Act ID Activity Name Duration Start Finish
Expansion of Bhilai Steel Plant (Rev - 6A-3)Expansion of Bhilai Steel Plant (Rev - 6A-3)Expansion of Bhilai Steel Plant (Rev - 6A-3)Expansion of Bhilai Steel Plant (Rev - 6A-3)Expansion of Bhilai Steel Plant (Rev - 6A-3)
001 Principal Approval for BSP Expansion 0 03-Apr-07 A
003 Stage - II Approval (Progress ively ) 240 14-Mar-08 A 29-Dec-14
004 Overall Completion of BSP Expansion 0 04-Sep-16
Pkg 060 Augmentation of Ore Handling Plant Part - APkg 060 Augmentation of Ore Handling Plant Part - APkg 060 Augmentation of Ore Handling Plant Part - APkg 060 Augmentation of Ore Handling Plant Part - APkg 060 Augmentation of Ore Handling Plant Part - A
369 Issue Draft TS (Issued) 0 01-May-07 A
370 Discussion with BSP 14 02-May-07 A 15-May-07 A
371 Issue Final TS (Issued) 15 16-May-07 A 30-Aug-07 A
372 Issue of NIT (Issued ) 8 31-Aug-07 A 07-Sep-07 A
373 Recpt of Tender at Bhilai 45 10-Sep-07 A 20-Nov-07 A
374 Recpt of Tender at Ranc hi 4 21-Nov-07 A 23-Nov-07 A
375 Scrutiny, Discussions & Tender Finalisation 75 10-Dec-07 A 30-Jan-08 A
376 Firming-up of price of the package & stage -II approval 45 31-Jan-08 A 14-Mar-08 A
376.1 Issue of LOI 0 25-Mar-08 A
377 Signing of contract with M/s HEC (24 months schedule) 0 09-Apr-08 A
Pkg 011-01B STG, Cooling water system and balance of plantPkg 011-01B STG, Cooling water system and balance of plantPkg 011-01B STG, Cooling water system and balance of plantPkg 011-01B STG, Cooling water system and balance of plantPkg 011-01B STG, Cooling water system and balance of plant
10600 Issue Draft TS 0 17-Mar-11 A
10610 Discussion with BSP 12 18-Mar-11 A 21-Mar-11 A
10780 Signing of Contract with Technofab Engg. Ltd. (12 months schedule)
0 25-Feb-12 A
10790 Engg., Supply, Execution, Testing & Comm.- DM water system
365 27-Feb-12 A 12-Aug-15
Pkg 011-02 Enabling works for Boiler,STG,BOPPkg 011-02 Enabling works for Boiler,STG,BOPPkg 011-02 Enabling works for Boiler,STG,BOPPkg 011-02 Enabling works for Boiler,STG,BOPPkg 011-02 Enabling works for Boiler,STG,BOP
062 Issue Draft TS 0 04-Feb-10 A
073 Discussion with BSP 7 05-Feb-10 A 13-Feb-10 A
084 Issue Final TS 14 14-Feb-10 A 26-Feb-10 A
085 Issue of NIT 14 27-Feb-10 A 10-Mar-10 A
096 Recpt of Tender at Bhilai 30 11-Mar-10 A 30-Apr-10 A
096.02 Scrutiny, Discussions & Tender Finalisation 30 01-May-10 A 22-Jul-10 A
129 Firming-up of price of the package 15 23-Jul-10 A 01-Sep-10 A
131 Signing of contract 0 18-Sep-10 A
272 Enabling works for Boiler,STG,BOP 152 19-Sep-10 A 25-Oct-12 A
Pkg 020 Second Sintering M/c (360 sqm) in SP-3Pkg 020 Second Sintering M/c (360 sqm) in SP-3Pkg 020 Second Sintering M/c (360 sqm) in SP-3Pkg 020 Second Sintering M/c (360 sqm) in SP-3Pkg 020 Second Sintering M/c (360 sqm) in SP-3
086 Issue Draft TS (Issued) 0 25-Apr-07 A
087 Discussion with BSP 15 26-Apr-07 A 10-May-07 A
088 Issue Final TS (Issued) 9 11-May-07 A 15-Jun-07 A
107.1 Discussion with BSP 12 05-Sep-08 A 10-Sep-08 A
107.2 Issue Final TS 20 11-Sep-08 A 20-Sep-08 A
107.3 Issue of NIT 37 21-Sep-08 A 25-Sep-08 A
121 Recpt of Tender at Bhilai 43 26-Sep-08 A 29-Nov-08 A
132 Scrutiny, Discussions & Tender Finalisation 60 01-Dec-08 A 14-May-09 A
133 Firming-up of price of the package & Mngt. Approval 30 15-May-09 A 05-May-10 A
134 Signing of contract with M/s PGEW 0 05-Jun-10 A
135 Engg., Supply, Execution, Testing & Comm.- Lime dosing 273 07-Jun-10 A 04-Nov-11 A
Pkg 021-C Electrics & Automation System under modernization of SP-IIPkg 021-C Electrics & Automation System under modernization of SP-IIPkg 021-C Electrics & Automation System under modernization of SP-IIPkg 021-C Electrics & Automation System under modernization of SP-IIPkg 021-C Electrics & Automation System under modernization of SP-II
157.3 Issue of NIT 37 05-Jan-09 A 13-Jan-09 A
157.4 Recpt of Tender at Bhilai 43 14-Jan-09 A 12-Mar-09 A
157.5 Scrutiny, Discussions & Tender Finalisation 60 14-Mar-09 A 01-Feb-10 A
163 Firming-up of price of the package & Mngt. Approval 30 02-Feb-10 A 04-Mar-10 A
164 Signing of contract with M/s Siemens 0 06-May-10 A
Pkg 038-01 Augmentation Facili ties of MH system for SMS-2Pkg 038-01 Augmentation Facili ties of MH system for SMS-2Pkg 038-01 Augmentation Facili ties of MH system for SMS-2Pkg 038-01 Augmentation Facili ties of MH system for SMS-2Pkg 038-01 Augmentation Facili ties of MH system for SMS-2
267 Issue Draft TS (Issued ) 0 22-Jun-07 A
278 Discussion with BSP 7 23-Jun-07 A 30-Jun-07 A
279 Issue Final TS 14 02-Jul-07 A 22-Jan-08 A
290 Issue of NIT 10 23-Jan-08 A 17-Mar-08 A
301 Recpt of Tender at Bhilai 45 18-Mar-08 A 30-Jun-08 A
312 Recpt of Tender at Ranc hi 5 01-Jul-08 A 04-Jul-08 A
323 Scrutiny, Discussions & Tender Finalisation 60 05-Jul-08 A 26-Mar-09 A
334 Firming-up of price of the package (Retendered ) 25 27-Mar-09 A 01-Feb-11 A
334.1 Issue of LOI 0 16-Feb-11 A
345 Signing of contract with Anupam Industries Ltd. (9 months schedule)
Pkg 038-05 Combined blowing of argon / nitrogen in convertersPkg 038-05 Combined blowing of argon / nitrogen in convertersPkg 038-05 Combined blowing of argon / nitrogen in convertersPkg 038-05 Combined blowing of argon / nitrogen in convertersPkg 038-05 Combined blowing of argon / nitrogen in converters
Pkg 038-06 Modernisation of BOF automation system (SMS-II)Pkg 038-06 Modernisation of BOF automation system (SMS-II)Pkg 038-06 Modernisation of BOF automation system (SMS-II)Pkg 038-06 Modernisation of BOF automation system (SMS-II)Pkg 038-06 Modernisation of BOF automation system (SMS-II)
