PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03 CDM – Executive Board page 1 CLEAN DEVELOPMENT MECHANISM PROJECT DESIGN DOCUMENT FORM (CDM-PDD) Version 03 - in effect as of: 28 July 2006 CONTENTS A. General description of project activity B. Application of a baseline and monitoring methodology C. Duration of the project activity / crediting period D. Environmental impacts E. Stakeholders’ comments Annexes Annex 1: Contact information on participants in the project activity Annex 2: Information regarding public funding Annex 3: Baseline information Annex 4: Monitoring plan
58
Embed
Switch From Single Cycle to Combined Cycle (CC) CDM Project at Shirvan Power Plant
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 1
CLEAN DEVELOPMENT MECHANISM
PROJECT DESIGN DOCUMENT FORM (CDM-PDD)
Version 03 - in effect as of: 28 July 2006
CONTENTS
A. General description of project activity
B. Application of a baseline and monitoring methodology
C. Duration of the project activity / crediting period
D. Environmental impacts
E. Stakeholders’ comments
Annexes
Annex 1: Contact information on participants in the project activity
Annex 2: Information regarding public funding
Annex 3: Baseline information
Annex 4: Monitoring plan
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 2
SECTION A. General description of project activity
A.1. Title of the project activity:
Switch from Single Cycle to Combined Cycle (CC) CDM Project at Shirvan Power Plant
PDD v.1.1
12/04/2011
A.2. Description of the project activity:
The proposed project activity consists in the conversion of an existing open cycle gas power plant to a
combined cycle gas power plant. The project activity is located close to the city of Shirvan, in North
Khorasan, Islamic Republic of Iran. The Shirvan power plant consists of 6 gas turbines, which are
divided in three different blocks. However, since only two blocks are being converted from open to
combined cycle, the project boundary will be limited to blocks one and two which are being converted
from open to combined cycle.
Purpose of the proposed project activity:
- Scenario existing prior to the start of the implementation of the project activity:
Blocks 1 and 2 of Shirvan power plant are currently operating with 4 gas turbines of 159 MW
gross capacity each under ISO conditions. The overall gross capacity of the two blocks is
therefore 636 MW under ISO conditions. Taking into account the site characteristics, the gross
capacity of the two blocks is 560 MW. The power plant is connected to the grid.
- Project scenario
The project activity consists in converting of block one and block two of the existing open cycle
power plant in Shirvan to a combined cycle power plant. For the conversion 4 heat recovery
steam generators (HRSG) and two steam turbines, each rated at 159 MW gross capacity under
ISO conditions, will be added. Overall, the proposed project activity will lead to an increase in
the gross capacity of block one and block two of the power plant from 636 MW to 954 MW
under ISO conditions. At site conditions, the combined cycle power plant will have a gross
capacity of 840 MW.
- Baseline scenario
The baseline scenario is equivalent to the continuation of the current practice, ie. the electricity
to meet the demand in the grid system will be generated:
1) By the operation of the existing power plant in open cycle mode;
2) By the operation of existing grid-connected power plants; and
3) By the addition of new generation sources to the grid.
Reduction of greenhouse gases:
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 3
The conversion from open to combined cycle leads to significant efficiency gains, since the waste heat
from the existing gas turbines will be used to produce steam which will power the steam turbines. This
increase in efficiency will lead to an increase in the production of electricity, while keeping fossil fuel
consumption constant. The additional electricity produced will be supplied to the national grid, and will
displace other fossil fuel generated electricity, thereby reducing overall CO2 emissions. The project
activity is expected to reduce overall emissions of CO2 by 6,453,239t over 10 years (see section A.4.4 for
detailed values).
Contribution to sustainable development:
The proposed project activity contributes to sustainable development in Iran through a number of ways:
- More efficient use of Iran’s gas reserves: the efficiency gains achieved by the conversion from
open to combined cycle will help preserve finite fossil fuel resources
- Ensuring stable supplies of electricity: The proposed project activity will contribute to providing
stable power supplies to the population and industries of Iran, without increasing the
consumption of fossil fuels.
