Top Banner
SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng
15

SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Dec 19, 2015

Download

Documents

Bryce Stone
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

SWANA Chapter Conference 2008

West Edmonton Landfill

Leachate Treatment Plant

By Steve Johnson M.Eng, P.Eng

Page 2: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Introduction

• Leachate Management Options

• West Edmonton Leachate treatment process

• Treatment Plant Commissioning/Status

• Lessons learned

Page 3: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Leachate Management Options

• Dispose to municipal wastewater treatment plant

• Dispose to deepwell

• recirculate

• Onsite treatment

• Mechanical plant

• Evaporator

• wetlands

• Do nothing

Page 4: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Leachate treatment process

• Phases of leachate management since 1974• Do nothing

• dust control

• Recirculation/offsite deep well disposal

• Develop leachate treatment plant

Page 5: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Leachate treatment process

In 2006 evaluate leachate treatment options• Consultants

• Leachate quantity estimate

• Technology evaluation

• Disposal options

• Haul to deepwell – unreliable

• Recirculation no longer approved by AENV

• City of Edmonton sewer bylaw

• To reduce liability best to treat on-site

Page 6: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Treatment Plant Commissioning/Status

• New Logic Research Inc. http://www.vsep.com/

• Vibratory Sheer Enhanced Processing technology

• Leachate pilot plant test conducted in US

• Pilot test basis• 5 day trial

• Several membranes investigated for pressures, short term line out, concentration, cleaning

Page 7: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Treatment Plant Commissioning/Status

                                                        

Page 8: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Treatment Plant Commissioning/Status

Page 9: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Treatment Plant Commissioning/Status

Page 10: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Treatment Plant Commissioning/Status

• Plant set up during fall of 2007• 4 Feed tanks• 3 mix tanks• 2 concentrate tanks• 2 permeate tanks• Hot water tank• VSEP skid• Pumps, valves, hoses

• Treatment R&D trials for approximately 6 months• Leachate mixes as quality varies throughout landfill• Single pass and percent recovery modes• pH, anti-scaling, and process temperature

Page 11: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Treatment Plant Commissioning/Status

• Quality targets• Permeate - City of Edmonton sanitary sewer bylaw

• Permeate - Agriculture irrigation guideline

• Concentrate - Non-haz waste – AB User’s Guide

• Operational finding with current leachate mix• Single pass mode

• 4 to 4.5 m3/hr depending on cleaning frequency

• Permeate to concentrate ratio of 80:20

Page 12: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Treatment Plant Commissioning/Status

• Operational finding with current leachate mix (cont.)• Percent recovery mode

• Membrane efficiency decreases at a faster rate then single pass

• Concentrate quality worse then single pass

Current Operation• Six hours per day five days per week

• Two hours per day for cleaning

Page 13: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Treatment Plant Commissioning/Status

• Future developments• R&D to trial temperature adjustment (heat exchanger), pH

adjustment, and anti-scaling to determine affect on membrane performance

• Plan to add another shift in route to automate plant for 24 hr/d operation

• To include additional feed, blend, and concentrate tanks

• Treatment target of 6 to 7 m3/hr

Page 14: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Lessons learned

• New computer hard drives can crash (have a back-up)• There is always one or more parameters where mass balance

doesn’t apply to the laboratory results between feed, concentrate and permeate

• New Logic Research has good customer service and documentation (process binders, operations binders)

• Plant design to include upgraded breaker and checkvalve in cleaning loop

• Laboratory response time is inadequate for R&D• Limited odour experienced • R&D takes much longer than anticipated

Page 15: SWANA Chapter Conference 2008 West Edmonton Landfill Leachate Treatment Plant By Steve Johnson M.Eng, P.Eng.

Questions