8/11/2019 Substation Operation Aand Maintenance Mannuals
1/20
i
Substation
Operation and
Maintenance
8/11/2019 Substation Operation Aand Maintenance Mannuals
2/20
Table of Contents
iii
CONTENTS
1 Substations and Switchyards. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1Introduction to Substations and Switchyards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1Basic Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
Substations: Protective Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5Regulation, Monitoring, and Communication Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .9Switchyards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
Switchyard Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2 Safety in Substations and Switchyards. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .21Hazards and Safety Practices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Safety Practices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
Electrical Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22Chemical Safety. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
Personal Safety . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Using Support Devices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
Dangers and Accidents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30Safety Review. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
3 Power Transformers, Part 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .33Transformer Principles. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
Power Transformers, Current Transformers, and Potential Transformers . . . . . . . . . . . . . . . . . . . . . 35
Power Transformer Cooling Systems, Self-Cooled . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
Power Transformers Cooling Systems, Forced Air/Oil . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
4 Power Transformers, Part 2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .53Visual Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53Inspection of a Transformers Exterior Condition. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
Inspection of a Transformers Sealing System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55Inspection of a Transformers Cooling System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56Gas and Oil Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
Testing for Combustible Gas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
Testing for Oxygen . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
Testing Oil Insulating Strength . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59Tap Changers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
No-Load Tap Changers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
Load Tap Changers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
Tap Changer Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64De-Energizing, Isolating, and Grounding a Power Transformer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
Tap Changer Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66Physical Condition of the Tap Changer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67Mechanical Operation of the Tap Changer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
Electrical Operation of the Tap Changer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
Turns Ratio Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69Calculating the Turns Ratio . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Identifying Bushing Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
Performing the Turns Ratio Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71
Insulation Resistance Test. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72
8/11/2019 Substation Operation Aand Maintenance Mannuals
3/20
Substation Operation and Maintenance
iv
Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72Test Connections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73
5 New Power Transformer Inspection and Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .75On-Car Inspections and Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75
Moving a New Power Transformer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77
On-Site Inspections and Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81
6 Power Transformer Turns Ratio Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .87The Purpose of Transformer Turns Ratio Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87
Test Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88Test Connections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92
Test Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 93
Evaluating Test Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
7 Power Transformer Oil Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .99The Purpose of Transformer Oil Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
Oil Dielectric Test Set . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100
Dielectric Breakdown Strength Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101Oil Sample Taking. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103
Lab Tests. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107
8 Power Transformer Insulation Resistance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .113The Purpose of Insulation Resistance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 113
Test Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 115Test Connections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 118
Test Procedures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 120
Evaluating Test Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 124
9 Power Transformer Temperature Indicator Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .127Temperature Indicators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 127Temperature Indicator Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 132Heater Circuit Testing, Part 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 134
Heater Circuit Testing, Part 2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 138
10 Power Transformer Pressure Relay Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .143Sudden Pressure Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 143
Fault Pressure Relays. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 146
Testing a Sudden Pressure Relay . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 148Testing a Fault Pressure Relay . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 152
11 Circuit Breaker Operation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .157Introduction to Circuit Breakers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 157
Air-Magnetic and Air-Blast Circuit Breakers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 160
Oil and Vacuum Circuit Breakers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162Gas-Blast and Gas-Puffer Breakers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 163
Solenoid and Motor/Spring Operating Mechanisms. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 166
Pneumatic and Hydraulic Operating Mechanisms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 169
12 Circuit Breaker Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .175General Circuit Breaker Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 175
Operating Mechanism Maintenance, Part 1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 179
8/11/2019 Substation Operation Aand Maintenance Mannuals
4/20
v
Operating Mechanism Maintenance, Part 2. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 182
Air-Magnetic and Vacuum Breaker Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 187
Oil Circuit Breaker Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 192
13 New Circuit Breaker Inspections and Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .199Receiving . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 199
Installation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 203Post-Installation Inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 206
Proof Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 208
14 SF6 Gas Properties and Handling. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .213Properties of SF6. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 213
Personal Protection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 215Handling SF6 Gas and Its Decomposition Products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 218
Cleanup . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 221
15 Vacuum Bottle Hi-Pot Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .225Vacuum Interrupter Principles . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 225
Test Principles, Precautions, and Preparations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 227Hi-Pot Test Setup and Steps. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 231Watching for Signs of Breakdown. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 234
