1 Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. http://www.sciencedirect.com/science/article/pii/S0263786315001106 Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques Fernando Acebes a María Pereda b David Poza a Javier Pajares a José Manuel Galán b a INSISOC, Departamento de Organización de Empresas y Comercialización e Investigación de Mercados, Escuela de Ingenierías Industriales, Universidad de Valladolid, Paseo del Cauce 59, Valladolid 47011, Spain b INSISOC, Área de Organización de Empresas, Departamento de Ingeniería Civil, Escuela Politécnica Superior, Universidad de Burgos, Edificio La Milanera, C/Villadiego S/N, Burgos 09001, Spain INSISOC, Área de Organización de Empresas, Departamento de Ingeniería Civil, Escuela Politécnica Superior, Universidad de Burgos, Edificio La Milanera, C/Villadiego S/N, Burgos, 09001, Spain Abstract The aim of this paper is to describe a new integrated methodology for project control under uncertainty. This proposal is based on Earned Value Methodology and risk analysis and presents several refinements to previous methodologies. More specifically, the approach uses extensive Monte Carlo simulation to obtain information about the expected behavior of the project. This dataset is exploited in several ways using different statistical learning methodologies in a structured fashion. Initially, simulations are used to detect if project deviations are a consequence of the expected variability using Anomaly Detection algorithms. If the project follows this expected variability, probabilities of success in cost and time and expected cost and total duration of the project can be estimated using classification and regression approaches. Keywords: Project Management, Earned Value Management, Project Control, Monte Carlo Simulation, Project Risk Management, Statistical Learning, Anomaly detection. 1. Introduction Project control and monitoring involve comparing a plan or baseline with the actual performance of the project. The analyses of these deviations are aimed at taking actions, if needed, to early correct the possible problems that can put in danger the objectives of the plan. The most popular managerial methodology used in Project Management is Earned Value Management (EVM). This framework integrates in a unified approach, three dimensions of the project –scope, time and cost– using monetary units as common pivotal measure (Abba and Niel, 2010, Anbari, 2003, Blanco, 2013, Burke, 2003, Cioffi, 2006, Fleming and Koppelman, 2005, Henderson, 2003, Henderson, 2004, Jacob, 2003, Jacob and Kane, 2004, Kim et al., 2003, Lipke, 2003, Lipke, 2004, Lipke, 1999, McKim et al., 2000). Preprint. Please do not cite this document, use instead: Acebes, F., Pereda, M., Poza, D.J., Pajares, J., Galán, J.M. (In Press) Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. International Journal of Project Management, doi: 10.1016/j.ijproman.2015.06.012 http://www.sciencedirect.com/science/article/pii/S0263786315001106
20

Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

May 02, 2023

Download

Documents

Nacho Nacho
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

1  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques 

Fernando Acebes a 

María Pereda b 

David Poza a 

Javier Pajares a 

José Manuel Galán b 

 

aINSISOC, Departamento de Organización de Empresas y Comercialización e Investigación de Mercados, Escuela de Ingenierías Industriales, Universidad de Valladolid, Paseo del Cauce 59, Valladolid 47011, Spain 

bINSISOC, Área de Organización de Empresas, Departamento de Ingeniería Civil, Escuela Politécnica Superior, Universidad de Burgos, Edificio La Milanera, C/Villadiego S/N, Burgos 09001, Spain INSISOC, Área de Organización de Empresas, Departamento de Ingeniería Civil, Escuela Politécnica Superior, Universidad de Burgos, Edificio La Milanera, C/Villadiego S/N, Burgos, 09001, Spain 

 

Abstract 

The aim of  this paper  is  to describe a new  integrated methodology  for project control under uncertainty. This proposal is based on Earned Value Methodology and risk analysis and presents several refinements to previous methodologies. More specifically, the approach uses extensive Monte Carlo simulation to obtain information about the expected behavior of the project. This dataset  is  exploited  in  several  ways  using  different  statistical  learning methodologies  in  a structured  fashion.  Initially,  simulations  are  used  to  detect  if  project  deviations  are  a consequence  of  the  expected  variability  using  Anomaly  Detection  algorithms.  If  the  project follows this expected variability, probabilities of success in cost and time and expected cost and total duration of the project can be estimated using classification and regression approaches. 

Keywords: Project Management, Earned Value Management, Project Control, Monte Carlo 

Simulation, Project Risk Management, Statistical Learning, Anomaly detection. 

 

1. Introduction Project control and monitoring involve comparing a plan or baseline with the actual performance of 

the project. The analyses of these deviations are aimed at taking actions, if needed, to early correct 

the possible problems that can put in danger the objectives of the plan. The most popular managerial 

methodology used  in Project Management  is Earned Value Management  (EVM). This  framework 

integrates  in  a  unified  approach,  three  dimensions  of  the  project  –scope,  time  and  cost–  using 

monetary units as common pivotal measure (Abba and Niel, 2010, Anbari, 2003, Blanco, 2013, Burke, 

2003, Cioffi, 2006, Fleming and Koppelman, 2005, Henderson, 2003, Henderson, 2004, Jacob, 2003, 

Jacob and Kane, 2004, Kim et al., 2003, Lipke, 2003, Lipke, 2004, Lipke, 1999, McKim et al., 2000).  

Preprint. Please do not cite this document, use instead:  

Acebes, F., Pereda, M., Poza, D.J., Pajares, J., Galán, J.M. (In Press) Stochastic Earned Value Analysis using Monte Carlo Simulation 

and Statistical Learning Techniques. International Journal of Project Management, doi: 10.1016/j.ijproman.2015.06.012 

http://www.sciencedirect.com/science/article/pii/S0263786315001106  

Page 2: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

2  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

Recent research enhances the standard approach to EVM incorporating statistical analysis, learning 

curves or fuzzy set theory, especially for project predictions at completion (Colin and Vanhoucke, 

2014, Hazir, 2014, Lipke et al., 2009, Moslemi Naeni and Salehipour, 2011, Naeni et al., 2011, Narbaev 

and De Marco, 2014, Plaza and Turetken, 2009, Tseng, 2011, Wauters and Vanhoucke, 2014). An 

active  area  of  development  is  currently  focused  on  integration  of  EVM with  risk management 

analysis. Progress  in this  line has produced decision tools based on two metrics to estimate  if the 

deviations may be caused by structural problems or if they are compatible with the expected range 

of variability, derived from the stochastic nature of the project –estimated variability of costs and 

durations of project activities‐ (Pajares and López‐Paredes, 2011). These results have been refined 

using Monte Carlo simulation and statistical control charts (Acebes et al., 2014). 