797 Issue Draft TS 0 29-Oct-07 A
798 Discussion with BSP 7 30-Oct-07 A 06-Nov-07 A
799 Issue Final TS 14 07-Nov-07 A 03-Mar-08 A
800 Issue of NIT 14 04-Mar-08 A 08-May-08 A
801 Recpt of Tender at Bhilai 45 09-May-08 A 20-Jul-08 A
802 Recpt of Tender at Ranc hi 5 21-Jul-08 A 28-Jul-08 A
Pkg 038-12 Dedusting of lime facilities at + 47m levelPkg 038-12 Dedusting of lime facilities at + 47m levelPkg 038-12 Dedusting of lime facilities at + 47m levelPkg 038-12 Dedusting of lime facilities at + 47m levelPkg 038-12 Dedusting of lime facilities at + 47m level
617 Issue Draft TS (Issued ) 0 14-Sep-07 A
628 Discussion with BSP 7 15-Sep-07 A 25-Sep-07 A
639 Issue Final TS 14 26-Sep-07 A 23-Jan-08 A
650 Issue of NIT 10 24-Jan-08 A 18-Feb-08 A
765 Signing of contract 0 19-Jun-10 A
766 Engg., Supply, Execution, Testing & Comm.- SMS 2 Augm. 273 19-Jun-10 A 28-Sep-12 A
128.1 Firming-up of price of the package 45 29-Jul-08 A 30-Mar-09 A
128.2 Issue of LOI 0 31-Mar-09 A
128.3 Signing of Contract with M/s SVAI (33 months schedule) 0 18-Apr-09 A
128.31 Engg , Supply of equipments, ref of CCP 699 19-May-09 A 25-Dec-14
128.32 Erection of Eqpts, Ref of CCP (SVAI Scope) 211 05-Jun-15 02-Jan-16
128.4 Testing & Comm. of casters 121 30-Apr-16 29-Aug-16
128.5 Billet caster-1 0 31-May-16
128.6 Billet Caster -2 0 15-Jul-16
128.7 Bloom Caster 0 29-Aug-16
128.8 Beam blank Caster 0 29-Aug-16
Pkg 027 Hot Metal Desulphurisation (2 nos)Pkg 027 Hot Metal Desulphurisation (2 nos)Pkg 027 Hot Metal Desulphurisation (2 nos)Pkg 027 Hot Metal Desulphurisation (2 nos)Pkg 027 Hot Metal Desulphurisation (2 nos)
136 Issue Draft TS (Issued ) 0 18-Jun-07 A
137 Discussion with BSP 8 19-Jun-07 A 26-Jun-07 A
138 Issue Final TS (Issued ) 15 27-Jun-07 A 11-Jul-07 A
139 Issue of NIT (Issued ) 8 07-Aug-07 A 14-Aug-07 A
140 Recpt of Tender at Bhilai 45 16-Aug-07 A 22-Nov-07 A
141 Recpt of Tender at Ranc hi 5 15-Nov-07 A 20-Nov-07 A
142 Scrutiny, Discussions & Tender Finalisation 60 21-Nov-07 A 28-Feb-08 A
143 Firming-up of price of the package & stage-II approval 45 29-Feb-08 A 01-Sep-08 A
Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)Pkg 029A1 Main Cranes for BOF and CCP (+ 120t - 7 Nos priority crane)
158 Issue Draft TS (Issued ) 0 22-Jun-07 A
159 Discussion with BSP 12 28-Jun-07 A 09-Jul-07 A
160 Issue Final TS (Issued ) 14 24-Jul-07 A 31-Oct-07 A
161 Issue of NIT 16 01-Nov-07 A 16-Nov-07 A
161.3 Scrutiny, Discussions & Tender Finalisation 30 24-Sep-08 A 05-Mar-09 A
162 Firming up of price & Stage-II approval 45 06-Mar-09 A 13-May-09 A
162.1 Issue of LOI 0 29-May-09 A
166 Signing of contract with M/s HEC (24 months schedule) 0 29-Jun-09 A
167 Engg., Supply, erection, Testing & Comm.- Large Cranes forSMS-3
730 29-Jun-09 A 10-Jul-15
Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)Pkg 029A2 Main Cranes for BOF and CCP (+120 t- 10 nos. crane)
238.4 Scrutiny, Discussions & Tender Finalisation 30 20-Aug-09 A 17-Oct-10 A
262 Firming up of price & Stage-II approval 15 18-Oct-10 A 27-Jan-11 A
262.1 Issue of LOI 0 29-Jan-11 A
366 Signing of contract with M/s HEC (24 months schedule) 0 12-Feb-11 A
447 Engg., Supply, Erection, Testing & Comm.- Large Cranes forSMS-3
731 13-Feb-11 A 02-Dec-15
Pkg 029B Main Cranes for BOF and CCP ( below 120 t)Pkg 029B Main Cranes for BOF and CCP ( below 120 t)Pkg 029B Main Cranes for BOF and CCP ( below 120 t)Pkg 029B Main Cranes for BOF and CCP ( below 120 t)Pkg 029B Main Cranes for BOF and CCP ( below 120 t)
168 Issue Draft TS (Issued ) 0 22-Jun-07 A
179 Discussion with BSP 12 28-Jun-07 A 09-Jul-07 A
190 Issue Final TS (Issued ) 14 24-Jul-07 A 25-Oct-07 A
201 Issue of NIT 2 26-Oct-07 A 27-Oct-07 A
212 Recpt of Tender at Bhilai 28 28-Oct-07 A 10-Jan-08 A
233 Recpt of Tender at Ranc hi 4 11-Jan-08 A 14-Jan-08 A
234 Scrutiny, Discussions & Tender Finalisation (Retendered) 30 15-Jan-08 A 01-Oct-09 A
234.1 Issue Final TS 14 16-Oct-09 A 10-Feb-10 A
234.2 Issue of NIT 2 11-Feb-10 A 15-Feb-10 A
234.3 Recpt of Tender at Bhilai 28 16-Feb-10 A 12-May-10 A
234.4 Recpt of Tender at Ranc hi 4 13-May-10 A 14-May-10 A
234.5 Scrutiny, Discussions & Tender Finalisation (Package split into two packages)
Pkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-IIIPkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-IIIPkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-IIIPkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-IIIPkg 029B1 EOT CRANES FOR BOF & CCP OF SMS-III
11050 Issue Draft TS (Issued ) 0 03-May-11 A
11060 Discussion with BSP 12 04-May-11 A 30-Jun-11 A
11070 Issue Final TS (Issued ) 14 01-Jul-11 A 20-Jul-11 A
11080 Issue of NIT 16 21-Jul-11 A 05-Aug-11 A
11080.1 Scrutiny, Discussions & Tender Finalisation 30 01-Sep-11 A 26-Feb-12 A
11080.2 Firming up of price & Stage-II approval (Re-tendered) 45 27-Feb-12 A 25-Jun-12 A
11080.21Issue of NIT 10 26-Jun-12 A 02-Jul-12 A
11080.22Scrutiny, Discussions & Tender Finalisation 30 01-Aug-12 A 26-Nov-12 A
11080.23Firming up of price & Stage-II approval (Re-tendered) 45 27-Nov-12 A 24-Dec-12 A
11080.33Issue of NIT 10 02-Apr-13 A 12-Apr-13 A
11080.43Scrutiny, Discussions & Tender Finalisation 30 01-Jun-13 A 26-Aug-13 A
11080.53Firming up of price & Stage-II approval 45 27-Aug-13 A 17-Jan-14 A
11080.6 Issue of LOI 0 30-Jan-14 A
11090 Signing of contract 0 18-Feb-14 A
11100 Engg., Supply, erection, Testing & Comm.- EOT cranes for BOF & CCP for SMS-III
547 19-Feb-14 A 18-Aug-15
Pkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-IIIPkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-IIIPkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-IIIPkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-IIIPkg 029B2 EOT CRANES, REPAIR TROLLIES & UNDER SLUNG CRANES FOR BOF & CCP OF SMS-III
11120 Issue Draft TS (Issued ) 0 10-May-11 A
11130.1 Discussion with BSP 12 11-May-11 A 30-Jun-11 A
11140 Issue Final TS (Issued ) 14 01-Jul-11 A 20-Jul-11 A
Pkg 031 Hot Metal Handling System (Torpedo Ladles)Pkg 031 Hot Metal Handling System (Torpedo Ladles)Pkg 031 Hot Metal Handling System (Torpedo Ladles)Pkg 031 Hot Metal Handling System (Torpedo Ladles)Pkg 031 Hot Metal Handling System (Torpedo Ladles)
180 Issue Draft TS 0 17-Oct-07 A
181 Discussion with BSP 8 18-Oct-07 A 10-Dec-07 A
182 Issue Final TS 10 11-Dec-07 A 15-Jan-08 A
183 Issue of NIT 4 16-Jan-08 A 16-Feb-08 A
184 Recpt of Tender at Bhilai 43 17-Feb-08 A 30-Apr-08 A
185 Recpt of Tender at Ranc hi 5 01-May-08 A 10-May-08 A
186 Scrutiny, Discussions & Tender Finalisation (Retendered) 60 11-May-08 A 09-Mar-09 A
186.1 Issue Final TS 10 18-Apr-09 A 21-May-09 A
186.2 Issue of NIT 4 22-May-09 A 25-Jul-09 A
186.3 Recpt of Tender at Bhilai 43 26-Jul-09 A 22-Sep-09 A
186.4 Recpt of Tender at Ranc hi 5 24-Sep-09 A 05-Oct-09 A
Pkg 032 Propane Storage and Distribution SystemPkg 032 Propane Storage and Distribution SystemPkg 032 Propane Storage and Distribution SystemPkg 032 Propane Storage and Distribution SystemPkg 032 Propane Storage and Distribution System
191 Issue Draft TS 0 29-Jan-10 A
192 Discussion with BSP 8 30-Jan-10 A 25-Feb-10 A
193 Issue Final TS 7 26-Feb-10 A 09-Mar-10 A
194 Issue of NIT 17 10-Mar-10 A 03-Apr-10 A
195 Recpt of Tender at Bhilai 45 05-Apr-10 A 04-May-10 A
196 Recpt of Tender at Ranc hi 5 05-May-10 A 07-May-10 A
197 Scrutiny, Discussions & Tender Finalisation 55 08-May-10 A 15-Feb-11 A
198 Firming-up of price of the package & Mngt. Approval 25 24-Feb-11 A 03-Mar-11 A
198.1 Issue of LOI 0 16-Mar-11 A
199 Signing of Contract with M/s OGPE (12 months schedule) 0 06-Apr-11 A
Pkg 033-A2 Civil Work for BOF & CCP ShopPkg 033-A2 Civil Work for BOF & CCP ShopPkg 033-A2 Civil Work for BOF & CCP ShopPkg 033-A2 Civil Work for BOF & CCP ShopPkg 033-A2 Civil Work for BOF & CCP Shop
206 Recpt of Tender at Bhilai 45 14-Nov-07 A 30-Dec-07 A
207 Recpt of Tender at Ranc hi 4 31-Dec-07 A 03-Jan-08 A
208 Scrutiny, Discussions & Tender Finalisation ( Retendered) 40 04-Jan-08 A 08-Jun-08 A
275 Issue of NIT 5 17-Apr-09 A 28-Apr-09 A
276 Recpt of Tender at Bhilai 45 29-Apr-09 A 30-Apr-09 A
276.1 Recpt of Tender at Ranc hi 4 01-May-09 A 02-May-09 A
276.2 Scrutiny, Discussions & Tender Finalisation 30 04-May-09 A 31-Oct-09 A
276.3 Firming-up of price of the package 20 02-Nov-09 A 20-Nov-09 A
276.4 Issue of LOI 0 24-Nov-09 A
276.5 Signing of Contract 0 05-Dec-09 A
276.50A Civil Work for BOF & CCP Shop 577 05-Dec-09 A 19-Feb-11 A
276.51A Signing of Contract with HSCL (20 months schedule) 0 21-Feb-11 A
276.52 Civil Work for BOF & CCP Shop (HSCL) stopped 577 21-Feb-11 A 31-Dec-12 A
276.53 Signing of Contract with Simplex (14 months schedule) 0 28-Feb-13 A
276.61 Civil Work for BOF & CCP Shop (Simplex) 425 01-Mar-13 A 09-Dec-14
Pkg 033A1 Piling work for BOF & CCP ShopPkg 033A1 Piling work for BOF & CCP ShopPkg 033A1 Piling work for BOF & CCP ShopPkg 033A1 Piling work for BOF & CCP ShopPkg 033A1 Piling work for BOF & CCP Shop
286 Recpt of Tender at Bhilai 30 11-Aug-09 A 27-Aug-09 A
328 Scrutiny, Discussions & Tender Finalisation 30 28-Aug-09 A 11-Nov-09 A
329 Firming-up of price of the package 15 12-Nov-09 A 31-Dec-09 A
330 Issue of LOI 0 01-Jan-10 A
331 Signing of Contract with M/s ERA (20 months schedule) 0 23-Jan-10 A
332 Piling Work for BOF & CCP Shop 273 25-Jan-10 A 16-Nov-14
Pkg 033-B Structural Work for BOF & CCP ShopPkg 033-B Structural Work for BOF & CCP ShopPkg 033-B Structural Work for BOF & CCP ShopPkg 033-B Structural Work for BOF & CCP ShopPkg 033-B Structural Work for BOF & CCP Shop
242 Issue Draft TS (Issued ) 0 24-Aug-07 A
243 Discussion with BSP 7 30-Aug-07 A 06-Sep-07 A
244 Issue Final TS 10 07-Sep-07 A 31-Oct-07 A
245 Issue of NIT 5 01-Nov-07 A 13-Nov-07 A
246 Recpt of Tender at Bhilai 22 14-Nov-07 A 25-Dec-07 A
247 Recpt of Tender at Ranc hi 4 26-Dec-07 A 31-Dec-07 A
247.1 Scrutiny, Discussions & Tender Finalisation (Retendered) 40 01-Jan-08 A 28-Aug-08 A
475 Issue of NIT 5 07-Mar-09 A 12-Mar-09 A
476 Recpt of Tender at Bhilai 22 13-Mar-09 A 15-Apr-09 A
477 Recpt of Tender at Ranc hi 4 16-Apr-09 A 27-Apr-09 A
477.1 Scrutiny, Discussions & Tender Finalisation 40 28-Apr-09 A 25-May-09 A
479 Firming-up of price of the package 40 26-May-09 A 15-Sep-09 A
479.2 Signing of Contract with M/s ERA (24 months schedule) 0 30-Sep-09 A
479.21 Structural Fabrication for BOF Shop 517 01-Oct-09 A 27-Oct-14
479.22 Structural Fabrication for CCP Shop 517 01-Oct-09 A 11-Nov-14
479.3 Structural Work for BOF Shop 547 06-Oct-11 A 02-Jun-15
479.4 Structural Work for CCP Shop 547 06-Oct-11 A 03-Feb-15
Pkg 036 Mobile equipment ( By BSP directly)Pkg 036 Mobile equipment ( By BSP directly)Pkg 036 Mobile equipment ( By BSP directly)Pkg 036 Mobile equipment ( By BSP directly)Pkg 036 Mobile equipment ( By BSP directly)
273 Issue Draft TS 0 30-Sep-14
274 Discussion with BSP 6 01-Oct-14 06-Oct-14
322 Issue Final TS 14 07-Oct-14 20-Oct-14
355 Issue of NIT 9 21-Oct-14 29-Oct-14
487 Recpt of Tender at Bhilai 43 30-Oct-14 11-Dec-14
496 Supply of mobile equipment 547 26-Jan-15 25-Jul-16
