Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011
9

Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.

Jan 16, 2016

Download

Documents

Arleen Dennis
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.

Stave Lake Water Supply and Treatment Project

Business Case for P3 Canada Fund Funding Request

AMWSC April 04 2011

Page 2: Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.

© Deloitte & Touche LLP and affiliated entities.

Purpose of business case

• Determine if the Project may qualify for financial support from the P3 Canada Fund– Must be a P3 delivery model including design & construction plus one

or more of operations, maintenance, financing– Must provide public benefit– Must provide “value for money” according to accepted CDN practice– Project structure and procurement process must follow best practice

• Level of support: up to 25% of eligible costs• Form of support: repayable, non-repayable, interest-free loan, other

• Business case contents guided by P3 Canada Fund submission guide• Methodology guided by Partnerships BC practices

2

Page 3: Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.

© Deloitte & Touche LLP and affiliated entities.

Recommended procurement option: Hybrid DBFO+DBO

3

DBFO for “Bundle A”• Intake & Pump Station• Water Treatment Plant• Reservoir Expansion• Partial public, partial private

financing• Long term warranty benefit

from the private financing

DBO for “Bundle B”• Transmission Mains• No private financing

Page 4: Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.

© Deloitte & Touche LLP and affiliated entities.

Recommended procurement option: Hybrid DBFO+DBO

Basis for recommendation:• Maximizes construction time and cost certainty (on-time, on-budget)• Maximizes long term cost certainty• Reduces AMWSC’s retained risk and transfers considerable risk to the contractor• Provides long term performance guarantee appropriate for each Bundle• Estimated project “value for money1” of $33.2 M or 10.6%

• Estimated “value for money” to AMWSC of up to:– $83.5 M or 26.7%

… depending on level of P3 Canada Fund contribution

4

1 Net present value of cost savings over the design, construction, and operating period (approx 29 years in total), as compared to traditional design-bid-build procurement.

NPV of Costs Value for Money

Traditional DBB $ 313.1 M - -

Hybrid DBFO+DBO $ 279.8 M $ 33.2 M 10.6 %

Page 5: Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.

© Deloitte & Touche LLP and affiliated entities.

Recommended procurement option: Hybrid DBFO+DBO

Key Features• AMWSC sets water quality standards and capacity of the system• One contractor is selected through a competitive process for the

combined DBFO+DBO• The contractor designs and builds, and then operates and maintains,

Bundle A and Bundle B for 25 years – for a fixed price• AMWSC pays for approximately 35% of the construction costs of

Bundle A during construction, the balance is financed by the contractor• AMWSC pays for 100% of the construction costs of Bundle B during

construction• AMWSC makes annual payments for operations and maintenance• AMWSC makes annual payments to repay the contractor’s financing on

Bundle A• Payments to the contractor are at risk: penalties are applied if the

contractor does meet the terms of the contract

5

Page 6: Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.

© Deloitte & Touche LLP and affiliated entities.

Comparison of procurement models

Project Responsibility

Design-Build Design-Build-Operate Design-Build-Finance-Operate

PlanningMunicipality

Municipality Municipality

DesignConsultant selected on qualifications and price

Qualified special-purpose P3 contractor selected on design, long term plan, and price. Typically a consortium of firms.

Qualified special-purpose P3 contractor selected on design, long term plan, and price. Typically a consortium of firms.

ConstructionQualified general contractor selected by tender

OperationMunicipal staff or short-term tendered contracts

MaintenanceMunicipal staff or short-term tendered contracts

RehabilitationMunicipal staff or individual contracts

FinancingMunicipal Finance Authority BC (MFABC)

MFABCPortion: contractor

Portion: MFABC

Funding Municipality Municipality

Asset Ownership

Municipality Municipality

6 CONFIDENTIAL

Page 7: Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.

© Deloitte & Touche LLP and affiliated entities.

Risk allocation

Retained by AMWSC Transferred to P3 Contractor

Planning Design

Environmental approvals Construction cost & schedule

Rights to raw water Operations - water quantity

Land assembly Operations - water quality

Sizing of facilities Operations – power/chemical usage

Changes in regulation Minor maintenance

Operations - power price Rehabilitation (major maintenance)

Operations - chemical price Handback condition of infrastructure at end of operating period

Raw water quality outside defined “window”

Raw water quality inside defined “window”

7

Page 8: Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.

© Deloitte & Touche LLP and affiliated entities.

Funding request from P3 Canada Fund

• Funding request for 25% of eligible costs in the form of a non-refundable contribution

• Contribution would be received during the construction period and used to offset the AMWSC’s milestone payments to the contractor

8

Estimated P3 Canada Fund Contribution for 25% of Eligible Costs ($millions, nominal “as-spent” dollars)

DBFO Bundle A DBO Bundle B Total Contribution

$ 49.3 M $ 21.9 M $ 71.2 M

• P3 Canada Fund investment offers incremental value for money and a resultant incremental reduction in AMWSC’s costs of water provision

Value for Money

Without P3 Canada Fund Investment (1) $ 33.3 M 10.6%

With 25% P3 Canada Fund Investment (2) $ 83.5 M 26.7%

Incremental VFM From 25% P3 Canada Fund Investment (2)-(1) $ 50.2 M 16.1%

Page 9: Stave Lake Water Supply and Treatment Project Business Case for P3 Canada Fund Funding Request AMWSC April 04 2011.