UITP, CH Brussels, 10-12-09 1/4 Support and User Group -Kick-off-meeting- Time: 10.12.2009 11:00h – 16:30h Place: UITP, Brussels Participants: Organisation Participant Name Initials Organisation Participant Name Initials UITP Caroline Hoogendoorn CH Q’Straint, Europe Alexander Roth AR UITP Yves Amsler YA Metro Lisboa Luis Arega Lopes LL TRIT Florian Steiner FS Ferrocarrils de la Generalitat Francisco Tomás Gómez FG TRIT Peter Wigger PW Ferrocarrils de la Generalitat Juan José Gimeno JG INRETS Vincent Benard VB De Lijn Paul Arends PA INRETS Latifa Furlan LF RATP Jean-Paul Richard JR RATP Daniel Coineau DC TUD Jörg Schütte JS TUD Astrid Schindelhauer AS BME Sághi Balázs SB Bus & Rail Hartmut Schmidt HS UNIFE Bernard von Wullerstorff BW TelSys Dr. Sven Scholz SS Metro de Madrid S.A. María Adela Matamoros Arroyo AM
4
Embed
Support and User Group -Kick-off-meeting-€¦ · -Kick-off-meeting-Time: 10.12.2009 11:00h – 16:30h Place: UITP, Brussels Participants: Organisation Participant Name Initials Organisation
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
10. WP08 - Level of sophistication and relevant technology of security surveillance systems http://ftp.uitp.org/ftproot/euroteam/modsafe_sug_wp8.pdf
UITP
11. WP09 - Global approach for Integrated security needs http://ftp.uitp.org/ftproot/euroteam/modsafe_sug_wp9.pdf
UITP
12. WP12 – Dissemination and Exploitation http://ftp.uitp.org/ftproot/euroteam/modsafe_sug_wp12.pdf
UITP
UITP, CH Brussels, 10-12-09
3/4
Time Item Comments 11:10
– 11:25
Welcome and Presentation of attendees
Brigitte Ollier (UITP, Director EU Projects Unit) opened the meeting and welcomed all the participants. Subsequently, all participants introduced themselves. Caroline Hoogendoorn is replacing Sebastian Emig as European Projects Manager and namely concerning MODsafe. Minor changes in the sequence of the presentation were introduced and WP3 was not going to be presented.
11:25 –
11:40
Presentation of the MODsafe project and project structure
TRIT presented the idea behind MODsafe, explained why the project was needed and what the expected project results were. He also provided an overview of project size, structure, and participating partners.
11:40 –
16:00
Presentation of the MODsafe Work Packages (WP) by the WP leaders
Nine WP leaders presented the WP managed by them, as follows:
- WP1 Description of the State of the Art (INRETS)
- WP2 MODSafe Hazards and Risks Analysis (TUD)
- WP4 Common Safety Requirements (TelSys)
- WP5 Functional and Object oriented Safety Model (TUD)
- WP6 Safety Life Cycle Responsibilities (TRIT)
- WP7 Acceptance, Approval, Certification (BME)
- WP8 Level of sophistication and relevant technology of security surveillance systems (UITP)
- WP9 Global approach for Integrated security needs (UITP)
- WP12 Dissemination and Exploitation (UITP)
The presentations included the objectives and tasks of each WP, timescale and key deliverables.
16:00 –
16:15
Concluding remarks YA informed the operators that: - their feedback was welcome on different documents
(to start, DC has send them the draft deliverable D6.1. for comments – deadline: January 8th – comments to be sent directly to RATP and TRIT)
- they can participate in different working groups (if they wish to do so, they must contact CH)
- CH was their contact point if they had any questions ([email protected])
The next network of operators will be held in Brussels (UITP premises) on May 27th.