- Technology and know-how transfer: the proposed project activity will lead to training of the
local staff, and help the spread of modern power plant technology in Iran.
A.3. Project participants:
Name of Party involved ((host)
indicates a host Party)
Private and/or public entity(ies)
project participants (as
applicable)
Kindly indicate if the Party
involved wishes to be considered
as project participant (Yes/No)
Islamic Republic of Iran (host) Iran Power Development Company
(IPDC) (Project owner - Public
entity)
No
Switzerland Swiss Carbon Assets Ltd. (Carbon
consultant - Private entity)
No
Switzerland Energy Changes Projektentwicklung
GmbH (Carbon consultant - Private
entity)
No
A.4. Technical description of the project activity:
A.4.1. Location of the project activity:
A.4.1.1. Host Party(ies):
Islamic Republic of Iran
A.4.1.2. Region/State/Province etc.:
North Khorasan Province
A.4.1.3. City/Town/Community etc.:
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 4
Shirvan
A.4.1.4. Details of physical location, including information allowing the
unique identification of this project activity (maximum one page):
Shirvan is located in the province of North Khorasan, in north-eastern Iran, as shown on the map below:
The power plant is located on Shirvan-Mashad Road 12 kilometres from Shirvan, in North Khorasan
Province.
Geographical coordinates:
- Site latitude:37 degrees, 0 minutes and 22 seconds North
- Site longitude: 58 degrees, 2 minute and 34 seconds East
- Site altitude: 1160 meters
Location of power plant
Shirvan
Shirvan
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 5
A.4.2. Category(ies) of project activity:
Energy industries (non-renewable sources), sectoral scope 1.
A.4.3. Technology to be employed by the project activity:
Scenario existing prior to the start of the implementation of the project activity:
The existing Shirvan power plant consists of 6 units of Ansaldo – v94.2 gas turbines, arranged in three
blocks. The turbines have a gross installed capacity of 159 MW per unit at ISO conditions, with a net
capacity per unit of 158.667 MW at ISO conditions. Two gas turbines together form one block. The
Ansaldo – v94.2 gas turbines achieve 31% – 34% efficiency, and are designed for a life time of 25 years.
The 4 gas units from block one and two were synchronized on the following dates:
- Unit 1: March 16 2006
- Unit 2: May 10 2006
- Unit 3: July 5 2006
- Unit 4: September 6 2006
The proposed project activity includes the addition of:
- Four heat recovery steam generators (HRSGs), one per gas turbine in the first two blocks of the
power plant
- Two steam turbine-generator in blocks one and two
The particulars of the steam turbines:
SIEMENS-E30-16-1*6.3-7 Model
2 Number Of Units
159(With SF) Nominal Capacity Per Unit (MW)
153.8 Rated Net Capacity Per Unit (MW)
25 Design Life Time (yr)
The particulars of the steam turbine generators:
2 Number Of Units
200,000 Output Power Per Unit (KVA)
SALIENT Kind Of Rotor
3000 Rated Speed (RPM)
0.8 Power Factor
7331 Current (A)
15750 Voltage (V)
50 Frequency (Hz)
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 6
With the proposed project activity, the gross installed capacity of block one and two of Shirvan power
plant will increase to 954 MW at ISO conditions – an increase of 50%. The nameplate efficiency of the
power plant will increase to 49% - 51%.
The fuel consumption will be measured by turbine gas flow meters (for natural gas) or turbine oil flow
meters (for diesel) respectively. Electricity meters measuring the amount of electricity produced by the
generators and the auxiliary consumption of the power plant will be installed. All meters will be subject
to regular maintenance in line with manufacturer or industry standards.
The baseline scenario is the same as the scenario existing prior to the start of the implementation of the
project activity (i.e. continuation of current practice).
Involved greenhouse gases: CO2.
For calculation of expected emission reductions the following yearly energy and mass flows are assumed.
The consumption of diesel and natural gas are not expected to increase compared to the current situation.