Pkg 037 Centralised telecommunication system for full expansionPkg 037 Centralised telecommunication system for full expansionPkg 037 Centralised telecommunication system for full expansionPkg 037 Centralised telecommunication system for full expansionPkg 037 Centralised telecommunication system for full expansion
253 Issue Draft TS 0 20-Jun-08 A
254 Discussion with BSP 6 21-Jun-08 A 31-Mar-10 A
255 Issue Final TS 14 01-Apr-10 A 20-Apr-10 A
256 Issue of NIT 9 21-Apr-10 A 30-Apr-10 A
257 Recpt of Tender at Bhilai 43 01-May-10 A 11-Jun-10 A
Pkg 047-01 Drop Test Facility for URMPkg 047-01 Drop Test Facility for URMPkg 047-01 Drop Test Facility for URMPkg 047-01 Drop Test Facility for URMPkg 047-01 Drop Test Facility for URM
11210 Issue Final TS 14 01-Jun-11 A 15-Jun-11 A
11220 Issue of NIT 9 28-Jun-11 A 05-Jul-11 A
11230 Recpt of Tender at Bhilai 43 06-Jul-11 A 31-Oct-11 A
11240 Recpt of Tender at Ranc hi 6 01-Nov-11 A 10-Nov-11 A
Pkg 052-B Structural Work for URMPkg 052-B Structural Work for URMPkg 052-B Structural Work for URMPkg 052-B Structural Work for URMPkg 052-B Structural Work for URM
857 Issue Draft TS (Issued ) 0 01-Sep-07 A
858 Discussion with BSP 4 03-Sep-07 A 06-Sep-07 A
859 Issue Final TS 12 07-Sep-07 A 26-Oct-07 A
860 Issue of NIT 10 27-Oct-07 A 15-Nov-07 A
861 Recpt of Tender at Bhilai 45 16-Nov-07 A 31-Dec-07 A
862 Recpt of Tender at Ranc hi 5 01-Jan-08 A 05-Jan-08 A
863 Scrutiny, Discussions & Tender Finalisation (Retendered) 60 06-Jan-08 A 08-Jun-08 A
930 Issue of NIT 10 20-Apr-09 A 28-Apr-09 A
9390 Recpt of Tender at Bhilai 45 29-Apr-09 A 30-Apr-09 A
9400 Recpt of Tender at Ranc hi 5 01-May-09 A 02-May-09 A
941.1 Scrutiny, Discussions & Tender Finalisation (Retendered ) 30 04-May-09 A 16-Jan-10 A
941.2 Issue of NIT 10 28-Jan-10 A 01-Feb-10 A
941.3 Recpt of Tender at Bhilai 45 02-Feb-10 A 03-Mar-10 A
942 Recpt of Tender at Ranc hi 5 17-Mar-10 A 24-Mar-10 A
943 Scrutiny, Discussions & Tender Finalisation 30 25-Mar-10 A 27-Oct-10 A
944 Firming-up of price of the package & stage-II approval 15 28-Oct-10 A 11-Nov-10 A
945 Issue of LOI 0 25-Nov-10 A
946 Signing of Contract with M/s HSCL (20 months schedule) 0 10-Dec-10 A
947 Structural work for Universal Rail Mill 609 10-Dec-10 A 10-May-15
Pkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etcPkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etcPkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etcPkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etcPkg 070 Augmentation of MSDS - I, III, IV, V & VI incl. HT network, etc
403 Issue Draft TS (Issued ) 0 13-Jul-07 A
404 Discussion with BSP 20 20-Jul-07 A 08-Aug-07 A
405 Issue Final TS (Issued ) 15 27-Aug-07 A 15-Sep-07 A
406 Issue of NIT (Issued ) 24 16-Sep-07 A 29-Sep-07 A
407 Recpt of Tender at Bhilai 45 01-Oct-07 A 15-Dec-07 A
408 Recpt of Tender at Ranc hi 5 16-Dec-07 A 20-Dec-07 A
409 Scrutiny, Discussions & Tender Finalisation 60 21-Dec-07 A 07-Apr-08 A
410 Firming-up of price of the package & stage-II approval 30 08-Apr-08 A 02-Sep-08 A
410.1 Issue of LOI 0 03-Sep-08 A
411 Signing of Contract with M/s AREVA (24 months schedule) 0 25-Sep-08 A
Pkg 071A All Distribution HT Sub-Stations located near Main Tech. PkgsPkg 071A All Distribution HT Sub-Stations located near Main Tech. PkgsPkg 071A All Distribution HT Sub-Stations located near Main Tech. PkgsPkg 071A All Distribution HT Sub-Stations located near Main Tech. PkgsPkg 071A All Distribution HT Sub-Stations located near Main Tech. Pkgs
414 Issue Draft TS 0 29-Jan-09 A
417 Issue of NIT 9 23-Jan-10 A 01-Feb-10 A
418 Recpt of Tender at Bhilai 45 02-Feb-10 A 08-Mar-10 A
419 Recpt of Tender at Ranc hi 5 09-Mar-10 A 29-Mar-10 A
420 Scrutiny, Discussions & Tender Finalisation (Retendered ) 30 30-Mar-10 A 18-Sep-10 A
420.1 Issue of TS 0 30-Sep-10 A
420.2 Issue of NIT 9 01-Oct-10 A 16-Oct-10 A
420.3 Recpt of Tender at Bhilai 45 18-Oct-10 A 10-Nov-10 A
420.4 Recpt of Tender at Ranc hi 5 11-Nov-10 A 17-Nov-10 A
420.5 Scrutiny, Discussions & Tender Finalisation 30 18-Nov-10 A 22-Feb-11 A
421 Firming-up of price of the package & Mngt. Approval 30 23-Feb-11 A 29-Jul-11 A
422 Signing of Contract with M/s ABB (20 months s chedule) 0 02-Sep-11 A
Pkg 075 Interplant Fuel Gas & Industrial Gas Piping for all UnitsPkg 075 Interplant Fuel Gas & Industrial Gas Piping for all UnitsPkg 075 Interplant Fuel Gas & Industrial Gas Piping for all UnitsPkg 075 Interplant Fuel Gas & Industrial Gas Piping for all UnitsPkg 075 Interplant Fuel Gas & Industrial Gas Piping for all Units
430 Recpt of Tender at Bhilai 45 15-Mar-10 A 30-Apr-10 A
431 Recpt of Tender at Ranc hi 5 01-May-10 A 03-May-10 A
432 Scrutiny, Discussions & Tender Finalisation 60 04-May-10 A 01-Oct-10 A
433 Firming-up of price of the package & Mngt. Approval 30 02-Oct-10 A 01-Nov-10 A
433.1 Issue of LOI 0 21-Dec-10 A
434 Signing of Contract with TATA Projects (15 months schedule)
0 22-Jan-11 A
435 Engg., Supply, Execution, Testing & Comm.- I/P Gas Piping 456 21-Jan-11 A 25-Apr-15
Pkg 075A Energy monitoring systemPkg 075A Energy monitoring systemPkg 075A Energy monitoring systemPkg 075A Energy monitoring systemPkg 075A Energy monitoring system
433.11 Issue of draft TS 0 26-Nov-10 A
433.31 Issue of final TS 0 10-Mar-11 A
9670 Issue of NIT 9 11-Mar-11 A 04-May-11 A
9680 Recpt of Tender at Bhilai 30 05-May-11 A 25-Jun-11 A
9690 Recpt of Tender at Ranc hi 5 27-Jun-11 A 30-Jun-11 A
9700 Scrutiny, Discussions & Tender Finalisation 60 30-Jun-11 A 16-Mar-12 A
9710 Firming-up of price of the package & Mngt. Approval 30 17-Mar-12 A 29-May-12 A
