Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., Thane Project “VISION” Document END USER MANUAL Version No. 1 Module Production Planning (PP) Page 1 of 118 END USER MANUAL SAP, PRODUCTION PLANNING (PP) MODULE PROJECT “VISION” SUJAN BARRE THOMAS ANTIVIBRATION SYSTEMS PVT. LTD., Thane Prepared By, HARRIS PANCHAL SAP Consultant, PP Mahindra IT Consulting Pvt. Ltd., Mumbai
118
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 1 of 118

END USER MANUAL

SAP, PRODUCTION PLANNING (PP) MODULE

PROJECT

“ V I S I O N ”

SUJAN BARRE THOMAS ANTIVIBRATION SYSTEMS PVT. LTD.,

Thane

Prepared By,

HARRIS PANCHAL

SAP Consultant, PP

Mahindra IT Consulting Pvt. Ltd., Mumbai

Page 2: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 2 of 118

DOCUMENT CONTROL

Sr. No. RevisionDate of

CreationDate of

ModificationRemarks

1 1.0 07-February-09 07-February-09 ---

Security Classification: COMPANY CONFIDENTIAL

Page 3: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 3 of 118

Contents

1. CHECK SCHEDULING AGREEMENT – MD04....................................................................................4

2. CHECK STOCK OF MATERIAL - MMBE.............................................................................................6

3. EXPLODED BOM VIEW – CS11 ..........................................................................................................9

4. RESERVATION CREATION ...............................................................................................................11

4.1a BY MANUAL CREATION THROUGH – MB21...................................................................11

4.1b RESERVATION DISPLAY – PRINT FOR INTIMATION – MB25.......................................14

4.1c STOCK TRANSFER POSTING – MB26 ............................................................................18

4.2 BY MANUAL CREATION THROUGH – MB1B ....................................................................19

5. CHECK BILL OF MATERIAL – CS03 ................................................................................................21

5.1 CHECKING STANDARD BOM.............................................................................................21

5.2 ADDING AN ALTERNATIVE BOM .......................................................................................23

6. CHECK ROUTING – CA03 .................................................................................................................25

6.1 CHECKING STANDARD ROUTING ....................................................................................25

6.2 ADDING AN ALTERNATIVE ROUTING ..............................................................................28

7. PRODUCTION ORDER CREATION – MANUAL – CO01..................................................................30

8. SHOP FLOOR PRINTING – PRODUCTION ORDER – CO04 ...........................................................35

9. PRODUCTION ORDER CONFIRMATION – CO11n ..........................................................................39

10. QUALITY INSPECTION – QA32.......................................................................................................43

11. PRODUCTION ORDER SETTLEMENT – KO88 ..............................................................................51

12. PRODUCTION ORDER TECO – (Technically Complete) – CO02 ................................................53

13. CHECK PRODUCTION ORDER REPORTS ....................................................................................55

13.1 PRODUCTION ORDER INFORMATION SYSTEM - COOIS ............................................56

13.2 CAPACITY PLANNING - STANDARD OVERVIEW – CM01 ............................................61

13.3 CAPACITY PLANNING - CAPACITY EVALUATION – CM50 ..........................................63

13.4 ORDER PROGRESS REPORT – CO46............................................................................66

13.5 DISPLAYING PRODUCTION ORDER CONFIRMATION – CO14 ....................................68

13.6 CHECK PRODUCTION ORDER DELIVERY – MB51........................................................69

13.7 CHECK RAW MATERIAL ISSUE – MB51 .........................................................................71

13.8 CHECK RAW MATERIAL RECEIPT – MB51.....................................................................73

13.9 MATERIAL USAGE ANALYSIS - MCRE............................................................................75

13.10 ANALYZE PRODUCTION ORDER – KKBC_ORD ..........................................................77

13.11 CHECKING FAILED GOODS MOVEMENT - COGI ........................................................79

14. PRODUCTION ORDER – THROUGH DEMAND MANAGEMENT ..................................................80

14.1 CREATE PLANNED INDEPENDENT REQUIREMENT – MD61.......................................80

14.2 MRP – AT PLANT LEVEL – MD01.....................................................................................83

14.3 MRP – AT MATERIAL LEVEL – MD02 ..............................................................................85

14.4 PRODUCTION ORDER CONFN. WITH REWORK – CO11n............................................93

14.5 PRODUCTION ORDER CREATION – REWORK – CO07 ................................................97

14.6 REWORK PRODUCTION ORDER CONFIRMATION – CO11n......................................101

14.7 GOODS RECEIPT OF REWORK ORDER – MB31 .........................................................104

15. MRP – FOR PLANNED ORDER + PURCHASE REQUISITION ....................................................107

16. CO-PRODUCT SCENARIO ............................................................................................................114

Page 4: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 4 of 118

1. CHECK SCHEDULING AGREEMENT – MD04

Sales & Distribution (SD) Module would be inputting Scheduling Agreement in the SD Module which

would be visible in the Stock Requirement List (Dynamic Listing).

SAP ECC menu Logistics → Production → MRP → Planning → Evaluations → Stock/Requirements List

Transaction code MD04

Here enter the Material and the Plant who’s Requirements are to be checked.

Page 5: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 5 of 118

Here you can see the Scheduling Agreement inputted by SD.

Page 6: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 6 of 118

2. CHECK STOCK OF MATERIAL - MMBE

The Stock of the Raw Material is checked against the Selection criteria.

