P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
Summary Progress Report No. 3
For
Repairs for
Ketch Building
Tall Ships Condominium Project
Salem, South Carolina
MCA Architecture, Inc. Forensics Division
October 12, 2015 MCA Project No. F11705.F
-
Tall Ships Condominium Association Ketch Building Salem, South
Carolina
Summary Progress Report No. 3 MCA Forensics Project No.
F11705.F
October 12, 2015 Page
P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
2
Table of Contents
1. Summary Progress Report No. 3
2. Supporting Photographs
3. Project Schedule - Ketch
4. Application for Payment No. 4
5. MCA Invoice No. 6
6. Copy of Change Order no. 1 (wood rot repair overage)
7. Copy of Change Order no. 2 (tall columns and adjacent
walls)
8. Price Proposals for Additional Scope of Work to Repair Tall
Columns and Adjacent End Walls at the Ketch, Yawl, Square Rigger
and Cutter Buildings dated August 19, 2015
-
Tall Ships Condominium Association Ketch Building Salem, South
Carolina
Summary Progress Report No. 3 MCA Forensics Project No.
F11705.F
October 12, 2015 Page
P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
3
Project Facts
This repair project scope at the Ketch Building includes the
replacement of five (5) bow window stacks of three (3) each, three
(3)end walls including the windows and the removal and replacement
of adjacent EIFS (Synthetic Stucco) wall systems back to stud
exposure.
Framing is inspected for rot and replaced as needed.
Gutters will be removed and eave fascia will be inspected and
repaired.
Fifteen porch columns and three chimney stacks are also being
inspected and repaired at the Ketch Building.
Southeastern Wall Systems, Inc., of Lexington, South Carolina is
the General Contractor for the project. Southeastern was awarded
the Contract in April, 2015 in the amount of $704,366.00.
Mr. Jerry Bullard is the Owner and Project Manager. Mr. Elmer
Solis is the Project Superintendent.
MCA Architecture, Inc., of Greenville, South Carolina is the
Architect of Record and has prepared drawings with specifications
indicating the scope of work and will provide inspection and
coordination during the construction process.
Time and material costs for the wood framing repairs including
the termite damage were approved last meeting. See Change Order
No.1 attached in the amount of $80,233.35 with backup. (This work
has been completed)
Also last meeting the Contractor was authorized to proceed with
the repair of 2 tall columns (one at Ketch and one at Yawl) plus
two adjacent walls at Ketch. See Change Order No. 2 attached in the
amount of $21,020.00 with attached MCA drawings nos. A700 and A701
indicating the limited scope of work.
A pending price proposal for the remaining Scope of Work to
Repair other Tall Columns and Adjacent End Walls at the Ketch,
Yawl, Square Rigger and Cutter Buildings dated August 19, 2015 is
itemized in attachment 8. (Except for the work authorized above in
Change Order no. 2 .) MCA Architecture, Inc., recommends that the
work should be performed along with the present scope of work at
each building if possible. We would like to get approval to
complete the remaining three (3) tall columns at Ketch as part of
this project.
-
Tall Ships Condominium Association Ketch Building Salem, South
Carolina
Summary Progress Report No. 3 MCA Forensics Project No.
F11705.F
October 12, 2015 Page
P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
4
Summary Progress Report
Submittal data on the windows and stucco materials were
submitted and approved before May 12, 2015.
Scaffolding erection started June 1, 2015 and completed July 10,
2015. Demolition work began July 6, 2015 and completed July 31,
2015. Windows were delivered to the site on July 1, 2015.
The demolition work exposed multiple areas of moisture intrusion
and wood rot.
At the end walls, window and balcony header framing was found to
be rotted. Extensive moisture and some termite damage has occurred
on the north end of stack 33.
There was existing framing rot at many levels under the Bow
Windows.
Additional wall framing alignment discrepancies are continuing
to be found at each of the Bow Window areas at all floors. The
Contractor was instructed to rework the window framing to fit the
templates of the new Andersen Windows and include the extra time
and material in the rot allowance. This procedure has become
proto-typical.
Wood framing repairs are complete at the 15 bow windows and at
the three (3) end walls. All bow windows and end wall windows are
installed. Both interior and exterior finishing at these windows is
complete.
At the porch column work the framing has been removed. All
columns required rot replacement and structural wood repairs.
Temporary shoring will remain in place at all private porch columns
until work is complete. The concrete patch and curb have been
re-poured. The new stucco at the porch columns is in progress.
Application of the waterproof “gold coat” to the wood sheathing
is complete. Application of EIFS foam board and base coat is
complete at all walls. Application of the EIFS finish coat is
started.
The Contractor continues to perform the work efficiently and
with care.
Photographic documentation follows.
-
Tall Ships Condominium Association Ketch Building Salem, South
Carolina
Summary Progress Report No. 3 MCA Forensics Project No.
F11705.F
October 12, 2015 Page
P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
5
Views taken September 8, 2015.
Work in progress including “gold coat” water barrier, end wall
windows, bow windows and application of foam and EIFS base coat.
Stucco at porch columns.
-
Tall Ships Condominium Association Ketch Building Salem, South
Carolina
Summary Progress Report No. 3 MCA Forensics Project No.
F11705.F
October 12, 2015 Page
P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
6
Views taken October 1, 2015.
Work in progress including “gold coat” water barrier, end wall
windows, bow windows and application of foam and EIFS base coat.
Stucco at porch columns.
-
Tall Ships Condominium Association Ketch Building Salem, South
Carolina
Summary Progress Report No. 3 MCA Forensics Project No.
F11705.F
October 12, 2015 Page
P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
7
Views taken October 1, 2015.
Windows are installed. Interior finishing is complete.
-
Tall Ships Condominium Association Ketch Building Salem, South
Carolina
Summary Progress Report No. 3 MCA Forensics Project No.
F11705.F
October 12, 2015 Page
P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
8
Views taken October 1, 2015.
Work in progress for repairs at the chimney and gutter
flashings.
-
Tall Ships Condominium Association Ketch Building Salem, South
Carolina
Summary Progress Report No. 3 MCA Forensics Project No.
F11705.F
October 12, 2015 Page
P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
9
Views taken October 1, 2015.
Test cut at Yawl building tall column indicates minimal water
intrusion where vertical cracking occurred.
Test cut at Ketch building tall column indicates water intrusion
and rusty lath. Steel column is supported on a concrete footing.
The stucco terminates just below the grade line. The steel column
is in good condition.
-
Tall Ships Condominium Association Ketch Building Salem, South
Carolina
Summary Progress Report No. 3 MCA Forensics Project No.
F11705.F
October 12, 2015 Page
P.O. Box 6537, Greenville, SC 29606 Tel. 864.232.8204 Fax
864.370.9359
MCA Architecture, Inc. Forensics Division
10
Views taken October 8, 2015.
Views showing installed bow windows and end wall windows. The
stucco finish coat and copper flashing is in progress.
Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide
Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number
9Slide Number 10