In this work, we initially investigate the alternative use of Anomaly Detection algorithms to detect 

structural deviations in projects. Assuming the stochastic definition of the project, we then advance 

the  research proposing  the use of  statistical  learning  techniques  and Monte Carlo  simulation  to 

estimate the probability of over‐runs (delays or over‐costs) and the success decision boundaries. The 

analysis  is  completed with  additional methodologies  to  predict  not  only  over‐runs  but  also  the 

expected budget and time. 

The rest of the paper is organized as follows. First, in the 2. Background section, we review previous 

methodologies related to the same problem we face in this research. Then in the 3. Methodology 

section, we explain the statistical learning methodologies we use in our framework, and how we can 

apply them for project control. In particular, we explain the role of Anomaly Detection Algorithms, 

and Classification and Regression techniques. Finally, we address a case study to show how these 

methodologies work together with EVM for project control. 

 

2. Background EVM does not provide a way  to determine whether deviations are due  to  the expected  range of 

variability associated with the stochastic nature of the project or they may be caused by unexpected 

events  affecting  project  runtime.  Knowing  the  reasons  for  project  over‐runs would  provide  the 

project  manager  with  valuable  information  for  decision‐making.  Concretely,  the  fact  of  the 

deviations exceeding the expected variability would be a warning sign that the project realization is 

probably not  running  as planned. Being  aware of  this  situation would  allow  applying  actions  to 

redirect the evolution of the project. 

With this idea in mind, previous research has provided two different frameworks based on EVM that 

inform whether deviations are within the probabilistic expected level or not: the Schedule Control 

Index  (SCoI) / Cost Control  Index  (CCoI) Framework  (Pajares and López‐Paredes, 2011) and, more 

recently, the Triad Methodology  (Acebes et al., 2014). 

 

2.1 The Schedule Control Index (SCoI) and Cost Control Index (CCoI) Framework Pajares and Lopez‐Paredes (2011) use Monte Carlo simulation to obtain the statistical distribution of 

the cost and the duration at the end of the project. This information is used to select the confidence 

level (both in terms of time and in terms of cost) that will be used to monitor the performance of the 

project). If the cost (time) at the end of a particular project is below the cost (time) at the selected 

confidence level, the cost overrun (delay) is considered to be caused by the randomness of the real 

costs (durations) of the activities. Therefore, the difference between the project cost (duration) at 

the confidence level and the mean project cost (duration) gives an idea of the maximum deviation 

Page 3: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

3  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

that can be explained by the stochastic nature of the cost (duration) of the activities. In other words, 

this difference is considered as the size of the cost / time buffers for the project.  

Nevertheless, knowing the size of these buffers at the very end of the project is useless since it does 

not  permit  to make  decisions  that  rectify  the  project  performance  during  runtime.  It would  be 

desirable, however, to know what portion of these buffers is available at any particular time during 

the project execution. To this aim, the authors develop a system to redistribute the size of project 

cost and time buffers throughout the project life cycle. In order to determine the portion of buffer 

that  corresponds  to  each  period,  the  authors  define  the  Project  Risk  Baseline  as  the  residual 

uncertainty to complete the remaining activities of the project. Then, every time interval is provided 

with a portion of the cost / time buffers namely ACBft and ASBft respectively. The size of these buffers 

are  proportional  to  the  risk  eliminated  between  two  consecutives  periods  (i.e.  the  difference 

between two adjacent points in the risk baseline).  

The  authors  define  two  control  indices  based  on  these  buffers:  Cost  Control  Index  (CCoI)  and 

Schedule Control  Index  (SCoI), which are equal  to  the  traditional  indices used by EVM: Schedule 

Variance (SV) and Cost Variance (CV) plus the corresponding portion of the cost / time buffer ACBft=ES 

/ ASBft: 

SCoIt= ASBft + SV 

CCoIt= ACBft=ES + CV 

Therefore, the new criteria to diagnose the time performance of the project are the following: the 

project is behind schedule if SV < 0 (as in the traditional EVM). However, depending on the value of 

ASBft, this delay may be due to by the randomness of the real duration of the activities or caused by 

structural problems. If ASBft is greater than SV (and thus SCoIt > 0), we infer that the delay falls within 

the expected variability. However, if SV is greater than ASBft (and thus SCoIt < 0), the delay may be 

caused by structural problems and thus require measures to redirect the performance of the project.  

Similarly, the index CCoIt warns about cost overruns (CV > 0) and, when they occur, it reports whether 

the overruns are within the expected variability (CCoIt > 0) or not (CCoIt < 0). 

 

2.2 The Triad Methodology: (x, t, c) Acebes et al.  (2014) developed a different method to determine whether the project deviations are 

within the expected variability or whether, on the contrary, they are due to undiscovered factors 

affecting  the project performance.  This method  also uses Monte Carlo  simulation  to obtain  the 

statistic distribution of all the possible realizations of a project. However, unlike the method shown 

above, the authors directly determine the statistical distribution of cost and time at  intermediate 

percentages of completion of the project.  

For every realization of a Monte Carlo simulation, the system provides a final cost and time. That is, 

when the percentage of completion of a simulation is 100% (x = 100%), we obtain the final cost for 

that simulation (c100%) and the final duration for that simulation (t100%). This triad (100%, t100%, c100%,) 

gives a name  to  this methodology. Afterwards,  the algorithm calculates  the cost and  time at  the 

desired intermediate time intervals for that particular simulation. It is important to mention that the 

percentage of completion of the project is calculated in terms of cost. This means that, for example, 

the project is 50% completed at the time when the cost of that realization of the simulation reached 

a half of its final value. Therefore, at this point of the simulation, the triad that defines the state of 

the project is (50%, t50%, c50%). 

Page 4: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

4  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

Each realization of the Monte Carlo simulation will reach the intermediate points of completion at 

different levels of cost and time. This leads to a point cloud (in terms of time and cost) at the selected 

intermediate points. This information allows calculating statistical information at these intermediate 

time  intervals.    Therefore, we  can  determine  a  confidence  level  that may  be  used  during  the 

realization of the real project to check  if the actual values of cost and time at that percentage of 

completion  fall within  the  confidence  level  (project  under  control)  or  not  (need  for  corrective 

measures).  

In order to determine if the cost / time of a running project is under control (or not) at any time for 

a given confidence interval, the authors represent the values of the triads in two dimensional graphs: 

one for cost monitoring (x, cx) and another for time monitoring (tx,x). 

3. Methodology 

3.1 Triads and Monte Carlo simulation The basis of  this  research  stems  from  the  triad method by Acebes et al.  (2014) described  in  the 

previous section. In the same way, we also generate a data universe (realizations of the project) by 

means of Monte Carlo simulation, and this data is used to find the statistical properties of the project 

at any point during its execution.  