16 Circuit Breaker Time-Travel Characteristics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .237Purpose and Principles of Time-Travel Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 237
Circuit Breaker Operations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 239
Circuit Breaker Time Characteristics . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242
Circuit Breaker Travel Characteristics. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 244
17 Circuit Breaker Time-Travel Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .249Time-Travel Test Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 249
Drop-Bar Recorder Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 253Light-Beam Recorder Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 259
Digital Timer/Analyzer Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 263
18 Circuit Breaker Time-Travel Test Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .267Time-Travel Recordings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 267
Electrical Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 270Mechanical Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272
Velocities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 275
19 Contact Resistance Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .279The Purpose of Contact Resistance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 279
Test Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 280
Test Connections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 283Test Procedures and Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 285
20 Capacitors and Reactors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .289Function of Capacitors and Reactors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 289
Clearing Capacitor Banks. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 292
Capacitor Bank Maintenance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 297
Capacitor Resistor and Insulator Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 300Capacitor Capacitance Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 302
8/11/2019 Substation Operation Aand Maintenance Mannuals
5/20
Substation Operation and Maintenance
vi
Shunt Reactors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 305
Series Reactors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 309
21 Voltage Regulators . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .313Voltage Regulator Operation, Part 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 313
Voltage Regulator Operation, Part 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315
Voltage Regulator Control, Part I . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 319Voltage Regulator Control, Part 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 322
Field Inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 325
Field Control Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 326Regulator Replacement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 329
22 Protective Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .333Introduction to Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 333
Overcurrent Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 336
Directional Overcurrent Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 340
Reclosing Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 343Voltage Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 345
Auxiliary Relays. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 347
Solid-State Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 348
23 Protective Relays, Transmission Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .351Introduction to Protective Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 351
Differential Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 354Transfer Tripping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 359
Distance Relays . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 362
Zoned Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 363
Pilot Wire Relaying . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 366Breaker Failure Relaying. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 369
24 Control Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .373Control Functions, Modes, and Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 373
Voltage Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 376
Distribution Feeder Fault Control. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 377Transmission and Subtransmission Feeder Fault Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 380
Station Fault Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 382
Source Circuit Fault Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 384
Routine Checks of Control Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 387
25 Substation Batteries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .391Substation DC Control System Overview. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 391
Cell Components and Electrochemical Action . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 394Cell and Battery Ratings. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 398
Battery Inspection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 401
26 Substation Battery Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .405Voltage and Resistance Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 405
Specific Gravity Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 407Integrity and Capacity Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 410
Impedance Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 415
8/11/2019 Substation Operation Aand Maintenance Mannuals
6/20
vii
27 Substation Battery Chargers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .419Charger Functions and Components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 419DC Control System. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 420
Freshening Charge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 421
Float and Equalizing Charges . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 424
Charger Inspection and Adjustment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 426
28 Substation Battery, Cell and Charger Replacement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .429Cell Replacement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 429Replacing Battery Cells. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 429
Battery Removal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 432
Auxiliary Battery and Auxiliary Battery Trailer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 432
Battery Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 436Inspecting New Cells . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 436
Placing New Cells on the Battery Rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 437
Preparing Electrical Contact Surfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 438Making Intercell Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 439
Battery Charger Replacement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 440Taking the Existing Charger Out of Service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 440
Installing a New Charger . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 441
8/11/2019 Substation Operation Aand Maintenance Mannuals
7/20
Substations and Switchyards
1
CHAPTER
1
Substations and Switchyards
Electricity is a necessity of modern life. Transmission and distribution (T&D) systems provide electricity
to consumers wherever and whenever it is needed. Two of the major components of a typical T&D systemare substations and switchyards.
This chapter examines the role that substations and switchyards play in a T&D system and discusses someof the equipment that is commonly used in substations and switchyards. Security and safety precautionsassociated with substations and switchyards are also covered when appropriate.
Introduction to Substations and Switchyards
Major Components of a Transmission and Distribution System
The major components of a transmission anddistribution system typically include transmissionlines, distribution lines, substations, and switch-
yards. Transmission lines carry electricity from the
generating plant where it is produced, and distri-bution lines carry electricity to the houses, offices,and industries where it is used.
The distances between generating plants andconsumers are often too great to allow electricity
to be carried directly from the plants to theconsumers. To carry electricity over long distances,transmission and distribution systems need voltage
changing substations, which are referred to in thisprogram as substations. An example of a substa-
tion is shown in Figure 1-1. At substations, voltageis increased for efficient transmission over longdistances or decreased for distribution to nearbycustomers.