Year EGCC,y FCDiesel, y (lit) FCNG, y (Nm3)
1 2,618,429 55,795,231 424,413,371
2 2,607,955 55,572,050 422,715,718
3 2,597,523 55,349,762 421,024,855
4 2,587,133 55,128,363 419,340,755
5 2,576,785 54,907,850 417,663,392
6 2,566,478 54,688,218 415,992,739
7 2,556,212 54,469,465 414,328,768
8 2,545,987 54,251,587 412,671,453
9 2,535,803 54,034,581 411,020,767
10 2,525,660 53,818,443 409,376,684
A.4.4. Estimated amount of emission reductions over the chosen crediting period:
Years Annual estimation of emission reductions
in tonnes of CO2 e
1 655,793
2 653,443
3 651,102
4 648,771
5 646,449
6 644,136
7 641,833
8 639,539
9 637,254
10 634,919
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 7
Total estimated reductions (tonnes of CO2e) 6,453,239
Total number of crediting years 10
Annual average over the crediting period of
estimated reductions (tonnes of CO2 e)
645,324
A.4.5. Public funding of the project activity:
There is no public funding for the project activity.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 8
SECTION B. Application of a baseline and monitoring methodology
B.1. Title and reference of the approved baseline and monitoring methodology applied to the
project activity:
ACM0007 Version 04, “Consolidated methodology for conversion from single cycle to combined cycle
power generation”
“Tool to calculate the emission factor for an electricity system”, Version 2
“Tool to determine the remaining lifetime of equipment”, Version 1
“Combined tool to identify the baseline scenario and demonstrate additionality”, Version 2.2
“Tool to calculate project or leakage CO2 emissions from fossil fuel combustion”, Version 2
B.2. Justification of the choice of the methodology and why it is applicable to the project
activity:
Applicability criteria of the methodology ACM0007, Version 04
This methodology applies to project activities that utilize previously-unused waste heat from a power
plant, with a single-cycle capacity, be it a gas turbine or an internal combustion engine and utilize the
heat to produce steam for a turbine thus making the system combined-cycle.
The proposed project activity involves the conversion of block one and block two at the grid connected
power plant in Shirvan from single-cycle to combined-cycle mode. It will use previously unused waste
heat from the power plant to power the steam turbines.
Waste heat generated on site is not utilizable for any other purpose on-site
Waste heat cannot be used for other purposes on site, since no other source of demand if located nearby.
The project activity does not increase the lifetime of the existing gas turbine or engine during the
crediting period, determined using the “Tool to determine the remaining lifetime of equipment”;
The project does not involve any upgrade or modification to the existing gas turbines themselves.
Therefore, the conversion does not affect the lifetime of the installed equipment. The gas turbines have a
lifetime of 25 years, as indicated in official documentation by the manufacturer. This is in line with the
“Tool to determine the remaining lifetime of equipment”, Version 1.
The table below shows the commissioning dates of the different gas turbines and the expected end-date
of the lifetime of the gas turbines:
Number of power unit Number of gas turbine Synchronization date End-date of lifetime
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 9
of gas turbine
Block 1 Gas turbine 1 16.03.2006 16.03.2031
Gas turbine 2 10.05.2006 10.05.2031
Block 2 Gas turbine 3 05.07.2006 05.07.2031
Gas turbine 4 06.09.2006 06.09.2031
The project has a crediting period of 10 years. Therefore, the installed equipment will not reach the end
of its lifetime during the crediting period.
Project developers have access to appropriate data to estimate the combined margin emission factor, as
described in the “Tool to calculate the emission factor for an electricity system”, of the electricity grid to
which the proposed project is connected
The project developers have access to the appropriate data. The combined margin emission factor was
calculated as described in the “Tool to calculate the emission factor for an electricity system”, Version
02. See section B.6.3 below.
B.3. Description of the sources and gases included in the project boundary:
The spatial extent of the project boundary includes the power plant at the project site and all power
plants considered for the calculation of the baseline CO2 emission factor. A flow diagram of the project
boundary, physically delineating the project activity is presented below:
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 10
The following table illustrates which emissions sources are included and which are excluded from the
project boundary for determination of both baseline and project emissions.