9720 Signing of Contract 0 30-May-12 A
9730 Engg., Supply, Execution, Testing & Comm.-Energy monitoring system
547 01-Jun-12 A 04-Sep-16
Pkg 075B Storage vessel and PRMS for O2,N2Pkg 075B Storage vessel and PRMS for O2,N2Pkg 075B Storage vessel and PRMS for O2,N2Pkg 075B Storage vessel and PRMS for O2,N2Pkg 075B Storage vessel and PRMS for O2,N2
Pkg 077-01 Water Supply System for BOF& CCPPkg 077-01 Water Supply System for BOF& CCPPkg 077-01 Water Supply System for BOF& CCPPkg 077-01 Water Supply System for BOF& CCPPkg 077-01 Water Supply System for BOF& CCP
448 Issue Draft TS 0 15-Apr-10 A
449 Discussion with BSP 8 16-Apr-10 A 22-Nov-10 A
450 Issue Final TS 14 26-Nov-10 A 10-Dec-10 A
451 Issue of NIT 9 02-Jan-11 A 11-Jan-11 A
452 Recpt of Tender at Bhilai 30 31-Jan-11 A 18-Feb-11 A
453 Recpt of Tender at Ranc hi 5 18-Feb-11 A 22-Feb-11 A
454 Scrutiny, Discussions & Tender Finalisation (Retendered) 45 23-Feb-11 A 02-Apr-11 A
454.1 Issue Final TS 14 04-Apr-11 A 07-Jun-11 A
454.2 Issue of NIT 9 08-Jun-11 A 16-Jun-11 A
454.3 Recpt of Tender at Bhilai 30 17-Jun-11 A 16-Jul-11 A
454.4 Recpt of Tender at Ranc hi 5 18-Jul-11 A 02-Aug-11 A
454.5 Scrutiny, Discussions & Tender Finalisation 30 03-Aug-11 A 17-Mar-12 A
455 Firming-up of price of the package & Mngt. Approval 30 19-Mar-12 A 28-Jun-12 A
457 Engg., Supply, Execution, Testing & Comm.- Water Supply system
456 30-Jun-12 A 17-Aug-15
Pkg 077-02 Water Supply System for BRM & URM incl. RHFPkg 077-02 Water Supply System for BRM & URM incl. RHFPkg 077-02 Water Supply System for BRM & URM incl. RHFPkg 077-02 Water Supply System for BRM & URM incl. RHFPkg 077-02 Water Supply System for BRM & URM incl. RHF
9530 Issue Draft TS 0 31-Mar-11 A
9540 Discussion with BSP 8 01-Apr-11 A 01-Jun-11 A
9550 Issue Final TS 14 02-Jun-11 A 16-Jun-11 A
9560 Issue of NIT 9 17-Jun-11 A 04-Jul-11 A
9570 Recpt of Tender at Bhilai 30 05-Jul-11 A 24-Aug-11 A
9580 Recpt of Tender at Ranc hi 5 25-Aug-11 A 30-Aug-11 A
9590 Scrutiny, Discussions & Tender Finalisation 30 01-Sep-11 A 30-May-12 A
9600 Firming-up of price of the package & Mngt. Approval 30 31-May-12 A 16-Jun-12 A
9610 Signing of Contract 0 22-Sep-12 A
9620 Engg., Supply, Execution, Testing & Comm.- Water Supply 456 24-Sep-12 A 17-Aug-15
Pkg 078 Make-up Water Supply System AugmentationPkg 078 Make-up Water Supply System AugmentationPkg 078 Make-up Water Supply System AugmentationPkg 078 Make-up Water Supply System AugmentationPkg 078 Make-up Water Supply System Augmentation
459 Issue Draft TS 0 31-Jul-09 A
460 Discussion with BSP 10 01-Aug-09 A 31-Aug-09 A
461 Issue Final TS 14 01-Sep-09 A 23-Apr-10 A
462 Issue of NIT 7 24-Apr-10 A 03-Jun-10 A
463 Recpt of Tender at Bhilai 45 04-Jun-10 A 07-Aug-10 A
464 Recpt of Tender at Ranc hi 5 09-Aug-10 A 13-Aug-10 A
465 Scrutiny, Discussions & Tender Finalisation (retendered) 60 14-Aug-10 A 01-Dec-10 A
Pkg 098-2 Track mobile locomotivePkg 098-2 Track mobile locomotivePkg 098-2 Track mobile locomotivePkg 098-2 Track mobile locomotivePkg 098-2 Track mobile locomotive
601 Issue Draft TS 0 25-Jan-08 A
602 Discussion with BSP 10 26-Jan-08 A 03-Jun-08 A
603 Issue Final TS 14 04-Jun-08 A 12-Jun-08 A
604 Issue of NIT ( Direct procurement by BSP) - (Package re-tendered)
8 13-Jun-08 A 25-Jun-11 A
605 Issue of Draft TS 0 25-Dec-12 A 31-Dec-12 A
615 Discussion with BSP 10 01-Jan-13 A 10-Jan-13 A
625 Issue Final TS 15 11-Jan-13 A 28-Jan-13 A
635 Issue of NIT 8 29-Jan-13 A 30-Aug-13 A
635.17 Recpt of Tender at Bhilai 35 02-Sep-13 A 08-Nov-13 A
635.27 Recpt of Tender at Ranc hi 5 09-Nov-13 A 09-Dec-13 A
635.37 Scrutiny, Discussions & Tender Finalisation 60 10-Dec-13 A 23-Jun-14 A
635.47 Firming-up of price of the package & Mngt. Approval 25 30-Sep-14 24-Oct-14
635.57 Issue of LOI 0 01-Nov-14
635.67 Signing of Contract 0 01-Dec-14
635.77 Procurement of Mobile road tenasport Equipmets (Truck, Damper)
243 02-Dec-14 01-Aug-15
Pkg 098-3 Mobile Fire fighting equipmentsPkg 098-3 Mobile Fire fighting equipmentsPkg 098-3 Mobile Fire fighting equipmentsPkg 098-3 Mobile Fire fighting equipmentsPkg 098-3 Mobile Fire fighting equipments
611 Issue Draft TS 0 10-Jul-08 A
612 Discussion with BSP 10 11-Jul-08 A 05-Jan-10 A
Pkg 099B Hot Metal Rail Weigh bridgePkg 099B Hot Metal Rail Weigh bridgePkg 099B Hot Metal Rail Weigh bridgePkg 099B Hot Metal Rail Weigh bridgePkg 099B Hot Metal Rail Weigh bridge
11440 Issue Draft TS 0 03-Mar-12 A
11450 Discussion with BSP 14 05-Mar-12 A 19-Mar-12 A
11460 Issue Final TS 15 20-Mar-12 A 30-Jul-12 A
11470 Issue of NIT 10 31-Jul-12 A 24-Aug-12 A
11480 Recpt of Tender at Bhilai 45 25-Aug-12 A 07-Oct-12 A
11490 Recpt of Tender at Ranc hi 5 08-Oct-12 A 15-Oct-12 A
11500 Scrutiny, Discussions & Tender Finalisation 45 16-Oct-12 A 08-Dec-12 A
11510 Firming-up of price of the package & Mngt. Approval 10 10-Dec-12 A 31-Mar-14 A
11530 Engg., Supply, Execution, Testing & Comm.- Hot Metal Rail Weigh Bridge
365 16-May-14 A 31-May-15
Pkg 100-2 Road works & road culvert over Tandula canalPkg 100-2 Road works & road culvert over Tandula canalPkg 100-2 Road works & road culvert over Tandula canalPkg 100-2 Road works & road culvert over Tandula canalPkg 100-2 Road works & road culvert over Tandula canal
10380 Signing of Contract with M/s HSCL 0 25-Feb-10 A
10390 Construction of road works & road culvert over Tandula canal
365 26-Feb-10 A 31-Dec-14
