» c: c.c c: tJ) r+ I\.) (J1 '-- I\.) o o <.0 11 1J I
»
c:
c.c
c:
tJ)
r+
I\.)
(J
1
'- I\
.)
o o <.0
11
1J
I
Agenda • Introduction
• Purpose
• EPU Overview and Schedule
• EPU Parameters
• Unique Features
• Plant Modifications
• Proposed Technical Specification Changes
• RS-OO1 Matrix Review
• Closing Discussion
2 I=PL
Introduction • St. Lucie Team Attendees
- Liz Abbott (FPL) - Licensing Director, Power Uprates
- Jack Hoffman (FPL) - Licensing Manager, S1. Lucie EPU
- Eric Katzman (FPL) - Licensing Manager, S1. Lucie Plant
- Jay Kabadi (FPL) - Manager, S1. Lucie Fuels
- Chris Wasik (FPL) - Licensing Supervisor, S1. Lucie EPU
- Jeff Brown (FPL) - I&C Supervisor, S1. Lucie EPU
- Steve Cornell (FPL) - Mechanical Supervisor, S1. Lucie EPU
- Dave Brown (FPL) - Operations Supervisor, S1. Lucie EPU
- Ken Garner (Westinghouse) - EPU Project Manager
- Dale Graves (Shaw) - EPU Project Manager
r=PL 3
Purpose
• Provide Staff with a comprehensive overview of the proposed St. Lucie Unit 1 Extended Power Uprate
• Identify any FPL actions to strengthen overall LAR submittal
• Encourage active dialog between FPL and Staff to gain most benefit from the meeting
• Agree on communication plan going forward
F=PL
Uprate Team Experience • Extended Power Uprate Team
- Dedicated engineering team on-site • Senior, experienced S1. Lucie design engineers in key
positions • Direct interface with site and fleet engineers for
technical and licensing evaluations - Home office support with extensive nuclear experience
• Specific experience with Uprate LARs • Uprate implementation experience • Active participant in the development of NEI uprate
guidance
• Experienced Shaw and Westinghouse Teams - Have implemented over 40 successful uprates - Members with specific involvement with several up
I=PL. 5
LAR Process
• Benchmarking against other successful uprate LARs (specifically Ginna, Comanche Peak and Millstone)
• Review and incorporation of previous RAts, SEs and industry DE
• Integrated LAR review by senior team including independent industry experts
6 I=PL
UDrate Team - Key Players • Westinghouse
- NSSS system & component analyses
• Areva - Fuel design and safety analyses - NSSS component analyses (reactor head and pressurizer)
• Shaw - Balance of Plant (BOP) analyses
• B&W Canada - Replacement steam generator analyses
• NAI - Dose analysis
• Siemens - Turbine generator evaluations
7 I=PL
EPU Schedule
• LAR Submittal - November 2009 • NRC approval of LAR - January 2011 • Modifications
- Spring 201 0 • Limited scope - performed under 10 CFR
50.59
• NRC approval not required • No changes in plant operating conditions
- Fall 2011, EPU implementation
8 F=PL.
St. Lucie EPU Specifics • Second uprate for St. Lucie
- 5.5% stretch power uprate implemented in November 1981
• Core thermal power increase from 2700 MWt to 3020 MWt - 10% EPU (2700 MWt to 2970 MWt) - 1.70/0 MUR (2970 MWt to 3020 MWt)
• Safety analysis values - 3030 MWt (0.30/0 measurement uncertainty) - 3050 MWt total NSSS power (includes 20 MWt for
Rep heat)
9 I=PL
Uprate Paramerers
Parameter I
Value II
Comments I
Thermal Design Flow (Total, gpm)
375,000
551
°to 10°A> (Avg)
Current value is 365,000 gpm. Minimum measured flow is 390,000 gpm (includes flow measurement uncertainty of 15,000 gpm)