SAP ECC menu Logistics → Material Management → Inventory Management → Environment → Stock → Stock Overview

Transaction code MMBE

Double click on the Transaction code and give the selection condition as per your requirement.

Page 7: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 7 of 118

Click on Execute

The System will Show you the Stock as of that particular Item. The system will show you the Actual

stock lying at different areas such as Unrestricted, Quality Inspection, Reserved and Blocked Stock etc.

Page 8: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 8 of 118

If the stock is not available at IS01 (Issuing In-Between Storage Location), then, In-House Stock

transfer of components has to be done, i.e. ST01 to IS01. Production Order will be consuming the

Stock from ST01 (General Storage Location) to IS01 (In-between / WIP Storage Location).

Also if the production department has determined the total quantity required for a particular material,

say ROH, then they can check the same by exploding the total BOM Quantity.

Page 9: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 9 of 118

3. EXPLODED BOM VIEW – CS11

To check the Total Raw Material requirement by means of Exploding the Total BOM of a particular

Material.

SAP ECC menu Logistics → Production → Master Data → Bills of Material → Reporting → BOM Explosion→ Material BOM

Transaction code CS11

Enter Material / Plant / Required Qty. / BOM Application and click on Execute icon.

Page 10: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 10 of 118

After the execution, it will show the Total Requirement for that Finish Product in terms of Raw Material

requirement.

Page 11: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 11 of 118

4. RESERVATION CREATION

4.1a BY MANUAL CREATION THROUGH – MB21

Now known the total quantity the Reservation needs to be created for the total requirement which was

being put at the time of exploding the BOM.

SAP ECC menu Logistics → Material Management → Inventory Management → Reservation → Create

Transaction code MB21

Enter Movement No.: 311 for Plant 1000.

Page 12: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 12 of 118

Enter Material, its Quantity, Unit oF Measure, the Receving Storage Location (IS01) and Storage

Location (ST01)

And Click on SAVE. Reservation is created and it will be shown with a Green Tick and a Reservation

No. being created.

Page 13: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 13 of 118

Note the Reservation No. shown in the System Status bar.

Page 14: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 14 of 118

4.1b RESERVATION DISPLAY – PRINT FOR INTIMATION – MB25

SAP ECC menu Logistics → Material Management → Inventory Management → Reservation → Reservation List

Transaction code MB25

Enter Material & Plant 1000.

Page 15: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 15 of 118

Click on Execute

Reservation List Display will be seen.

Select the Reservation Line and Click on Change Layout From Drop Down menu

Page 16: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 16 of 118

Select Choose to select the saved Layout.

Page 17: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 17 of 118

Now you can see the details as per the selected Layout.

Select this line and Click on Print Option. Once the Spool is created, go to Spool Management to select

the print to be printed as a Hard Copy which then can be given to the Stores for issuing the material

from ST01 to IS01.

Page 18: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 18 of 118

4.1c STOCK TRANSFER POSTING – MB26

SAP ECC menu Logistics → Material Management → Inventory Management → Reservation → Picking

Transaction code MB26

You can enter here the Material / Reservation No. / Order No. / Plant as per your filtering requirement.

After entering you can simply select the One Reservation which you want to post, multiple selection is

also possible. If only 1 is to be posted then you need to delete the other postings and then Post the one

which was kept.

Goods movement would take place, which would mention it by Displaying a Green Tick mark in the

status bar.

Now the required material is available at IS01.

Page 19: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 19 of 118

4.2 BY MANUAL CREATION THROUGH – MB1B

SAP ECC menu Logistics → Logistics Execution → Internal Whse Processes → Posting Change → Inventory Management→ Enter Posting Change

Transaction code MB1B

Here with this TCode you can directly post the required stock within plant.

Page 20: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 20 of 118

Enter the following details on the main Screen viz.

1. Movement Type: 311

2. Plant: 1000

3. Storage Location (Where the goods exists, Transfer from location): ST01

On the next screen Enter the following:

1. Rcvg SLoc (Where the material is needed to consume): IS01

2. Enter the Material details and Storage Location

And SAVE to post the material to the required Storage location.

Page 21: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 21 of 118

5. CHECK BILL OF MATERIAL – CS03

5.1 CHECKING STANDARD BOM

Now enter the Material number of which you BOM you want to see and execute.

SAP ECC menu Logistics → Production → Master Data → Bills OF Material → Material BOM → Display

Transaction code CS03

Page 22: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 22 of 118

System will show you the Bill Of Material with details like material included in bill of material, description

of the component, quantity required with unit of measure.

Page 23: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 23 of 118

5.2 ADDING AN ALTERNATIVE BOM

At times there are chances that an Alternative Material is available to produce a particular component.

In that case an Alternative BOM for the same FERT would be required.

To do so, CS01 can be used to create an Alternate over an Existing BOM.

It would highlight that an Alternative 2 added to BOM and a New Page for entering the BOM

components would come where you can enter the new / alternate components.

SAP ECC menu Logistics → Production → Master Data → Bills OF Material → Material BOM → Create

Transaction code CS01

Page 24: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 24 of 118

Other relevant details such as Storage Location and SAVE the BOM.

Once you have created it and when you open the BOM in change mode it would show you 2

alternatives and you can select which one you want to view / modify.

Page 25: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 25 of 118

6. CHECK ROUTING – CA03

6.1 CHECKING STANDARD ROUTING

SAP ECC menu Logistics → Production → Master Data → Routings →Standard Routings → Display

Transaction code CA03

Enter the Material Number & Plant to display the Routing.

