Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors status Finances Schedule and Milestones
29

Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

Jan 15, 2016

Download

Documents

Edith King
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

Status and ScheduleM. Della NegraUS CMS Collaboration Meeting Florida State University, 11 May 2002Civil Engineering and MagnetUpdates on sub-detectors statusFinancesSchedule and Milestones

Page 2: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 2

UXCExperimental Cavern UXC55

More than 50% complete

UXC55 ready July 04

Page 3: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 3

USC

Service Cavern USC55

More than 50% complete

USC55 ready March 04

Page 4: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 4

Swiveling PlatformSwiveling Platform (Korea)Assembly finished at Pt. 5

Page 5: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 5

Swiveling test in 2002

A counterweight will be installed to simulate the equivalent weight and momentum due to the cantilevered 250 t of the Cold Mass

Page 6: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 6

Status of ConductorCMS Conductor Production Status

April 18th, 2002

0

5

10

15

20

25

SC strands Cable High PurityAluminium

Insert AAReinforcement

Conductor Coil modules

Balance

Coil module +2

Coil module +1

Coil module 0

Coil module -1

Coil module -2

Prototype coil

CMS-22

CMS-21

CMS-20

CMS-19

CMS-18

CMS-17

CMS-16

CMS-15

CMS-14

CMS-13

CMS-12

CMS-11

CMS-10

CMS-9

CMS-8

CMS-7

CMS-6

CMS-5

CMS-4

CMS-3

CMS-1

CMS-2 Proto.Outokumpu Brugg KWSumitomo

Nexans Cortaillod Alusuisse

Techmeta Ansaldo

Production status September 30th 2001Each length is 2650m long

Page 7: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 7

Winding Prototype

Full diameter 6m1/4 length ~0.6m

4 layers winding using spare length of 2.65km – progressing well

Page 8: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 8

CB-2 mandrel ready

Coil is made of 5 submodules

CB-2, CB-1, CB0, CB+1, CB+2

Mandrel for CB-2 is finished

~6 months late – problem with supply of special elements in high strength alloy for mandrels, plates and flanges.

CB-2 completed end 02

CB+2 completed end 03

Page 9: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 9

Compressors for Cryogenics at point 5

Page 10: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 10

Tracker Outer Barrel Module

with ST sensors

• 50% of Si Strip Tracker budget committed• Si modules from the Milestone 200 produced in different production centers• Start of Si module production shifted from June 2002 to Nov. 2002 due to hybrid optimization (safer design and cost).

Hybrid

APV

Page 11: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 11

First 4 received, flex cable First 4 received, flex cable ok !!!ok !!!

20 + 20 ordered, delivery ½ 20 + 20 ordered, delivery ½ MayMay

All mechanical test up to All mechanical test up to now are oknow are ok

Specifications ready by Specifications ready by 25/525/5

Going to tender asapGoing to tender asap

Production Hybrids

Page 12: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 12

Outer barrel rod fully equipped for system test

First small sub-system (outer barrel ‘rod’) equipped with modules

Page 13: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 13

Beam Pipe EDR and Pixel installation

EDR went well and pixel EDR went well and pixel installation was proven to be installation was proven to be compatible with our compatible with our expectations.expectations.

Page 14: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 14

Crystals and Photodetectors

All 138 ovens at BTCP modified to grow large boules Offers in hand for endcap xtals

Expected rate of 5000 APDs/month reached. 25k out of 130k APDs delivered

APDs

VPTs

First 500 production VPTs delivered

Page 15: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 15

ECAL: Mechanics

Module assembly

Endcap ‘Supercrystal’

Assembly of modules for first supermodule (SM1) started in CERN and Rome.