Besides changing voltage for transmission ordistribution, a transmission and distributionsystem must also be able to ensure that users will
continue to receive electricity even if part of thesystem fails. To meet this rquirement, circuits
Figure 1-1. Substation.
Figure 1-2. Switchyard.
8/11/2019 Substation Operation Aand Maintenance Mannuals
8/20
Substations and Switchyards
11
Shunt reactors are used to improve substationefficiency by adding inductive load to counterbal-ance capacitive loads. A shunt reactor, like the one
shown in Figure 1-33, looks like a power trans-former, except that the bushings on a shunt reactor
are connected with the source circuit; there are nomajor connections leading out of a shunt reactor(such as the secondary connections on a powertransformer).
Monitoring Equipment
Monitoring equipment is used to provide a meansof watching substation equipment and systems
for problems so that they can be limited andcorrected. Commonly used types of monitoringequipment include potential transformers, current
transformers, meters, and relays.
Potential transformers
Potential transformers are devices that reduce linevoltage to a proportionally lower and safer voltage
for metering and relaying. A potential transformer,like the one shown in Figure 1-34, normally has alarge porcelain bushing that insulates the higher
voltage conductor going into the transformer. Thetransformer itself is usually enclosed in a metalhousing. The output wires of the transformers are
enclosed in conduit to protect them. These wiresconnect to meters or relaying equipment in acontrol house.
Potential transformers come in many shapesand sizes. They are sometimes difficult to distin-
guish from other devices such as some currenttransformers and surge arrestors. For this reason,potential transformers are often identified in
substations by signs like the one shown in Figure1-35.
Current Transformers
In contrast to potential transformers, which
reduce line voltage, current transformers reduceline current to a proportionally lower currentfor metering or relaying. Current transformers
can look like potential transformers or surge arrestors. One identifying feature on the currenttransformer shown in Figure 1-36 is a large canister on top of the bushing with a conductor
Figure 1-32. Capacitor bank.
Figure 1-33. Shunt reactor.
Bushings
Source circuit
Shunt reactor
Figure 1-34. Potential transformer.
Bushing
Transformer housing
Conduit
8/11/2019 Substation Operation Aand Maintenance Mannuals
9/20
Power Transformers, Part 1
49
are not always forced-oil/forced-air cooled.
Power transformers with other kinds of coolingsystems can also be gas sealed. Figure 3-36 showsa gas-sealed, self-cooled/forced-air-cooled power
transformer. The cooling system is recognizable by
the combination of the radiator and the fan.Regardless of the type of cooling system that agas-sealed power transformer has, the gas sealsystem works in basically the same way. The simpli-fied illustration in Figure 3-37 represents the
sealing system of a gas-sealed power transformer.The components of the sealing system are a gascylinder, two pressure regulators, two gauges, and a
pressure relief device.
The windings in a gas-sealed power transformer
are completely covered by oil. The rest of theenclosure is filled with gas, which is suppliedthrough tubing from the cylinder. The regulators
ensure that gas is supplied at a pressure slightlyabove atmospheric pressure. This slight positivepressure keeps air and moisture from leaking into
the enclosure.
When the transformer is operating, the windingsheat the oil, causing it to expand. As the expanding
oil compresses the gas, the pressure inside the
enclosure increases. If the pressure rises enoughto exceed a predetermined high value, the relief
device releases gas from the transformer enclosureto atmosphere. The release of gas continues untilpressure returns to an acceptable value.
When the transformer becomes cooler, forexample, during a period of reduced load, the
oil also becomes cooler, and it contracts. As theoil contracts, the pressure inside the transformerenclosure drops. If the pressure falls below a prede-
termined low value, a regulator adds gas from the
cylinder to the enclosure until the pressure returnsto an acceptable value.
The regulators and the relief device in a gas-sealedpower transformer regulate gas flow. The gauges indicate pressure. For example, the gaugeshown in Figure 3-38 indicates the pressure inside the gas cylinder. As gas in the cylinder is used,
the cylinder pressure drops. A low pressure reading means that the gas is running out, and thecylinder may need to be replaced.
Figure 3-35. Gas cylinder, regulators, gauges,
and pressure relief device.
Regulators
Gascylinder
Guage
Figure 3-36. Gas-sealed power transformer,Example 2.
Radiators
Gascylinder
Guage
Figure 3-37. Simplified representation of a
gas-sealed power transformer.
