STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 23.05.13 1.First Floor Slab :Completed 2.Second Floor Slab: 1 & 2 Flats Shuttering Work Completed Bar Bending work In Progress
Jun 08, 2015
STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 23.05.13
1.First Floor Slab :Completed2.Second Floor Slab: 1 & 2 Flats Shuttering Work Completed Bar Bending work In Progress
STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 23.05.13
1.First Floor Slab : Completed2.Second Floor Slab :Flats No 1 & 2 Completed
STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 23.05.13
1.Ground Floor Slab : Completed2.First Floor Slab : Flat No 01 Shuttering work In Progress
STATUS REPORT OF MY HOME ABHRA Tower-”D”As On 23.05.13
1.First Floor Slab: Completed2.Second Floor Slab : Flat No 1 & 2 flats Completed and 4th and 5th Flats shuttering
Completed,3rd flat Beam Bottom shuttering Work started
STATUS REPORT OF MY HOME ABHRA Tower-”E”As On 23.05.13
1.First Floor Slab :Completed2.Second Floor Slab : Flat no 1 & 2 Shuttering completed
STATUS REPORT OF MY HOME ABHRA “TOTAL SITE”As On 23.05.131.Total Site Ground Floor slab Completed
2.Total Site First Floor slab Except Tower :C Remain All Completed3.Total Site Second Floor Slab: Tower B & E 1 & 2 Flats Completed