Top Banner

of 28

Structural Condition Report June 2009 Issue 05-06-09

May 30, 2018

Download

Documents

tpitts
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    1/28

    090121

    CONDITIONSURVEY REPORT OF GAELSCOIL NA CAMOIGE

    Prepared for:

    Cairde Group

    Gaelscoil Na Camge

    June 2009

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    2/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    2

    09121

    CONTENTS

    1.0 INTRODUCTION

    2.0 SCOPE

    3.0 DESCRIPTION

    4.0 DISCUSSION

    5.0 RECOMMENDATIONS

    6.0 PHOTOGRAPH LOCATION AND DEFECT IDENTIFICATION

    APPENDIX A PHOTOGRAPHS

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    3/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    3

    1.0 INTRODUCTION

    On the instruction of the Cairde Group, Downes Associates carried out a walk through

    structural appraisal of the various school buildings compromising Gaelscoil Na Camige.

    The survey was carried out by Mr Liam Keogh, Chartered Engineer of Downes Associates onthe 26th May 2009. A number of record photographs were taken during the course of the

    survey. Where referred to in the text, these photographs are included in Appendix A of this

    report.

    2.0 SCOPE

    2.1 The inspection comprised a walk through the various buildings & access to two of the roof

    areas. No opening up works were carried out during the inspection, i.e. the inspection was

    superficial only and could not take account of work that is inaccessible to an ordinary person

    walking around the property; or covered up; or underground. Access to the remaining to roofswas discouraged by the landlord representative during the inspection.

    2.2 The building was inspected on a dry / mild day, of course defects in buildings can depend on

    weather, and it may be that other defects may become apparent during other weather

    conditions.

    2.3 Photographs were taken during the inspection that show the condition of various elements as

    found. These photographs are enclosed in Appendix A. These photographs are presented so

    as to give a general record of the condition of the building.

    2.4 The report is confined to commenting on the present condition of the structure as found. The

    report is not intended to catalogue the extent of any building defects, but rather to comment on

    their nature, i.e. it is not a schedule of dilapidation. Further detailed investigation of particular

    elements of structure may be required at a later date. Recommendations are made with

    regard to remedial works or further review. The report does not deal in detail with items such

    as quality of finishes, weathering details, conservation or planning issues, mechanical and

    electrical installations, fire certificate requirements and other non-structural issues. Where

    issues arising from these are obvious a comment is included to give an overall impression of

    the building as found.

    3.0 DESCRIPTION OF THE BUILDINGS

    The school is located off Watery Lane, Clondalkin, and comprises four separate buildings.

    There is bitumen surfaced play area & pavement around the buildings & grassed areas to

    either end of the site. The buildings are poratcabin type structures of various configurations to

    provide the accommodation. There are two single classroom modules with their own toilets, a

    three classroom & associated staff room, administration offices & toilets module and a four

    classroom module with Head Teacher office and associated toilets. These will be referred to

    as Blocks A, B C & D respectively for the purposes of identification in the report.

    The construction of the modular prefabricated units generally appears to be of timber framedconstruction, with a thin rendered external render finish on plywood sheeting or an external

    painted sheet steel lined wall arrangement. All are flat roofed buildings with falls for rainwater

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    4/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    4

    run-off to the gutter system, discharging to external rainwater downpipes. All of the roofs

    appear to have had either replacement single ply roofing membranes applied, or addition of

    supplementary profiled coated steel roofing sheets. Two prefabricated cabins modules fixed

    together make up each classroom or the administration accommodation rooms. A central

    spine beam, either appearing as an upstand or downstand beam, clear span the length of

    each room and are supported on the end walls. These beams generally appear to be of timberconstruction, and are bolted together along their length at the interface of any two joined

    modules. These beams support one side of the roof. The external walls, all punctuated with

    windows support the other side of the roof. Floors are generally plywood sheeting, supported

    on a timber joisted floor deck. The floor deck and walls are supported at intervals by blockwork

    piers, in turn probably supported off isolated pad foundations internally and possibly on a

    perimeter strip footing foundation. Block B is supported on a trailer chassis, possibly the one

    originally used to transport the unit to the site. All of the buildings are raised off of the ground

    for weathering purposes. Steps up from external ground level to the internal floor level are

    provided, generally constructed of 215mm solid masonry blocks. Timber guard/balustrades are

    also provided.