Regulators
Gascylinder
Oil Windings
Guage
Tubing
Pressure relief device
8/11/2019 Substation Operation Aand Maintenance Mannuals
10/20
Power Transformers, Part 2
65
Next, both selector switch A and selector switch B are rotated clockwise, so that selector switch
B slides over to tap 2, and selector switch A slides across tap N to the opposite end of the tap.(Selector switch A remains on tap N.) Since current is not flowing through selector switch B,there is no arcing as the switch changes taps.
Then, transfer switch B is closed, so that current flows across the reversing switch and the raise
tap, labeled R, from left to right through a portion of the tapped winding, across tap 2 andselector switch B, across transfer switch B, and out lead X0. Current continues to flow across theneutral tap, across selector switch A, across transfer switch A, and out lead X0.
Transfer switch A is then opened to interrupt current flow through selector switch A. Both
selector switch A and selector switch B are rotated clockwise, so that selector switch A slides overto tap 2, and selector switch B slides across tap 2 to the opposite end of the tap.
Once selector switch A is on tap 2, transfer switch A is closed, so that current again flows acrossselector switch A and transfer switch A and out lead X0. This completes the tap change. Thenew tap position is shown in Figure 4-18. With
the reversing switch in the Raise position and theselector switches on tap 2, a portion of the tappedwinding is added to the secondary winding. This
changes the ratio of secondary turns to primaryturns and effectively raises the secondary voltage.The first tap position that adds turns to the
secondary winding is called one-raise.
As the selector switches are moved clockwise tothe other taps, turns are added to the secondary to
raise the secondary voltage. When all of the tappedwindings are added, the tap changer is at the full-
raise position.
Figure 4-19 shows the tap changer at full-raise.
To lower the secondary voltage, the selectorswitches are rotated counterclockwise back to theneutral tap. Then, the reversing switch slides from
the Raise position (R) to the Lower position (L),and the selector switches rotate counterclockwisefrom tap N to tap 4.
Figure 4-20 shows the new tap position called:
on-lower.
When the reversing switch is in the Lower position, and the selector switches are on tap 4,current flows from left to right across the secondary winding, across the reversing switch and theLower tap, from right to left through part of the tapped winding, across tap 4 and the selector
switches, across the transfer switches, and out lead X0.
Figure 4-18. Tap changer at one-raise position.
Figure 4-19. Tap changer at full-raise position.
8/11/2019 Substation Operation Aand Maintenance Mannuals
11/20
Power Transformer Insulation Resistance Testing
121
between the high voltage winding and ground to be tested. Although the low voltage winding
is not included in this test, current leakage to the low voltage winding could affect the resis-tance measurement. To avoid this problem, a lead is connected to the guard (G) terminal of themegohmmeter and the low voltage (X) terminal of the transformer. The guard diverts current
that leaks to the low voltage windings so that this leakage current is not included in the test
measurement.
Connections for Testing the Resistance Between the Low Voltage Winding and Ground
The connections for testing the insulation resis-tance between the low voltage winding andground are illustrated in Figure 8-18. One test
lead is connected to the earth (-) terminal of themegohmmeter and to a transformer case ground.Another test lead is connected to the line (+)
terminal of the megohmmeter and to the lowvoltage (X) terminal of the transformer. A lead is
also connected between the guard (G) terminalof the megohmmeter and the high voltage (H)
terminal of the transformer to divert currentthat leaks to the high voltage winding so that thisleakage current is not measured.
Connections for Testing the Resistance Between the
Low Voltage Winding and the High Voltage Winding
The connections for testing the resistance betweenthe low voltage winding and the high voltage
winding are illustrated in Figure 8-19. One testlead is connected to the earth (-) terminal ofthe megohmmeter and to the high voltage (H)terminal of the transformer. Another test lead is
connected to the line (+) terminal of the megohm-meter and to the low voltage (X) terminal of thetransformer. A lead is also connected between the
guard (G) terminal of the megohmmeter and atransformer case ground to divert current thatleaks to ground so that this leakage current is not
measured.
Connections for Testing the Insulation Resistance
Between the Transformer Core and Ground
A transformer core to ground test is a type ofinsulation resistance test that is typically performedafter a transformer has been moved or after any
work has been done inside a transformer. As illus-trated in Figure 8-20, a core ground connects thecore that the windings are wound around to the
Figure 8-18. Connections for testing insulation
resistance between the low voltage winding
and ground.