However, we make a change in the variables making up the triad. Specifically, we consider a triad 

comprised of the terms (EV, t, c) instead of (%, t, c).  That is to say, for every realization of the Monte 

Carlo simulation, we register the values of EV (earned value) along with the corresponding cost (c) at 

several intermediate points (t) along the project life cycle. This refinement overcomes some of the 

limitations of the technique proposed by Acebes et al. (2014), as it required assuming that EV was 

linear with work execution (i.e. EV = % ∙ BAC; BAC: Budget At Completion) whereas the methodology 

proposed in this article does not require such a hypothesis. Furthermore, the new approximation is 

more usable and intuitive from a practitioners’ viewpoint. In fact, when monitoring a project it is not 

straightforward to calculate the accurate percentage of completion; whereas EV (i.e. the budgeted 

cost of work performed) is a concept project managers are familiar to work with.  

Therefore, by means of Monte Carlo simulation, we obtain ‐ at certain levels of EV along the project 

execution  ‐ a point cloud that represents the time and the actual cost of every realization of the 

simulation. Then, advanced  statistical methodologies are applied  to  this data. On  the one hand, 

treating the data as a classification problem allows knowing whether the project will finish in time 

and cost. On the other hand, processing  the data as a regression problem allows  forecasting  the 

expected cost and time at termination of the project.  

3.2 As a 2D density distribution. Anomaly Detection algorithm Acebes et al. (2014) try to discern the ranging of expected variability generating different instances 

of the project according to the planned variability in different development stages. These simulation 

results are used to build percentile curves to estimate the expected ranges of costs and time. This 

approach represents an  improvement compared to previous techniques but  ignores the time‐cost 

correlation that is sometimes implicit in the definition of duration and cost of individual activities. 

Decoupling  these magnitudes  can  prevent  from  detecting  anomalous  situations  in  the  project 

(producing  false  negatives). One  of  the  contributions  of  this work  is  to  propose  the  techniques 

developed  for  anomaly  detection  (also  known  as  novelty  detection,  outlier  detection,  deviation 

detection or exception mining (Ding et al., 2014)) together with Monte Carlo simulation and triad 

methodology  as  support  tool  to  control  and monitor  stochastic  projects  (estimating  if  project 

deviations are consequences of the project variability) and ‐ if needed ‐ to prompt the appropriate 

correcting actions.  

Page 5: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

5  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

Novelty detection entails finding the observations in test data that differ in some respect from the 

training data (Pimentel et al., 2014). Typically the problem emerges in situations in which there are 

enough data from normal events but data about abnormal situations is rare or inexistent. Precisely 

the goal of a solution to this problem is identifying observations that deviate or are inconsistent with 

the sample data in which they occur (Hodge and Austin, 2004).  

In  order  to  identify  situations  during  development  of  the  project  abnormal  to  the  stochastic 

definition of the project, again multiple instances of the project are simulated using the methodology 

described in the previous section. Given a development stage of the project determined by an earned 

value, the idea is to build a model that describes the normal range of behavior of the project. This 

normality model  is used as a test, comparing  it with the development of the real project.   A wide 

range of the techniques to solve this problem gives then a score  (sometimes probabilistic) to the 

given observation that compared with a decision threshold results in a report about the abnormality 

of the situation. Basically, if the deviations of the project can be explained by its planned variability 

or if they are indicating abnormal performance and the need to take correction measures. 

There are several families of strategies to deal novelty detection techniques (Hodge and Austin, 2004, 

Markou  and  Singh,  2003a,  Markou  and  Singh,  2003b,  Pimentel  et  al.,  2014).  Given  their 

interpretability, in this work we use a probabilistic approach. These methodologies are focused on 

estimating the generative probability density function from the training data. This function is then 

used to calculate the probability that a new observation may have been generated by the distribution 

(Pimentel et al., 2014).  Taking into account that the amount of data is obtained by simulation (and 

consequently can be large enough to have low variance) we have used a non‐parametric approach –

multivariate density estimation– to reduce bias. 

Multivariate density estimation involves fitting a surface, a kernel, on every point of the data set and 

smoothing its contribution into the space around. Then all surfaces are aggregated together giving 

the overall density function. This process is summarized in Fig.  1 

 

Fig.  1. 2D kernel density estimation approach. Every point in the dataset includes an individual kernel (left), all the individual kernels are aggregated to obtain a general density function (right). Based on 

http://en.wikipedia.org/wiki/Multivariate_kernel_density_estimation 

The selection of the smoothing parameter, bandwidth, is crucial because it determines the quantity 

of smoothing of the kernels and so the accuracy of the fitting. In multivariate density estimation, the 

bandwidth  is  a matrix  that  allows  the  orientation  of  the  kernels  and  so  the  orientation  of  the 

estimated density surface. Different techniques for bandwidth selection have been widely studied 

for the univariate case, but the best methodology is yet considered case‐dependent (Zambom and 

Dias, 2012). For the multivariate problem, the most advanced selector to date is the smooth cross‐

validation  (SCV) methodology, which  fits  a  full  bandwidth matrix  (previous  techniques  adjusted 

diagonal bandwidth matrices) (Duong and Hazelton, 2005). 

Page 6: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

6  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

We have used the function Hscv for the smoothed cross‐validation (SCV) bandwidth selector and the 

function kde for kernel density estimation with radial kernels, both from the R package ks (Duong, 

2007). 

 

3.3 As a classification problem Analyzing the data as a classification problem allows us to estimate the probability of the project of 

finishing in time and/or in cost. The following sections are devoted to explaining what we understand 

by classification and the type of validation used to select a classification technique and estimate its 

error. The different classifier algorithms used are then succinctly presented.. 

3.3.1 Classification 

A  classification problem aims  to predict a quantitative variable, often  called  response, output or 

dependent  variable,  with  a  set  of  qualitative  and/or  quantitative  variables  called  predictors, 

independent variables, or just variables.  Adopting this perspective –a classification problem– with 

the  simulated  triads  can  be  very  useful  for  project  control  analysis.  Let’s  assume  a  stochastic 

monitored project in any intermediate situation, a relevant question for a project manager could be: 

“will the project finish in time and cost?” Or more precisely, “how likely is the project to finish in time 

and  cost?”.  If  completing  the  project  in  time  is modelled  as  a  quantitative  variable  Yes/No  or 

completing  the  project  under  budget  is  also modelled  as  quantitative  variable  Yes/No,  all  the 

ingredients for a classification problem are present. 

Using the EVM framework, any project in progress can be characterized by its t=AT (actual time), its 

AC (actual cost) and  its percentage of completion xAT=EVAT / BAC. We propose using classification 

algorithms  (classifiers)  that  fed  with  this  information  can  provide  an  answer  to  the  previous 

questions. In order to do so, our methodology  involves selecting an appropriate classifier and, for 

each x of analysis (when x is equal to xAT), training the classifier with the Monte Carlo simulations. 