EE EDR mid-2002

Page 16: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 16

Supermodule Assembly

Assemble a few ‘bare’ SMs in 2002

Page 17: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 17

ECAL Electronics

CMS and LHCC Reviews in 2001 revealed major cost overruns in electronicsLast RRB: Double speed of optical links – half cost of links – BUT insufficientAction - Mar 02: Alter electronics architecture to contain costs – generate L1 trigger primitive (25 xtals) on-detector rather than off-detector – reduce links and off detector electronics by factor ~ 10. FPPA: Final submission May02Electronics team reorganised, synergy between ECAL, Tracker & Preshower electronics

91000 Data and Control Links800 Off-detector Trig/DAQ Boards

12000 Data and Control Links120 Off-detector Trig/DAQ Boards

TDR TP

Page 18: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 18

ECAL Planning

Goal: Apr 07 - ECAL complete and commissionedAdvance the detailed test (also system test) of 1st SM to mid-2003 (final analog electronics + emulated FPGA digital part)EB electronics mounted in 2004/2005 – calibrate at least 9 SMs in 2004EE and SE mounted in 2005/2006, calibrate 1 Dee in 2006

Electronics Schedule

Page 19: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 19

Evolution of CMS Data Acquisition

New modular design of Event Builder - Break into a number of functionally identical, parallel, smaller DAQ systems

A 64x64 system is feasible today

Submit DAQ TDR end-02

Page 20: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 20

High Level Trigger

Lvl-1 trigger in construction phase nowHLT running in processor farm – immense amount of data generated – exercising remote sites

Detailed analysis leads to < 400> ms/event (on a “PIII @ 700 MHz box”)Maximum flexibility: full event data available; using offline software (very important to understand HLT performance)

In terms of “2007” CPU units, this is 3*1.5 years away.CPU needs should be within reach

A 50kHz system at startup will need ~ 2500 CPU’s

N(CPU) = (0.4 sec x 50000 sec-1)/(2*2*2)= 20000/8 = 2500

At (staged) startup: 50kHz @ Lvl-1 and 80Hz to storageDiscovery physics “safe”. SM physics: ~ resource-driven

High luminosity: in DAQ TDR at end-2002

CPU time/evt L1-rate Moore’s law

Page 21: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 21

Construction: Commitment Profile

By end of 2002 ~70% of the available funds will have been committed.62.7 MCHF of additional funds need to be committed soon in order to have a complete initial low luminosity detector in 2007.

Apr 02 RRB

Page 22: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 22

~20 MCHF Staging/Savings ?

After RRB13 the Director of Research requested CMS to prepare plans for the case where 20 MCHF of the shortfall is not covered (with respect to the RRB13 shortfall of 67.9 MCHF) BUT with the hope of getting it later.

Staging/Saving already applied for 1st Physics Run ~5 MCHFHCAL: Reduce no. of longitudinal samplings 2.0 MCHF ME1/1a: Reduce no. of electronics channels 1.5 MCHFME4/1: re-stage electronics 1.5 MCHF

Additional Staging Considered for 1st Physics Run ~8.5 MCHF TRIDAS: Start with 50% of DAQ Capacity 8.0 MCHF Infrastructure: SCX Cooling and Ventilation Plant 0.5 MCHF

Additional Saving Under Technical Evaluation ~5 MCHFLV Supplies: Use 400Hz, 400V system 5.0 MCHF

Decision in June 2002.

TOTAL Staging/Savings ~ 18.5 MCHF

Page 23: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 23

Additional Collaborators

Serbia Corner Pieces Magnet approved in Mar CMS Week 400 kCHF protocol agreement

Milan, INFN ECAL approved in Mar CMS Week Naples, INFN RPCs approved in Mar CMS Week

Brazil YE4+ farm YE4 funded (500 kCHF), application in 2002

Ireland ECAL electr.?, farm Visited CERN 18-19 FebExpect application in mid-02

Mexico Silicon Tracker Expect application soonNZ farm+Pixels Applic. received, Pres. in June

Visit at CERN S. Thompson Thailand ME electronics boards in progressUS-NP (HI) TriDAS, farm Successful workshop in MIT 8.02

Proposal submitted to DoE March 15

0.9 MCHF already in Financial Plan.

Page 24: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 24

High Luminosity Upgrades

10. Items (upgrades) for high luminosity ~ 19 MCHF

10.1 ME4/2 mechanics and electronics 9.210.2 ME4/1 electronics 1.510.3 ME4/1 assembly in PNPI 0.510.4 Restore ME1/1a electronics 1.510.5 Neutron Shielding (extra) 1.010.6 3rd Forward Pixel Layer ~2.510.7 5th endcap RPC layer ~2.0 10.8 Extra Installation Costs ~1.0

The decision to build many of these items will only be taken after inspection of the first physics data. This upgrade cost comes on top of the 62.7 MCHF shortfall. A plan for the funding of the upgrade will have to be worked out in due time. Basic ingredients are new collaborators or upgrade plans by funding agencies willing to upgrade items in which they have been working on.

