OWNER REFERENCE Project Package Originator Discipline Doc. Type
Unit n Serial n
RAPID FE1 TPX CVS SPN 0001 0009
PETRONAS RAPID PROJECT FEED PHASE
CONTRACTOR REFERENCE Rev. Page Project Unit n Doc. Type Doc.
Code Sequent. n
1 1 / 7 60987R 0001 JSS 1800 9001
Project Specification Steel Structures
6098
7R-0
001-
FOR
-000
3_F
1 21-Dec-12 IFE Issued for Execution E Benito SY Ng/CF Chang DC
Argawal/JM Maurice
0 16-Aug-12 IFE Issued for Execution E Benito SY Ng/CF Chang DC
Argawal/JM Maurice
B 07-May-12 IFA1 Issued for Approval E Benito SY Ng/CF Chang DC
Argawal/JM Maurice
A 16-Mar-12 IFA Issued for Approval E Benito SY Ng/CF Chang DC
Argawal/JM Maurice
REV. DATE DD-MMM-YY STATUS REVISION MEMO WRITTEN BY (name &
visa)
CHECKED BY (name & visa)
APPROVED BY (name & visa)
Sections changed in last revision are identified by a vertical
line in the margin.
Subject to the provision of Article 13 of the CONTRACT, TECHNIP
hereby grant PETRONAS the copyright of this document. No part of
this document may be reproduced, stored in a retrieval system or
transmitted in any form or by any means (electronic, mechanical,
photocopying, recording or otherwise) without the permission of the
copyright owner.
CONFIDENTIAL Not to disclose without authorization Electronic
Filename: RAPID-FE1-TPX-CVS-SPN-0001-0009_1.docx
PROJECT SPECIFICATION
STEEL STRUCTURES (Supplement to PTS 34.28.00.31 dated Feb.
2008)
OWNER Approval: PETRONAS
Name: Date (DD-MMM-YY):
Signature:
Document Class: Z Pages modified under this revision: 5
-
OWNER REFERENCE Project Package Originator Discipline Doc. Type
Unit n Serial n
RAPID FE1 TPX CVS SPN 0001 0009
PETRONAS RAPID PROJECT FEED PHASE
CONTRACTOR REFERENCE Rev. Page Project Unit n Doc. Type Doc.
Code Sequent. n
1 2 / 7 60987R 0001 JSS 1800 9001
Project Specification Steel Structures
Subject to the provision of Article 13 of the CONTRACT, TECHNIP
hereby grant PETRONAS the copyright of this document. No part of
this document may be reproduced, stored in a retrieval system or
transmitted in any form or by any means (electronic, mechanical,
photocopying, recording or otherwise) without the permission of the
copyright owner.
CONFIDENTIAL Not to disclose without authorization
CONTENTS
1. PURPOSE
............................................................................................................................................................................
3 2. REFERENCE DOCUMENTS
...........................................................................................................................................
3 3. ACRONYMS AND DEFINITIONS
..................................................................................................................................
3 4. CODES AND STANDARDS
..............................................................................................................................................
5
4.1 APPLICABLE CODES & STANDARDS
..............................................................................................................................
5 4.2 ORDER OF PRECEDENCE
................................................................................................................................................
5
5. AMENDMENTS TO PETRONAS TECHNICAL STANDARD
....................................................................................
5
-
OWNER REFERENCE Project Package Originator Discipline Doc. Type
Unit n Serial n
RAPID FE1 TPX CVS SPN 0001 0009
PETRONAS RAPID PROJECT FEED PHASE
CONTRACTOR REFERENCE Rev. Page Project Unit n Doc. Type Doc.
Code Sequent. n
1 3 / 7 60987R 0001 JSS 1800 9001
Project Specification Steel Structures
Subject to the provision of Article 13 of the CONTRACT, TECHNIP
hereby grant PETRONAS the copyright of this document. No part of
this document may be reproduced, stored in a retrieval system or
transmitted in any form or by any means (electronic, mechanical,
photocopying, recording or otherwise) without the permission of the
copyright owner.
CONFIDENTIAL Not to disclose without authorization
1. PURPOSE This Project Specification covers the minimum
requirements for Steel Structures to be used for the RAPID
(Refinery And Petrochemical Integrated Development) Project.