For each simulation j and an x of analysis, Txjand Cxjare the independent variables of the classification problem to train the classifier, and the output of each instance is the state of the project from the 

budget perspective, i.e., if the j simulation finished under budget or not; or the state of the project 

from the time perspective, i.e., if it finished in time or not. Once the classifier is trained, the output 

of the monitored project can be predicted given its current AT, AC and EV. Beyond that, taking into 

account that many classification algorithms do not only compute the most likely output but also the 

probability of each response, the classifier can also provide the probability of finishing in time and 

under budget if no additional correction measures are taken. Moreover, project managers can also 

be  reported with  the decision boundaries of  the  algorithm,  that  is,  the  lines AT, AC  for  a  given 

intermediate x that partitions the space of development of the project in more chances to finish in 

time or cost than to incur in delay or over‐cost. Or in other words, what are the stochastic limits of 

time, cost in the development of the project that maintain a favorable forecast for the project. 

3.3.2 Nested Cross Validation 

Classification algorithms often capture patterns that are characteristic of the particular training data 

set but that cannot be generalized to  independent data, especially  in high flexible and  low biased 

models. Classifiers overfit training data, and hence we can only trust in those assessments based on 

data not used during training.   

Cross‐validation  techniques  group  together  a  family  of  strategies  to  properly  select  the  specific 

model among several options or assess  the model’s performance of a given choice. K‐fold cross‐

validation  is one of the most popular approaches. This process consists  in randomly partitioning a 

data  set  into k  subsets –folds– with  the  same number of elements. Correlatively  the  classifier  is 

trained using k‐1 folds and assessed with the remaining fold as independent data. Averaged results 

Page 7: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

7  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

of k rounds decrease the influence of any particular training/test data division. Moreover, multiple 

measures of  the performance allow estimating  the dispersion and  the  test error of  the  statistic. 

Previous research shows that k=5 or k=10 provide an adequate bias‐variance trade‐off of models 

assuming a moderate computational cost (Hastie et al., 2009). 

Although cross‐validation can be used  for model selection and model assessment,  recent studies 

(Anderssen et al., 2006, Varma and Simon, 2006) warn about an optimistic bias in error estimation 

when  the  error  obtained  during  model  selection  is  reported  as  an  estimation  of  the  model 

performance.  In order  to obtain an unbiased estimation of  the  true performance error a nested 

cross‐validation scheme has been suggested (Anderssen et al., 2006, Varma and Simon, 2006).  

Stone (1974) summarizes the gist of nested cross‐validation as “cross‐validatory assessment of the 

cross‐validatory choice”. Nested cross‐validation involves two nested loops: an inner loop aimed at 

model selection in which the parameters of the algorithm are estimated, and an outer loop to assess 

the unbiased performance of the model selected in the inner loop. Original data is partitioned using 

a k‐fold cross‐validation scheme. The inner loop receives iteratively data from k‐1 folds which in turn 

are employed as input data in a k‐fold analysis for every combination of parameters tested for model 

selection. The model with lower error in the inner fold is tested in the outer loop. 

    

3.3.3 Quadratic Discrimination Analysis 

One of  the most popular Bayesian classifiers  is  the discriminant analysis. Given an observation x, 

these algorithms are based on computing the probabilities Pr(Y = k|X = x) for each possible class k, 

and  assigning  the  observation  to  the  class with  higher  probability.  In  order  to  estimate  these 

conditional probabilities (posterior probabilities) Bayes’ theorem is used: 

Pr Y |X

∑  

(1) 

Where  is  known  as  prior  probability  and  denotes  the  probability  that  a  randomly  chosen 

observation belongs  to  the class k and    is  the density  function of X  for an observation  that 

belongs to the class k ( | ). When the training data contains enough observations 

and comes from a random sample,  can be estimated as the proportion of each class. However, 

obtaining an estimation of    requires  some assumptions about  the  form of  the distribution. 

Quadratic  discriminant  analysis  (QDA)  assumes  that  each    follows  a multivariate Gaussian 

distribution with a class‐specific mean and a class‐specific covariance matrix (Hastie et al., 2009). This 

assumption entails estimating more parameters  than  if we suppose  that the covariance matrix  is 

equal for all the classes (Linear discriminant analysis), however this a better choice since QDA is more 

flexible –boundaries separating classes can be any conic section and consequently nonlinear– and 

the size of the training set is not a major concern for this application. Besides, this classifier directly 

gives a probability of belonging to each k class, something relevant from a risk management point of 

view. A  project manager  controlling  a  project  in  an  intermediate  stage  is  not  only  interested  if 

finishing a project on time  is more probable than completing  it with delay but also  is relevant to 

estimate the probabilities of each event. We have used R package “MASS”  (Venables and Ripley, 

2002) for the QDA classification analysis in this work.   

 

3.3.4 Random Forest 

A tree is a nonparametric model composed of nodes and links in a hierarchical structure that can be 

used  for classification or regression.  In a classification problem, every node represents a test and 

terminal nodes associate an  input that passes all tests until that terminal node, with a class  label. 

Page 8: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

8  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

Tree models present many advantages. They are invariant to monotonic transformations, robust and 

straightforward to interpret. But they can suffer from high variance problems, that is, the tendency 

to overfit.  

Random Forests are a technique for reducing variance  in high‐variance  low bias machine  learning 

methods (Breiman, 2001)). Based on the concept of bagging and bootstrap aggregation (Breiman, 

1996)), random forests consist on building an ensemble of models, trees, to form a super model, the 

forest. Each tree is built from an uncorrelated bootstrap sample from the training data set, using in 

each node only a subset of the predictors available to decide. Once all the trees are trained, they are 

all grouped in a combined metric, such as a majority rule vote in the case of a classification problem.  

Random forest are becoming widely used by reason of  its advantageous features (Criminisi et al., 

2011): they have fast and parallelizable algorithms, do not suffer from overfitting, and can exploit 

“Out‐Of the Bag” (OOB) data to analyze the relative importance of the predictors in the classification 

decision and to estimate the classification error pretty accurately. 

 

Fig.  2. The random forest algorithm generates ntree CART trees (T), each one trained from a bootstrapped sample X and using stochastically selected features at each split. For classification problems each tree of the forest (ensemble) votes to give a consensual class. 

 

3.3.5 Support Vector Machines 

Support Vector Machines  (SVM) are  supervised  learning algorithms  initially developed  for binary 

classification but posteriorly generalized for multiclass classification or regression analysis.  In fact, 

the regression version of this algorithm has been recently used in Project Management for prediction 

and project control purposes (Wauters and Vanhoucke, 2014). However, the use of SVM in this paper 

is focused on classification. 