Pkg 100-3 Storm water drainage system ( merged with 100-4)Pkg 100-3 Storm water drainage system ( merged with 100-4)Pkg 100-3 Storm water drainage system ( merged with 100-4)Pkg 100-3 Storm water drainage system ( merged with 100-4)Pkg 100-3 Storm water drainage system ( merged with 100-4)
10400 Issue Draft TS 0 09-Dec-11 A
10410 Discussion with BSP 10 10-Dec-11 A 25-Feb-12 A
10420 Issue Final TS 11 27-Feb-12 A 07-Mar-12 A
10430 Issue of NIT 10 30-Sep-14 09-Oct-14*
10440 Recpt of Tender at Bhilai 35 10-Oct-14 13-Nov-14
10450 Recpt of Tender at Ranc hi 5 14-Nov-14 18-Nov-14
10470 Firming-up of price of the package & Mngt. Approval 20 03-Jan-15 22-Jan-15
10470.1 Issue of LOI 0 30-Jan-15
10480 Signing of Contract 0 01-Mar-15
10490 Construction of storm water drainage system 303 02-Mar-15 29-Dec-15
Pkg 110 Part- A Survey of New Sites & Soil TestingPkg 110 Part- A Survey of New Sites & Soil TestingPkg 110 Part- A Survey of New Sites & Soil TestingPkg 110 Part- A Survey of New Sites & Soil TestingPkg 110 Part- A Survey of New Sites & Soil Testing
618 Issue Draft TS (Issued) 0 28-May-07 A
619 Discussion with BSP 5 29-May-07 A 01-Jun-07 A
620 Issue Final TS (Issued ) 8 02-Jun-07 A 05-Jun-07 A
621 Issue of NIT (Issued ) 5 07-Jun-07 A 30-Jul-07 A
622 Recpt of Tender at Bhilai 45 01-Aug-07 A 15-Sep-07 A
623 Recpt of Tender at Ranc hi 5 17-Sep-07 A 22-Sep-07 A
624 Scrutiny, Discussions & Tender Finalisation 45 23-Sep-07 A 02-Jan-08 A
626 Signing of Contract 0 03-Jan-08 A
627 Survey work and Submission of report and Soil Test ing 180 04-Jan-08 A 16-Oct-08 A
Pkg 110 Part B Survey of New Sites & Soil TestingPkg 110 Part B Survey of New Sites & Soil TestingPkg 110 Part B Survey of New Sites & Soil TestingPkg 110 Part B Survey of New Sites & Soil TestingPkg 110 Part B Survey of New Sites & Soil Testing
838 Issue Draft TS (Issued) 0 28-May-07 A
839 Discussion with BSP 5 01-Jun-07 A 02-Jun-07 A
840 Issue Final TS (Issued ) 8 03-Jun-07 A 05-Jun-07 A
841 Issue of NIT (Issued ) 5 06-Jun-07 A 31-Jul-07 A
844 Scrutiny, Discussions & Tender Finalisation 50 01-Aug-07 A 02-Jan-08 A
846 Signing of Contract 0 03-Jan-08 A
847 Survey work and Submission of report and Soil Test ing 180 04-Jan-08 A 28-Aug-08 A
Pkg 111-01 Construction of Fly-overs & Road NetworkPkg 111-01 Construction of Fly-overs & Road NetworkPkg 111-01 Construction of Fly-overs & Road NetworkPkg 111-01 Construction of Fly-overs & Road NetworkPkg 111-01 Construction of Fly-overs & Road Network
879 Issue Draft TS 0 14-Sep-07 A
880 Discussion with BSP 10 15-Sep-07 A 25-Sep-07 A
881 Issue Final TS 10 26-Sep-07 A 07-Jan-08 A
882 Issue of NIT 8 08-Jan-08 A 13-Mar-08 A
883 Recpt of Tender at Bhilai 45 14-Mar-08 A 21-Apr-08 A
884 Recpt of Tender at Ranc hi 5 22-Apr-08 A 29-Apr-08 A
885 Scrutiny, Discussions & Tender Finalisation 60 30-Apr-08 A 19-Feb-09 A
885.1 Firming-up of price of the package & Mngt. Approval 30 20-Feb-09 A 29-Jun-09 A
885.11 Issue of NIT (Retendered) 8 20-Jul-09 A 31-Jul-09 A
885.12 Firming-up of price of the package & Mngt. Approval 30 01-Sep-09 A 17-Jun-10 A
885.13 Issue of LOI 0 18-Jun-10 A
885.2 Signing of Contract with M/s SP Singla construction (24 months schedule)
0 14-Jul-10 A
885.3 Construction of Fly-overs & Road Network 730 15-Jul-10 A 16-Feb-16
Pkg 113 Relocation of TSS and Construction PowerPkg 113 Relocation of TSS and Construction PowerPkg 113 Relocation of TSS and Construction PowerPkg 113 Relocation of TSS and Construction PowerPkg 113 Relocation of TSS and Construction Power
651 Issue Draft TS (Issued ) 0 27-Jun-07 A
652 Discussion with BSP 10 05-Jul-07 A 14-Jul-07 A
653 Issue Final TS (Issued ) 14 05-Aug-07 A 04-Sep-07 A
654 Issue of NIT (Issued ) 8 14-Sep-07 A 21-Sep-07 A
655 Recpt of Tender at Bhilai 45 24-Sep-07 A 14-Nov-07 A
656 Recpt of Tender at Ranc hi 5 15-Nov-07 A 19-Nov-07 A
657 Scrutiny, Discussions & Tender Finalisation 60 20-Nov-07 A 02-Mar-08 A
658 Firming-up of price of the package & Mngt. Approval 25 03-Mar-08 A 27-Mar-08 A
659 Signing of Contract with M/s ABB 0 01-May-08 A
659.1 Contractual Finish 0 31-Mar-09 A
660 Relocation of TSS and Construction Power 303 02-May-09 A 28-Nov-14
Pkg 114 New Centralised Compressed Air StationPkg 114 New Centralised Compressed Air StationPkg 114 New Centralised Compressed Air StationPkg 114 New Centralised Compressed Air StationPkg 114 New Centralised Compressed Air Station
662 Issue Draft TS (Issued) 0 01-May-07 A
663 Discussion with BSP 15 22-May-07 A 05-Jun-07 A
664 Issue Final TS (Issued) 15 06-Jun-07 A 21-Jun-07 A
665 Issue of NIT (Issued ) 4 22-Jun-07 A 25-Jun-07 A
666 Recpt of Tender at Bhilai 45 28-Aug-07 A 31-Oct-07 A
667 Recpt of Tender at Ranc hi 4 01-Nov-07 A 03-Nov-07 A
668 Scrutiny, Discussions & Tender Finalisation 75 30-Nov-07 A 01-Feb-08 A
669 Firming-up of price of the package & stage-II approval 30 02-Feb-08 A 14-Mar-08 A
669.1 Issue of LOI 0 22-Mar-08 A
670 Signing of Contract 0 21-Apr-08 A
671 Engg., Supply, Execution, Testing & Comm.- Central CAS 730 22-Apr-08 A 05-Mar-11 A
Pkg 114A Centralised Compressed Air Station for MillsPkg 114A Centralised Compressed Air Station for MillsPkg 114A Centralised Compressed Air Station for MillsPkg 114A Centralised Compressed Air Station for MillsPkg 114A Centralised Compressed Air Station for Mills
11540 Issue Draft TS (Issued) 0 27-Jul-11 A
11550 Discussion with BSP 15 04-Aug-11 A 02-Jan-12 A
11560 Issue Final TS (Issued) 15 03-Jan-12 A 04-Apr-12 A
11570 Issue of NIT 4 14-May-12 A 17-May-12 A
11580 Recpt of Tender at Bhilai 45 18-May-12 A 28-Jun-12 A
11590 Recpt of Tender at Ranc hi 4 29-Jun-12 A 11-Jul-12 A