    Internally the fabric of the building consists painted plaster ceilings & walls and a linoleum

    covered floor. Lighting is provided by traditional florescent double bulb units. The toilets in

    Block D have been provided with a retro fit rudimentary ventilation system. The remaining

    toilets are either ventilate naturally via very small wall vent grill units or via the top hung

    opening window. Heating is generally electric floor mounted units. There is a covered electric

    element type heating unit in the hall/cloaks area of Block B.

    External water tank arrangements are provided on the roofs of Blocks C & D.

    4.0 DISCUSSION

    4.1 Block A.

    4.1.1 A single classroom module consisting two portacabin elements with a newer toilet block

    extension.

    4.1.2 The units appear to have an external painted sheet steel external liner, aluminium/steel

    windows & doors and timber floor with plater lining boards to the walls & ceilings. A new

    extension providing for 2 WCs and a storeroom has been constructed. The roof covering is

    single ply torch on type membrane. Extensive repairs to the membrane have been carried out

    over the years.

    4.1.3 The structure & fabric of the building reflet the original specification for this type of structure

    when it was constructed. The unit appears to be approximately 20 years old. The internal floor

    to ceiling height is 2.17 metres, normally 2.4 metres is considered the minimum.

    4.1.4 Ventilation of the classroom is via open able windows only. The toilets have no mechanical

    ventilation, as required by the current building regulations, normally 15 litres/second or by

    rapid ventilation, i.e. opening a window. The 6500mm2 background ventilation is met by the

    wall vents.

    4.1.5 The roof shows signs of extensive patch repairs and these have been poorly carried out in

    areas. Local ponding of rainwater was visible on the day of the inspection.

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    5/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    5

    4.1.6 The sharp end of the fixings screws used to install the window grills is visible after penetrating

    the widow frame. This is a health & safety issue.

    4.1.7 The linoleum joint bars would appear to constitute a trip hazard.

    4.1.8 There is no fire/smoke detector provided in the store room. Provision of adequate emergency

    lighting should be confirmed by a fire consultant. A review of all on the building with respect to

    this item is recommended.

    4.1.9 The fuse board arrangement should be confirmed in writing as safe for the environment by a

    suitably qualified electrician or electrical engineer.

    4.2 Block B

    4.2.1 A single classroom module consisting two portacabin elements with toilets & entrance cloak

    room. No access gained to roof.

    4.2.2 The units appear to be timber framed with a thin cementitious render applied to plywood

    external sheeting.

    4.2.3 The most unusual aspect of this unit is that the building is supported on an agricultural type

    trailer chassis. This chassis is a steel lattice type framework, in turn supported on concrete

    masonry blocks. The steelwork is now subject to extensive rust penetration.

    4.2.4 The heating element arrangement located in the entrance cloakroom appears unusual for this

    type of occupancy. This arrangement should be confirmed in writing as safe for the

    environment by a suitably qualified electrician or electrical engineer.

    4.3 Block C.

    4.3.1 Three classrooms and staffroom & office accommodation is provided in this block. The units

    appear to be steel sheet lined externally.

    4.3.2 The side wall to one of the classrooms shows signs of structural distress and is significantly

    bowed along its length. A new liner wall has been installed internally. The external steel sheet

    shows signs of severe corrosion in one location & this is the probable cause of the bowing in

    the wall. It is probable that the wall studs and the external sheeting acts as a diaphragm type

    structure to support the roof & provide stability to the structure. The deterioration in the wall is

    a cause for concern & a further evaluation is recommended immediately. This should include

    a temporary propping arrangement along this wall until either a full structural appraisal & any

    associated strengthening regime is carried out, or until replacement units are installed for this

    classroom. This appraisal should be carried out by a charted structural engineer.

