Energy Planning and Approval Strategies Sustainable Energy Policy 1
34

Sustainable Energy Policy1. 2 Strategic – BC Hydro Long Term Planning Project level Environmental Assessment ▪ Federal ▪ Provincial Integration.

Dec 29, 2015

Download

Documents

Edward Townsend
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Energy Planning and Approval Strategies

Sustainable Energy Policy 1

Page 2: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Overview

Sustainable Energy Policy 2

Page 3: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

outline

Strategic – BC Hydro Long Term Planning

Project level Environmental Assessment

▪ Federal▪ Provincial

Integration

Sustainable Energy Policy 3

Page 4: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

BC Hydro – supply gap

Sustainable Energy Policy 4

Page 5: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

BC Hydro - planning

Integrated electricity planning - the long-term planning of electricity generation, transmission, and demand-side resources to reliably meet forecast requirements.

2000s - long-term acquisition plan (LTAP) every 4 yrs Needs to be reviewed and approved by BCUC

2010 Clean Energy Act – IRP replaces LTAP Same problem for analysis and decision-

making but different consultation, review, and

approval

Sustainable Energy Policy 5

Page 6: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Utility planning

Planning context, objectivesGross (pre-DSM) demand forecastsResources (supply and DSM) – ID and

measurementDevelop resource portfoliosEvaluate and select resource

portfoliosDevelop action planConsultGet approval Sustainable Energy Policy 6

Page 8: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

BCUC decision – rejected plan for 4 reasons

1. did not adequately addressed self‐sufficiency

2. DSM plan not adequately supported by analysis

3. Rejected plan to reduce its reliance on Burrard Thermal

4. Rejected special target for Clean Power Call

Sustainable Energy Policy 8

Page 9: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

BCUC decision –bottom line Mostly, critical of the lack of evidence

or analysis underlying BC Hydro’s plan not a challenge to government policy,

but as a criticism of BC Hydro for not providing sufficient evidence that it was complying with government policy

Exception: refusal to endorse BC Hydro’s desire to reduce reliance on Burrard Thermal

Sustainable Energy Policy 9

Page 10: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

BCUC decision - controversy  Critics of private power projects, including the

BC New Democratic Party, declared victory, claiming the decision is a rejection of the BC government’s plan to rely on private power for future electricity supply. 

Climate activists blasted BCUC “a serious blow to the clean energy transition and climate leadership in British Columbia.”

First Nations denounced the Commission for creating roadblocks to their ability to use green power projects to promote economic development.

Sustainable Energy Policy 10

Page 11: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

BC government response

April 2009 Throne Speech : BC government clarified that the BCUC “will receive specific direction”  

October 2009: Special direction #2: ordered BCUC to rely on no more than 900 MW capacity and 0 GW/yr firm energy

May 2010: Clean Energy Act passed. New IRP process Removed from BCUC scrutiny

Sustainable Energy Policy 11

Page 12: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Sustainable Energy Policy 12

Page 13: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Evaluation

What are the consequences of removing BC Hydro planning from BCUC review?

Sustainable Energy Policy 13

Page 15: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Change in Self-sufficiency Timing delayed by rate review Old: by 2016 enough B.C.-based energy to

meet customer demand even in critical water conditions; and by 2020, an extra 3,000 gigawatt hour per year of insurance energy

New: by 2016, enough B.C.-based energy to meet customer demand in an average water year

The Province will also propose changes to the Clean Energy Act to eliminate the insurance requirement Sustainable Energy Policy 15

Page 16: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Project level – Environmental Assessment

Sustainable Energy Policy 16

Page 17: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Approved plan calls for new independent power projects

What happens now?

Sustainable Energy Policy 17

Page 18: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Ashlu Creek

Sustainable Energy Policy 18

Page 19: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Ashlu Creek

49.9 MW – Ledcor – Innergex

Extensive review by Squamish-Lillooet Regional District (SLRD)

SLRD rejected BC government passed

Bill 30 to “bring certainty” to approval process – 2006

Project approved – commercial operation began Dec 09

Sustainable Energy Policy 19

Page 20: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Should local or regional governments have the right to veto power projects?