11600 Scrutiny, Discussions & Tender Finalisation 75 12-Jul-12 A 01-Dec-12 A
11610 Firming-up of price of the package & stage-II approval 30 03-Dec-12 A 15-May-13 A
11615 Issue of LOI 0 30-May-13 A
11620 Signing of Contract 0 07-Jun-13 A
11630 Engg., Supply, Execution, Testing & Comm.- Central CAS (Retendered)
240 07-Jun-13 A 26-Nov-13 A
12701 Issue Final TS (Issued) 15 02-Dec-13 A 16-Dec-13 A
12702 Issue of NIT 4 06-Jan-14 A 10-Jan-14 A
12703 Recpt of Tender at Bhilai 45 11-Jan-14 A 20-Feb-14 A
12704 Recpt of Tender at Ranc hi 4 21-Feb-14 A 26-Feb-14 A
12705 Scrutiny, Discussions & Tender Finalisation 75 27-Feb-14 A 09-Jul-14 A
12706 Firming-up of price of the package & stage-II approval 30 10-Jul-14 A 09-Oct-14
12707 Issue of LOI 0 10-Oct-14
12708 Signing of Contract 0 09-Nov-14
12709 Engg., Supply, Execution, Testing & Comm.- Central CAS 240 09-Nov-14 06-Jul-15
Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)Pkg 115 Construction Water ( By BSP as enabl ing works)(Package Dropped)
673 Issue Draft TS 0 25-Feb-08 A
674 Discussion with BSP 7 26-Feb-08 A 23-May-08 A
675 Issue Final TS 10 24-May-08 A 19-Jun-08 A
676 Issue of NIT 8 20-Jun-08 A 24-Jun-08 A
677 Recpt of Tender at Bhilai 45 25-Jun-08 A 20-Aug-08 A
678 Recpt of Tender at Ranc hi 5 21-Aug-08 A 27-Aug-08 A
679 Scrutiny, Discussions & Tender Finalisation 45 28-Aug-08 A 01-Jan-09 A
Pkg 116 A Relocation of PSS storesPkg 116 A Relocation of PSS storesPkg 116 A Relocation of PSS storesPkg 116 A Relocation of PSS storesPkg 116 A Relocation of PSS stores
684 Issue Draft TS (Issued ) 0 02-Jun-07 A
685 Discussion with BSP 10 10-Jun-07 A 19-Jun-07 A
686 Issue Final TS (Issued ) 14 05-Jul-07 A 21-Jul-07 A
687 Issue of NIT (Issued ) 7 05-Sep-07 A 11-Sep-07 A
688 Recpt of Tender at Bhilai 45 12-Sep-07 A 20-Oct-07 A
689 Recpt of Tender at Ranc hi 5 21-Oct-07 A 26-Oct-07 A
690 Scrutiny, Discussions & Tender Finalisation 45 26-Oct-07 A 30-Nov-07 A
691 Firming-up of price of the package & Mngt. Approval 25 01-Dec-07 A 26-Dec-07 A
692 Signing of Contract 0 08-Jan-08 A
692.1 Contractual Finish 0 07-Aug-09 A
693 Dismantling & Relocation of PSS stores 580 09-Jan-08 A 20-Sep-12 A
Pkg 116 B1 Tap Hole Mass ShopPkg 116 B1 Tap Hole Mass ShopPkg 116 B1 Tap Hole Mass ShopPkg 116 B1 Tap Hole Mass ShopPkg 116 B1 Tap Hole Mass Shop
715 Discussion with BSP 10 10-Jun-07 A 19-Jun-07 A
716 Issue Final TS 14 05-Jul-07 A 11-Jan-08 A
717 Issue of NIT 4 12-Jan-08 A 29-Jan-08 A
718 Recpt of Tender at Bhilai 45 30-Jan-08 A 30-Jun-08 A
749 Recpt of Tender at Ranc hi 5 01-Jul-08 A 04-Jul-08 A
750 Scrutiny, Discussions & Tender Finalisation 50 05-Jul-08 A 13-Jul-08 A
751 Firming-up of price of the package & Mngt. Approval 30 14-Jul-08 A 15-Oct-08 A
751.1 Issue of LOI 0 22-Oct-08 A
752 Signing of Contract 0 22-Nov-08 A
753 Dismantling & Relocation of tap hole mass shop 273 23-Nov-08 A 16-Aug-12 A
Pkg 116 B2 LT substation for tap hole mass shopPkg 116 B2 LT substation for tap hole mass shopPkg 116 B2 LT substation for tap hole mass shopPkg 116 B2 LT substation for tap hole mass shopPkg 116 B2 LT substation for tap hole mass shop
914 Issue Draft TS (Issued ) 0 17-Dec-07 A
914.1 Discussion with BSP 10 18-Dec-07 A 25-Feb-08 A
914.2 Issue Final TS 14 26-Feb-08 A 18-Mar-08 A
914.3 Issue of NIT 4 19-Mar-08 A 26-Apr-08 A
931 Firming-up of price of the package & Mngt. Approval 30 18-Jan-09 A 25-Mar-09 A
931.1 Issue of LOI 0 31-Mar-09 A
931.2 Signing of Contract 0 31-Mar-09 A
931.3 Dismantling & Relocation of LT substation 580 01-Apr-09 A 29-Mar-14 A
Pkg 117 Project Building, Other Site offices & StoresPkg 117 Project Building, Other Site offices & StoresPkg 117 Project Building, Other Site offices & StoresPkg 117 Project Building, Other Site offices & StoresPkg 117 Project Building, Other Site offices & Stores
695 Issue Draft TS 0 27-Nov-07 A
696 Discussion with BSP 10 28-Nov-07 A 20-Dec-07 A
697 Issue Final TS 14 21-Dec-07 A 18-Jan-08 A
698 Issue of NIT 5 19-Jan-08 A 27-Mar-08 A
699 Recpt of Tender at Bhilai 45 28-Mar-08 A 15-May-08 A
700 Recpt of Tender at Ranc hi 5 16-May-08 A 20-May-08 A
915.6 Dismantling of Existing Bldgs 180 29-Jun-07 A 20-Jun-08 A
Pkg 118-B Dismantling Works Part-BPkg 118-B Dismantling Works Part-BPkg 118-B Dismantling Works Part-BPkg 118-B Dismantling Works Part-BPkg 118-B Dismantling Works Part-B
705 Issue Draft TS (Issued) 0 25-Apr-07 A
706 Discussion with BSP 1 26-Apr-07 A 10-May-07 A
707 Issue Final TS (Issued) 2 11-May-07 A 16-May-07 A
708 Issue of NIT (Issued ) 5 20-Jul-07 A 24-Jul-07 A
709 Recpt of Tender at Bhilai 45 25-Jul-07 A 09-Sep-07 A
713 Signing of Contract with M/s HSCL 0 16-Jan-08 A
714 Dismantling of Existing Bldgs 180 17-Jan-08 A 25-Jun-12 A
9155 Recpt of Tender at Bhilai 45 08-Apr-09 A 30-May-09 A
9157 Scrutiny, Discussions & Tender Finalisation 45 01-Jun-09 A 14-Aug-09 A
9158 Firming-up of price of the package & Mngt. Approval 25 15-Aug-09 A 30-Sep-09 A
9158.1 Issue of LOI 0 30-Oct-09 A
9159 Placement of Order by BSP 0 09-Jan-10 A
9160 Execution 365 11-Jan-10 A 30-Nov-14
Pkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shopPkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shopPkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shopPkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shopPkg 119-02 Electrical power & ventilation facilities for Mechanical & quenching car repair shop
9165 Recpt of Tender at Bhilai 45 30-Jun-09 A 30-Jul-09 A
9166 Recpt of Tender at Ranc hi 5 01-Aug-09 A 04-Oct-09 A
