System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells” Michael Schilmoeller Tuesday, September 27, 2011
55

System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

Feb 25, 2016

Download

Documents

ryann

System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”. Michael Schilmoeller Tuesday, September 27, 2011. Overview. Uncertainties Their representation Cells in the RPM. Uncertainties. Hydrogeneration Natural Gas Price Non-DSI Loads - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

System AnalysisAdvisory Committee

Futures, Monte Carlo Simulation,and CB “Assumption Cells”

Michael SchilmoellerTuesday, September 27, 2011

Page 2: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

2

Overview

–Uncertainties–Their representation–Cells in the RPM

Page 3: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

3

Uncertainties• Aluminum Prices• Carbon Penalty• Commercial

Availability• Conservation

Performance• Construction Costs• Electricity Price

• Hydrogeneration• Natural Gas Price• Non-DSI Loads• Production Tax Credit

Life• REC Values• Stochastic FOR

Page 4: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

4

The Navigator–Permits a user to find plants,

cost and energy calculations, imbalance estimates, and so forth easily in the RPM

–Uses hyperlinks and windows

Page 5: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

5

Aluminum Prices– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 6: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

6

Aluminum Prices

t

tt

t

ttttttt

pbadtdz

pdpp

pdzdtpaabdtdzpdtpbapdpp

ofdeviation standard theis level mequilibriu theis

reversion of rate thecontrolshich constant w is processes discretefor 1 valuehas which size, step theis

process N(0,1) a fromdrawn a is step previous thefrom in change theis

questionin variablestochastic is where

)1()(

80 random variables, one for each period, to generate geometric Brownian motion in aluminum prices

5th Plan, Appn P, page P-83 ff

Page 7: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

7

Aluminum Prices

Fifth Power Plan price assumption

Sixth Power Plan price assumption (oops)

Page 8: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

8

Carbon Penalty– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 9: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

9

Carbon Penalty

2 random variables, determining the timing and size of penalty arrival

Page 10: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

10

Carbon Penalty

0

20

40

60

80

100

120

Sep-

09

Sep-

10

Sep-

11

Sep-

12

Sep-

13

Sep-

14

Sep-

15

Sep-

16

Sep-

17

Sep-

18

Sep-

19

Sep-

20

Sep-

21

Sep-

22

Sep-

23

Sep-

24

Sep-

25

Sep-

26

Sep-

27

Sep-

28

$200

6/U

S to

n C

O2

100%90%80%70%60%50%40%30%20%10%0%mean

Source: workbook "New CO2 Distribution 090425.xls", chart "Carbon Distribution"

5th Plan, Appn P, page P-133 ff6th Plan, Appn J, page J-4 ff

Page 11: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

11

Commercial Availability– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 12: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

12

Commercial Availability

6th Plan, Appn J, page J-14, J-15

1 random variable, determining the delay (periods) after construction could begin, absent availability constraints

Page 13: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

13

Conservation Performance– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 14: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

14 14

Technical Feasibility of Lost Opportunity Conservation

Supply Curves

0

50

100

150

200

250

0 50 100 150 200 250

Lost Opportunity (Q)

real

leve

lized

$/M

Wh

(P)

201020152020

source: Q:\MS\Council Presentations and Communication\100511 P4 Portland\graphics\supply curves for illustration.xls

Page 15: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

15 15

Effect on the Supply Curve

Supply curves

Page 16: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

16

Conservation Performance

6th Plan, Appn J, page J-5;Power Committee Meeting, Tuesday May 11, 2010

1 random variable, determining the scaled shift of all the supply curves in the future

Page 17: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

17

Construction Costs– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 18: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

18

Construction Costs

6th Plan, Chap 9, page 9-14 ff;

Page 19: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

19

Construction Costs

6th Plan, Chap 9, page 9-14 ff;

Page 20: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

20

Construction Costs

6th Plan, Appn J, page J-11 ff;Generation Resource Advisory Committee, December 18, 2008 and January 22, 2009

1 random variable, determining the scaled shift of all the supply curves in the future

Complex cost futures are pre-computed , stored in binary form in the workbook, and drawn according to this “seed” value

Page 21: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

21

Electricity Prices– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 22: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

22

Electricity Prices

6th Plan, Chap 9, page 9-11 ff

Page 23: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

23

Casual Regimes

5th Plan, Appn P, page P-65 ff

• Short-term (hourly to monthly)– Positive correlation of electricity price with loads– Hourly correlations to hydro, natural gas price– Quarterly averages correlations to all three

• Long-term (quarterly to yearly)– Negative correlation of electricity price with loads– Supply and demand excursions– Changing technology, regulation

Page 24: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

24

Electricity Prices Before Adjustments

5th Plan, Appn P, page P-65 ff

Adjustments for longer-term response include• Hydro year selection• Quarterly loads• Gas price effects• Energy balance (supply vs. demand) effects

The model generates an “independent” electricity price future devoid of these effects; adjustments for these effects are made deterministically during the chronological simulation

Page 25: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

25

“Independent” Electricity Price

8 random variables, determining the underlying scenario path of electricity price and the nature of up to two excursions

