Stream Bank Stabilization Options and Techniques Rob Cronauer Watershed Specialist January 22, 2016
58

Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Aug 31, 2018

Download

Documents

duongtram
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Stream Bank Stabilization Options and Techniques

Rob Cronauer

Watershed Specialist

January 22, 2016

Page 2: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Options• #1 Rip-rap

• #2 Rip-rap

• #3 Rip-rap

• #4 Rip-rap

• #5 Other

Page 3: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Rip-Rap

• The #1 used stream stabilization method…and for good reason…..it works!

• Choose proper size

• Install correctly

• There are some right and wrong ways to install

Page 4: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 5: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 6: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Not recommended to place rip-rap on layer of fabric

The fabric can “tent” allowing water behind it. Can be very strong such as a bed sheet catching a falling person.

Page 7: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 8: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 9: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Prevent erosion around and/or under rip-rap• Use large enough rock the stream can’t move

• “key” the rock into the stream bed

• “key” the rock into the upstream and downstream embankments, similar to bridge abutments

• Greatest stream velocity is at the toe of the slope

Page 10: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mowing as close as possible to stream banks prevents woody vegetation and roots to stabilize the bank. The vertical bank on left will never become stabilized.

Page 11: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Would have preferred a more gentle slope but septic system was here

Page 12: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Place largest stone on the “face” of the rip-rap placement, where the greatest velocities are.

Page 13: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Chinking/choking in the voids between the angular stones helps “knit” them together. Use the largest size possible that will still find the voids in the rocks.

Page 14: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 15: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 16: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Jacobs Creek,

Laurellville

BEFORE

Page 17: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Jacobs Creek, LaurelvilleJacobs Creek,

Laurelville

1 year after

project

Page 18: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Jacobs Creek, Laurelville

R-7 keyed into the bank

“chocked with 2b”, and

trees planted on top of

slope, willow stakes on

slope

3 years AFTER

construction

Page 19: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

No room to slope back bank because of the house

Page 20: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Stream won’t move this size rock. Rock keyed into stream bed. Rock above stream will stabilize entire bank. Stream will erode gravel bar. Rock sloped into creek to achieve maximum slope for stability.

Page 21: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mowing as close as possible to stream banks prevents woody vegetation and roots to stabilize the bank. The vertical bank on left will never become stabilized.

Page 22: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Banks have been sloped back to establish vegetation on the banks and the rocks are at the toe, where the greatest velocities exists

Page 23: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mowing as close as possible to stream banks prevents woody vegetation and roots to stabilize the bank. The vertical bank on right will never become stabilized.

Page 24: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Rock at toe of slope only needed on outside bend in the creek

Page 25: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 26: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 27: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Achieving vegetation on banks is crucial to stabilization, and should be a priority immediately after excavation. Erosion control matting can help in this process and can help prevent erosion if the stream should floodbefore grass can become established.

Page 28: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 29: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Shupe Run, Willows Park,

Mt.Pleasant

BEFORE

Page 30: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Shupe Run, Willows

Park, Mt. Pleasant

AFTER

Rock toe with fill and

live stakes

Page 31: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Gabion baskets

• don’t use

• If you have to use them, the greatest chance for failures are from erosion at the start of them, beginning of them, or at the bottom of them

• Must have them embedded into the stream bed and banks, to prevent velocity from getting behind or under them

Page 32: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 33: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 34: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 35: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

The stream couldn’t move the rocks, but could erode out from under and around them

Page 36: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Rock deflectors installed to maintain velocity throughout channel to reduce sediment deposition

Page 37: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Dredging is a temporary solution to a permanent problem.Try to reduce the sediment loading from the source. If that can’t be accomplished increase channel capacity or modify flow.

Page 38: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Some other techniques rather than rip-rap• Stone structures, log structures, bank grading, etc…

• More pleasing to the eye with a more “natural” look

• Can often use on-site materials

• Design for fish habitat

• Should you desire, there are alternatives to rip-rap

Page 39: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 40: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Can be modified into a pond intake

Page 41: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Haymaker Run, Murrysville

Log cross vane, used for a

pond intake, see 4”pvc on

left downstream log

Page 42: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 43: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mowing as close as possible to stream banks prevents woody vegetation and roots to stabilize the bank. The vertical bank on left will never become stabilized.

Page 44: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 45: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 46: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Notice the velocity “white water”

is at the ends of the logs and

well away from the bank

Page 47: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 48: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 49: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mill Creek, Ligonier

BEFORE

Cut leaning trees

Page 50: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mill Creek,

One year after construction

Page 51: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mill Creek

AFTER

Multi-log deflectors

installed, one rootwad, and

live stakes on slopes, and

trees on top of slope

Page 52: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mill Creek

Sediment deposits “building bank”

after first storm

Page 53: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...
Page 54: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mill Creek, Ligonier

BEFORE

Page 55: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mill Creek, Ligonier

Rootwads one year after

construction

Page 56: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Mill Creek

2 years AFTER

Rootwads installed

Page 57: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

Many, many more options

• If your going to use rip-rap keep in mind a few keys. Use large enough rock, embed into banks and stream bed, consider choking with smaller rock. *use oversize rock in urban settings

• If your looking for an alternative to rip-rap, options are endless. I would be happy to help out.

Page 58: Stream Bank Stabilization Options and Techniqueswcdpa.com/wp-content/uploads/Stream-stabilization-.pdf · Stream Bank Stabilization Options and Techniques ... beginning of them, ...

THANK YOU!• Rob Cronauer (724) 837-5271