Page 26: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 26 of 118

System will display the routing of the material with details such as work center used operation

performed, Base quantity and the Activities. If the Group No. is already visible in the field, remove the

same and give Enter.

A Production Resource Tool (PRT) i.e. in case of SBT it is a Mould can be checked. In the above view

9th Column shows the TICK MARK which is grayed for PRT being applied to that operation. Select this

operation and click on above.

Page 27: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 27 of 118

CONTROL KEY:

You maintain the control key for operations in Customizing for Shop Floor Control. This is customizing

operation.

For SBT Scenario we are using 3 Control Keys viz.

1. PP01 - Routing/Ref. op. set - internal proc.

2. PP03 - Routing - in-house prod. auto. goods rct

3. PP07 - For Rework

PP01

Is used for all Operations other than the Last Operation as it has a Auto GR Tick which will allow the

components to be Goods received after the Final confirmation.

PP03

Is used for the Last operation or where Goods Receipt is to take place.

NOTE: Auto Goods Receipt can take place in 1 Operation only in the whole Routing sequence.

PP07

This is specifically used for to be used in Rework Order operations. Manual GR is mandatory for

Rework Orders.

Page 28: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 28 of 118

6.2 ADDING AN ALTERNATIVE ROUTING

To add an alternative routing you have through TCode CA01 itself.

SAP ECC menu Logistics → Production → Master Data → Routings →Standard Routings → Create

Transaction code CA01

Here it would show that Sequence No. 1 with Group Counter 1 is the only one existing. Hence to create

an Alternate Routing for the same FERT, i.e. if 1 Single Product is having more than 1 way of

manufacturing the product.

Click on NEW .

Page 29: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 29 of 118

Here you can see the Counter as 2.

Enter the Usage as 1 and Status 4 and click on Operations.

Now you can enter the new sequence of operation that you want and give Enter.

Enter the Setup Time, Machine Time and Labour Time and SAVE.

Page 30: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 30 of 118

7. PRODUCTION ORDER CREATION – MANUAL – CO01

Enter the following:

1. Material Number: XXXXXXXX

2. Production Plant: 1000

3. Order Type ZS01

SAP ECC menu Logistics → Production → Shop Floor Control → Order →Create → With Material

Transaction code CO01

Page 31: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 31 of 118

Enter the following:

1. Quantity of Production

2. Basic Dates (As per the Scheduling Type)

Page 32: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 32 of 118

As we have an Alternative Routing for the FERT, you need to select the Icon Production Version

in the top frame.

It would then prompt you for the Routing which needs to be selected for the FERT as per the machine

availability.

Select the required sequence and then you can continue as per the regular Production Order

execution.

PRE-REQUISITE FOR PRODUCTION VERSION:

Production version needs to be maintained in Work Scheduling View or MRP4 View of the

Material Master for the FERT’s who have more than 1 combination of BOM and/or Routings.

Now, Click on the following:

1. Material Availability Check

It would show that the Material is available or not, if not it would mention that the material is shortage

and material need to be made available at the required storage location.

Page 33: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 33 of 118

Click on the following:

1. Capacity Check

It would show whether the Capacity is Available or not.

Page 34: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 34 of 118

Click on the Calculator on the Top Frame, to calculate the costs. Thereafter the system should

message as shown below.

Click on the Green Flag to RELEASE the Order.

System would show that the Order has been released.

Now you can SAVE the production order and note the Production Order No.

Page 35: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 35 of 118

8. SHOP FLOOR PRINTING – PRODUCTION ORDER – CO04

Enter the Production Order No. & Plant and give Execute.

SAP ECC menu Logistics → Production → Shop Floor Control → Control → Print

Transaction code CO04N

Page 36: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 36 of 118

Select the Order description line and Press F8 (Execute).

Page 37: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 37 of 118

Select OWN SPOOL REQUESTS from the Pull Down Menu and select the latest Spool and select the

printer to Print the Shop Floor Paper.

Page 38: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 38 of 118

The Production Order print can now be taken by the Production Supervisor and can move the same

along with the Material being provided from IS01.

Once the Production Order is printed the same cannot be printed as a New Print, it has to be printer as

a RE-PRINT and the Heading would show DUPLICATE for the Shop Floor personnel’s to understand

that it is a Duplicate Print of the prodcution Order.

Page 39: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 39 of 118

9. PRODUCTION ORDER CONFIRMATION – CO11n

SAP ECC menu Logistics → Production → Shop Floor Control →Confirmation → Enter → For Operation

Transaction code CO11N

Page 40: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 40 of 118

As we would be Confirming the Order Operation Wise we can go for Time-Ticket Confirmation.

Enter the Order No. and the Operation which you want to confirm and Click on ACTUAL. DATA

to get the Existing Data which has come along with the Production Order. Here you

can now enter the ACTUAL Data which you have got through Production to be seen as the Variance

during the Production Order reporting.

Page 41: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 41 of 118

Also select on Confirmation Type, for the Qty is to be processed and the reservations to be cleared,

select Final Confirmation and Clear Open Reservations.

Page 42: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 42 of 118

Also you can click on Goods Movement to enter the Actual material usage for

the Qty entered on the main confirmation screen.

Here you can see 2 Goods Movement i.e. Goods Issue and Goods Receipt to be happening in a Single

Confirmation command.

Thereafter click on SAVE.

Check for any System Messages which appear in the Status Bar.

Now the material has been posted to QA for Quality Inspection. The same can be checked in the Stock

Overview List of the FERT material.

