SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.
23

SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

Jan 14, 2016

Download

Documents

Ada Richard
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

West Fork of Beaver RiverWest Point, OH.

Pre-project pictures. Note eroding outer bank.

Page 2: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMARFlow

Page 3: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Page 4: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Page 5: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

During Installation-Sept 2002

SUBMAR

Exposed pipeline now protected by Submar Articulated Concrete Mattress

Flow

Page 6: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

07/29/03, approximately one year later

SUBMAR

Page 7: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

NOTE: We did not build the two upstream

Bendway Weirs

Page 8: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Close-up of Bendway Weirs

Page 9: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

Looking DS. Recently constructed low, relatively short (average of 25 ft. long) Bendway Weirs, Sept 2002

SUBMAR

Page 10: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

Looking DS. The same 2 low, relatively short Bendway Weirs, 5 years later Sept 17, 2007.

Bank is stable (very flat slope angle compared to the angle of repose) & well vegetated.

SUBMAR

Page 11: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

Looking DS at three Bendway Weirs-

freshly constructed-Sept 2002

SUBMAR

Page 12: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Pix by derrick 9-17-2007

Looking DS at the same 3 Bendway Weirs 5 years after construction. Fines in BW’s have washed out,

but well graded 18 to 24 inch stone is stable. Bank is stable.

Page 13: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

Looking US at two low elevation Bendway Weirs, two years after

construction, 05/11/2004.

SUBMAR

Page 14: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

Looking US at the same two low elevation Bendway Weirs, five

years after construction, 9/17/2007. Note stable bank.

SUBMAR

Page 15: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

Looking US at a barely visible Bendway Weir, two

years after construction (05/11/2004)

SUBMAR

Page 16: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Pix by derrick 9-17-2007 Looking US at a barely visible Bendway Weir, five years after construction,

bank is stable, & Bendway Weir is barely noticeable.

Page 17: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

Flow from left to right over low-elevation Bendway Weir, two years after installation

SUBMAR

Page 18: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Pix by derrick 9-17-2007Flow from left to right over same low-elevation Bendway Weir, five years after installation

Page 19: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Great aquatic habitat due to the deep pools created by the Bendway Weirs. These pools were full of high quality fishes,

indicating that water quality is excellent. {5 years after project completion}

Pix by derrick 9-17-2007

Page 20: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Pipeline protection, two years after installation

Page 21: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Pipeline protection, five years after installation

Pix by derrick 9-17-2007

Page 22: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

SUBMAR

Evidence of recent deposition due to flooding in the field

adjoining the project

Pix by derrick 9-17-2007

Page 23: SUB MAR West Fork of Beaver River West Point, OH. Pre-project pictures. Note eroding outer bank.

The end