“ Status of the Loran Recapitilization Project” FAA Team Meeting – July 2002 CDR G. K. Weeks Jr., U. S. Coast Guard, Commanding Officer USCG Loran Support Unit
Jan 31, 2016
“Status of the Loran Recapitilization Project”
FAA Team Meeting – July 2002
CDR G. K. Weeks Jr., U. S. Coast Guard, Commanding Officer
USCG Loran Support Unit
North American Loran-C System
TTX (11 US)
SSX (13 US)
NSX (1 Pending)
LSU (SSX, TTX, NSX)
Control Site (2 US)
PCMS Site (24 US)
Transmitting Sites
Completed- Cesium Installs (24 US, 2 Canadian)- TTM Installs (Master Stations)- ABS Installed (29 station, 24 US online)
Loran Station Timing and Control Equip.
LORSTA Equipment….LORSTA Equipment….Timing and Frequency Equip:Timing and Frequency Equip:
First Article Testing Ongoing
at LSU
First Production Units Oct 2002
First Install, George, WA
Nov 2002
Loran Station Operations Room UPS
OPS Room UPS:OPS Room UPS:
All SSX Installs completed. LorSta George completed. Installation at rest of the TTX sites will start after X.25 to Frame Relay transition is completed (Spring 03).
Loran Station Transmitter UPS
Transmitter UPS:Transmitter UPS:
LSU Baseline completed
Jupiter Inlet, partially completed,
transformer install pending
Malone and Raymondville completed.
George completed
Grangeville, 23 Aug 02
Carolina Beach, 20 Sep 02
Loran Station Transmitter (circa 2003-2004)
Replacement Transmitters
New SSX Transmitter:New SSX Transmitter:
Factory Acceptance testing at
Megapulse 12 Aug 2002
LSU install Sep 2002
George install to be completed
Thanksgiving, 2002
Kodiak back on the schedule for
Summer 2003.
Loran SSX Switch Gear
New SSX Switchgear:New SSX Switchgear:
Installed at LSU and
LorSta Grangeville
Lorsta Jupiter and Carolina
Beach scheduled for Sep 2002
Loran Station Remote Automated Integrated Loran (RAIL)
RAIL:RAIL:
5 LorSta’s participating in Limited
Installation testing.
O’Scope Cards contract awarded
Deliveries started arriving
Routers finally onboard LSU
Final Form Rail in FAT
Network Transition X.25 to Frame Relay
LORSTA Equipment….LORSTA Equipment….Routers:Routers:
Sprint terminating X.25 services
by Jun 2003 (Dec 2002…)
MCI Worldcom selected to
provide Frame Relay for Loran
Installations at the two control
sites (NAVCEN & NAVCEN Det)
and the 24 US PCMS sites slated
to begin August 2002.
Loran Station Casualty Control Receiver
LORSTA Equipment….LORSTA Equipment….Casualty Control Receiver:Casualty Control Receiver:
Locus LRS IIID
Installed at 5 stations
George, Seneca, Jupiter, Carolina
Beach and Grangeville
Resolving Master station auto-naming
problem found at Seneca
Remaining receivers to be installed
with final form RAIL installations
Loran Towers
LORSTA TowersLORSTA Towers
Tower Study Completed
Critical: Port Clarence (1350’)
PP estimates earliest possible
move to Nome as 2004-2005
Monitor Sites (PCMS/SAM)
Completed- 29 PCMS Sites (24 US, 5 Canadian) Locus LRS-IIID All-in-View Receivers
“Status of the Loran Recapitilization Project”
Points of Contact:
CDR G. K. Weeks Jr., USCG Loran Support Unit, [email protected]
Mike Campbell, USCG Loran Support Unit, [email protected]
LCDR J. Boyer, USCG Loran Support Unit, [email protected]
Loran Station HP-5071A Oscillators
LORSTA Equipment….LORSTA Equipment….Cesium Clocks:Cesium Clocks:
Installed at all US & 2
Canadian stations
Primary Chain Monitor Set (circa 2000)
PCMS EquipmentPCMS Equipment
29 Locations (24 U.S. & 5 Canadian)
Installed and operational.