Sustainable Energy Policy 20

Page 21: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Environmental Assessment

Environmental Assessment as a policy tool – a “procedural policy instrument” Requires analysis and procedure but does not

specify outcome

Sustainable Energy Policy 21

Page 22: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Stages in EA

1. Proposal from proponent2. Screening – is EA required and if so

what kind?3. Scoping – what issues?4. Assessment of the proposal5. Report preparation, submission,

and review6. Decision: recommendation by EA

body, authoritative decision by political body

7. Monitoring and compliance follow-up

Sustainable Energy Policy 22

Page 23: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Environmental Assessment - Federal

Canadian Environmental Assessment Act Came into force in 1995 Since 1972, governed by cabinet

guidelines applies to anything that requires federal

approval or permit Procedures managed by

Canadian Environmental Assessment Agency, within Environment Canada

Usually, if federal EA no provincial EA Sustainable Energy Policy 23

Page 24: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

CEAA Process

1. Determine if an environmental assessment is required

2. Identify responsible authority (RA)3. screening – initial assessment

If potentially significant adverse effects or significant public concern, requires mediation or panel review

4. Conduct the analysis and prepare the environmental assessment report

5. RA Reviews environmental assessment report6. Make environmental assessment decision7. Implement mitigation and follow-up program, as

appropriate Sustainable Energy Policy 24

Page 25: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

CEAA approval standards

(a) where, taking into account the implementation of any mitigation measures that the responsible authority considers appropriate,

(i) the project is not likely to cause significant adverse environmental effects, or

(ii) the project is likely to cause significant adverse environmental effects that can be justified in the circumstances

the responsible authority may exercise any power or perform any duty or function that would permit the project to be carried out in whole or in part

Sustainable Energy Policy 25

Page 26: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

CEAA results

99% of projects approved

Sustainable Energy Policy 26

Page 27: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Case study: Prosperity Mine

Gold and copper mine west of Williams Lake BC

Proposal would use Fish Lake as tailings pond

Federal EA process Proponent insisted

a BC EA be done

Sustainable Energy Policy 27

Page 28: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Case study: Prosperity Mine

PROVINCE

BC gov approves despite serious problems identified by gov agencies in quality of analysis and magnitude of impacts

FEDERAL

Panel assessment far more rigorous on data, analysis

Concluded significant impacts to environment and First Nations concerns

Cabinet rejects mine proposal

Sustainable Energy Policy 28

Update: Taseko has resubmitted a revised proposal that is now under review

Page 29: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

EA issues in CanadaLibrary of Parliament Paper, Conference Board

Vertical Coordination (across jurisdictions)

Horizontal Coordination (across agencies) Includes issues of “substitution”

ScopingCumulative effectsFollowupStrategic assessmentsMissing? Sustainable Energy Policy 29

Page 30: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Cumulative effects?

“effects that are additive or interactive and result from the recurrence of actions over time. Cumulative impacts are incremental and result when undertakings build on or add to the impacts of previous impacts.”

Consideration required in federal rules, permitted but not required in BC

What is the best way to deal with cumulative effects in project level assessments?

Sustainable Energy Policy 30

Page 31: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Enviro Checklist for EA

Sustainability as core objective

Strengthen public participation

Meaningfully engage Aboriginal governments as decision makers

Legal framework for strategic and regional EA

Require comprehensive, regional cumulative effects assessments

Coordinate multiple jurisdictions with highest standards

Transparency Fair, predictable,

accessible Rights over

efficiency

Sustainable Energy Policy 31

Page 32: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Cabinet Directive on Streamlining Regulation (2007): Underlying principles: protect and advance the public interest; promote a fair and competitive market

economy; make decisions based on evidence; create accessible, understandable, and

responsive regulation; advance the efficiency and effectiveness

of regulation; and require timelines, policy coherence, and

minimal duplication.

Sustainable Energy Policy 32

Page 33: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Institutions for renewable energy expansion – criteria (Jaccard et al)

Sustainable Energy Policy 33

Page 34: Sustainable Energy Policy1. 2  Strategic – BC Hydro Long Term Planning  Project level  Environmental Assessment ▪ Federal ▪ Provincial  Integration.

Alternatives, consequencesJaccard et alIRP + PROJECT SPECIFIC ASSESSMENT/APPROVALS risks larger than

necessary local environmental effects

Risks less satisfied public

STRATEGIC ASSESSMENT Risks delay in

renewable development (and climate change mitigation)

Sustainable Energy Policy 34

An important tradeoff that needs to be considered in process design