Material qty. can be seen in Quality Inspection Stage.

Page 43: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 43 of 118

10. QUALITY INSPECTION – QA32

SAP ECC menu Logistics → Quality Management → Quality Inspection →Worklist → Inspection → Change Data

Transaction code QA32

Page 44: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 44 of 118

First check the Stock Overview MD04 for the FERT material.

You can check the QM Lot being created.

The inspection of the components would be done in the QA Department and thereafter you can type in

the TCode QA32 for viewing the Inspection Lot which has been created in the QA.

In the Inspection Lot Enter Plant & Material who’s Inspection Lot is to be checked.

Page 45: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 45 of 118

Select the Inspection Lot which is to be confirmed after Inspection and click on Usage Decision Box at

the top .

Page 46: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 46 of 118

Select the Usage Code 04 GOODS RECEIPT FROM PRODUCTION ACCEPT and Give ENTER

and select on INSPECTION LOT STOCK .

Here you can enter the Quantity which is OK, To Be Scrapped or to be moved to Block Storage.

For E.g.:

Total Qty.: 5 Nos.

Unrestricted Use: 3 Nos.

To Block Storage (Rework): 1 Nos.

To New Material (Scrap): 1 Nos.

Page 47: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 47 of 118

As the Scrap would be posted against a Pre-Defined Scrap material, say TEST-SCRAP, the Material

has to be selected against “To New Material”.

Page 48: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 48 of 118

Page 49: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 49 of 118

After the Usage Decision is Saved, selected Inspection Lot appears with a TICK mark on its left side

and a Lot No. is created which can be seen at the System Status bar.

Click on REFRESH button to see the QM Lot being cleared (not appearing anymore in the list).

Page 50: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 50 of 118

You can also check the Stock Overview for this FERT component whose inspection has been done.

The same can be done through Transaction Code MMBE.

Also you can see that the Qty has been reduced from Quality Inspection Stock and Qty. 3 nos. has

been moved to Un-Restricted Use and 1 Nos. in Blocked Storage.

Page 51: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 51 of 118

11. PRODUCTION ORDER SETTLEMENT – KO88

SAP ECC menu Logistics Production->Shop Floor Control->Period End Closing ->Settlement-> Individual Processing

Transaction code KO88

Page 52: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 52 of 118

On the: Initial Screen, make the following entries:

Field name User action and values Comment

Order 1000128 Example

Settlement period 10 Example

Fiscal year 2008 Example

Processing type Automatic Example

Deselect Test run & Select Check trans. Data. Click on Execute Button

Variance amount has been settled to the Price Difference account

Page 53: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 53 of 118

12. PRODUCTION ORDER TECO – (Technically Complete) – CO02

The production Order remains Open and Changeable until it is explicitly completed. In this context,

distinction is made between logistical and the accounting based completion.

TECO – After the completion of the production order the order is no longer logistically relevant; that is, it

is marked as being no longer MRP relevant, and all the reservations for the components and capacity

requirements that may still exist are deleted. The production order is assigned the status TCMP, which

stands for Technically Completed (TECO). It is also now no longer possible to post any sots to the

production order. Moreover, it is no longer possible to trigger any confirmation for the production order.

SAP ECC menu Logistics → Production → Shop Floor Control → Order →Change

Transaction code CO02

Page 54: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 54 of 118

After opening the order in Change Mode, from the pull down menu select, Functions->Restrict

Processing -> Technically Complete.

You can see now that the Order Status has now changed to TECO.

Page 55: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 55 of 118

13. CHECK PRODUCTION ORDER REPORTS

All the necessary reports for PRODUCTION PLANNING Module can be get from the above menu.

SAP ECC menu Information systems General Report Selection Production Planning Production Control

Page 56: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 56 of 118

13.1 PRODUCTION ORDER INFORMATION SYSTEM - COOIS

The order information system is a tool for shop floor control and process industries with reporting

functions for production orders, planned orders and process orders. Evaluations take place - as with the

IOC logical database, via the original order tables.

On the Production Order Information System screen, make the necessary entries to run the report as

desired.

SAP ECC menu Information systems General Report Selection Production Planning Production Control Order Information System

Transaction code COOIS

Page 57: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 57 of 118

You can view all the orders in the system, including the orders with deletion flags or deletion indicators.

Archived orders are not taken into account.

The order information system has the following display options:

In an individual object list, a list is generated for the selected object (for instance, order header,

operation, and component). You can define the structure and appearance of the individual

object list with a layout

On the object overview the individual orders are displayed with their subordinate objects in a

hierarchical structure. With an overall profile, you can define which fields are displayed and

which objects (order headers, items, sequences, and so on) are read or displayed. In addition,

you can define which fields are displayed for the individual objects

Page 58: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 58 of 118

Reports regarding SCRAP / REJECTION can also be seen through this report where in you need to select CONFIRMATION as the header of the report.

Page 59: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 59 of 118

HEADER - ORDER WISE

HEADER - ITEMWISE

HEADER - DOCUMENTED GOODS MOVEMENT

HEADER - OPERATION WISE

Page 60: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 60 of 118

HEADER - COMPONENT WISE

HEADER - CONFIRMATION WISE

HEADER - AUTOMATIC GOODS MOVEMENT WISE

Page 61: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 61 of 118

13.2 CAPACITY PLANNING - STANDARD OVERVIEW – CM01

You can use capacity evaluations to analyze capacity loads in your company. You can adjust the

analyses for each user according to the planning level, planning horizon and the area of responsibility.

