STUDI PERENCANAAN EMBUNG KATES (STUDI LOKASI : EMBUNG KATES, DESA KATES, KECAMATAN KAUMAN , KABUPATEN TULUNGAGUNG) Skripsi Diajukan Kepada Universitas Muhammadiyah Malang Untuk Memenuhi Salah Satu Persyaratan Akademik Dalam menyelesaikan Program Sarjana Teknik Disusun Oleh: NIBRAS ROHADATUL ‘AISY 201310340311239 JURUSAN TEKNIK SIPIL FAKULTAS TEKNIK UNIVERSITAS MUHAMMADIYAH MALANG 2017
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
STUDI PERENCANAAN EMBUNG KATES
(STUDI LOKASI : EMBUNG KATES, DESA
KATES, KECAMATAN KAUMAN ,
KABUPATEN TULUNGAGUNG)
Skripsi
Diajukan Kepada Universitas Muhammadiyah Malang
Untuk Memenuhi Salah Satu Persyaratan Akademik
Dalam menyelesaikan Program Sarjana Teknik
Disusun Oleh:
NIBRAS ROHADATUL ‘AISY201310340311239
JURUSAN TEKNIK SIPIL
FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH MALANG
2017
STUDI PERENCANAAN EMBUNG KATES
(STUDI LOKASI : EMBUNG KATES, DESA
KATES, KECAMATAN KAUMAN ,
KABUPATEN TULUNGAGUNG)
Skripsi
Diajukan Kepada Universitas Muhammadiyah Malang
Untuk Memenuhi Salah Satu Persyaratan Akademik
Dalam menyelesaikan Program Sarjana Teknik
Disusun Oleh:
NIBRAS ROHADATUL ‘AISY201310340311239
JURUSAN TEKNIK SIPIL
FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH MALANG
2017
LEMBAR PENGESAHAN
Judul : STUDI PERENCANAAN EMBUNG KATES (STUDI LOKASI :EMBUNG KATES, DESA KATES, KECAMATAN KAUMAN,KABUPATEN TULUNGAGUNG)
Nama : Nibras Rohadatul ‘AisyNIM : 201310340311239
Pada tanggal 29 Juli 2017 telah diujikan oleh Tim Penguji:
AbstractIn dry season, the large part of area in Tulungagung province usually run dry. Many rivers thatalways have much water in rainy season dried up, even get dryness in some area at dry season. Thedesign capacity of the reservoir is based on the rainfall data. But during the rainy season the watercan overflow, kates dam planning can be one of solution to the problem. To find the capacity ofwater intake to the reservoir its needed data conversion from the rainfall data to discharge waterdata. Design of spillway is based on analisys of planned flood discharge that uses sintethicNakayasu unit hydrograph. Main dam uses fill type. Its needed to make a stability control for thedesign of reservoir construction from dangerous condition. As the result the planned flood dischargeis 29,58 m3/sec, storage volume 30.879,70 m3, in +141,27 m elevation as used as reference spillwayelevation , elevation of higest water level at +142,17 m, elevation peak of the dam at +143,17 m,elevation bottom of the river at +133,26 m, high freeboard is 1 m, high of the dam is 10 m, broad ofthe dam is 7 m, slope gradient of up stream 1 :2, slope gradient of down stream 1 :2. The reservoirconstruction stable in various forces of dangerous condition. The storage can fulfill the people needof raw water until 25 year that estimated 6.069 l/person/day for 5141 people..Keywords: Dam, Standart water, Storage Capacity.
AbstrakSaat musim kemarau beberapa tempat sering terjadi kekeringan salah satunya berada di desa Kates,kecamatan Kauman, kabupaten Tulungagung. Masyarakat sekitar desa Kates, bahkan bisakekurangan air saat musim kemarau. Namun saat musim penghujan air bisa melimpah. PerencanaanEmbung Kates bisa menjadi salah satu solusi permasalahan. Perencanaan Kapasitas Embung bisadidasarkan pada data curah hujan. Dan data curah hujan di konversikan ke data debit air.Perencanaan Pelimpah yang digunakan berasal dari perhitungan santuan sintetik Nakayasu. TubuhEmbung menggunkan tipe urugan. Setelah desain konstruksi embung diperoleh, maka dilakukancontrol stabilitas agar bangunan aman terhadap kondisi bahaya. Dari hasil analisa diperoleh debitbanjir rencana periode ulang 50 tahun sebesar 29,58 m3/dt, volume tampungan sebesar 30.879,70 m3
berada pada elevasi +141,27 m yang digunakan sebagai elevasi mercu pelimpah , elevasi muka airbanjir pada ketinggian +142,17 m, elevasi puncak bendungan pada ketinggian +143,17 m, elevasidasar sungai pada ketinggian +133,26 m, tinggi jagaan diambil 1 m, tinggi bendungan 10 m, lebarmercu bendungan 7 m, kemiringan lereng up stream 1 : , kemiringan lereng down stream 1 : 2.Konstruksi stabil terhadap gaya-gaya yang terjadi pada kondisi yang berbahaya. Tampungan yangada, mampu memenuhi kebutuhan air baku(air minum) penduduk pada proyeksi 25 tahun yangberjumlah 5141 jiwa dengan kebutuhan air sebesar 6.069 lt /org/hari.Kata kunci :Air Baku Embung, Kapasitas tampungan