Storage Is Here – Grid-Ready
• ARRA Funding - Batteries
– 8 battery companies received $1.14 billion,
– primarily automotive, but spillover possible
• ARRA Funding – Storage
– Flywheels, Amber Kinetics, Beacon Power
– CAES, NYSEG, PG&E, SustainX “mini-CAES”
– Li Batteries, Seeo Inc., SCE project, DTE/A123
– Lead Batteries, East Penn Ultrabattery
– Si Batteries, 44 Tech Inc.
– Zi/Br, PSNM
– Redox, Ktech Corp
Short-Term Energy Storage in A/S Markets
California ISODemonstrated:-100 kW Beacon FlywheelInterconnected:- 2 MW AES A123 batteries
New York ISO: 5/12/09Demonstrated:-100 kW Beacon flywheels
Planned:-(2) 20 MW Beacon flywheel plants (Stephentown, Glenville)-(3) 20 MW AES battery plantPJM: Spring 2009
Operating:-1 MW AES Altairnano batteries at PJM HQ
Planned:
-20 MW Beacon flywheel plant (Chicago)-20 MW Battery plant (PA)
ISO New England
Operating: 3 MW Beacon Flywheels
Midwest ISO: 1/1/10
Demonstrated:-2 MW AES Altairnano batteries
Operating:- 15 MW Alcoa Reynolds DR
ISOs that have market rules in place to allow energy storage to provide regulation are attracting investment
Initial Driving Force – FERC Order 890
• FERC modified the Regulation and Frequency Response Services tariff to allow provision of those services by generating and non-generation resources. See Order No. 890 at P 888.
“We therefore modify Schedules 2, 3, 4, 5, 6, and 9 of the pro forma OATT to indicate that Reactive Supply and Voltage Control, Regulation and Frequency Response, Energy Imbalance, Spinning Reserves, Supplemental Reserves and Generator Imbalance Services, respectively, may be provided by generating units as well as other nongeneration resources such as demand resources where appropriate.”
Energy Storage in Other ISOs
• Status of Storage in Regulation markets:
– NYISO: FERC approved new market rules for Limited Energy Storage Resources (LESRs) to provide Regulation on May 15, 2009
– Midwest ISO: FERC approved new tariff for Stored Energy Resources (SERs) based on NYISO proposal on December 31, 2009
– PJM: Implemented a frequency-based signal for energy storage resources in March 2009; allow resources to self-manage energy and capacity
– CAISO: Non-generators proposing an energy management method similar to NYISO, is in stakeholder discussions
– ISO-NE: Currently operating a pilot program for alternative technologies, such as energy storage, to provide Regulation and developing permanent market rules
Barriers to Alternative Technologies
Challenge/Barrier Why? Recommendation
Regulation resources required to be dispatched in energy market
• Storage resources not designed for continuous energy injection
• Allow “regulation only” providers
Energy bias in Regulation signal
• Storage fills up or empties • Allow resources to manage their energy level (i.e. NYISO/MISO method)
Reg. High/Low Limit rules don’t work for storage
• Generator/Load rules work for resources that either only inject or only withdraw, not both
• Create storage asset category for resources that both inject and withdraw
Inability to settle net energy at wholesale
• Storage provides regulation by injecting and withdrawing energy (recycles energy)
• Allow net energy settlement at LMP
Pilot Data: Generation Dispatch Method is Not Effective
When Energy Storage does not have the ability to modify its energy base-point, it results in high fade time and under utilization of the resource
• Originally energy base-point was fixed at zero
• When hit extreme state-of-charge LESR faded until signal moved in opposite direction
• No ability to adjust energy base-point
• No ability to utilize LESR’s available regulation capacity
Fade time Fade time
NYISO/MISO: Energy Storage Tariff
•Created New Resource Category:
Limited Energy Storage Resource (LESR) or
Stored Energy Resource (SER)
•Allowed to supply Regulation only
–Eliminated requirement to bid into the energy market
LESR/SER energy level managed by ISO to maintain regulation capability
Resources dispatched based on speed of response
•Hourly Energy Settlement = Net Injections/Withdrawals *LMP
PJM Frequency Based Signal• PJM developed a new ‘frequency-based’ AGC for storage devices;
• Could be similar to ERCOT’s current AGC due to the fact that ERCOT is an ‘island’
• PJM allows storage to self manage its energy base point and capacity in real time under existing market rules
Energy Storage AGC based off the Frequency Error•More volatile – fast changing•Utilizes storage’s fast response speed•Less energy bias
Generator AGC based off of the ACE value•Contains longer term energy trends
The combination of signal and energy management enables LESR/SERs to continuously provide regulation (no fade)
ISO-NE Pilot: “Mileage” Component
2008 Status ISO-NE PJM NYISO CAISOFast First Dispatch N N N
Pay-for-Performance N N N
Maximum Allowable Response time 5 minutes 5 minutes 5 minutes 10 minutes
Regulation Procurement (as % of Avg. Load)
0.80% 1.11% 1.13% 1.35%
Regulation Procurement vs. NE 100%(baseline)
139% 141% 169%
“Regarding compensation, some storage technologies appear able to provide a nearly instantaneous response to regulation signals, in a manner that is also more accurate than conventional resources. These two characteristics can reduce the size, and hence overall expense, of the regulation market. Most existing tariffs or markets do not compensate resources for superior speed or accuracy of regulation response, but such payment may be appropriate in the future ...”
- FERC Chairman WellinghoffTestimony, Senate Hearing on Energy Storage, Dec. 10, 2009
TEXAS Activities
Presidio Battery – AEP
Renewable Technologies Working Group
– Storage; TRIPS Report, MDO5
- Whitepaper on Storage Issues
- http://www.goodcompanyassociates.com/files/manager/StoragePaper20100120.pdf
- Storage key element of 2010 RTWG Agenda
Project 38118 – Storage Investigation