Available capacities and capacity requirements can be selected according to various criteria and

cumulated using any period split you choose.

You can use work center hierarchies to cumulate the available capacities of production work centers

and their capacity requirements to superior planning work centers.

SAP ECC menu Logistics Production Capacity Planning Evaluation Work Center View Load

Transaction code CM01

On the Capacity Planning: Selection screen, make the necessary entries to run the report as desired.

Page 62: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 62 of 118

In the capacity evaluation you can display the planned capacity requirements and the remaining

capacity requirements

Page 63: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 63 of 118

13.3 CAPACITY PLANNING - CAPACITY EVALUATION – CM50

To Check all the Capacity Available for more than 1 Work Center.

SAP ECC menu Logistics Production Shop Floor Control Information System Capacity Evaluation Extended EvaluationWork Center View

Transaction code CM50

Page 64: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 64 of 118

On the Capacity Evaluation : Selection screen, make the necessary entries to run the report as desired.Here you can get a complete capacity evaluation for more than 1 Work Center, i.e. a Range of Work Centers can be inputted here.

Page 65: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 65 of 118

Likewise, all the selected range of work centers can be seen here.

Page 66: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 66 of 118

13.4 ORDER PROGRESS REPORT – CO46

When you work with the order progress report, you can

Choose the individual objects in the report in a flexible manner

Adapt the contents and the presentation of the report (for example, include hierarchy levels later)

Execute functions (for example, convert planned orders)

Go to object maintenance (for instance, Change production order)

SAP ECC menu Logistics Production MRP Evaluations Order Progress

Transaction code CO46

A progress report can be displayed for more than one sales order or a WBS element. The requirement

elements and procurement elements are displayed.

If you want to display all objects for a sales order, enter the sales order with item number. By entering a

material or production order, you can further limit the number of objects displayed.

If you want to display objects from the Project System, you have to choose a network or a material. The

selected object (network or material) must be assigned to a WBS element. Depending on what you

have entered, a structure is displayed, from which you can select a network or material.

Page 67: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 67 of 118

Page 68: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 68 of 118

13.5 DISPLAYING PRODUCTION ORDER CONFIRMATION – CO14

You use this to display the confirmations of production orders.

SAP ECC menu Logistics Production Shop Floor Control Confirmation Display

Transaction code CO14

On the Display Production Order Confirmation: Initial screen, make the necessary entries to run the

report as desired.

If several confirmations exist, the system branches to an operation overview containing the

confirmations. Choose one or more confirmations. If you choose more than one confirmation then you

can switch between confirmations in the detail display. You can print the operation overview and define

a user-specific layout for it (column selection and sorting).

If only one confirmation exists, the system branches directly to the detail screen for the confirmation.

Page 69: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 69 of 118

13.6 CHECK PRODUCTION ORDER DELIVERY – MB51

SAP ECC menu Logistics → Material Management → Inventory Management → Environment → List Displays → Material Documents

Transaction code MB51

Page 70: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 70 of 118

After selecting MB51 Enter filtering criteria’s such as Material, Plant, Movement Type, etc.

Click on Execute.

2 highlighted in the Boxes displays the GR done 1st by Original Production Order and later through

Rework Production Order.

Page 71: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 71 of 118

13.7 CHECK RAW MATERIAL ISSUE – MB51

Enter and Input the Filtering criteria’s. Here we input 261 and 262 Goods Movement for Issuing of Raw

material.

SAP ECC menu Logistics → Material Management → Inventory Management → Environment → List Displays → Material Documents

Transaction code MB51

Page 72: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 72 of 118

Page 73: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 73 of 118

13.8 CHECK RAW MATERIAL RECEIPT – MB51

Enter and Input the Filtering criteria’s. Here we input 101 and 102 Goods Movement for Issuing of Raw

material.

SAP ECC menu Logistics → Material Management → Inventory Management → Environment → List Displays → Material Documents

Transaction code MB51

Page 74: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 74 of 118

This report would display the Total Receipt of Raw Material in the plant i.e. the Qty. which is being

procurred externally.

Note: Attached herewith is an Non-SBT example (as no live data is available at present in the System).

Page 75: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 75 of 118

13.9 MATERIAL USAGE ANALYSIS - MCRE

SAP ECC menu Information Systems → Logistics → Production →Material → Material Consumption

Transaction code MCRE

Page 76: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 76 of 118

Enter the Plant and Production Order whose Material Consumption Analysis is to be done and click on

Execute.

Click on Sujan Barre Thomas and click on Switch Drill Down and select the Level at which you want to

analyze. Say you want to analyze at the Order Level, so select Order.

Here you can see the Total Requirement Qty (Planned Qty.) vs Withdrawal Qty. (Actual Consumption).

Page 77: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 77 of 118

13.10 ANALYZE PRODUCTION ORDER – KKBC_ORD

This will report based on Production as well as Accounting for a particular order.

Enter the Order No. which is to be analyzed.

You can also select Layouts to select which type of Report you would like to see for that particular

order.

Transaction code KKBC_ORD

Page 78: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 78 of 118

Say you select the first layout, Target/Actual – Comparison, now click on Execute.

Select on to select the required fields.

Page 79: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 79 of 118

13.11 CHECKING FAILED GOODS MOVEMENT - COGI

You can check Errors in Goods Movement through COGI Transaction code.

