SUN CITY HILTON HEAD COMMUNITY ASSOCIATION, INC. PURRYSBURG POOL UPDATE
Jan 03, 2016
Project Status
• Substantially Complete with Phases 1 & 2.
• Current Expenditures $1.18m
• Now beginning the final phase. Phase 3.
Construction Phasing
• Phase 1 - Project began by replacing >>>>>>>>>rooftop dehumidifiers.
• Phase 2 - Interior and exterior renovations. - Re-plastering pool revealed
……………….deteriorated condition of shell.
*** Use of machinery and overhead hazards for ceiling work …prevented pool level work until final phase of renovations.
*** Shell condition was unknown until final phase of work.
Phase 1 Dehumidifiers Replacement
• Project began by replacing rooftop dehumidifiers.
• Cost $400k• Work is substantially
complete.
Phase 2 Renovation
• Interior envelope found compromised by moisture intrusion.
• Wall studs and finishes undergone replacement.
• Phase 2 began with initial pool scope to re-plaster only.
Phase 2 Interior / Exterior Surfaces
• Interior and exterior renovations began March 10th
• Cost $800k• Work is substantially
complete.
Phase 3 Launch
• Pool shell condition found unfavorable.
• Deterioration evaluated by Engineering Professionals to determine if current shell is “Fit for Use”
• Recommendations range from Partial Replacement and Localized Repairs to Full replacement.
Phase 3 Action Plan
• Board of Directors has approved full replacement of pool and spa, reducing future risk and extending useful life of the pool.
• Additional cost is $400k
Phase 3 Project Timeline
• New Permit Required (6-8 Weeks)• Construction Work (approximately 7 weeks)• Estimated Completion October 15, 2011
HOW WILL WE PAY FOR THE PURRYSBURG POOL REPAIRS?
• The Community Association maintains a Reserve Fund to cover major repairs and replacement of capital assets such as swimming pools
• If you check your quarterly statement you will notice a $55 charge for reserves
• As of June 1, 2011, the HOA Reserve Fund contains about $6.5 million