It has been developed on the basis of the PETRONAS Technical
Standard n PTS 34.28.00.31 dated February 2008, amended herein (the
Project Specification therefore supplements the initial PTS).
These requirements shall be used throughout all steps of the
Project and by all parties: CONTRACTOR, SUBCONTRACTORS, LICENSORS,
EPCC CONTRACTORS, Vendors, etc.
2. REFERENCE DOCUMENTS RAPID-FE1-TPX-ENG-PRC-0001-0104
(60987R-0001-PP-0104), Project Procedure Glossary of Terms and
Abbreviations.
RAPID-FE1-TPX-ENG-PRC-0001-0205 (60987R-0001-PP-0205), Project
Procedure - Project Specifications and Procedures supplementing
PETRONAS Technical Standards (PTS)
RAPID-FE1-TPX-CVS-DES-0001-0002 (60987R-0001-JSD-1700-9001),
Project Specifications Minimum Requirement for Structural Design
Engineering, supplementing to PETRONAS Technical Standards (PTS
34.00.01.30 dated Nov 2010)
3. ACRONYMS AND DEFINITIONS This section defines the type of
amendments to the PETRONAS Technical Specification (PTS) named
above for PETRONAS purpose: (Dev.) Deviation - Any departure from
PTS mandatory requirement that has
impact on technical integrity or safety of the facilities.
(Supp.) Supplement/ Amendment - Any addition, deletion or
enhancement of
PTS requirement based on lesson learnt, engineering best
practices and experiences to enhance the technical integrity or
safety of the facilities.
(Spec.) Project Specific Requirement/ Instruction - Any specific
requirement
or instruction for RAPID PROJECT as a result of particular
geography, climate, special process, etc. that is unique to the
PROJECT.
For users readability purpose, the words used to identify
amendments to PTS are defined as follows: (Add ) Adds the
requirement(s) tot the referenced paragraph of the PTS.
(Mod.) Changes the referenced paragraph sentence of the PTS as
indicated. (Clarif.) Provides interpretation of the referenced
paragraph / sentence of the
PTS.
-
OWNER REFERENCE Project Package Originator Discipline Doc. Type
Unit n Serial n
RAPID FE1 TPX CVS SPN 0001 0009
PETRONAS RAPID PROJECT FEED PHASE
CONTRACTOR REFERENCE Rev. Page Project Unit n Doc. Type Doc.
Code Sequent. n
1 4 / 7 60987R 0001 JSS 1800 9001
Project Specification Steel Structures
Subject to the provision of Article 13 of the CONTRACT, TECHNIP
hereby grant PETRONAS the copyright of this document. No part of
this document may be reproduced, stored in a retrieval system or
transmitted in any form or by any means (electronic, mechanical,
photocopying, recording or otherwise) without the permission of the
copyright owner.
CONFIDENTIAL Not to disclose without authorization
(New ) Indicates the addition of a new paragraph compared to the
PTS. (Canc.) Cancel the requirement to the referenced paragraph of
the PTS.
The following terms used in this document have the meaning
defined below:
CONTRACT The Form Of Agreement together with the documents in
order of priority, including the exhibits, drawings, specifications
and documents referred to and in the order of precedence listed in
the Form of Agreement.
CONTRACTOR Company(ies), joint ventures or consortium appointed
by OWNER with specified authority to perform the WORK in accordance
with the CONTRACT, here the Consortium of Technip France and
Technip Geoproduction (M) Sdn Bhd.
OWNER Petroliam Nasional Berhad (PETRONAS) which includes its
representative, successors, nominees and permitted assigns and
shall where the context so admits and requires, also include its
employees, agents and designated representative.
PROJECT Refinery And Petrochemicals Integrated Development
(RAPID) Project in the State of Johor, Malaysia.
SCOPE OF WORK The scope of work to be performed and services to
be rendered by CONTRACTOR under the CONTRACT in relation to the
realization of the PROJECT.
WORK Works, tasks and WORK to be performed by CONTRACTOR as
specified in or to be inferred from the CONTRACT, more specially
set out in the SCOPE OF WORK which may be modified by CHANGE
ORDER.