Current value is 549°F
Tube plugging asymmetry of ± 20/0 between the two steam generators
Best estimate predictions for HP turbine design
Based on initial startup testing and EPU RSG analysis
RCS Tcold (OF)
SG Tube Plugging (%)
SG Pressure (psia) (at Outlet Nozzle)
856
0.1 0/0Steam Generator Moisture Carryover, (0A»
10 I=PL
Uprate Parameters
• Four parameter cases developed to establish design parameters
- Case 1: T cold =535°F at 00/0 SGTP
- Case 2: Tcold =535°F at 100/0 SGTP
- Case 3: Tcold =551°F at 0% SGTP
- Case 4: T cold =551°F at 100/0 SGTP
11 I=PL
prate Parameters I
Thermal Design Parameters NSSS Power (% current)
MWt
106 Btu/hr Reactor Power MWt
106 Btu/hr Thermal Design Flow, loop gpm
Reactor 106 1b/hr I R~actor Coolant Pressure'l pSla Core Bypass, 0/0 I Reactor Coolant Temperature, of
Core Outlet Vessel Outlet Core Average Vessel Average Vessel/Core Inlet Steam Generator Outlet
NSSS PCWG Parameters for PSL1 EPU
I I
Current (8) I
100
--
2700
9,215
185,000
139.3 I
2250 I
EPU
Case 1 I Case 2 I Case 3 I Case 4
112
3050(5)
10,407
3030(4)
10,339
112
3050(5)
10,407
3030(4)
10,339
112
3050(5)
10,407
3030(4)
10,339
112
3050(5)
10,407
3030(4)
10,339
187 500(2), 187,500(2) 187 500(2), I 187 500(2),
143.8
2250
3.7 4.2(9)I
- 593.3 594 591
565.2-571.3 563
535548.5
548.5 534.6
I 143.8 I
I 2250 I
I 4.2(9) I
593.3 591 565.2 563 535
534.6 I
140.8 I
2250 I
4.2(9) I
608.2 606 580.8 578.5 551
550.6 I
140.8
2250
4.2(9)
608.2 606 580.8 578.5 551
550.6
12 FPL.
Uprate Parameters NSSS PCWG Parameters for PSL1 EPU
EPU
Thermal Design Parameters Case4Case 2 Case 3 Case 1 Current (8)
NSSS Power (% current) 112
MWt
112 112 112100
3050(5)
106 Btu/hr
3050(5) 3050(5)3050(5)-10,407 10,407
Steam Generator Steam Outlet
10,407 10,407-
530.6(6) 527.7529.1 513.9 510.9Temperature, of Steam Outlet 890(1,6) 868(1)770(1) 750(1)878Pressure, psia
Steam Outlet Flow, 106 11.8 12.84/13.42(6) 12.83/13.4012.78/13.36 12.78/13.35
Ib/hr total Feed Temperature, of
409.0/441.0432.4 409.0/441.0 409.0/441.0 409.0/441.0
Steam Outlet Moisture, 0.1 0.10.1 0.1 .0.1
0/0 max. Design Fouling Factor, hr. sq. ft. of/Btu 0.00005 0.000050.00005 0.00005 0.00005
Tube Plugging Level 10(7)10(7)0 0 0(%)
Notes: 1) 13 psi steam generator internal pressure drop incorporated. 2) Thermal design flow of 187,500 gpmlhot leg (each steam generator contains one hot leg and two cold legs). 3) Minimum measured flow based on a 15,000 gpm flow measurement uncertainty, 4) Upper limit on core thermal power. 5) Rep net heat input of 20 MWt included in NSSS power. 6) If a high steam pressure is more limiting for analysis purposes, a greater steam pressure of 908 psia, steam temperature of 533.1°F, and
steam flow of 13.43 x 106 Ib/hr should be assumed. This is to envelop the possibility that the plant could operate with better than expected steam generator performance.
7) SGTP of up to 10% average tube plugging with a maximum asymmetry of +1- 2% of the actual average value between steam generators
and a maximum peak tube plugging level of up to 12%. ""i,,:t!;!iiiiii;;i iii!; ;Illiii¥ii!li!ii!:i!lili~8) Current parameters obtained from Tables 4.4-1, 4.4·2, 4.4-3, 4.4-4, 5.1-1 and 5.3-1 of the UFSAR. 9) EPU analysis conservatively increased bypass assumption to 4.2%.