Source Gas Included? Justification / Explanation
Baseline
Scenario Baseline: Grid
electricity generation
CO2 Yes Main emission source
CH4 No Excluded for simplification. This is conservative
N2O No Excluded for simplification. This is conservative
On-site fossil fuel
consumption to operate
project power plant in
CO2 Yes An important emission source
CH4 No Excluded for simplification. This emission source is
assumed to be very small
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 11
open cycle mode. N2O No Excluded for simplification. This emission source is
assumed to be very small
Project Activity
On-site fossil fuel
consumption to operate
the gas turbine or
engine of project power
plant.
CO2 Yes An important emission source
CH4 No Excluded for simplification. This emission source is
assumed to be very small
N2O No Excluded for simplification. This emission source is
assumed to be very small
On-site fossil fuel
consumption to
supplement waste heat
in operating Steam
turbine.
CO2 Yes May be an important emission source
CH4 No Excluded for simplification. This emission source is
assumed to be very small
N2O No Excluded for simplification. This emission source is
assumed to be very small
B.4. Description of how the baseline scenario is identified and description of the identified
baseline scenario:
In line with the requirements of ACM0007 Version 04, the “Combined tool to identify the baseline
scenario and demonstrate additionality” Version 2.2 is used to determine the baseline.
Step 1: Identification of alternative scenarios
This step serves to identify all alternative scenarios to the proposed CDM project activity that can be
then baseline scenario through the following Sub-steps:
Step 1a: Define alternative scenarios to the proposed CDM project activity
Identify all alternative scenarios that are available to the project participants and that provide outputs
or services with comparable quality, properties and application areas as the proposed CDM project
activity. These alternative scenarios shall include:
- The proposed project activity undertaken without being registered as a CDM project activity
Description of Alternative Plausibility Check
The project activity (i.e switch from
open to combined cycle at block one
and block two of the power plant) not
implemented as a CDM project
Delivers comparable output as project activity.
Is available to IPDC (a project participant).
� Plausible but not financially attractive (see step 3)
- All other plausible and credible alternative scenarios to the project activity scenario, including
the common practices in the relevant sector, that deliver outputs or services (e.g. electricity, heat
or cement) with comparable quality, properties and application areas, taking into account,
where relevant, examples of scenarios identified in the underlying methodology;
The tool gives further guidance that credible alternative scenarios shall:
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 12
- be situated in the Islamic Republic of Iran
- be available to the project participants
New power plants using technologies other than the one used in the project activity, which attain a
similar scale than the proposed project activity:
Description of Alternative Plausibility Check
Open cycle Medium-Large Gas Turbine
Technical lifetime up to 20 years
Efficiency up to 34.5%
Source: Information provided by
Ministry of Energy of Iran
Can deliver comparable output as project activity, subject to
fuel availability.
Is available to IPDC (a project participant).
� Plausible, but faces fuel availability barrier (see step
2).
Steam Plant (using residual fuel oil and
natural gas)
Technical lifetime: 30 years
Source: World Bank Iran Power Sector
Note
Efficiency: up to 37-39%
Source: UNFCCC-Tool: Tool to
calculate the emission factor for an
electricity system
Can deliver comparable output as project activity, subject to
fuel availability.
Is not available to IPDC (a project participant), since not being
developed anymore due to high capital costs and lead times in
construction.
Not plausible => excluded.
Coal Power Plant
Technical lifetime: 40 years
Source: OECD study - Projected costs
of generating electricity 2005 update
Efficiency: 37-50%
Source: UNFCCC-Tool: Tool to
calculate the emission factor for an
electricity
Can deliver comparable output as project activity, subject to
fuel availability.
Is not available to IPDC (a project participant), since no coal
fired power plants have been developed in Iran.
Not plausible => excluded.
Diesel Oil Power Plant
Technical lifetime: 20 years
Source: OECD study - Projected costs
of generating electricity 2005 update
Efficiency: 30-46%
Source: UNFCCC-Tool: Tool to
calculate the emission factor for an
electricity system
Cannot deliver comparable output as project activity, since
diesel oil power plants are built at much lower capacity1.
Is available to IPDC (a project participant).
