Top Banner
Peer Review Oct 2006.ppt | 10/17/2006 BOEING is a trademark of Boeing Management Company. Copyright © 2004 Boeing. All rights reserved. Superconducting Flywheel Development Phil Johnson FESS Program Manager Boeing Phantom Works DOE Energy Storage Systems 2006 Peer Review
14

Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Sep 22, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Peer Review Oct 2006.ppt | 10/17/2006BOEING is a trademark of Boeing Management Company.Copyright © 2004 Boeing. All rights reserved.

Superconducting Flywheel DevelopmentPhil Johnson FESS Program Manager Boeing Phantom Works

DOE Energy Storage Systems 2006 Peer Review

Page 2: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 2Copyright © 2004 Boeing. All rights reserved.

50kW / 5kWh Flywheel Energy Storage SystemOff-Grid Demo System

Objective:•Design, build and deliver a flywheel energy storage system tailored for off-grid applications utilizing a High Temperature Superconducting (HTS) Bearing

Goal:•Successfully integrate the FESS system into a demonstration site

One of three deployment options for the demo system, shown in relation to

diesel genset and balance of system. Status: •The qualification testing of the 5kWh rotor is complete•The direct cooled HTS bearing fabrication is complete•The initial testing of the HTS bearing exceeded expectations•Funding interruption has slid schedule

Page 3: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 3Copyright © 2004 Boeing. All rights reserved.

Typical Load Profile for Remote Village in Alaska

• Now served by multiple diesel systems• Reasonable match for 50 kW power system

• Data provided courtesy of Alaska Energy Authority

Kwigillingok, Alaska (population 338)Photo and data credits Virtual Tourist.com &

encyclopedia.thefreedictionary.com

Page 4: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 4Copyright © 2004 Boeing. All rights reserved.

Proposed System Architecture for Deployment of a 50kW / 5kWh Flywheel Energy Storage System

Benefits of Using FESS Instead of Idling 2nd Generator on Standby• Reduce Generator Maintenance by 50% (estimate)• Reduce Fuel Costs by $80k/yr (estimate)• Lower Pollution

Flywheel Energy Storage System would supply powerduring short peak demand periods

Page 5: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 5Copyright © 2004 Boeing. All rights reserved.

Flywheel Energy Storage Systems Basic Operation

Uninterrupted Regulated (Load Leveled) Power Out

High PulsedPower Out

Surges

Outage

Noise

Freq Var

Spikes

Sags

Page 6: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 6Copyright © 2004 Boeing. All rights reserved.

50kW / 5kWh Flywheel Energy Storage System Project Roadmap

Phase IV: Field Test

• Rotor/bearing• Materials • Reliability

• Applications• Characteristics• Planning

• Site selection• Detail design• Build/buy• System test

• Install• Conduct field testing• Post-test evaluation

6/99 – 9/99

10/07 – 9/08

10/06 – 10/076/06 – 10/-06 (funding interruption)

11/01 – 12/05

5/00 – 3/01 3/01 – 11/-01 (funding interruption)

1/04 – 05/-04 (funding interruption)Phase I: Application ID and Initial System Specification

Phase II: Component Development and Testing

Phase III: System Integration and Laboratory Testing

Phase I: Significant Outputs

•Unit characteristics

•System specification document

Phase II: Significant Outputs

•Prelim design complete

•HTS crystal array complete

•Material lifetime data

•Rotor improvements complete

•Rotor qualification testing complete

•HTS Direct Cooled HTS bearing

Phase III:

•Started October 17, 2006

Page 7: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 7Copyright © 2004 Boeing. All rights reserved.

50 kW / 5kWh Flywheel Energy Storage System 2006 Component Focus

HTS Bearing Stator

Hex YBCO

• Fabrication of direct cooled HTS Bearing

• Initial testing of direct cooled HTS Bearing exceeded expectations

HTS Bearing Rotor

Page 8: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 8Copyright © 2004 Boeing. All rights reserved.

Challenge with HTS Stability Magnetic Assembly Resolved

During assembly by subcontractor, magnet segments chipped and magnets did not align properly.

Worked with subcontractor to resolve manufacturing and assembly issues resulting in a superior assembly

Improved Stability Magnet Subassembly

Page 9: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 9Copyright © 2004 Boeing. All rights reserved.

Previous DOE/Boeing Flywheel terrestrial cryogenics

Return LN2 & N2 (Two phase flow)

LN2

Cryostat (HTS)

Cold Head (to re-condense N2 gas for closed loop LN2 Operation) & ~ Liter Size LN2 Reservoir

Use of a Thermosiphon eliminated a cryogenic pump requirement

HTS Stability Bearing Cryostat Installed in DOE 5 kWh Flywheel

HTS Stability Bearing Cryostat Installed in DOE 10 kWh Flywheel Input LN2 (gravity fed)

Page 10: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 10Copyright © 2004 Boeing. All rights reserved.

Direct Cooling Approach on HTS Bearing

HTS Stability Magnet Assembly (Boeing Patented)

G10 Scuff Plate

HTS Crystal Set (Boeing Patented)

Substrate

Heat Spreader

G10 Strong Back

G10 Support Structure

Cold Head ConnectionTo Heat Spreader

Benefits:•~60% fewer parts

•Reduced power requirements

•Eliminates the requirement for LN2

•Reduces maintenance •Constraint is now the compressor service requirement of maintenance check once every 10,000 hours for Gifford McMahon technology, once every 20,000 hours for Pulse Tube technology

Page 11: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 11Copyright © 2004 Boeing. All rights reserved.

Direct Cooling Approach on HTS Bearing

Page 12: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 12Copyright © 2004 Boeing. All rights reserved.

Direct Cooled HTS Bearing Exceeds LN2 Temperature

LN2 Temperature

Page 13: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 13Copyright © 2004 Boeing. All rights reserved.

Summary / Program Status

• Stability magnet sub-assembly issues were resolved

• Direct Cooling approach worked well and exceeded goal of LN2 temperatures

• Funding interrupt has slid schedule

• Detailed design is ready to move forward

• Current plans include fabrication of motor / generator and lift magnet system moving towards full system integration

Page 14: Superconducting Flywheel Development 2006 Peer Review... · Peer Review Oct 2006.ppt | 2 50kW / 5kWh Flywheel Energy Storage System Off-Grid Demo System Objective: •Design, build

Boeing Technology | Phantom Works Superconducting Flywheel Development

Peer Review Oct 2006.ppt | 14Copyright © 2004 Boeing. All rights reserved.

Acknowledgements

• I would like to acknowledge the help, timely advice, and program guidance of:

• Dr. Imre Gyuk of the U.S. Department of Energy through the Energy Storage Program

• Nancy Clark and John Boyes of Sandia National Laboratories