SAP ECC menu Logistics → Production-Process → Process Order →Environment → Material Movement→ Failed Goods Movement

Transaction code COGI

Page 80: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 80 of 118

14. PRODUCTION ORDER – THROUGH DEMAND MANAGEMENT

14.1 CREATE PLANNED INDEPENDENT REQUIREMENT – MD61

As part of material requirements planning using the net change method, the planned independent

requirements are exploded across the entire BOM structure. As a result, the system also determines

dependent requirements for purchased parts and raw materials.

SAP ECC menu Logistics → Production → Production Planning → Demand Management → Planned Independent Requirement →Create

Transaction code MD61

Page 81: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 81 of 118

On the Create Planned Independent Requirement: Initial Screen, enter the following data:

Field name Description Comment

Planned Independent Requirements for

Material Enter Material Code. Finished Good MTS

(You have to select the radio button)

Plant Enter Plant Code. Always Enter Production Plant.

Selection parameters

VersionSelect Verson Number.

Always select Active Version

Planning horizon

From From Date

To To Date

Change system default if necessary.

Planning periodSelect the appropriate

Planning Period

The default planning period is M (month). You can change the default value for this field by changing the user settings.

Page 82: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 82 of 118

Check the Stock Requirement List for the same through MD04.

The Independent Requirement which is generated can be seen here in the RED box being highlighted.

Page 83: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 83 of 118

14.2 MRP – AT PLANT LEVEL – MD01

MD01 is used for running the MRP for specific plant or number of plants to maintain the scope of

planning. In the scope of planning you can maintain number of plants and can use the scope to run

MRP for maintained plants.

Usually this is followed when the First MRP is run at the time of first Run in Production Environment.

Thereafter MRP is run at Material Level i.e. MD02. So if you want to run MRP for all plant and material

in that case we use MD01

SAP ECC menu Logistics → Production → MRP → Planning → Total Planning→ Online

Transaction code MD01

Page 84: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 84 of 118

Page 85: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 85 of 118

14.3 MRP – AT MATERIAL LEVEL – MD02

MD02 is used to run MRP for a particular Material. This run would be for just one material , single item ,

multi level ( will explode whole BOM for particular material )

SAP ECC menu Logistics → Production → MRP → Planning → Total Planning→ Single Item, Multi Level

Transaction code MD02

Page 86: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 86 of 118

Enter the following details:

1. Enter Material Name

2. Enter Plant

3. Select Processing Key

Specifies the type of MRP run. The following types are possible:

net change planning: NETCH

net change planning in the planning horizon : NETPL

online regenerative planning : NEUPL

4. Create Planned Order / Purchase Requisitions (In case of BOP)

5. Delivery Schedules: Whether To Create or No

6. Create MRP List

7. Planning Mode & Scheduling

Above details are shown in the image above. ENTER to run the MRP.

An MRP List will be generated.

Page 87: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 87 of 118

Now the Planned Orders will be generated for this PIR.

Through MD04 you can select this Planned Order. Shown below.

Page 88: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 88 of 118

Select the Row of Planned Order, and Click on CONVERT TO PRODUCTION ORDER through this

Icon .

Page 89: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 89 of 118

Clicking on this, will take you to the Production Order Screen.

Enter the following:

3. Quantity of Production

4. Basic Dates (As per the Scheduling Type)

Click on the following:

1. Material Availability Check

It would show that the Material is available or not, if not it would mention that the material is shortage

and material need to be made available at the required storage location.

Page 90: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 90 of 118

Click on the following:

2. Capacity Check

It would show whether the Capacity is Available or not.

Click on the Calculator on the Top Frame, to calculate the costs. Thereafter the system should

message as shown below.

Click on the Green Flag to RELEASE the Order.

Page 91: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 91 of 118

System would show that the Order has been released.

Now you can SAVE the production order and note the Production Order No.

Page 92: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 92 of 118

Refresh the Stock Requirement List (MD04) to see the Planned Order being now converted to status

Production Order (Shown in red box below).

Shop Floor Printing can be performed thereafter through Transaction Code: CO04N.

SAP ECC menu Logistics → Production → Shop Floor Control → Control → Print

Transaction code CO04N

Page 93: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 93 of 118

14.4 PRODUCTION ORDER CONFN. WITH REWORK – CO11n

SAP ECC menu Logistics → Production → Shop Floor Control →Confirmation → Enter → For Operation

Transaction code CO11N

Page 94: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 94 of 118

As we would be Confirming the Order Operation Wise we can go for Time-Ticket Confirmation.

Enter the Order No. and the Operation which you want to confirm and Click on ACTUAL. DATA

to get the Existing Data which has come along with the Production Order. Here you

can now enter the ACTUAL Data which you have got through Production to be seen as the Variance

during the Production Order reporting.

As we would be doing REWORK activity in this Production Order, we can first check the Stock for the

part across the plant through T Code MMBE.

Page 95: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 95 of 118

On confirmation screen let us consider 200 as Yield Qty. and 100 as Qty. which is to be REWORKED.

Save the Confirmation

Check for any System Messages which appear in the Status Bar.

Now the material Qty. 200 has been posted to QA for Quality Inspection. The same can be checked in

the Stock Overview List of the FERT material.

Page 96: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 96 of 118

You can go back to CO02 for Production Order No. 100123 to see the status of the Qty.

Here you can see that out of the Total Qty. Delvrd is 200 and 100 is reworked which can be seen

through Operation Overview at the extreme Right End.