Page 26: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

26

Jumps in Electricity Price

5th Plan, Appn P, page P-65 ff

Page 27: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

27

Underlying “Path” of Electricity Price

5th Plan, Appn P, pages P-25 ff and P-65 ff

The underlying path consists of the original benchmark forecast and the combined effects of a random offset and a random change in slope

A more complete description will be provided with the description of natural gas prices

Page 28: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

28

Hydrogeneration– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 29: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

29

Hydrogeneration• Monthly energies, east and west of the

cascades, are provided by the HYDREG model and are consistent with GENESYS

• Sustained peaking estimates based on these energies enable us to allocate hydrogeneration energy on and off peak

• Hydro years are selected at random from among the 70 years of hydrogeneration available

Page 30: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

30

Hydrogeneration

20 random variables determine the hydro year

5th Plan, Appn P, pages P-55 ff

Page 31: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

31

Natural Gas Price– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 32: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

32

Natural Gas Price

6th Plan, Chap 9, page 9-13 ff

Page 33: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

33

Natural Gas Price

47 random variables: three factor multipliers, two for each of two possible jumps, and 40 seasonal specific variances (fall and spring)

Page 34: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

34

NGP: Factor Multipliers

5th Plan, Appn P, pages P-26 ff

Page 35: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

35

NGP: Factor Multipliers

y = 0.0003x2 + 0.0007x - 0.0019

-0.02

0.00

0.02

0.04

0.06

0.08

0.10

0.12

1 3 5 7 9 11 13 15 17

Quadratic Component

Quadratic Component

Poly. (Quadratic Component)

5th Plan, Appn P, pages P-49 ff

Page 36: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

36

NGP: Specific Variances

5th Plan, Appn P, pages P-55 ff

Page 37: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

37

Jumps

5th Plan, Appn P, pages P-33 ff

Note: this example is for electricity price

Page 38: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

38

NGP: Jumps

5th Plan, Appn P, pages P-49 ff

Page 39: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

39

NGP: Distributions

5th Plan, Appn P, pages P-49 ff

Page 40: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

40

Non-DSI Frozen Efficiency Load– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 41: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

41

Non-DSI Frozen Efficiency Load

6th Plan, Chap 9, page 9-13

Page 42: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

42

Non-DSI Frozen Efficiency Load

46 random variables: three factor multipliers, three for a possible jump, and 40 seasonal specific variances (summer and winter)

Note: our “weather corrected” load does not include the specific variance terms

Page 43: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

43

Non-DSI Frozen Efficiency Load

5th Plan, Appn P, pages P-37 ff

Page 44: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

44

Production Tax Credit Life– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 45: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

45

Production Tax Credit Life

1 random variable, representing the likely life of tax credits, assuming no carbon penalty and assuming the purpose of the credit is primarily to make the technology commercially competitive

Page 46: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

46

Production Tax Credit Life

5th Plan, Appn P, pages P-90 ff

Page 47: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

47

Production Tax Credit Value

5th Plan, Appn P, pages P-90 ff

Page 48: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

48

Renewable Energy Credit Value– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 49: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

49

Renewable Energy Credit Value

80 random variables, one for each period, to generate geometric Brownian motion in aluminum prices

5th Plan, Appn P, pages P-95 ff, but modified for the 6th Plan (see Chap 9, page 9-19)

Page 50: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

50

Stochastic Unit Forced Outages– Aluminum Prices– Carbon Penalty– Commercial Availability– Conservation Performance– Construction Costs– Electricity Price– Hydrogeneration– Natural Gas Price– Non-DSI Loads– Production Tax Credit Life– REC Values– Stochastic FOR

Page 51: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

51

Stochastic Unit Forced Outages

1 random variable, representing “seed” value for an endogenous calculation of beta and gamma-distributed random variables

Page 52: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

52

Stochastic Unit Forced Outages

In the RPM, real estate is expensive and used intensively. A single row of energy data will represent multiple units added over distinct points in time, each with its own construction cycle modeled.

Page 53: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

53

Stochastic Unit Forced OutagesGetting the forced outage calculation right, where each cohort can consist of multiple units, and units are added over time, is solved by making the calculation internally.

6th Plan, Appn J, page J-15 ff

Page 54: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

54

Summary

1 Aluminum Prices 802 Carbon Penalty 23 Commercial Availability 14 Conservation Performance 15 Construction Costs 16 Electricity Price 87 Hydrogeneration 208 Natural Gas Price 479 Non-DSI Loads 46

10 Production Tax Credit Life 111 REC Values 8012 Stochastic FOR 1

288

Page 55: System Analysis Advisory Committee Futures, Monte Carlo Simulation, and CB “Assumption Cells”

55

Concluding Remarks• The values for the 288 random variables are

drawn at the beginning of each game, or “future”• All aspects of the future are calculated in the

model before the chronological simulation of the resource portfolio’s performance

• Where decisions are necessary during the chronological simulation, the model references only “past” values of the given future

• You can use the Navigator feature in the RPM to explore these on your own