Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core contents begins to crush immediately (~200 tons)
8

Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core.

Dec 17, 2015

Download

Documents

Mervyn Ferguson
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core.

Start condition: support removed for all columns on one floor (97th floor)Collapse between 97-98th floorUpper part = 13 floors + roof and antennaCore contents begins to crush immediately (~200 tons)

Page 2: Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core.

Collision phase 1: outer floor truss matrix impacts and begins to crush office contents (~250 tons)

Page 3: Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core.

Floor slab (4.35”height

Floor truss matrix (height = 29 in; width 60 ft; depth 206 ft)

Office contents (height approx. 4 ft; width 60 ft; depth 206 ft; long span mass ~90 tons)

Open (height = 5’9”)

Portion of cross section outside of the core

Page 4: Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core.

Collision phase 2: core floor horizontal members impact and begin to crush core office contents (~50 tons)

Page 5: Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core.

Collision phase 3: outer floor truss matrix impacts upper-most floor of lower partFloor truss connections are designed for gravity loads not resistance to upward impacts.Upper floor truss connections are broken and floor truss matrix is dissociated from structure. (This is corroborated by NIST’s observations that truss seats on upper floors were bent upward and had bolt tear out.)Concrete floor of the lower-most floor of the upper part probably fractures due to strains with no support.Lowest upper-part floor trusses probably collapse to some extentTop-most lower-part floor remains mostly intact

Page 6: Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core.

Collsion phase 4: core horizontal members impact upper-most floor of lower partCore horizontal members are most likely bolted and welded with no bias toward upward or downward forcesAn even number of upper and lower horizontal members fractureEqual amount of floor fracture for upper and lower floors within coreHorizontal member fractures probably lead to some bending of core columns

Page 7: Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core.

Collision phase 5: first possibility of end to end impact of columnsEnd to end impact in occurs in a low percentage of cases due to tilting of the upper part and bending of columns during phase 4Predominately floor punch through

Page 8: Start condition: support removed for all columns on one floor (97th floor) Collapse between 97-98th floor Upper part = 13 floors + roof and antenna Core.

Potential conclusions

• Floor dissociation, core horizontal member fracture, and column-floor punch through lead to a high level of concrete comminution

• Inelastic collision energy considerations– Energy for fracturing at least an entire floor of horizontal

members needs to be accounted for– Strain energy for truss seats and trusses needs to be accounted

for– Strain energy for concrete needs to be accounted for– Strain energy for crushing >500 tons of building contents

• Basic mass on spring concept probably still valid except there are two springs and there is time for rebound before the next collision