SUBCONTRACTOR Any third party Subcontractor engaged by
CONTRACTOR in connection with the WORK.
LICENSOR Process Licensors selected by OWNER for the process of
LICENSED UNITS of the FACILITIES.
EPCC CONTRACTORS The person or persons, company, join venture or
consortium whose proposal has been accepted by OWNER for
Engineering, Procurement, Construction and Commissioning Contract
for the PROJECT including its personnel, representatives,
successors and permitted assignee.
The acronyms used in this document have the meaning defined
below: - FEED Front-End Engineering Design - PTS PETRONAS Technical
Standard - RAPID Refinery And Petrochemicals Integrated Development
- EPCC Engineering Procurement Construction and Commissioning
Contract - MS EN Malaysia Euro Norms - BS British Standard
-
OWNER REFERENCE Project Package Originator Discipline Doc. Type
Unit n Serial n
RAPID FE1 TPX CVS SPN 0001 0009
PETRONAS RAPID PROJECT FEED PHASE
CONTRACTOR REFERENCE Rev. Page Project Unit n Doc. Type Doc.
Code Sequent. n
1 5 / 7 60987R 0001 JSS 1800 9001
Project Specification Steel Structures
Subject to the provision of Article 13 of the CONTRACT, TECHNIP
hereby grant PETRONAS the copyright of this document. No part of
this document may be reproduced, stored in a retrieval system or
transmitted in any form or by any means (electronic, mechanical,
photocopying, recording or otherwise) without the permission of the
copyright owner.
CONFIDENTIAL Not to disclose without authorization
4. CODES AND STANDARDS
4.1 Applicable Codes & Standards This list of codes comes in
addition to the codes listed into the PTS.
MS 1553 : 2002 Malaysian Standard - Code of Practice on Wind
Loading for Building Structure
MS EN 1990-2010 Malaysian Standard National Annex - Malaysian
National Annex to Eurocode - Basis of Structural Design
MS EN 1991-1-1:2010 Malaysian National Annex to Eurocode 1:
Actions on structure - Part 1-1: General Actions - Densities,
Self-Weight, Imposed Loads for Buildings
MS EN 1993-1-1:2010 Malaysian National Annex to Eurocode 3,
Design of Steel Structures-Part 1-1, General Rules and Rules for
Buildings
BS EN 1990 Eurocode Basis of Structural Design
BS EN 1991 Eurocode 1 Actions on Structures
BS EN 1993 Eurocode 3 Design of Steel Structures
BS EN 1998 Eurocode 8 Basis of Structure for Earthquake
Resistance
BS 5950, Part 1 to Part 12 Structural Use of Steelwork in
Building
UBBL 1984 Uniform Building By-Laws
AISC Steel Construction Manual 14TH Edition-2010
Unless otherwise specified, the latest applicable revision of
codes and standards shall be considered.
4.2 Order of precedence In case of conflict between Laws,
Project Specifications and Codes & Standards, the following
order of precedence shall be considered:
- 1. Malaysian Laws and applicable regulatory requirements, - 2.
Project Specifications and supplemented PTS, - 3. Applicable
Malaysian Codes and Standards, - 4. Applicable International Codes
and Standards.
If a Lower Level requirement is more stringent than an upper one
in the above documents, a request shall be raised to OWNER for
written decision before proceeding with the Design, Manufacture or
Construction.
5. AMENDMENTS TO PETRONAS TECHNICAL STANDARD The table below
defines the amendments to be considered to the PTS 34.28.00.31
dated Feb 2008 , Steel Structures.
When the amended PTS refers to other PTS, please refer to the
Project Procedure - Project Specifications and Procedures
Supplementing PETRONAS Technical Standards (PTS),
RAPID-FE1-TPX-ENG-PRC-0001-0205 (60987R-0001-PP-0205), that
provides the equivalence with applicable Project
Specifications.
-
OWNER REFERENCE Project Package Originator Discipline Doc. Type
Unit n Serial n
RAPID FE1 TPX CVS SPN 0001 0009
PETRONAS RAPID PROJECT FEED PHASE
CONTRACTOR REFERENCE Rev. Page Project Unit n Doc. Type Doc.
