STP 7 OSHT 1313 JHA Slides
Jan 14, 2016
Group Exercise
• Review the following 4 slides of a job taking place. Write a JHA that addresses ESH and interruption concerns. Assume the following conditions exist:
Scope of Work: Excavate a 5’ wide, 3’11” deep trench in preparation for an electrical duct bank installation and backfill
Environment: OutsideTime of Year: FallWeather: Dry, calm windLocation: Lewisville Data Center Parking Lot