Page 97: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 97 of 118

14.5 PRODUCTION ORDER CREATION – REWORK – CO07

PRE-REQUISITIES:

For Rework Order Following Pre-Requisites have to be followed.

1. A separate Rework Order has to be Created without Reference to any Material.

2. Goods Receipt for a Rework Order has to be done manually.

SAP ECC menu Logistics → Production → Shop Floor Control → Order →Create → Without Material

Transaction code CO07

Page 98: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 98 of 118

Production Order Initial Screen will appear. Here enter Production Plant & Order Type for that Rework

Order.

GENERAL TAB

Thereafter on the Header Screen, Enter the following:

1. Material Description

2. Total Qty. to be reworked and Its Unit of Measurement

3. Basic Dates

Page 99: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 99 of 118

After giving ENTER it would give a Dialogue Box.

Here select on GENERATE OPERATION.

On the next Screen, i.e. Main Settlement Rule: Overview enter the following:

1. Category: ORD (i.e. to be settled against a Production Order)

2. Settlement Receiver: Production Order No. (In this case it is 1000123) & give ENTER.

Here it will now show the relevant details.

Go Back now.

Page 100: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 100 of 118

ASSIGNMENT TAB

Enter MRP Controller

Enter Profit Center

GOODS RECEIPT

Control Data: Stock Type ; X – Quality Inspection

Thereafter Click on Operation Overview Icon

Select the following:

Work Center on which the rework is taking place

Control Key: PP07 (For Rework Production)

Can also enter the Operation Description and give ENTER.

Thereafter Click on Component Overview to enter the components to be processed.

Enter the Component to be reworked.

Enter the Quantity (can be calculated through CS11 for total requirement as per the rework

quantity).

After entering the details and giving ENTER it would ask for the Operation Assignment, i.e. the

component is to be assigned to which Operation. Select the operation and give Enter. Also

check for the Storage Location i.e. from where the Material will be issued, which should be

IS01 in our case.

Go back now.

Like a Normal Production, Check for Material Availability, Capacity Availability, Pre-Cost it and then

Release the Rework (Production) Order and Save it and note the Rework Production Order No.

Page 101: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 101 of 118

14.6 REWORK PRODUCTION ORDER CONFIRMATION – CO11n

SAP ECC menu Logistics → Production → Shop Floor Control →Confirmation → Enter → For Operation

Transaction code CO11N

Page 102: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 102 of 118

As we would be Confirming the Order Operation Wise we can go for Time-Ticket Confirmation.

Enter the Order No. and the Operation which you want to confirm and Click on ACTUAL. DATA

to get the Existing Data which has come along with the Production Order. Here you

need to enter the ACTUAL Data which you have got through Production as the same will not be copied.

Page 103: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 103 of 118

Check for any System Messages which appear in the Status Bar.

Now the material has been posted to QA for Quality Inspection. GR for the order needs to be done

manually.

Page 104: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 104 of 118

14.7 GOODS RECEIPT OF REWORK ORDER – MB31

NOTE: Goods Receipt for a REWORK Order has to be done manually. Auto GR is not possible.

Now, here enter the following:

Movement Type: 101

Order No. would be the parent Production Order, 1000123

Plant : 100

Storage Location : FG01

SAP ECC menu Logistics → Production → Shop Floor Control → Goods Movement → Goods Receipt

Transaction code MB31

Page 105: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 105 of 118

After entering select the item No.1

Click on

And SAVE. You can see the Document No.

Page 106: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 106 of 118

You can go back to the Order 1000123 and see that all the 300 Nos. have been delivered.

Components are now posted to QA, which can be checked through MMBE

Hereafter the QA Cycle can be followed Index Point No. 11 to clear the Production Order.

Page 107: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 107 of 118

15. MRP – FOR PLANNED ORDER + PURCHASE REQUISITION

So far we have seen MRP being run to generate PLANNED ORDER further to generate Production

Order to be run in Production environment. Now here we would see the MRP to be run to generate

Planned order as well as Purchase Requisition by a Single MRP Run through MD02.

MD02 is used to run MRP for a particular Material. This run would be for just one material , single item ,

multi level ( will explode whole BOM for particular material ).

SAP ECC menu Logistics → Production → MRP → Planning → Total Planning→ Single Item, Multi Level

Transaction code MD02

Page 108: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 108 of 118

Here we take another Material as an Example.

FERT Material: TEST-FG12

Requirement in MD61 : 35 Qty.

First we check the existing Stock for TEST-FG12 through MD04.

Page 109: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 109 of 118

Enter the following details:

1. Enter Material Name

2. Enter Plant

3. Select Processing Key

Specifies the type of MRP run. The following types are possible:

net change planning: NETCH

net change planning in the planning horizon : NETPL

online regenerative planning : NEUPL

4. Create Planned Order / Purchase Requisitions (In case of BOP)

5. Delivery Schedules: Whether To Create or No

6. Create MRP List

7. Planning Mode & Scheduling

Above details are shown in the image above. ENTER to run the MRP.

An MRP List will be now generated.

Page 110: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 110 of 118

Now we go back to MD04 to check the Stock.

We can see that NO STOCK is available to Manufacture the FERT, shown as “0” in Available Qty. in

BLUE colour.

Click on the Eye Glass to get the new Dialogue Box.

Now click on to see the Order Report.

Page 111: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 111 of 118

Here you can see the Components which are contained in that FERT. And can Browse through, by

Double Clicking on the components to check the availability and the List below will show the latest

Stock position for that particular component.

