Top Banner
Stephen Milton Undulator System Update [email protected] 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th , 2006
15

Stephen Milton Undulator System [email protected] 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Dec 21, 2015

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

LCLS Undulator System Update

S. Milton, ANL

FAC, April 20th, 2006

Page 2: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Outline

SafetySlideESH Work Authorization form

1st ArticlesInitial MeasurementsMu-metal shieldsGo forward plan

SUTQuick StatusLong range plan

Vacuum SystemSingle path recommendationFocus on solving all issuesFull length prototype in June

RF BPM ProgressMechanicalBrazingTesting

Beam Finder Wire ProgressOTR S1Beam Loss Monitoring System

Delayed due to engineering availability

SLAC MeasurementsMMF (SLAC)Assembly Planning

Page 3: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Integrated Safety Management

Damaged Translation SlideMany CausesRoot Issue

Did not fully follow all ISM processes

Corrective ActionsRetraining in ISM basicsAdditional engineering and administrative controls put in place

Page 4: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Work Authorization Checklist

Page 5: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

1st Articles (See White’s Talk)

One each received from the two vendors

Initial Measurements and Tuning

x/y trajectories well under the 2 micron limit

RMS phase error well under the 10 deg. limit

Page 6: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Undulator Production

Mu-metal ShieldsWill be implemented to buck Earth’s fieldCurrently working out the tuning procedure and overall effectiveness

Go AheadWill be given shortly to the vendors pending overall acceptance

Production PlansExpect 10 to 15 complete by end of fiscal year

Page 7: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Single Undulator Test (See Pile’s Talk)

Phase IComplete assembly with either production or mock up in magnet measurement labFull fit up expected plan by the end of April

Phase IIComplete assembly with all production componentsTunnel mockup includedWill remain at ANL for refinement, trouble shooting, and value engineering

Page 8: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Vacuum System (See Walter’s Talk)Single Path Pursued

Our project management oversight group was adamant about not pursuing an alternate time.

Considered too costlyMake what we have work

Current focusSolve all issues

PrototypeFull length prototype expected late June early July completion

ScheduleStill considered an undulator system critical path item

Page 9: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

RF BPM

First Prototype CompletedBench Measurements

No surprises

Installation for Beam TestPlanned to install in ITS by end of month

3 BPM TestPlanned installation mid to late summer

ScheduleStill considered an undulator system critical path item

Page 10: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Beam Finder Wire (See Walter’s Talk)

Excellent Progress

Testing of positioningExcellent results

5 micron repeatability

Expect PrototypeMid Summer

Page 11: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

OTR S1Location

Near beam dump after analyzing magnet at 135 MeV point in linac

PerformanceSimilar to what ANL was designing for the undulator

PlanBuild what we had designed for phase I and test in operation

Improve design performance if warranted in the future

Page 12: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Beam Loss Monitoring System

Basic concept establishedDetails, however, are notSchedule

Not yet on critical path, but we clearly are falling behind on the plan

PlanGet an appropriate engineer and physicist on this

This has proven difficult to maintain

Page 13: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

SLAC Work

Measurement Bench (See Wolf’s talk)ANL bench on loan for development of overall production measurement and tuning planPrototype undulator at SLAC

Magnet Measurement Facility (See Wolf and Pope’s Talks)

Building construction completedEquipment to move in in the coming weeksThis will be a busy place

Page 14: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Assembly Planning (See Pope’s Talk)

SLAC working closely with ANLThe SUT will be used heavily in refining overall assembly sequence

Component deliverySchedule and assemble being refined to match planned component arrivals

This is already forcing us to optimize our effort planning to improve the arrival timing

Page 15: Stephen Milton Undulator System Updatemilton@aps.anl.gov 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.

Stephen Milton

Undulator System Update [email protected]

20 April, 2006

Summary

Things are getting excitingProduction undulators are starting to arrive and be measured

There is still much to be doneThere are a few kinks we need to work out

Eg. The beam loss monitor workWe must keep our eye on some key items

BPMsVacuum Chambers

But we still believe we will meet all our critical milestones while not compromising performance