The gist of SVM  is founded on a simple binary  linear classification algorithm, the maximal margin 

classifier, which given a set of training examples, each belonging to one of two classes,  finds  the 

optimal separating hyperplane that divides the space of features into the two categories maximizing 

the  separation margin  between  the  classes  (James  et  al.,  2013).  This  algorithm  classifies  new 

Page 9: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

9  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

observations  to  the  class  according  to  the  side  of  the  hyperplane.  Although  very  intuitive,  this 

classifier requires that the categories be linearly separable which is not often the case. 

SVM refines this idea extending it to non‐linear decision boundaries enlarging the feature space using 

kernels but also including the concept of soft margin –some training examples are allowed to be in 

the wrong side of the margin or even the hyperplane– in order to deal with non‐separable cases. 

One of the problems of SVM comes from the fact that they do not directly give a probability about 

the prediction, a key feature to control and monitoring support for a project manager. This is usually 

circumvented  fitting a  logistic distribution using maximum  likelihood to the predicted data of the 

classifiers (Platt, 2000).  

In  this  paper  SVM  classifiers  with  radial  kernels  have  been  implemented  using  R  package 

‘e1071’(Dimitriadou et al., 2008).  

 

3.4 As a regression problem Data obtained from the triad method not only can be used to estimate the probability to  incur  in 

overruns.  Considering  that  information  as  a  regression  problem,  the  expected  cost  and  time  at 

termination of  the project can also be estimated.  In  the next sections we give some background 

about the definition of the regression problem and explain the techniques used in this paper. The 

validation approach is again nested cross‐validation.   

3.4.1 Regression 

A  regression  problem  entails  the  prediction  of  a  qualitative  or  continuous  variable,  also  called 

response, output or  independent variable as  in the classification problem, with a set of qualitative 

and/or quantitative variables, the predictors.   

In this section we  look to the EVM from another perspective: a regression problem which aims to 

predict the expected budget and time left at a given time defined by a triad (xAT, Txi, Cxi). With this 

technique, if the project is over‐run, we can predict the over‐cost and the delay it is experiencing; or 

the opposite way, how much budget and time the project has left until the finalization. Hence, the 

expected budget and the expected delay are our response variables, and Txi and Cxi our predictors.  

Typically the relationships between the predictors and the response are non‐linear in real problems. 

Although  linear models have some benefits such as that allow  for relative simple  inference, non‐

linear models are more flexible and may lead to more accurate predictions, at the expense of a less 

interpretable model. One option  to approach  this  is  to  include non‐linear  transformations of  the 

predictors in a linear regression model. In this work we address for an even more flexible alternative, 

the Generalized Additive Models. 

 

3.4.2 Generalized Additive Models 

The  Generalized  Additive  Models  (Hastie  and  Tibshirani,  1990)  allow  to  define  non‐linear 

relationships between the predictors and the response, without losing the additive characteristic of 

the multivariable linear regression models which allow to discern the individual contributions of each 

predictor to the response. The regression problem is reformulated such that: 

 

 (2) 

Page 10: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

10  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

Where fi are the unspecified smooth functions. Not all functions need to be non‐linear. We can also 

define nonparametric functions  in two predictors, or different functions for each  level of a factor 

(qualitative variable). 

In this work we have used two types of flexible representations for fi(X): natural splines, an expansion 

of basis functions, and local regression, which belong to the group of scatterplot smoothers. 

To fit both regression models, we have used the Backfitting algorithm (Hastie et al., 2009) for fitting 

additive models estimating all  functions simultaneously by  iteratively smoothing partial residuals.  

We have used the R package “gam: Generalized Additive Models” (Wood, 2006).  

 

3.4.3 Natural Splines 

A smooth function can be represented by using an expansion of basis functions, such as polynomials. 

A  spline  is a  function piecewise‐defined  that allows  for  local polynomial  representation, defining 

several  function  intervals separated by knots. To smooth the places where the polynomial pieces 

connect, one can impose the function to have continuous first and second derivatives in the knots; 

this approach is called cubic spline and it is the most used type, although higher degree fits can be 

used if more smoothness is needed in the joints. 

A natural spline imposes the additional constraint that the function is linear beyond the boundary 

knots, to avoid the erratic behavior of polynomials near the boundaries (Hastie et al., 2009). 

We have used the package “splines” for R. The function ns() generates a natural cubic spline basis 

matrix and the positions of the knots are adjusted using the observations, given the number of knots.  

 

The model proposed is a GAM using natural splines (ns) as functions, as equation (3) summarizes: 

 

 

 

(3) 

The  number  of  knots  for  both  predictors  has  been  selected  simultaneously  so  that  the model 

minimizes the Mean Square Error of the predictions, using the nested cross‐validation methodology.

 

3.4.4 Local Regression 

Local regression  is a different approach for fitting a smooth function.  It  is a nonparametric model 

which involves fitting a low‐degree polynomial model at each point of the training data set, using a 

subset of the data.   The points are weighted so that the closest have the highest weight, using a 

function  to  assign  these weights,  known  as  kernel,  and  a  parameter  to  define  the  size  of  the 

neighborhood (related to the kernel used), and the model is fitted applying weighted least squares 

regression. The degree of the polynomials to be used also needs to be defined, typically 1 or 2. 

We have used the R package “gam” and the function “lo()” to fit a GAM model with local regression 

(loess from package “stats”) as building blocks, as equation (4) summarizes:  

 

 

(4) 

The degree of polynomials to be fit is set to 1 (default). The size of the neighborhood is controlled by 

the parameter span or α (“for α < 1, the neighborhood includes proportion α of the points, and these 

Page 11: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

11  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

have tricubic weighting (proportional to (1 ‐ (dist/maxdist)^3)^3). For α > 1, all points are used, with 

the ‘maximum distance’ assumed to be α^(1/p) times the actual maximum distance for p explanatory 

variables.”) (Cleveland et al., 1992). The value of span for both predictor models has been chosen 

from 0.1 to 1 using nested cross‐validation and selecting the combination of both span parameters 

that minimizes the Mean Square Error of the predictions. 

 

4. Case study 

4.1 Description We illustrate our approach with an example. This selected case has been previously used in project 

network research (Acebes et al., 2014) and is based on Lambrechts et al. (2008). 

The  activity‐on‐node  (AON)  network  is  shown  in  Fig.    3.  The  network  activity  durations  of  this 

example are modeled as normal distributions, one of the most common  in project  literature. The 

chosen network topology highlights the role of parallel paths to better  illustrate the usefulness of 

the approach. 

 

Fig.  3. AON Network 

The details of the parameters used to model this case are described in Table 1. Please note that for 

the sake of simplicity, costs are modelled depending deterministically on duration  (variable costs 

determine the cost of the task for time unit). All the methods explained can be used relaxing this 

assumption and including any stochastic distribution in costs and durations.  