Not plausible => excluded.
Nuclear Power
Technical lifetime: 60 years
Delivers comparable output as project activity.
1 The largest diesel oil power plant ever built in Iran has a capacity of 125 MW, less than 50% than the proposed
project activity. No more diesel power plants have been built since 1992 in Iran.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 13
Efficiency: 36%
Source: IEA Energy Technology
Essentials – Nuclear power
http://www.iea.org/techno/essentials4.p
df
Is not available to IPDC (a project participant), since nuclear
power plant at Bushehr is developed by the Atomic Energy
Organization of Iran (AEOI).
Not plausible => excluded.
Large hydropower plant
Technical lifetime (up to 100 years)
Efficiency 34% - 56%
Source: IEA Energy Technology
Network http://www.etsap.org/E-
techDS/PDF/E07-hydropower-GS-
gct.pdf
Can deliver comparable output as project activity, if big
enough reservoir to supply base-load electricity.
Is not available to IPDC (a project participant), since hydro
power plants in Iran are developed by either Iran Water and
Power Resources Development Co. (IWPCO) or the
Khuzestan Water & Power Authority (KWPA)
Not plausible => excluded.
Wind
Technical lifetime: 25 years
Source: OECD study Emission
baselines estimating the unknown
/2000
Efficiency: up to 40%
Source:
http://en.wikipedia.org/wiki/Wind_powe
r#Capacity_factor
Does not deliver comparable output as project activity, since
wind farms are an intermittent source of power. Therefore
wind farms cannot be used to displace base load capacity.
Is available to IPDC.
Not plausible => excluded.
- If applicable, continuation of the current situation and, where relevant, the “proposed project
activity undertaken without being registered as a CDM project activity” undertaken at a later
point in time (e.g. due to existing regulations, end-of-life of existing equipment, financing
aspects).
Description of Alternative Plausibility Check
Continuation of the current practice, ie.
that to meet the demand in the grid
system the electricity will be generated:
1) By the operation of the existing
power plant in open cycle
mode;
2) By the operation of existing
grid-connected power plants;
and
3) By the addition of new
generation sources to the grid
Delivers comparable output as project activity.
Is available to IPDC (a project participant).
� Plausible
Outcome of Step 1a: List of plausible alternative scenarios to the project activity
Scenario Title of Alternative
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 14
1 The project activity (i.e switch from open to combined cycle at block one and
block two of the power plant) not implemented as a CDM project
2 Open cycle Medium-Large Gas Turbine
3 Continuation of the current practice
Sub-step 1b: Consistency with mandatory applicable laws and regulations
The alternative(s) shall be in compliance with all mandatory applicable legal and regulatory
requirements.
In addition, the methodology ACM0007 v.04 specifies explicitly that the following regulations should be
taken into account:
• Regulations for utilization of waste heat on the premises where it is generated;
No regulations for the utilization of waste heat on the premises exist.
• Regulation on energy efficiency norms for power projects; and
No regulation on energy efficiency norms for power plants exists. Open cycle and combined
cycle power plants continue to operate in Iran, showing that they satisfy all existing energy
efficiency norms for power plants.
Emission norms for power projects.
Open cycle and combined cycle power plants continue to operate in Iran, showing that they
satisfy all existing emission norms for power plants.
No other mandatory applicable laws and regulations exist which could exclude any of the plausible
alternative scenarios.
Outcome of Step 1b: List of alternative scenarios to the project activity that are in compliance with
mandatory legislation and regulations […].
Scenario Title of Alternative
1 The project activity (i.e switch from open to combined cycle at block one and
block two of the power plant) not implemented as a CDM project
2 Open cycle Medium-Large Gas Turbine
3 Continuation of the current practice
Step 2: Barrier analysis
This Step serves to identify barriers and to assess which alternatives are prevented by these barriers.