9167 Scrutiny, Discussions & Tender Finalisation 45 05-Oct-09 A 18-Nov-09 A
9168 Firming-up of price of the package & Mngt. Approval 25 19-Nov-09 A 13-Dec-09 A
9168.1 Issue of LOI 0 21-Dec-09 A
9169 Placement of Order by BSP 0 09-Jan-10 A
9170 Electrical power & vetilation for mech. & quenching car shop 273 11-Jan-10 A 30-Dec-14
Pkg 119-03 Relocation of mech. repair shop-Technological servicesPkg 119-03 Relocation of mech. repair shop-Technological servicesPkg 119-03 Relocation of mech. repair shop-Technological servicesPkg 119-03 Relocation of mech. repair shop-Technological servicesPkg 119-03 Relocation of mech. repair shop-Technological services
9173 Issue Final TS 2 20-Apr-09 A 30-Apr-09 A
9174 Issue of NIT 5 01-May-09 A 12-May-09 A
9175 Recpt of Tender at Bhilai 45 13-May-09 A 17-Jun-09 A
9176 Recpt of Tender at Ranc hi 5 18-Jun-09 A 30-Jun-09 A
9177 Scrutiny, Discussions & Tender Finalisation 45 01-Jul-09 A 19-Aug-09 A
9178 Firming-up of price of the package & Mngt. Approval 25 20-Aug-09 A 30-Sep-09 A
9178.1 Issue of LOI 0 06-Oct-09 A
9179 Placement of Order by BSP 0 13-Oct-09 A
9180 Relocation of Mech. repair shop 182 14-Oct-09 A 30-Dec-14
Pkg 121 Rail welding lines for long railsPkg 121 Rail welding lines for long railsPkg 121 Rail welding lines for long railsPkg 121 Rail welding lines for long railsPkg 121 Rail welding lines for long rails
Pkg 001-SR-03 Silica bricks & Mortar for COB-11Pkg 001-SR-03 Silica bricks & Mortar for COB-11Pkg 001-SR-03 Silica bricks & Mortar for COB-11Pkg 001-SR-03 Silica bricks & Mortar for COB-11Pkg 001-SR-03 Silica bricks & Mortar for COB-11
2011 Issue Draft TS (Issued ) 0 27-Oct-07 A
2012 Discussion with BSP 10 28-Oct-07 A 07-Nov-07 A
2013 Issue Final TS 7 08-Nov-07 A 14-Nov-07 A
2014 Issue of NIT ( Direct procurement by BSP) 15 15-Nov-07 A 30-Nov-07 A
Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11Pkg 001-SR-04 Fire clay bricks & Mortar for COB-11
9440 Engg., supply & execution 456 25-Jun-13 A 31-Mar-15
Pkg 126-01 Fire fighting system for BOF & CCPPkg 126-01 Fire fighting system for BOF & CCPPkg 126-01 Fire fighting system for BOF & CCPPkg 126-01 Fire fighting system for BOF & CCPPkg 126-01 Fire fighting system for BOF & CCP
2101 Issue of draft TS 0 02-Jul-11 A
2101.1 Issue of Final TS 0 29-Sep-11 A
2101.2 Issue of NIT 8 30-Dec-11 A 07-Jan-12 A
2102 Scrutiny, discussion & tender finalisation 45 02-Apr-12 A 22-Mar-13 A
2103 Signing of contract 0 02-Apr-13 A
2104 Engg., supply and commissioning 365 02-Apr-13 A 30-Jun-15
Pkg 126-02 Fire fighting system for B&RM & URMPkg 126-02 Fire fighting system for B&RM & URMPkg 126-02 Fire fighting system for B&RM & URMPkg 126-02 Fire fighting system for B&RM & URMPkg 126-02 Fire fighting system for B&RM & URM
9450 Issue of final TS 0 13-Mar-12 A
9460 Scrutiny, discussion & tender finalisation 45 24-Jul-12 A 01-May-13 A
9470 Signing of contract 0 15-May-13 A
9480 Engg., supply and commissioning 365 15-May-13 A 30-Jun-15
Pkg 127 Illumination, earthing & lightning protection system for SMS-3Pkg 127 Illumination, earthing & lightning protection system for SMS-3Pkg 127 Illumination, earthing & lightning protection system for SMS-3Pkg 127 Illumination, earthing & lightning protection system for SMS-3Pkg 127 Illumination, earthing & lightning protection system for SMS-3
2111.3 Issue Final TS 15 01-Jun-11 A 17-Jun-11 A
2111.4 Issue of NIT 8 18-Jun-11 A 21-Jun-11 A
2111.5 Recpt of Tender at Bhilai 45 22-Jun-11 A 20-Sep-11 A
2111.6 Recpt of Tender at Ranc hi 5 21-Sep-11 A 26-Sep-11 A
2112 Scrutiny, discussion & tender finalisation (Retendered) 45 27-Sep-11 A 08-May-12 A
Pkg 136 Area lighting of plant premisesPkg 136 Area lighting of plant premisesPkg 136 Area lighting of plant premisesPkg 136 Area lighting of plant premisesPkg 136 Area lighting of plant premises
10229.5 Firming-up of price of the package & Mngt. Approval 30 19-Nov-14 18-Dec-14
10230 Signing of Contract 0 19-Dec-14
10240 Engg., Supply and construction of building 365 20-Dec-14 19-Dec-15
Pkg 140 Pipe conveyor from RMP-III to RMP-IIPkg 140 Pipe conveyor from RMP-III to RMP-IIPkg 140 Pipe conveyor from RMP-III to RMP-IIPkg 140 Pipe conveyor from RMP-III to RMP-IIPkg 140 Pipe conveyor from RMP-III to RMP-II
2206 Issue of NIT 0 15-Jan-10 A
2207 Scrutiny, Discussions & Tender Finalisation 60 15-Feb-10 A 10-Jul-10 A
2208 Firming-up of price of the package & Mngt. Approval 30 11-Jul-10 A 03-Jan-11 A
Pkg 142-01 CNC Roll & Ring Turning Lathes for URMPkg 142-01 CNC Roll & Ring Turning Lathes for URMPkg 142-01 CNC Roll & Ring Turning Lathes for URMPkg 142-01 CNC Roll & Ring Turning Lathes for URMPkg 142-01 CNC Roll & Ring Turning Lathes for URM
11740 Issue Draft TS 0 01-Jun-12 A
11742 issue of final TS 0 13-Jun-12 A
11743 Issue of NIT 10 14-Jun-12 A 11-Jul-12 A
11744 Recpt of Tender at Bhilai 35 12-Jul-12 A 12-Aug-12 A
11745 Recpt of Tender at Ranc hi 5 13-Aug-12 A 21-Aug-12 A
11750 Scrutiny, Discussions & Tender Finalisation 60 22-Aug-12 A 31-May-13 A
Pkg 142-02 Roll & Repair Shop Equipment for URMPkg 142-02 Roll & Repair Shop Equipment for URMPkg 142-02 Roll & Repair Shop Equipment for URMPkg 142-02 Roll & Repair Shop Equipment for URMPkg 142-02 Roll & Repair Shop Equipment for URM
11780 Issue Draft TS 0 25-Jul-12 A
11781 issue of final TS 0 18-Aug-12 A
11782 Issue of NIT 10 18-Aug-12 A 20-Aug-12 A
11783 Recpt of Tender at Bhilai 35 20-Aug-12 A 30-Aug-12 A
11784 Recpt of Tender at Ranc hi 5 31-Aug-12 A 04-Sep-12 A
11790 Scrutiny, Discussions & Tender Finalisation 60 05-Sep-12 A 24-Apr-13 A