Table 1. Duration and cost of activities of the case study. Duration activities are modelled as normal distributions and costs depend linearly on duration. 

Id. Activity Duration Variance Variable Cost

A1 2 0.15 755

A2 4 0.83 1750

A3 7 1.35 93

A4 3 0.56 916

A5 6 1.72 34

A6 4 0.28 1250

A7 8 2.82 875

A8 2 0.14 250

 

In order to calculate the Earned Value of a simulated project, a baseline plan is needed.  

Table 2 shows the PV assumed for the exercise. 

Page 12: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

12  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

 

Table 2. Baseline plan for the project 

Planned Value 0 1 2 3 4 5 6 7 8 9 10 11 12 13

A0

A1 755 755

A2 1750 1750 1750 1750

A3 93 93 93 93 93 93 93

A4 916 916 916

A5 34 34 34 34 34 34

A6 1250 1250 1250 1250

A7 875 875 875 875 875 875 875 875

A8 250 250

A9

SUM 2598 2598 2759 2759 1043 1002 1002 2159 2159 2159 2125 1125 1125

PV 2598 5196 7955 10714 11757 12759 13761 15920 18079 20238 22363 23488 24613

 

Our analysis is focused when the percentage of work performed measured in terms of earned value 

of the project is 50% of the budget at completion (planned value at the end of the project), but the 

same reasoning could be applied to any other percentage. 

 

Fig.  4. 2D probability density estimation obtained for the case study when the EV=50% of BAC. Point 1 represents a point within the expected variability ranges. Point 2 can be considered a warning situation, and the probability that this point is reached just by random is only 5%. Point 3 is a point out of range which previous approaches do not detect as anomalous.  

 

Page 13: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

13  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

4.2 Results We begin the analysis with the anomaly detection system obtained through Monte Carlo simulation 

and posterior 2D density distribution. This analysis allows determining if given an advancement of 

the project –measured in terms of earned value (corresponding in this case to the 50% of the budget 

at completion)–  , the values of actual time and actual cost of the project are within the expected 

variability. In Fig.  4 100.000 simulation points of the project for that earned value and an adjusted 

density distribution that summarizes them are represented. Contour lines represent the probability 

that the project is without the expected range under the assumption that the project is following the 

stochastic process considered in the project definition. To illustrate the use, imagine that the project 

manager decides to control the status of the project at an instant in which the EV is 50% of the BAC, 

and the actual time and actual cost are given by point 1 in Fig.  4. In this case there is no evidence 

that suggests any process that is interfering beyond the expected variability of the project. On the 

contrary, if the point of the project is number 2, the probability that this situation has been obtained 

as  consequence  of  just  randomness  is  low  (5%)  and  perhaps  the  project  requires  to  figure  out 

whether there are additional structural causes that are taking place in the project which are deviating 

it  from  the planned  schedule. Note  that  this method  can detect  anomalies  consequence of  the 

expected correlation of time and cost (point 3) that may be considered as normal if those variables 

are decoupled as in previous methods (Acebes et al., 2014). Fig. 5 shows two rectangles computed 

using the triad methodology, one for the 95% confidence interval (percentiles Pd 2.5 and Pd 97.5 for 

time, and Pc 2.5 – Pc 97.5 for cost) and another for the 75% confidence interval (Pd 12.5 – Pd 87.5, 

Pc  12.5  –  Pc  87.5).  Comparing  these  predictions with  the  actual  anomaly  detection  estimation 

proposed in this work, one can see that, for example, a point in the 95%‐square top left area (like 

point 3) could be erroneously interpreted as a project within the assumed limits of variability using 

the triad methodology.  

 

Fig.  5. Comparison of triad methodology versus anomaly detection. Rectangles represent the 95% and 75% confidence intervals for time and cost using the triad methodology.  

 

If the conclusion of the previous result is that the model follows the expected variability, we can go 

beyond in the analysis and determine the probability of finishing the project with delay or overcost 

depending on the current situation (assuming that the project follows the stochastic pattern defined 

in the plan). As explained in the methodology section, from complete simulations of the project and 

Page 14: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

14  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

pivoting for the same earned value (in our example 50% of BAC), for each pair time and cost, each 

simulation is classified as a red point (Fig.  6, above on the left) if the simulated project finished with 

overbudget or green if the project finished with a cost lower than planned. With this dataset several 

classification models are assessed using nested cross‐validation.  In the case of our example, SVM 

with  radial kernel obtains better  results  than  the  rest of  the  tested classifiers  (although  this may 

depend on the project and the level of development). This model allows to represent the probability 

of overcost and the decision boundary which splits the points  in which  is more  likely to  finish on 

budget and the points in which is not. Fig.  6 represents with transparency the space where the model 

gives  classification  points  outside  the  range  the  simulation  data  set,  and  consequently  those 

predictions should be treated very carefully and in general untrusted. 

Analogously, and following the example we have calculated the probability to finish the project in 

time  depending  on  the  current  situation.  For  this  process,  several  classifying  algorithms  have 

obtained the same classification rate. We have represented the QDA model for its capacity to capture 

data  correlation.  It  is  interesting  to  notice  that  since  PV  has  been  calculated  using  PERT  (and 

consequently  is too optimistic) and that there are activities not yet performed with high variance, 

the perspectives to complete the project without delay are low even in the most favorable situations 

for this control stage. So much so that in this case there is not any classification boundary. 

 

Fig.  6. Project analysis as a classification problem. Simulation results are labelled as over‐run or not depending on the final simulation result (left). These datasets are used to fit classification models (right). These models give an estimation of the probability of over‐cost (up) or delay (bottom). Boundary decisions represent points in which the probability of over‐run is 0.5. 

Again,  our  analysis  can  provide  more  information  to  the  project  manager.  It  is  undoubtedly 

interesting to estimate the over‐run probabilities but it is also relevant to predict their size. From the 

simulation data and pivoting again for the level of project advancement given by the earned value, 

for each pair time‐cost we can figure out the simulated final duration and total cost of the project 

Page 15: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

15  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

(Fig.  7, left figures). This dataset can feed regression models to forecast the expected time and cost 

of the project if it follows the expected variability. In order to illustrate this process, we have fit two 

models  for  each  case  (time  and  cost):  a  generalized  additive model with  natural  splines  and  a 

generalized  additive model with  local  regression.  An  ANOVA  test  reports  that  for  this  case  the 

generalized additive model with natural splines gives better results with a significance of 0.001. The 

prediction performance of both models can be observed in Fig.  7 where the models have been used 

to make predictions over a grid and the prediction values have been represented with a heat map 

(using green color for favorable values and red for problematic ones). The area of data of the grid 

that is outside the case of study is represented with transparency; again, in this area the predictions 

of the models may be erroneous.  