Apply the following Sub-steps:
Sub-step 2a: Identify barriers that would prevent the implementation of alternative scenarios
Establish a complete list of realistic and credible barriers that may prevent alternative scenarios to
occur.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 15
Description of Barrier Plausibility Check
Technological barriers:
Access to fuel
Access to fuel is determined by locally available infrastructure and the
supply contracts entered into with the fuel supplier. Shirvan power plant is
connected to the gas network, but the gas supply contract stipulates a
maximum delivery of 300,000 Nm3 of natural gas per hour. This means that
the maximum available supply of natural gas for Shirvan power plant is
effectively capped. This limits possible capacity extensions for natural gas
fired power plants such as open cycle power plants.
Despite having the second largest gas reserves in the world, gas is becoming
seasonally scarce in Iran because of i) very low domestic gas price which
encourages overconsumption, ii) lack of investment in pipeline
infrastructure and storage that leads to local supply bottlenecks and iii)
underinvestment in gas exploration and extraction2. This has lead to power
plants using diesel in times of high demand of residential gas consumption
(ie. during the winter). This shows that there are severe limitations on how
much additional natural gas can be made available.
Outcome of Step 2a: List of barriers that may prevent one or more alternative scenarios to occur
- Access to fuel barrier
Sub-step 2b: Eliminate alternative scenarios which are prevented by the identified barriers
The following table shows through which factors the identified barriers affect power plant projects:
Barrier Indicators for barriers Explanation
Access to fuel
barrier
Electricity production per
unit of natural gas
(MWh/Nm3)
Due to the relative scarcity of natural gas and the limits
imposed by the gas supply contract for Shirvan Power
Plant, power plants which cannot deliver the equivalent
output as the combined cycle under the existing gas
supply contract will be excluded.
This will allow us to analyze which barrier is affecting which alternative.
Applicability of the different barriers to the scenarios:
Barrier &
indicator
Scenario 1:
project
activity
without CDM
Scenario 2:
open cycle
Scenario 3:
current
practice
Access to fuel
barrier
No additional
fuel needed
Yes,
insufficient gas
available
No additional
fuel needed
2 See World Bank Power Sector Note, p. 20 - 21
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 16
Access to fuel barrier:
Scenario 2: Open cycle power plant requires significant additional natural gas resources to be available.
As explained, gas in general is becoming scarcer in Iran and the local supply of natural gas in Shirvan is
limited by the existing gas supply contract. This contract stipulates that up to 300,000 Nm3 of natural gas
are available in Shirvan. This amount of natural gas is insufficient to increase the capacity at the site by
the same amount as in the proposed project activity.
The efficiency of the existing gas turbines are as follows:
Year Energy input (GJ) Electricity output GJ Efficiency
21/3/2007-20/3/2008 12,735,650 3,766,514 29.57%
21/3/2008-20/3/2009 25,018,172 7,630,996 30.50%
21/3/2009-20/3/2010 22,063,760 6,802,877 30.83%
Average 19,939,194 6,066,796 30.30%
An efficiency of 30.30% implies that when the open cycle power plant is running at full load (840 MW
site conditions), it consumes 258,864 Nm3 of natural gas. Therefore, compared to the amount stipulated
in the contract, only a surplus of 41,136 Nm3 natural gas per hour is available, which limits the
additional capacity that can be installed on site.
Maximum additional capacity that can be installed with 41,136 Nm3 natural gas per hour:
Scenario 2: Open cycle
Additional amount of natural gas
available (Nm3)
41,136
Efficiency % 30.30%
Maximum additional capacity (MW) 133
% of additional capacity installed under
proposed project activity (266 MW)
48%
This clearly shows that Scenario 2 would not deliver equivalent outputs to the proposed project activity
due to the limited amount of fuel available. Hence open cycle gas turbines are prevented by an access to
fuel barrier.
Outcome of Step 2: List of alternative scenarios to the project activity which are not prevented by any
barrier
Scenario Title of Alternative
1 The project activity (i.e switch from open to combined cycle at block one and
block two of the power plant) not implemented as a CDM project
3 Continuation of the current practice
If there are still several alternative scenarios remaining, including the proposed project activity
undertaken without being registered as a CDM project activity, proceed to Step 3 (investment analysis).
