STRENGTH TIE SYSTEM BEARLARGE CONCRETE PRESSURE

  • 7/28/2019 System Formwork by Rachna

    37/59

    7/9/2013 37

    DESIGN PROCEDURECONTD.

    DESIGN DONE FROM TOP TO BOTTOM1. SHEATHING MEMBER

    2.H-BEAM(SECONDARY MEMBER)3.WELAR(PRIMARY MEMBER)HDT TOWER

  • 7/28/2019 System Formwork by Rachna

    38/59

    7/9/2013 38

    SELF WEIGHT OF CONCRETE WITH

    REINFORCEMENT=25KN/M^3

    SELF WEIGHT OF FORMWORK VARIES

    BETWEEN 0.5KN/M^2 TO .75KN/M^2

    MINIMUM LIVE LOAD =2.5KN/M^2

    MINIMUM DESIGN LOAD=5.0 KN/SQM

  • 7/28/2019 System Formwork by Rachna

    39/59

    7/9/2013 39

    SHEATHING MEMBER:END CONDITION ASSUMED TO BE A PROPPED

    CANTILEVERBM=W*L^2/8

  • 7/28/2019 System Formwork by Rachna

    40/59

    7/9/2013 40

    SECONDARY MEMBER(H BEAM):END CONDITION IS ASSUMED TO BE SIMPLY

    SUPPORTEDLOAD INTENSITY =DESIGN LOAD*SPAN OFSHEATHING MEMBERBM=W*L^2/8

  • 7/28/2019 System Formwork by Rachna

    41/59

  • 7/28/2019 System Formwork by Rachna

    42/59

    7/9/2013 42

  • 7/28/2019 System Formwork by Rachna

    43/59

    7/9/2013 43

    DESIGN FOR WALL/COLUMNFORMWORK

    CONCRETE EXERTS A FLUID PRESSURE DhON THE FORMWORKPmax=

    D[C1*R^.5-(C2*K*(H-C1*R^.5)^.5) ORDh

    whichever is smaller

    VALUE OF C1FOR WALLS=1FOR COLUMNS=1.5

  • 7/28/2019 System Formwork by Rachna

    44/59

    7/9/2013 44

    VALUE OF C2 DEPENDS ON CONSTITUENTMATERIALS OF CONCRETE

    D=WEIGHT DENSITY OF CONCRETEH=VERTICAL FORM HIEGHTh=VERTICAL POUR HIEGHT

    K=TEMPERATURE COEFFICIENT TAKEN AS(36/T+16)^2R=RATE OF RISE M/HT=TEMPERATURE OF CONCRETE AT PLACING

    (degree celsius)

  • 7/28/2019 System Formwork by Rachna

    45/59

    7/9/2013 45

    PRESSURE DISTRIBUTION DIAGRAM

    H

    P max

    Pmax/D

    DESIGN OF WALERDESIGNED AS

  • 7/28/2019 System Formwork by Rachna

    46/59

    7/9/2013 46

    DESIGN OF WALER DESIGNED ASLATERALLY UNSUPPORTED BEAMSIGMAbc=.66*Fcb*Fy/(Fcb^n+Fy^n)^1/nFcb=ELASTIC CRITICAL STRESS(N/MM^2)Fy= YIELD STRESS OF STEEL IN( N/MM^2)

    N=FACTOR TAKEN AS 1.4Fcb=K1*(X+K2*Y)*C2/C1PERMISSIBLE SHEAR STRESS=0.4*Fy

    PERMISSIBLE DEFLECTION=L(SPAN)/325BENDING STRESS=M/ZSHEAR STRESS=F/Aweb

  • 7/28/2019 System Formwork by Rachna

    47/59

    7/9/2013 47

    STRIPPING TIME FORFORMWORK

    VERTICAL FORMWORK TO COLUMN, WALL AND BEAM :16-24HOURS

    SOFFIT FORMWORK TO SLABS( PROPS TO BEREFIXED AFTER REMOVAL OF FORMWOK) : 3DAYS

    SOFFIT FORMWORK TO BEAMS :7DAYS

  • 7/28/2019 System Formwork by Rachna

    48/59

    7/9/2013 48

    SAFETY IN FORMWORK

    BEFORE ERECTION OF STEEL FRAMESTAGING THOROUGH INSPECTIONDIAGNOL BRACES SHOULD BE IN PROPERPOSITION

    ALL CONNECTING DEVICES SHOULD BE INPLACEBRACING SHOULD BE PROVIDED IF TOWERHEIGHT INCREASES 6M

    AT HIEGHTS SAFETY BELTS SHOULD BEUSED BY WORKMEN

  • 7/28/2019 System Formwork by Rachna

    49/59

    7/9/2013 49

    L adder Safety

    Follow the 4:1 rule when using extension ladders

    6 m (20 ft)

    1.5 m (5 ft.)

  • 7/28/2019 System Formwork by Rachna

    50/59

    7/9/2013 50

    Erect First Tower Adjust and ensure the

    top level is same. Connect all pin bracing

  • 7/28/2019 System Formwork by Rachna

    51/59

    7/9/2013 51

  • 7/28/2019 System Formwork by Rachna

    52/59

    7/9/2013 52

  • 7/28/2019 System Formwork by Rachna

    53/59

    7/9/2013 53

    Use of lifeline above 2m

  • 7/28/2019 System Formwork by Rachna

    54/59

    7/9/2013 54

    LABOUR PRODUCTIVITY

    PRODUCTIVITY IS MAXIMUM OUTPUT FROMMINIMUM INPUT

    UNITS ARE SQM/MANDAY

    WORKING OF 8 HRS=1MANDAY

    PRODUCTIVITY=SHUTTERING AREA ACHIEVED DURING THEMONTH/MANDAYS

  • 7/28/2019 System Formwork by Rachna

    55/59

    7/9/2013 55

    MATERIALPRODUCTIVITY

    MATERIAL PRODUCTIVITY IS COMPAREDWITH STANDERED PRODUCTIVITYSTANDERED PRODUCTIVITY CALCULATEDON THE BASIS OF SHUTTERING AREACOMPLETED AND KG MONTH PER SQMTOTAL REQUIRED KG=

    SHUTTERING AREA *KG MONTH PER SQM

  • 7/28/2019 System Formwork by Rachna

    56/59

    7/9/2013 56

    ACTUAL PRODUCTIVITY ISTAKEN AS AVERAGE STOCKLEFT

    PRODUCTIVITY IN %=

    (ACTUALPRODUCTIVITY/STANDERED PRODUCTIVITY)*100

  • 7/28/2019 System Formwork by Rachna

    57/59

    7/9/2013 57

    RATE ANALYSIS

    ON THE BASIS OF NUMBER OF CARPENTERKHALASI AND HELPER,NUMBER OF HOURSOF WORK AND RATE/HR THE TOTAL AMOUNTIS CALCULATED FOR SHIFTING ,FIXING ANDREMOVINGPRODUCTIVITY IN SQM/MANDAYS IS

    CALCULATED

  • 7/28/2019 System Formwork by Rachna

    58/59

    7/9/2013 58

    BATCHING OFCONCRETE

    PAN TYPE BATCHING PLANTCAPACITY OF 60M^3/HR

    WEIGHED BATCHINGMIXINGTRANSPORTATION

    PLACING

    THANK YOU

  • 7/28/2019 System Formwork by Rachna

    59/59

    THANK YOU