Figure 8-19. Connections for testing insulation
resistance between the low voltage winding
and the high voltage winding.
Figure 8-20. Transformer core and core ground.
Core ground
Core
Tank, or caseground
8/11/2019 Substation Operation Aand Maintenance Mannuals
12/20
161
Circuit Breaker Operation
is no current flow. Circuit breakers are designed
to take advantage of these momentary absences ofcurrent flow to help extinguish arcs.
Classification of Circuit Breakers
Circuit breakers are generally classified accordingto the dielectric mediums they use to help extin-guish arcs. Four mediums that are commonly used
for this purpose are air, oil, vacuum and gas.
Figures 11-4 and 11-5 show two types of
breakers that use air as a dielectric medium. Theair-magnetic breaker (Figure 11-4) uses air and amagnetic field to help extinguish arcs.
The air-blast breaker (Figure 11-5) uses a high-pressure blast of air.
Figure 11-6 shows an oil breaker. In an oil breaker,the contacts are submerged in insulating oil, whichhelps extinguish the arc.
Figure 11-7 shows a vacuum breaker. A vacuumbreaker encloses its contacts in a vacuum, which
Figure 11-4. Air-magnetic breaker.
Figure 11-5. Air-blast breaker.
Figure 11-6. Oil breaker.
Figure 11-8. Gas-blast breaker.
Figure 11-7. Vacuum breaker.
Figure 11-9. Gas-puffer breaker.
8/11/2019 Substation Operation Aand Maintenance Mannuals
13/20
167
Circuit Breaker Operation
As illustrated in Figure 11-21, a gas-puffer breaker interruptor is enclosed in a pipe-like tank,
which is filled with low-pressure SF6 gas. Theinterruptor is an insulated tube that houses thebreakers interrupting mechanisms and insulates
them from the outer tank.
The interruptors main features (Figure 11-22)include a stationary contact assembly, a movingcontact assembly with a non-conducting nozzle,and a chamber where gas is compressed during
the operation of the breaker. Each of the contactassemblies includes main contact fingers andarcing contact fingers.
When the circuit breaker is closed, the currentpath is through the stationary contact assembly,the main contact fingers and the moving contact
assembly. When the breaker trips (Figure 11-23),the moving contact assembly moves away from thestationary assembly and the main contact fingers
separate. Arcing does not occur, however, becausethe circuit is still complete through the arcingcontacts.
As the moving contact assembly moves awayfrom the stationary assembly, the SF6 gas in the
compression chamber is compressed. Compressingthe gas increases its dielectric strength. Eventually,
the moving contact assembly moves so far that thearcing contact fingers separate, and an arc forms(Figure 11-24).
When the arcing fingers separate, the compres-
sion chamber opens, and thehigh-pressure gasflows through the arc to the low pressure areasof the interruptor. The dielectric strength of the
high-pressure gas weakens the arc. As the gas flowsthrough the arc, the arc is lengthened and cooled,until it eventually extinguishes at a current zero.
Figure 11-21. Gas-puffer breaker.
Bushings
Interruptor
TankLow pressure
SF6gas
Figure 11-23. Gas-puffer breaker interruptor
main contacts open.
Main contactsseparate
Gas
comnpressingin chamber
Arcing contactsstill meet
Figure 11-24. Gas-puffer breaker interruptor -
arcing contacts open.
Arc
Figure 11-22. Gas-puffer breaker interruptor
closed.
Main contactfingers
Moving contactassembly
Compressionchamber
Arcing contactfingers
Stationarycontact assembly
Nozzle
8/11/2019 Substation Operation Aand Maintenance Mannuals
14/20
211
New Circuit Breaker Inspections and Tests
rod travel velocity, and a variety of other circuit
breaker operating characteristics. Figure 13-27 isan illustration of typical time-travel traces.
The time-travel test is typically performed forseveral types of breaker operations. The traces for
each operation can be analyzed to determine howthe breaker is performing in comparison withthe manufacturers specifications. If the breakersperformance does not fall within acceptable ranges,
the breaker must be properly adjusted before it canbe put in service.
Contact Resistance Test
Resistance in the closed contacts of a circuitbreaker can have a number of causes, including
arcing deposits, a loose or incomplete connection,or pitting from repetitive arcing. Contact resistance
creates heat that can reduce the life of the contactsand possibly even lead to breaker failure.