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 17
Step 3: Investment analysis
This Step serves to determine which of the alternative scenarios in the short list remaining after Step 2 is
the most economically or financially attractive. For this purpose, an investment comparison analysis is
conducted for the remaining alternative scenarios after Step 2. If the investment analysis is conclusive,
the economically or financially most attractive alternative scenario is considered as the baseline
scenario.
Since the continuation of current practice does not involve an investment on behalf of the project
proponent, a benchmark analysis is conducted. The IRR is chosen as a suitable financial indicator, since
it allows assessing whether a single project activity is financially attractive or not.
The national benchmark for investments in power plants as confirmed by the Ministry of Energy in Iran
is used. It is equal to 20%. The financial analysis is done over the period of conversion and operation of
the power plant. Only costs and revenues which are due to the conversions from open to combined cycle
power plant are taken into account.
The relevant data for calculation of the IRR are tabulated below:
Parameter (unit) Value combined
cycle
Source
Generated Electricity & fuel consumption
Nominal capacity ISO (MW) 318 IPDC – MAPNA
contract
Capacity at site condition (MW) 280 Ministry of
Energy
Degradation (%) 0.40% World Bank Iran
Power Sector
Note
Operating hours (%) 3168 Operating hours
open cycle
plant3
Auxiliary consumption (%) 1.60% World Bank Iran
Power Sector
Note
Costs
Investment costs per unit (EUR) 108,889,182 IPDC – MAPNA
contract
Investment costs per unit (USD) 9,689,964 IPDC – MAPNA
contract
Investment costs per unit (IRR) 1,099,490,909,09
2
IPDC – MAPNA
contract
Operation and maintenance costs
(USD/MWh)
0.69 World Bank Iran
Power Sector
Note
3 Based on historical data
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
SECTION C. Duration of the project activity / crediting period
C.1. Duration of the project activity:
C.1.1. Starting date of the project activity:
01/10/2007, first payment by IPDC to MAPNA for the proposed project activity.
C.1.2. Expected operational lifetime of the project activity:
20 years, 0 months
C.2. Choice of the crediting period and related information:
Fixed crediting period.
C.2.1. Renewable crediting period:
C.2.1.1. Starting date of the first crediting period:
Not applicable
C.2.1.2. Length of the first crediting period:
Not applicable
C.2.2. Fixed crediting period:
C.2.2.1. Starting date:
01/05/2011 or date of registration, whichever is later
C.2.2.2. Length:
10 years, 0 months
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 49
SECTION D. Environmental impacts
D.1. Documentation on the analysis of the environmental impacts, including transboundary
impacts:
Ghods Niroo carried out an Environmental Impact Assessment of the Shirvan Power Plant.
Section D.2 summarizes the main potential environmental impacts, recommended actions and monitoring
responsibilities.
D.2. If environmental impacts are considered significant by the project participants or the host
Party, please provide conclusions and all references to support documentation of an environmental
impact assessment undertaken in accordance with the procedures as required by the host Party:
Remarks Monitoring Agent Frequency of
monitoring
Monitoring
requirement
Recommended
action
Potential
Environmental
Impacts/issues
Main pollutant
parameters as are:
SOx ,NOx , HC ,
COx ,TSPM, H2S
Reliable Private Lab
Consulting
Companies
Approved by DOE
According to
EMS Plan( Stack
Sampling &
Monitoring
program)
Stack Emission
Standards
provided by
DOE10 of Iran
Should be
followed
Concentration of
air pollutant
parameters be
monitored
Emission of
Power plant main
stacks
HSE11 after
commencement
of operation :the
once every
months
Emission of any
ducts����
Main pollutant
parameters as are:
SO2 ,NO2 , HC ,
CO , PM10 , H2S
Reliable Private Lab
Consulting
Companies
Approved by DOE
According to
EMS Plan (air
quality Sampling
or Monitoring
program)
Clean air
Standards
provided by DOE
of Iran should be
followed
Ambient air
quality be
monitored Ambient Air
Different pollutant
parameters such as:
PM10, Mist , Fumes
& etc.