Page 25: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 25

April RRB (RRB14) Outcome

M&O MoU accepted, proceed with signatures

M&O cat A 2002 Budget accepted (1 MCHF with sharing according to nb of PhDs). No request for in kind contributions in 2002.

M&O Cat B: Must work out a way to share costs (by Oct RRB)

C&I costs accepted (positive report by scrutiny group). C&I profile peaks in 2003. Cash flow? 50% of C&I is manpower.

CMS Financial Plan well received. Expect ~ 54 MCHF additional funds for a shortfall of 62.7 MCHF.

Next step - Reach an agreement with Agencies by end June 02 on likely availability of funds (firm, less firm promisies), amounts and time profiles. Then prepare Financial Plan for Oct RRB (also discuss during LHCC CMS CR in Oct02)

Page 26: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 26

Expectations for additional funding at RRB14

Austria 600. 600. Belgium 870. 300.

Brazil 500. 500. Bulgaria 106.

CERN 13500. 13500. China 700. 700.Croatia 49. 49.

Cyprus 106.

Estonia 16. Finland 870. 870. France CEA 1000. 660.

France IN2P3 4000. 2000. Germany 2703. 2703. Greece 880.

Hungary 58.

India 774. 300. Iran 500. 500.Italy 12900. 12900 req.

Korea 458. Pakistan 428. Poland 528. Portugal 352. 352. RDMS 2250. 2250.

Serbia 400. 400. Spain 1350. 1350. Switzerland Taipei 410. Turkey 58. UK 1530. 1530. USA 15000. 12800.

TOTAL 62896. 54264.

Guideline Expect Guideline Expect

Page 27: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 27

V33 Draft Schedule: Extended Surface Phase

Objectives:

channel test of HV/LV

burn-in of electronics

flushing gas

readout test of 10% of subdet(MB,ME, RB etc)

vertical slice testswith test-beam DAQ & prototype final DAQ

Additional costs part of C & I

Page 28: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 28

v33 Draft Schedule

A new planning v33 is in preparation for the next LHCC comprehensive review.Objective: Complete CMS (except pixels and ME4) for 1 April 2007

• UX and US area ready (+12 months shift, now firm date) Jul 04.

• Install floor plates and shielding in UX area Nov 04- Apr 05

• Magnet test on surface (+9 months shift) Jan 05- Apr 05

• Start lowering CMS May 05

• ECAL Barrel (EB) ready for installation (+ 4 months) Jul 05

• Start EB installation + cabling (3 months float) Nov 05

•Tracker ready for installation Oct 05

• Start Tracker installation + cabling (3 months float) Feb 06

• EE+ (ECAL endcap positive z-side) calibration in SPS beam Apr 06- Sep 06

• Start EE+ installation Nov 06

• Start EE- installation Jan 07

• CMS closed ready Apr 07

Page 29: Status and Schedule M. Della Negra US CMS Collaboration Meeting Florida State University, 11 May 2002 Civil Engineering and Magnet Updates on sub-detectors.

M. Della Negra/CMS Status/USCMS-11 May2002 29

Conclusion

Magnet: Yoke finished. Conductor and winding well advanced. 1st coil delivered end 02 with 6 months delay. Not critical: HCAL, Endcap Muons : construction on schedule and well advanced.

Problems are being encountered but are also being overcome.

To watchProduction rate of DTs and RPCs – need to watch production rateStart of mass assembly of Si modules (Q4 2002)ECAL: Redesign of electronics chain. Very tight schedule.

Draft v33 CMS ScheduleMagnet test on surface Jan 05- Apr 05. Start lowering detector in May 05.CMS closed ready for 1’st beam 1st April 07.

CMS construction is proceeding at speed. A low luminosity detector can be ready for physics in 2007.

The low luminosity detector is the complete CMS detector, except the 4th forward muon station (ME4) and the 3rd forward pixel layer.