The purpose of contact resistance testing is todetect unacceptably high contact resistance levelsbefore failure occurs.
In principle, the test is performed by passing adirect current through the closed contacts of the
breaker and measuring the voltage drop across the
contacts (Figure 13-28). The test instrument usesthe current and voltage values to calculate anddisplay the contact resistance.
If the contact resistance exceeds an acceptable limit,the contacts may have to be cleaned or replaced.
Insulation Resistance Test
When a circuit breakers contacts are open, thebreakers insulation should provide a high resis-
tance to prevent current from flowing.
The purpose of insulation resistance testing is to
detect unacceptably low levels of insulation resis-tance before poor or weakened insulation results infailure.
In principle, the test is performed by applying ahigh DC voltage to one of the breakers bushing
terminals with the breakers contacts open (Figure13-29). Then, leakage current is measured either to
Figure 13-28. Performing a contact resistance
test.
Figure 13-29. Performing an insulation resistance
test.
Figure 13-26. Transducer and timing rod on an oil
circuit breaker.
Transducer
Timing rod
Figure 13-27. Time-travel traces.
8/11/2019 Substation Operation Aand Maintenance Mannuals
15/20
Substation Operation and Maintenance
294
the power factor in this case by using capacitor
banks, such as the one shown in Figure 20-8. Thecapacitor banks offset the excessive demand forinductive power, and thus bring the power factor
closer to unity.
Excessive demand for non-working capacitivepower also results in a lower power factor thandesirable. In this case, instead of increasing poweroutput to meet the demand for capacitive power,the utility can improve the power factor by using
shunt reactors. The shunt reactors offset theexcessive demand for capacitive power. Figure 20-9shows an example of a typical shunt reactor.
Clearing Capacitor Banks
The main steps for safely clearing a capacitor bankfor maintenance are similar to the steps taken to
clear any other device in a substation. These stepsinclude de-energizing, isolating, testing for dead,and grounding. However, a capacitor bank is
different from other devices in a substation in thatit stores an electrical charge even after the bank hasbeen separated from its source of energy. Because
of this ability to store a charge, some special safetyprecautions are required when clearing a capacitor
bank.
De-Energizing and Isolating a Capacitor Bank
A capacitor bank is de-energized by electricallyseparating the bank from its source of energy.
Figure 20-10 is a simplified illustration of a sectionof a substation that includes an energized three-phase bus, a three-phase circuit breaker, three
single-phase disconnect switches, and a three-phasecapacitor bank. In this example, the capacitor bankis de-energized by opening the circuit breaker.
A capacitor bank is isolated by physicallyseparating the bank from its source of energy. Asillustrated in Figure 20-11, the capacitor bank in
this example is isolated by opening the three single-phase disconnect switches. Opening these switchesprovides a visible break between the source of energy and the capacitor bank.
The actual switching devices that are operated and the sequence in which they are operatedvary with the design of the substation. In general, a capacitor bank is switched out only after
Figure 20-8. Capacitor bank.
Figure 20-9. Shunt reactor.
Figure 20-10. Substation capacitor bank.
Circuitbreaker
Disconnectswitches
Capacitorbank
8/11/2019 Substation Operation Aand Maintenance Mannuals
16/20
333
Voltage Regulators
Isolating the Regulator
After the bypass switch is closed, the regulatorcan be isolated from the circuit. This is done byopening the regulator source and load disconnect
switches. The disconnect switch that is opened
first depends on the design of the system and oncompany procedures.
The specific procedure for switching a regulatorout of service may vary. For example, the type of
switch shown in Figures 22-47 and 22-48 enablesthe regulator to be both bypassed and isolated inone switch operation. The switch in this exampleis made up of two bars. When the switch is closed,
one bar connects the source circuit to the sourcelead of the regulator. The other bar connects the
load lead of the regulator to the load circuit. Thetwo bars are separated by insulators.
By opening the switch, three switching operations
are completed in one action. The first operationis bypassing the regulator. When the switch isopened, a spring operated plate (Figure 21-48)
moves into the space where the switch was. Theplate connects the source circuit to the load circuit,and the regulator is bypassed.
For the second operation, the regulator is isolated
from the source circuit. When the switch is opened,there is a visible separation between the source
circuit and the regulator source lead.
For the third operation, the regulator is isolated
from the load circuit. When the switch is opened,there is a visible separation between the regulatorload lead and the load circuit.
