SunCoke Energy, Inc.
Dec 03, 2014
SunCoke Energy, Inc.
1. Overall Project Summary 2. Safety Plan 3. SunCoke Energy - Contacts 4. Bowen Engineering – Contacts 5. IEA – Contacts 6. Schedules & Logs 7. Operation Plans 8. Quality Control Plan 9. Site Plan & FGD Layout Plan 10. Challenges / Opportunities 11. Team Goals
TABLE OF CONTENTS
Project Summary
• Installation of a new FGD & Components
• Project was awarded on 11/07/08
• Project Value: $ 12,805,000.00
• Estimated start date: Dec. 12, ‘08
• Completion date: Aug. 01, ‘09
• NMA (National Maintenance Agreement) (Tab C) Extension Accepted 11/07/08
• Advance Mobilization Invoiced on 11/07/08 in the Amount of $ 1,920,750.00
Safety
• Weekly jobsite Safety Schedule• Site Specific Safety Plan • Site Specific Safety Incentive Program• JSA’s (Bowen)• Weekly Management Safety Audit• OSHA 300A / Safety Bulletin
Safety Plan
Steve Morey [email protected] VP - Construction
Chris Allen [email protected] Project Manager
Steve Van Nest [email protected] Director – Contracts
Mohammed Noor [email protected] Project Controls
David Kramer [email protected] Project Superintendent
Robert Bennett [email protected] Project Finance
SunCoke Key Contacts
CONTACT INFORMATION Contact Office # Cell # Email
Jeff Purdue – Southern District Manager 812-475-3880 812-305-3775 [email protected]
Aaron Purdue - Operations Manager 812-475-3880 812-305-3769 [email protected]
Robert Redden – Site Manager 812-475-3880 317-502-8975 [email protected]
Roger Havil – Project Superintendent 812-475-3880 812-305-6150 [email protected]
Marc Reynolds – Project Engineer 812-475-3880 812-483-8768 [email protected]
Tami Silver – Project Coordinator 812-475-3880 812-306-5829 [email protected]
Org Chart
Contact Information:
Portland, Maine - IEA Headquarters27 Pearl Street, Suite 1Portland, ME 04101
207-541-5800207-775-0936 (Fax)
Louis Asali - [email protected] – Program Manager
Martin Rilling - [email protected] – Project Manager - (207) 329-3705
Edwin Weddeke - [email protected] – Project Coordinator - (407) 637-9954
OPERATION PLANS
Quality Control Plan
Elevation – All elevations will be double checked by both the Foremen and Engineer and verified against the existing drawings & control
points.
Materials – Confirm Owner Supplied Materials & Damage
Foundation & Slab Quality – • Check all anchor bolts prior to erecting any material.• Check concrete Slab/Foundation elevations.• Establish work area and lay-down areas.
Challenges / Opportunities
Challenges
• Zero Injuries & Accidents• Meet and or beat Schedule & Budget• Gain knowledge of local work force• Working in a confined area• Critical Lifts• Weather
Opportunities• Build stronger SunCoke Energy
relationship thru collaboration & creativity to reduce time & effort.
• Reuse gang panels & miscellaneous tools from completed projects to enhance our budget.
• Utilize learning curve from completed projects to make professional decisions affecting schedule & Budget.
• Obtain additional work from SunCoke.
Team Goals
• Complete this project with ZERO recordable incidents and or accidents
• Become the best contractor SunCoke has ever had on their sites
• Complete this project ahead of schedule and budget• Insure our integrity and core values are portrayed in
all aspects• Utilize our good relationships to gain future work