    This item requires immediate attention due to the serious nature of the defect.

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    6/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    6

    4.3.3 The water tank on the roof requires a structural engineers sign off as it is probable that the

    original design specification did not allow for this type of loading. Additional strengthening

    works may be required subject to this review.

    4.3.4 The toilets are ventilated by window openings only & given the occupancy level this is totally

    inadequate.

    4.3.5 There has been a new strengthening/support beam installed in one of the classroom units.

    This appears to be in lieu of the support offered by the adjacent end partition support wall. It

    should be confirmed that this work has been carried out by a competent contractor & certified

    by their engineering department.

    4.3.6 Extensive replacement & repair if the roof membrane is evident throughout the roof to Block C.

    Some of the repairs have been carried out to a poor standard. The fixing arrangement for the

    weathering of the upstand beams appears somewhat contrived & the suitability of piercing a

    single ply membrane with fixings in this manner is questionable from a performance point of

    view.

    4.3.7 Water ingress from defective roof membranes has resulted in water ingress to this block.

    Local staining of the plasterboard ceiling is evident in areas. This staining is visible adjacent to

    lighting fittings so the associated risk if fire is evident. This is underscored by the standard of

    repairs noted in Item 4.3.6.

    4.4 Block D.

    4.4.1 Four classrooms and office accommodation is provided in this block. The units appear to be

    timber framed with a thin cementitious render applied to plywood external sheeting.

    4.4.2 New profiled metal deck roofing has been provided to this block. The repair patchwork to the

    ceiling of the rooms inside indicates that water penetration issues had been ongoing for some

    time. The effect of this water penetration on the original structure cannot be determined

    without significant opening up works. Some of the flashing details appear poorly executed at

    the eaves.

    4.4.3 A mechanical ventilation system has been installed in the toilets in this block. The adequacy of

    this system in terms of air change volumes should be verified.

    4.4.4 A water tank has been installed to the roof of this building; again structural adequacy of the

    existing structure should be confirmed by a structural engineer.

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    7/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    7

    5.0 RECOMMENDATIONS

    5.1 The wall defect to Block C, refer to item 4.3.2, should be actioned immediately.

    5.2 The buildings are prefabricated modular buildings of various vintages. It is usual for the design

    life of one of theses building to be in the order of 15 to 25 years. It is apparent that most or allof the buildings on the site have reached the expected design life for a structure of this type. It

    is not usual to carry out major renovations of structures of this type, as the levels of

    intervention required usually warrant replacement of the units with new prefabricated units or

    permanent structure buildings.

    None of the buildings appear to conform to any of the building standards associated with

    modern school buildings & their appropriateness as being fit for purpose must be questioned.

    It is probable that modern replacement units will be both cost effective & will address the

    performance issues of the existing units.

    5.3 A full appraisal of the fire detection and electrical system should be carried out for each of the

    buildings. The issue of ongoing water penetration and the effect on the electrical & fire

    detection systems require to be addressed in this review as this is a potential serious fire risk

    item to both the structure & the occupants.

    5.4 Consideration to carrying out an asbestos survey should also be given. A Type 2 survey is

    recommended at a minimum, as these buildings have potential for contamination due to their

    age.

    5.5 The access steps to the buildings do not conform to modern building regulation standards,

    however as many steps and goings are of varying dimensions, so they never conformed to the

    previous building regulations either. This defect has the most potential consequence if an

    evacuation of any of the buildings is required, over and above the constant trip/fall hazard

    associated with this type of defect.

    5.6 All modifications, i.e. water tank installations, Block C beam strengthening, and the suitability

    of the foundation structure to Block B, should be confirmed by a charted structural engineer.

    The natures of the alterations appear to be on a piece meal basis, as the requirement for

    additional functions arose in the school. It is therefore important to satisfy design & safety

    considerations via this review given the advanced age of the structures on the site.