Say we Click on IT-ROH03 (ROH material, whose Purchase Requisition is to be created).

Page 112: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 112 of 118

Here the one shown in RED Box, is the Planned Order which can be converted to Purchase

Requisition.

Click on Eye Glass.

Click on PUR. REQ. in the new dialogue Box. It will take you to Convert Planned order to Purchase

Requisition : Details Screen.

Here you can related information details such as, Storage Location (say ST01) and SAVE it. You will

get a Confirmation Message.

Page 113: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 113 of 118

REFRESH the list. Now you can see the List has been updated as shown in the RED BOXES below.

Further more, a PURCHASE ORDER can be created through PURCHASE REQUISITION. If release

Strategy has been set for Purchase Requisitions, the PR needs to be released before it is converted to

Purchase Order. This activity would be done by Purchase Dept. personnel.

Page 114: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 114 of 118

16. CO-PRODUCT SCENARIO

Products that are usually manufactured together can be produced using one production order.

The main product is the primary reason for the production process. It is displayed in the production

order header. The system also creates a separate order item for the main product.

A co-product is a product that is produced in conjunction with other products. The system creates a

separate order item in the production order for each co-product. As a result, it is possible to display

actual costs at co-product level.

Creating a production order to manufacture co-products has the following advantages:

Main product and co-product(s) are settled to different receivers

Goods movements can be posted simultaneously for all products manufactured in the order.

Pre-Requisities

The following prerequisites must be fulfilled if you want to create a production order with co-products or

by-products.

Prerequisite for the main product:

The indicator Co-product must be activated in the material master of the main product (MRP area)

Prerequisites for a co-product:

The indicator Co-product must be activated in the material master of the co-product (MRP area)

The co-product must be listed as an item in the bill of material of the main product with a

negative value.

On the Basic data tab page of the BOM item, the indicator Co-product must be activated in the

field group General data.

Example:

Say we have a Family Mould with 2 Family Components viz

1. TEST-COP01

2. TEST-COP02

Now say we want to take the Production of these 2 Family FERT’s.

Page 115: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 115 of 118

Say we consider the Header / Main Product is TEST-COP01 we create a Production Order for this

Header Material.

BOM For TEST-COP01 would be as seen below.

Highlighted in Red is the Famiyl Component with –ve (negative) Quantity.

When we check the Production Order it would show it as follows.

NOTE: GR for such an Order for a Co-Product scenario has to be done MANUALLY by MB31.

Also, whatever the Rejection / Scrap which is going to get posted will be of the Main Product whose

Production Order is being made.

Page 116: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 116 of 118

To Summarize:

1. A co-product is a product that is produced in conjunction with other products. The system

creates a separate order item in the production order for each co-product. As a result, it is

possible to display actual costs at co-product level.

2. The main product is the primary reason for the production process. It is displayed in the

production order header. The system also creates a separate order item for the main product.

3. The indicator Co-product must be activated in the material master of the main product (MRP 2)

as well as the Co-Product.

4. The co-product must be listed as an item in the bill of material of the main product with negative

Qty.

5. On the Basic data tab page of the BOM item, the indicator Co-product must be activated in the

field group General data.

6. Production Order would be of the Main Product, hence also the Confirmation and scrapping

would be of the Main Product Only.

7. Production Qty mentioned in the Production Order, say Qty. 10 means 10 Qty. of Co-Product 1,

and 10 Qty. of Co-Product 2.

8. Raw Material qty. to be issued would be the qty. required to product both the co-products.

9. In Production Order you need to maintain the settlement Rule in pull down menu i.e. Header ->

Settlement Rule

10. You cannot post Auto-GR for Co-Products. You have to follow Manual GR by MB31 101 Movt.

11. If you want to scrap co-product do the following steps.

Confirm all the qty as yield qty in . ( ok + scrap)

Do goods receipt for main product & co-product (total qty).

Physically you know the how much rejected qty. Move that qty from accepted str

location to rejection str location by using MB1B 311 mvt.

Now yield qty will reduce.

Check in MB51 with mvt type 311 with corresponding period, you came to know how

much quantities are rejected.

By 551 mvt materials scrap that rejected qty.

12. But if you want the Sell the scrap, then follow the following steps:

a. Confirm all the qty as yield qty ( ok + scrap)

b. Do goods receipt for main product & co-product (total qty).

c. Scrap the Material to a Scrap material, say SCRAP-MATERIAL through QA32 (QM).

Page 117: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 117 of 118

Suppose you have a Co-Product scenario for LH & RH of a particular FERT.

In this case you want to run only a few nos. of Cavity of RH keeping the nos. of cavities of LH running

as it is. In that case follow the below mentioned procedure.

Most important of all you need to maintain the Base Qty. relation of the 2 co-products.

Say for 4 Components of LH you want only 2 Components of RH. Here you need to maintain in BOM of

LH the following:

Select the Co-product with negative value (i.e. RH) and double click on Item No. to enter detail

information

Page 118: Ste by Step Sap Pp User Manual

Organization Sujan Barre Thomas Anti-Vibration Systems Pvt. Ltd., ThaneProject “VISION”

Document END USER MANUAL Version No.

1

Module Production Planning (PP)

Page 118 of 118

After entering, on the Basic Data Screen, maintain the negative Qty. as 0.50 –

Now you can go ahead and create the production order.

Now you will get only 2 Components of RH for 4 components of LH. Shown is the Production

Order.

One important thing to remember here is that the Cost apportionment is to be maintained