 

Fig.  7. Project analysis as a regression problem. Simulation results are labelled with the final simulated cost (up‐left) and simulated total duration (bottom‐left). These datasets are used to fit regression models (right). These models give an estimation of the probability of the expected over‐cost (up‐right) or expected delay (bottom‐right).  

All this information can be visually integrated in two intuitive graphical control figures (Fig.  8) very 

similar to the classical Earned Value Management charts. In just two pictures a project manager can 

obtain not only the popular EVM ratios and indexes but also predictions about the probabilities and 

expected cost and durations, boundary classifications and the data ranges  in which the project  is 

under the expected variability. 

At a desired time AT, where Earned Value in the example in Fig.  8 is 50% of BAC (50% EV) and actual 

cost AC, the project manager can have: the probability that the project is not within the expected 

variability of the project (represented in Fig.  8 as p(Anomaly)), the probability of over‐cost (p(OC), 

the expected over‐cost (negative values represent no over‐cost), and the boundary that classifies the 

point in the “not‐expected‐over‐cost” area (under the line), (these four measures in the top part of 

Fig.  8); and again the probability of the project in an anomaly situation (p(Anomaly)), the probability 

of delay (p(D)) and the expected delay (these three measures in the bottom part of Fig.  8).  

 

Page 16: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

16  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

 

Fig.  8. Information obtained by the methodology integrated with the classical Earned Value Management graph. The picture on the top represents the expected over‐cost, the probability of over‐cost, p(OC) and the range of expected variability of the project for the given advancement of the project measured in terms of EV. Analogous measures are represented for the time in the second picture (bottom).  

 

5. Conclusions In this work we have proposed a refinement for the traditional Earned Value Management method to  control projects  stochastically modelled. At any  stage  in  the development of  the project,  the project manager can monitor and control the status of the project. The only data that are needed to feed  the algorithm are  the stochastic definition of  the project,  the planned value curve, and  the traditional raw calculations of the EVM: EV, AT and AC  in that moment. The technique generates multitude of projects compatible with the definition of the project by Monte Carlo simulation. Using 

Page 17: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

17  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

EV as the pivotal measure of the advancement, the project can be analyzed as an anomaly detection, classification and regression problems.  

The approach allows detecting anomaly  situations  in  regard  to  the project definition  taking  into account  the  possible  correlation  between  time  and  cost  that  previous methodologies  ignored. Besides, probabilities of over‐runs and the expected time and duration can be also calculated. All this information can be also visually  integrated  in an  intuitive  framework compatible with  traditional EVM.  

No classifier or regression technique is universally better than any other for every possible context, and predicting in advance the relative performance is a challenging task (Bradley, 1997, Hastie et al., 2009). The proposed framework is independent from the algorithms and can be adapted to be used with any other or future detection, classification and regression method. To illustrate the example some of the state of the art techniques have been used, however the approach does not rely on the precise classification or regression algorithm used. On the contrary, we propose the assessment of several techniques and depending on the case to choose the appropriate one for the specific project using  cross‐validation.  Future  research  may  figure  out  the  a  priori  relationship  between  the properties of the project (number of tasks, probability distributions used, degree of parallelization of the project, etc) and the prediction results of the different classifiers and forecasting methods, this could reduce the computing time necessary to elaborate the control charts and reports. 

 

Acknowledgments. This research has been financed by the project  “Computational Models for Strategic Project Portfolio Management”,  supported  by  the  Regional  Government  of  Castile  and  Leon  (Spain)  with  grant VA056A12‐2  and  by  the  Spanish  Ministerio  de  Ciencia  e  Innovación  Project  CSD2010‐00034 (SimulPast CONSOLIDER‐INGENIO 2010). 

 

References. Abba, W., and F.A. Niel, 2010. Integrating technical performance measurement with earned value management. The Measurable News, 4 6‐8. 

Acebes, F., J. Pajares, J.M. Galán, and A. López‐Paredes, 2014. A new approach for project control under uncertainty. Going back to the basics. International Journal of Project Management, 32(3), 423‐434. Doi: 10.1016/j.ijproman.2013.08.003. 

Anbari, F.T., 2003. Earned Value Project Management Method and Extensions. Project Management Journal, 34(4), 12‐23. 

Anderssen, E., K. Dyrstad, F. Westad, and H. Martens, 2006. Reducing over‐optimism in variable 

selection by cross‐model validation. Chemometrics and Intelligent Laboratory Systems, 84(12), 69‐74. Doi: 10.1016/j.chemolab.2006.04.021. 

Blanco, V.D., 2013. Earned value management: a predictive analysis tool. Navy Supply Corps Newsletter, 66(2), 24‐27. 

Bradley, A.P., 1997. The use of the area under the ROC curve in the evaluation of machine learning algorithms. Pattern Recognition, 30(7), 1145‐1159. Doi: 10.1016/S0031‐3203(96)00142‐2. 

Breiman, L., 1996. Bagging predictors. Machine Learning, 24(2), 123‐140. Doi: 10.1007/BF00058655. 

Breiman, L., 2001. Random Forests. Machine Learning, 45(1), 5‐32. Doi: 10.1023/A:1010933404324. 

Page 18: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

18  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

Burke, R., 2003. Project Management. Planning and Control Techniques London etc., John Wiley & Sons. 

Cioffi, D.F., 2006. Designing project management: a scientific notation and an improved formalism for earned value calculations. International Journal of Project Management, 24(2), 136‐144. Doi: 10.1016/j.ijproman.2005.07.003. 

Cleveland, W.S., E. Grosse, and W.M. Shyu, 1992. Local regression models, in JM Chambers and TJ Hastie eds., Statistical Models: Wadsworth & Brooks/Cole. 

Colin, J., and M. Vanhoucke, 2014. Setting tolerance limits for statistical project control using earned value management. Omega, 49(0), 107‐122. Doi: 10.1016/j.omega.2014.06.001. 

Criminisi, A., J. Shotton, and E. Konukoglu, 2011. Decision Forests: A Unified Framework for Classification, Regression, Density Estimation, Manifold Learning and Semi‐Supervised Learning. Foundations and Trends in Computer Graphics and Computer Vision, 7(2‐3), 81‐227. Doi: 10.1561/0600000035. 

Dimitriadou, E., K. Hornik, F. Leisch, D. Meyer, and A. Weingessel, 2008. Misc functions of the Department of Statistics (e1071), TU Wien. R package version 1.6‐3. 

Ding, X., Y. Li, A. Belatreche, and L.P. Maguire, 2014. An experimental evaluation of novelty detection methods. Neurocomputing, 135 313‐327. Doi: 10.1016/j.neucom.2013.12.002. 