13 F=PL.
EPU Unique Features
• Packaging theMUR with the EPU submittal - Separate section to address MUR specifics
• Requires a Technical Specification Bases change for St. Lucie Unit 2 - Unit 2 Condensate Storage Tank (CST) TS Bases
include a water requirement for Unit 1
- CST volume affected by EPU
- Marked-up Unit 2 TS Bases page will be included in LAR
• No linked submittals
14 . F=PL
'PU Margin Improvements • Considered analytical and operating margin improvements
during EPU scoping phase
• Utilized insights from the plant margin management program
• Analytical margin improvement examples: - 480V Electrical Bus Voltage Margin Improvement
- Increased RCS flow
- Reduced Linear Heat Rate limit from 15.0 to 14.7 kW/ft
- Reduced Total Integrated Peaking Factor from 1.70 to 1.65
• Operating margin improvement examples: - Turbine cooling water HX replacement
- Steam bypass control system capacity increase
- Continuous containment purge system upgrade
15 FPL
Application of 10CFR50.59
• 10 CFR 50.59 will be applied to determine when prior NRC review is required
• Preliminary review indicates implementation of plant modifications will not require prior NRC
•review
• NRC review required for use of: - Leading Edge Flow Meter (LEFM) installation
- Continuous containment purge system modification
- Safety Injection Tank (SIT) design pressure increase
16 F=PL
Plant Modifications
• Fuel - EPU will transition to the Areva Advanced CE14 HIP
(High Thermal Performance) fuel design
- Differences with current design include: • M5™ fuel rod cladding and end caps
• Increase in initial helium backfill pressure
• MONOBLOC guide tubes
- M5™ exemption to be included in LAR
I=PL
Plant Modifications
• NSSS - Hot Leg Injection Flow Increase
- Continuous Containment Purge System Modification
- Increase Safety Injection Tank Design Pressure
- Setpoints and Scaling
• No RPS or ESFAS setpoint changes
18 I=PL
Plant Modifications
• Balance of Plant - Leading Edge Flow Meter - Measurement Uncertainty
Recapture
- Main Feedwater Pump Replacement
- Steam Generator Flow Control Valve Replacement
- High Pressure Feedwater Heater No.5 Replacement
- Heater Drain Pump Rotating Element Replacement
- Heater Drain Valve Replacements
- Moisture Separator Reheater Replacement
19 I=PL
Plant Modifications
• Balance of Plant - Condenser Upgrades
- Main Steam Isolation Valve Actuator Upgrade
- Steam Bypass Control System Capacity Increase
- Turbine Cooling Water Heat Exchanger Replacement
- Iso-phase Bus Duct Cooling Upgrade
- Main Transformer Cooler Upgrade (1A & 1B)
- 480V Electrical Bus Voltage Margin Improvement
- Setpoints and Scaling
F=PL
Plant Modifications • Turbine Generator
- High Pressure Turbine Steam Path Upgrade
- Low Pressure Turbine Steam Path Upgrade
- DEH Computer Replacement
- Main Generator Upgrade
- Generator Hydrogen Seal Oil Pressure Increase
- Main Generator Hydrogen Cooler Replacement
- Exciter Cooler Replacement
21 I=PL
Plant Modifications
• Switchyard - Replace switchyard disconnect switches
- Replace Midway Substation disconnect switches
- Install spacers between existing Midway conductors
22 I=PL
Proposed Tech Spec Changes
• Section 1.0 Definitions - Delete definition of "E Average Disintegration Energy"
- Add definition for "Dose Equivalent Xe-133"
- Revise definition for RTP from 2700 to 3020 MWt
• Section 2.0 Safety Limits - Figure 2.1-1 Rx Core Thermal Margin Safety Limit
Four RCPs Operating • Increase Vessel Flow from 365,000 to 375,000 gpm
23 F=PL
Proposed Tech Spec Changes
• Section 3/4.1 Reactivity Control Systems - 3.1.1.1 & 3.1.1.2 Shutdown Margin - Change boron
concentration from > 1720 to > 1900 ppm
- 3.1.2.2 - Revise boron injection flowpaths to credit RWT only in Mode 3 < 1750 psi and Mode 4
- 3.1.2.7 & 3.1.2.8 Borated Water Sources - Change boron concentration from;::: 1720 to ~ 1900 ppm
- Revise Figure 3.1-1 Min BAMT Volume vs. Stored BAMT Concentration
24 I=PL
Proposed Tech Spec Changes • Section 3/4.2 Power Distribution Limits
- 3.2.5 DNB Parameters - Change Table 3.2-1 DNB Margin Limits (TSTF-487)