Reliable Private Lab
Consulting
Companies
Approved by MOH
Initially 3months
after
commencement
of operation,
then once every
6months
Indoor air
Standards
provided by
MOH12 of Iran
Should be
followed
Indoor air quality
be monitored
Indoor Air
COx NOx HC Reliable Private Lab
Consulting
Companies
Approved by DOE
Quarterly Testing Passenger
&Trucks
Vehicles
emission
Standards
provided by
DOE of Iran
Should be
followed
Motor Vehicles
Exhaust Gas be
tested
Mobile Sources
LEQ at Daily & Reliable Private Lab According to Sound Level LEQ of Noise Out door Sound
10 Provincial Department of Environment = DOE
11 Department of power plant Health Safety Environment = HSE
12 Ministry of Health = MoH
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 50
Night Hours Consulting
Companies
Approved by DOE
EMS Plan (Noise
pollution Testing
or Monitoring
program
Standards
provided by
DOE of Iran
Should be
followed
pollution be
monitored
Level
SPL & LEQ Reliable Private Lab
Consulting
Approved by MOH
after
commencement
of operation :the
once every
months
Sound Level
Standards
provided by
MOH of Iran
Should be
followed
SPL & LEQ of
Noise pollution be
monitored In door Sound
Level
pH,BOD 5 ,COD,
TSS, TDS,ABS,
Total & Fecal
Coliforms, Oil &
Grease
Reliable Private Lab
Consulting
Approved by DOE
once every
months
Waste Water
discharge
Standards
provided by DOE
of Iran Should be
followed
Water Quality
parameters &
Level of oil &
grease in water be
monitored
Water Discharge
Reliable Private
Execution
Companies
Approved by
MOM°
every day Appropriate
positioning of
waste bins
Disposal off at the
waste disposal site
by Malayer
district Solid Waste
Reliable Private
Execution
Companies
Approved by DOE
or MOM°
Continuously Appropriate
positioning of
Hazardous waste
bins & Chambers
Disposal at the
hazardous waste
disposal site
Approved by DOE Industrial Waste
SECTION E. Stakeholders’ comments
E.1. Brief description how comments by local stakeholders have been invited and compiled:
To collect feedback from local stakeholders on the proposed project activity, the project participants
organized a public meeting on April 10 2011 (21.01.1390 in the Persian calendar). The meeting was
announced on April 6 2011 (17.01.1390) in a local newspaper. Direct invitations to key stakeholders were also sent. 35 stakeholders including workers at the power plant, members of neighboring
communities and authorities took part in the meeting. The meeting lasted for 1.5 hours. It was started
with a presentation on the proposed project activity and its benefits. Then background information on the
CDM and climate change were given. Finally there stakeholders were invited to comment directly on the
project. Stakeholder feedback was received verbally, and are compiled in the minutes of the meeting.
E.2. Summary of the comments received:
During the discussions, the following points were raised:
- Mr. Mousavi who works for the local administration asked, whether the CDM could also be used
to finance the conversion of the third block of the power plant to combined cycle, which is
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 51
currently not included in the project activity. The presenter explained that this option was being
evaluated.
- Ms Naghdi asked whether the fact that the project was going to benefit from the CDM was going
to increase local employment. No such concrete plans exist, but the presenter found this an
interesting suggestion. Other participants strongly supported this suggestion.
- Mr Jamshidi, a local resident expressed his wish that Shirvan was going to be the first CDM
project in Iran, to demonstrate the local commitment to preserving the environment.
- Multiple questions concerning the CDM were answered, and several new project ideas (landfill,
energy efficiency) were brought up.
In a final poll on the project, all present stakeholders expressed their strong support for the proposed
project activity.
E.3. Report on how due account was taken of any comments received:
The stakeholders attending the local stakeholder consultation meeting were all very supportive to the
proposed project. There were no objections received. The project participant will put proper measures
into effect as described in the EIA during construction and operation to minimize the negative impacts on
the environment.
PROJECT DESIGN DOCUMENT FORM (CDM PDD) - Version 03
CDM – Executive Board
page 52
Annex 1
CONTACT INFORMATION ON PARTICIPANTS IN THE PROJECT ACTIVITY