Physically Disconnecting the Regulator
Generally, single-phase regulators in a substation
are grouped in three-phase banks, as shown inFigure 21-49. To remove one of the regulators,all three units must be taken out of service. Afterthe regulators have been switched out of service,
they are tagged, tested for dead, and groundedaccording to company procedures.
To remove the regulator, its conductors are discon-nected from the regulator terminals. In Figure21-50, one of the conductors has been marked Figure 21-49. Three single-phase regulators.
Figure 21-46. Regulator bypass switch closed.
Sourcedisconnect
switch
Loaddisconnect
switch
Bypass switch
Figure 21-47. Disconnect switch.
Regulatorload lead
Barsseparated by
insulators
Regulatorsource lead
Sourcecircuit
Loadcircuit
Figure 21-48. Disconnect switch opened.
Load circuitcontact
PlateSourcecircuitcontact
8/11/2019 Substation Operation Aand Maintenance Mannuals
17/20
365
Protective Relays, Transmission Systems
The specific voltage-to-current ratio setting for a
distance relay is affected by several considerations.For example, a distance relay in substation A can beset for a voltage-to-current ratio that would cause
the relay to operate for a fault anywhere on the
section of line between substations A and B. Withthis setting, however, the relay might trip for a fault
near substation B but between substations B andC (Figure 23-37). This type of relay operation isundesirable, because the basic approach to trans-
mission line protection is to isolate only the section of line in which a fault occurs. For a fault
between substations B and C,a relay in substation B should open a breaker in substation B, and,possibly by transfer tripping, also open a breaker in substation C to isolate the fault. If a distancerelay in substation A operates, it would isolate thesection of line between substations A and B, eventhough that section of line does not have to be
isolated to remove the fault from the system.
Zoned ProtectionTo prevent undesirable operations, a distance relayis generally set to protect approximately 90% of
a line section. This protected section is typicallyreferred to as Zone 1 (Figure 23-38).
To protect line sections between substations,additional Zone 1 sections can be set up (Figure
23-39). However, with this type of protection,approximately 10% of each line section is leftunprotected.
A common way to provide complete protection
for line sections is to use a distance relay in eachsubstation that provides Zone 1 protection in theopposite direction (Figure 23-40). This arrange-
ment provides overlapping protection for each linesection between substations.
In addition to Zone 1 protection, a distance relay
may also provide Zone 2 and Zone 3 protection.For example, as illustrated in Figure 23-41, Zone
2 protection from substation A covers the linesection between substations A and B, as well aspart of the line section between substations B andC. Zone 3 protection from substation A covers the
line sections between substations A and B, substa-tions B and C, and part of the line section beyondsubstation C.
Figure 23-37. Fault between substations B and C.
Figure 23-38. Zone 1 protection.
Figure 23-41. Zone 2 and Zone 3 protection fromsubstation A.
Figure 23-40. Overlapping Zone 1 protection.
= Overlapping protection
Figure 23-39. Multiple Zone 1 protection.
Unprotected linesections
8/11/2019 Substation Operation Aand Maintenance Mannuals
18/20
Substation Operation and Maintenance
376
Sensing Equipment
Sensing equipment is equipment that changes a condition such as voltage or current to a valueor signal that can be measured. For example, potential transformers (Figure 24-1) change, ortransform, line voltage to a proportionally lower voltage for measurement.
Another example of sensing equipment is a current transformer. Current transformers (Figure24-2) transform line current to a proportionally lower current for measurement.
Measuring Equipment
The signals from sensing equipment are typically sent to measuring equipment and control-ling equipment. Measuring equipment measures the signal provided by sensing equipment andindicates the value of the condition being sensed. For example, a meter such as the ammetershown in Figure 24-3 indicates the value of current it receives from a current transformer.
Another example of measuring equipment is a recording meter, such as the one shown in Figure
24-4. A recording meter measures signals from sensing equipment and records the values of thesignals over a period of time.
Controlling Equipment
Controlling equipment detects the signals it gets from sensing equipment, and, if a signal isdifferent from a preset value, provides a signal that operates various other equipment. Anexample of controlling equipment is an overcurrent relay, such as the one shown in Figure 24-5.
An over current relay detects current that it receives from a current transformer. If the current
Figure 24-1. Potential transformer. Figure 24-2. Current transformer.
Figure 24-4. Recording meter.Figure 24-3. Ammeter.