Duong, T., and M.L. Hazelton, 2005. Cross‐validation Bandwidth Matrices for Multivariate Kernel Density Estimation. Scandinavian Journal of Statistics, 32(3), 485‐506. Doi: 10.1111/j.1467‐9469.2005.00445.x. 

Duong, T., 2007. ks: Kernel density estimation and kernel discriminant analysis for multivariate data in R. Journal of Statistical Software, 21(7), 1‐16. 

Fleming, Q.W., and J.M. Koppelman, 2005. Earned Value Project Management Newtown Square, PA, Project Management Institute. 

Hastie, T., R. Tibshirani, and J.H. Friedman, 2009. The Elements of Statistical Learning: Data Mining, Inference, and Prediction New York, NY, Springer. 

Hastie, T.J., and R.J. Tibshirani, 1990. Generalized additive models Boca Raton, FL, Chapman & Hall‐CRC. 

Hazir, Ö., 2014. A review of analytical models, approaches and decision support tools in project monitoring and control. International Journal of Project Management. Doi: 10.1016/j.ijproman.2014.09.005. 

Henderson, K., 2003. Earned schedule: a breakthrough extension to earned value theory? A retrospective analysis of real project data. The Measurable News, 1‐16. 

Henderson, K., 2004. Further developments in earned schedule. The Measurable News, 15‐22. 

Hodge, V.J., and J. Austin, 2004. A Survey of Outlier Detection Methodologies. Artificial Intelligence Review, 22(2), 85‐126. Doi: 10.1007/s10462‐004‐4304‐y. 

Jacob, D.S., 2003. Forecasting project schedule completion with earned value metrics. The Measurable News, 7‐9. 

Jacob, D.S., and M. Kane, 2004. Forecasting schedule completion using earned value metrics revisited. The Measurable News, 11‐17. 

James, G., D. Witten, T. Hastie, and R. Tibshirani, 2013. An Introduction to Statistical Learning with Applications in R New York, NY, Springer. 

Page 19: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

19  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

Kim, E.H., J. Wells, and M.R. Duffey, 2003. A model for effective implementation of Earned Value Management methodology. International Journal of Project Management, 21(5), 375‐382. Doi: 10.1016/S0263‐7863(02)00049‐2. 

Lambrechts, O., E. Demeulemeester, and W. Herroelen, 2008. Proactive and reactive strategies for resource‐constrained project scheduling with uncertain resource availabilities. Journal of Scheduling, 11(2), 121‐136. Doi: 10.1007/s10951‐007‐0021‐0. 

Lipke, W., 2003. Schedule is different. The Measurable News, 3 31‐34. 

Lipke, W., 2004. The probability of success. The Journal of Quality Assurance Institute, 14‐21. 

Lipke, W., O. Zwikael, K. Henderson, and F. Anbari, 2009. Prediction of project outcome: The application of statistical methods to earned value management and earned schedule performance indexes. International Journal of Project Management, 27(4), 400‐407. Doi: 10.1016/j.ijproman.2008.02.009. 

Lipke, W.H., 1999. Applying management reserve to software project management. Journal of Defense Software Engineering, 17‐21. 

Markou, M., and S. Singh, 2003a. Novelty detection: a review‐part 1: statistical approaches. Signal Processing, 83(12), 2481‐2497. Doi: 10.1016/j.sigpro.2003.07.018. 

Markou, M., and S. Singh, 2003b. Novelty detection: a review‐part 2: neural network based approaches. Signal Processing, 83(12), 2499‐2521. Doi: 10.1016/j.sigpro.2003.07.019. 

McKim, R., T. Hegazy, and M. Attalla, 2000. Project performance control in reconstruction projects. Journal of Construction Engineering and Management, 126(2), 137‐141. 

Moslemi Naeni, L., and A. Salehipour, 2011. Evaluating fuzzy earned value indices and estimates by applying alpha cuts. Expert Systems with Applications, 38(7), 8193‐8198. Doi: 10.1016/j.eswa.2010.12.165. 

Naeni, L.M., S. Shadrokh, and A. Salehipour, 2011. A fuzzy approach for the earned value management. International Journal of Project Management, 29(6), 764‐772. Doi: 10.1016/j.ijproman.2010.07.012. 

Narbaev, T., and A. De Marco, 2014. An Earned Schedule‐based regression model to improve cost estimate at completion. International Journal of Project Management, 32(6), 1007‐1018. Doi: 10.1016/j.ijproman.2013.12.005. 

Pajares, J., and A. López‐Paredes, 2011. An extension of the EVM analysis for project monitoring: The Cost Control Index and the Schedule Control Index. International Journal of Project Management, 29(5), 615‐621. Doi: 10.1016/j.ijproman.2010.04.005. 

Pimentel, M.A.F., D.A. Clifton, L. Clifton, and L. Tarassenko, 2014. A review of novelty detection. Signal Processing, 99 215‐249. Doi: 10.1016/j.sigpro.2013.12.026. 

Platt, J., 2000. Probabilities for SV Machines, in AJ Smola, PL Bartlett, B Schölkopf, and D Schuurmans eds., Advances in large margin classifiers: Cambridge, MA, MIT Press, 61‐74. 

Plaza, M., and O. Turetken, 2009. A model‐based DSS for integrating the impact of learning in project control. Decision Support Systems, 47(4), 488‐499. Doi: 10.1016/j.dss.2009.04.010. 

Stone, M., 1974. Cross‐Validatory Choice and Assessment of Statistical Predictions. Journal of the Royal Statistical Society.Series B, 36(2), 111‐147. 

Page 20: Stochastic earned value analysis using Monte Carlo simulation and statistical learning techniques

20  Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques. 

http://www.sciencedirect.com/science/article/pii/S0263786315001106   

Tseng, C.C., 2011. Statistical analysis for comparison of overall performance of projects using Weibull analysis on earned value metrics. Journal of the Chinese Institute of Industrial Engineers, 28(3), 165‐178. Doi: 10.1080/10170669.2010.532598. 

Varma, S., and R. Simon, 2006. Bias in error estimation when using cross‐validation for model selection. BMC Bioinformatics, 7(1), 91. Doi: 10.1186/1471‐2105‐7‐91. 

Venables, W.N., and B.D. Ripley, 2002. Modern applied statistics with S New York, Springer. 

Wauters, M., and M. Vanhoucke, 2014. Support Vector Machine Regression for project control forecasting. Automation in Construction, 47 92‐106. Doi: 10.1016/j.autcon.2014.07.014. 

Wood, S.N., 2006. Generalized additive models. An introduction with R Boca Raton, Fl, Chapman and Hall. 

Zambom, A.Z., and R. Dias, 2012. A review of kernel density estimation with applications to econometrics. arXiv preprint arXiv:1212.2812.