Code Sequent. n
1 6 / 7 60987R 0001 JSS 1800 9001
Project Specification Steel Structures
Subject to the provision of Article 13 of the CONTRACT, TECHNIP
hereby grant PETRONAS the copyright of this document. No part of
this document may be reproduced, stored in a retrieval system or
transmitted in any form or by any means (electronic, mechanical,
photocopying, recording or otherwise) without the permission of the
copyright owner.
CONFIDENTIAL Not to disclose without authorization
Type Word Description of Amendment
(Supp.) (Mod.) 2.2.1 General
Modify ENV 1993-1-1 with EN 1993-1-1
(Supp.) (Add.) 2.2.5 Deflection and displacement
Add: new paragraph :
The following criteria for horizontal displacement of pipe rack
and process structure frame shall apply for load combination B and
C of section 3.14 of PTS 34.00.01.30
Pipe rack : max. 1/100th of the height.
Process structure : max. 1/200th of the height and can be
further limited to accommodate equipment requirements by mechanical
/process.
(Supp.) (Add.) 2.3 CONSTRUCTION MATERIALS
After the word taking weldability, add : and the required
finished weldment mechanical properties into consideration.
Modify Table 3.2 and Annex C of ENV 1993-1-1 with Table 2.1 of
EN 1993-1-10
Add new paragraph The use of alternative material not listed in
EN 10025 shall be submitted to Principal for review and comments.
Alternative material shall be selected in accordance with
applicable codes and regulations.
(Supp.) (Mod.) 2.4.1 General
Modify sentences or shall be otherwise protected with and shall
be protected against corrosion according to Section 4.0
(Supp.) (Mod.) 2.4.4 Walkways, platforms, staircases, ladders
and hand railing
After the third paragraph, add : A handrails shall be fitted on
both side of the staircase when the width is 750mm or more.
Modify (see 4.) with (see Section 4.)
Modify toe plates 75 x 6mm with toe plates 100 x 6mm
2.4.5 Flooring and grating
Add new paragraph The method of fastening grating and floor
plate shall be per Project Standard drawings. A minimum of four
fasteners per panel shall be used at its support.
Modify P 28.022 with S 28.022
(Supp.) (Mod.) 3.2 WELDING AND WELDING INSPECTION
Modify sentences AWS D1.1 shall apply with All welding and
welding procedure shall be in accordance to ANSI / AWS D1.1.
(Supp.) (Add.) 5.1 GENERAL
Add new paragraph The contractor shall propose an inspection and
test plan for each phase of the design, fabrication and erection of
structural steel material.
(Supp.) (Mod.) 6.0 REFERENCES
STANDARD DRAWINGS
-
OWNER REFERENCE Project Package Originator Discipline Doc. Type
Unit n Serial n
RAPID FE1 TPX CVS SPN 0001 0009
PETRONAS RAPID PROJECT FEED PHASE
CONTRACTOR REFERENCE Rev. Page Project Unit n Doc. Type Doc.
Code Sequent. n
1 7 / 7 60987R 0001 JSS 1800 9001
Project Specification Steel Structures
Subject to the provision of Article 13 of the CONTRACT, TECHNIP
hereby grant PETRONAS the copyright of this document. No part of
this document may be reproduced, stored in a retrieval system or
transmitted in any form or by any means (electronic, mechanical,
photocopying, recording or otherwise) without the permission of the
copyright owner.
CONFIDENTIAL Not to disclose without authorization
Modify Grating P 28.022 with Grating S 28.022
Modify AWS D1.1 with ANSI /AWS D1.1
Modify ENV 1993-1-1 with EN 1993-1-1
1. purpose2. REFERENCE DOCUMENTS3. ACRONYMS and DEFINITIONS4.
CodeS and standards4.1 Applicable Codes & Standards4.2 Order of
precedence
5. AMENDMENTS TO PETRONAS TECHNICAL STANDARD
2012-12-21T14:54:44+0800Eduardo Benito
2012-12-26T09:46:04+0800SiangYoong Ng
2012-12-26T11:18:36+0800ChooiFoong Chang
2012-12-27T09:50:03+0800DineshChandra Agarwal
2013-01-02T08:24:47+0100Jean-Marc Maurice