    6.0 PHOTOGRAPH LOCATION AND DEFECT IDENTIFICATION

    Photo 1

    Photo 2

    Photo 3

    Photo 4

    Photo 5

    Photo 6Photo 7

    Block A: General view of classroom

    Block A: Floor covering join, possible trip hazard.

    Block A: Electrical fuse board, independent electrical report required.

    Block A: Store room in extension. No smoke detector.

    Block A: Fixing hazard to windows.

    Block A: Typical external view.Block A: View to rear of new extension. Note wall vents to WCs.

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    8/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    8

    Photo 8

    Photo 9

    Photo 10

    Photo 11

    Photo 12

    Photo 13Photo 14

    Photo 15

    Photo 16

    Photo 17

    Photo 18

    Photo 19

    Photo 20

    Photo 21

    Photo 22

    Photo 23Photo 24

    Photo 25

    Photo 26

    Photo 27

    Photo 28

    Photo 29

    Photo 30

    Photo 31

    Photo 32

    Photo 33

    Photo 34

    Photo 35

    Photo 36

    Photo 37

    Photo 38

    Block A: Typical roof membrane repair. Note sitting rainwater.

    Block A: Ditto.

    Block B: Typical external view.

    Block B: Typical internal view.

    Block B: Heating element. Appears to constitute fire/burning risk.

    Block B: Unique portacabin support system. Note steel corrosion.Block B: Ditto.

    Block B: Fire escape steps, no guarding & different riser & going dimensions.

    Trip/fall hazard

    Block C: Typical external view.

    Block C: External sheeting. Severe corrosion.

    Block C: Bow in external support wall.

    Block C: Access steps. Different riser dimensions, fall hazard.

    Block C: Access step. Trip hazard.

    Block C: Water tank to portacabin roof.

    Block C: Repair to roof membrane.

    Block C: Ditto.Block C: Weathering of upstand beam detail & patch repairs to membrane.

    Block C: Patch repair, no adhesion.

    Block C: Water ingress from roof causing staining to ceiling below.

    Block C: Water ingress at light fitting location

    Block C: Typical internal view.

    Block C: Typical view of WC. Note window ventilation only.

    Block D: Typical external view

    Block D: Water tank to roof of portacabin.

    Block D: Over-sheeting of original roof with profiled deck roof.

    Block D: Deterioration of external wall panels

    Block D: External escape steps, no guarding and riser & going compliance

    issues.

    Block D: Repairs to water damaged ceiling.

    Block D: Typical view of WC.

    Block D: Reto-fitted ventilation system in toilets.

    Block D: Typical internal view.

    Signed:

    _______________________________________

    Liam Keogh

    Chartered Engineer

    DOWNES ASSOCIATES

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    9/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    9

    APPENDIX A

    PHOTOGRAPHS

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    10/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    10

    Photograph 1

    Photograph 2

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    11/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    11

    Photograph 3

    Photograph 4

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    12/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    12

    Photograph 5

    Photograph 6

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    13/28

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    14/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    14

    Photograph 9

    Photograph 10

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    15/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    15

    Photograph 11

    Photograph 12

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    16/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    16

    Photograph 13

    Photograph 14

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    17/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    17

    Photograph 15

    Photograph 16

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    18/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    18

    Photograph 17

    Photograph 18

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    19/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    19

    Photograph 19

    Photograph 20

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    20/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    20

    Photograph 21

    Photograph 22

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    21/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    21

    Photograph 23

    Photograph 24

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    22/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    22

    Photograph 25

    Photograph 26

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    23/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    23

    Photograph 27

    Photograph 28

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    24/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    24

    Photograph 29

    Photograph 30

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    25/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    25

    Photograph 31

    Photograph 32

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    26/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    26

    Photograph 33

    Photograph 34

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    27/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    27

    Photograph 35

    Photograph 36

  • 8/14/2019 Structural Condition Report June 2009 Issue 05-06-09

    28/28

    Condition survey of Gaelscoil Na Camige, Clondalkin

    Photograph 37

    Photograph 38