8/11/2019 Substation Operation Aand Maintenance Mannuals
19/20
Substation Operation and Maintenance
396
If alternating current to the charger is interrupted for any reason, the battery will instantlyprovide direct current to the steady, continuous loads and, as required, to the intermittent loads.It will continue to supply the loads until alternating current is restored or until the battery is
fully discharged.
Cell Components and Electrochemical ActionSubstation battery maintenance and testing are more likely to be performed properly when theworker knows the construction of the battery cells, how the cells work, and what can go wrong
with the cells and why. This section describes the components and electrochemical action of atypical lead-acid substation battery cell.
Components of a Lead-Acid Cell
Battery cells used in substations are typicallylead-acid cells. The external components of atypical lead-acid cell (Figure 25-10) include a
container, which is often called a jar, positive andnegative terminal posts, and a vent with a flamearrestor. The flame arrestor shields explosivegases at the vent from external sparks or flames.
The internal components include a liquid calledan electrolyte, conductive lead-based plates, andnon-conductive separators. The electrolyte is
composed of sulfuric acid and water.
Figure 25-11 shows a cell that has been disas-
sembled so that the plates and separators can be
seen. The plates are arranged so that the negativeplates and the positive plates alternate. A cell always
has one more negative plate than positive, and theplates at each end of the cell are negative. This isbecause each positive plate needs a negative plate
on each side of it in order to function efficiently.All the positive plates are mechanically and electri-cally linked together by a bus bar and connected toone of the terminal posts. The negative plates are
also linked together, and they are connected to theother terminal post. The non-conductive separa-
tors insulate the negative and positive plates fromeach other.
The most widely used cell plate design is a type
called the pasted plate, although there is a varietyof other designs. The pasted plate uses porous leadcompounds for the chemically active portions of
the plate. This material is too soft to hold togetherby itself, so it is typically pasted onto a metal grid(Figure 25-12).
Figure 25-10. Components of a lead-acid cell.
Figure 25-11. Disassembled lead-acid cell.
Figure 25-12. Plate grid and lead.
8/11/2019 Substation Operation Aand Maintenance Mannuals
20/20
Substation Operation and Maintenance
terminal of cell 7 is connected to the positive
terminal of cell 8.
To begin the cell replacement procedure, the
jumpers are connected to cells 6 and 8 and tothe new cell (Figure 28-3). One end of a jumper
is connected to the negative terminal of cell 6,and the other end of the jumper is connected tothe positive terminal of the new cell. One endof a second jumper is connected to the positiveterminal of cell 8, and the other end of that jumper
is connected to the negative terminal of the newcell. The jumpers are connected to the terminal sothat they will not interfere with the removal and
reinstallation of the intercell connecting straps.
With the jumpers in place, the bad cell is then
disconnected from the battery by removing theintercell connecting straps between cells 6 and 7and between cells 7 and 8. Because the new cell is
connected in parallel, no arcing occurs when theintercell connecting straps are disconnected fromthe bad cell.
Next, the bad cell is removed from the battery rack,and the new cell is put in its place (Figure 28-4).
Once the new cell is in place, it is connected tothe adjacent cells in the battery. The intercell
connecting straps are reinstalled, connecting thenegative terminal of cell 6 to the positive terminalof the new cell, and the positive terminal of cell 8to the negative terminal of the new cell. Then, both
jumper cables are removed. Connecting a new cellin parallel with the old cell makes it possible toremove and replace a bad cell on a battery that is
still in service.
Bypassing a Cell Using a Diode and Jumpers
As shown in Figure 28-5, the equipment required
for bypassing a cell using a diode and jumpersincludes a jumper with a diode that is connectedin line with the jumper, and two jumpers without
diodes. Also shown in Figure 28-5 are a combus-tible gas detector, an ohmmeter, and the new cell tobe installed in place of the bad cell.
Some companies require that a combustible gasdetector be used whenever work is performed on
Figure 28-4. New cell installed between cells 6
and 8 with temporary jumper connections only.
Figure 28-2. Typical cell arrangement - one bad
cell.
Negative terminals Positive terminals
Bad cell
Figure 28-3. Jumper connections to bypass bad
cell.
New cell
PositiveNegative
Figure 28-5. Equipment for bypassing a cell using
a diode and jumpers.
New cell
Jumber withdiode
Jumperswithoutdiodes
Diode
Combustiblegas detector
Ohmmeter