• For Cold Leg Temperature, Pressurizer Pressure and Reactor Coolant Flow Rate, delete numerical limits and reference COLR for values
• Revise Reactor Coolant Flow Rate minimum value and also reference COLR
25 F=PL
Proposed Tech Spec Changes • Section 3/4.4 Reactor Coolant System
- 3.4.8 Specific Activity - Replace 1DOlE limit with Dose Equivalent Xe-133 limit (TSTF-490)
- 3.4.9 Pressure Temperature Limits - Update P-T Limit Curves for extended period of operation
- 3.4.13 Power Operated Relief Valves - Increase LTOP enable temperature for heatup
26 I=PL
Proposed Tech Spec Changes
• Section 3/4.5 Emergency Core Cooling Systems - 3.5.1 Safety Injection Tanks
• Change boron concentration from > 1720 to > 1900 ppm
• Change nitrogen cover gas pressure range to from 200 - 250 psig to 230 - 280 psig
- 3.5.2 ECCS Subsystems - Add new LCO for One OPERABLE Charging Pump per ECCS subsystem
- 3.5.4 Refueling Water Tank - Change boron concentration from ~ 1720 to > 1900 ppm
27 I=PL
Proposed Tech Spec Changes
• Section 3/4.6 Containment Systems - 3.6.1.4 Internal Pressure - Change max pressure from
2.4 psig to 0.5 psig
- 3.6.1.7 Containment Purge System - add new specification similar to Unit 2 to allow for containment purge at power
28 I=PL
Proposed Tech Spec Changes
• Section 3/4.7 Plant Systems - 3.7.1.3 Condensate Storage Tank - Change CST
Minimum Volume from 116,000 to 153,400 gallons • Current value does not include unusable volume or
uncertainties
• EPU value does include unusable volume and uncertainties
- Table 4.7-1, Steam Line Safety Valves - Increase Positive As-Found Tolerance from +1 % to +3%
29 I=PL
Proposed Tech Spec Changes
• Section 3/4.8 Electrical Power Systems - 3.8.1.1 A. C. Sources - Change EDG frequency criteria
from ± 20/0 to + 1%
• Section 3/4.9 Refueling Operations - 3.9.1 Boron Concentration - Change boron
concentration from > 1720 to > 1900 ppm - 3.9.11 Spent Fuel Storage Pool - Change boron
concentration from > 1720 to > 1900 ppm
30 I=PL
Proposed Tech Spec Changes • Section 3/4.1 0 Special Test Exceptions
- 3.1 0.1 Shutdown Margin - Change boron concentration from > 1720 to > 1900 ppm
• Section 3/4.11 Radioactive Effluents - 3.11.2.6 Gas Storage Tanks
• Change 100/E to DOSE EQUIVALENT XE-133 • Reduce noble gas curie limit
31 I=PL
Proposed Tech Spec Changes • Section 5.0 Design Features
- 5.3.1 Fuel Assemblies - revise paragraph to include M5 cladding material
- 5.6.1 Fuel Storage - Criticality
• 5.6.1.c.1 - Change fuel enrichment from 4.5 to 4.6 weight percent
• 5.6.1.d - Change fuel enrichment from 4.5 weight percent to 4.6 weight percent maximum initial planar average U-235
- Add fuel storage configurations for EPU fuel
I=PL
Prop ed Tech Spec Changes
• Section 6.0 Administrative Controls - 6.8.4.h Containment Leakage Rate Testing Program
increase Pa consistent with EPU containment analysis
- 6.9.11 Core Operating Limits Report (COLR) - update references specific to EPU
Other Changes • COLR changes
- Reduced Linear Heat Rate (LHR) limit from 15.0 to 14.7 kW/ft - Revised Axial Shape Index (ASI) limits for LHR - Reduced Total Integrated Peaking Factor (FrT) from 1.70 to 1.65 - Increased refueling boron concentration from
>1720 to >1900 ppm - Relocate limits of DNB parameters to COLR - Revise List of Approved Methodologies
• MUR/LEFM - Add the actions to be taken when the LEFM is degraded or out
of-service to the Licensee-Controlled Technical Specification Requirements of UFSAR Section 13.8
34 I=PL
Conformance with RS-001 • Application will follow RS-001 template
• St. Lucie Unit 1 not licensed to the Standard Review Plan - Licensed prior to the GOes and the SRP
- Designed/constructed based on proposed GOCs published in 1967
- CP issued in 1970; GDCs issued in 1971
- AEC concluded plant meets the intent of the GOCs
F=PL
RS-001 Matrix 1 Materials and Chemical Engineering
• RV Material Surveillance Program - Analysis performed to address EPU fluences - no changes
• P-T Limits & Upper-Shelf Energy - Limits revised to address EPU fluences, increasing EFPY for extended
period of operation
• Pressurized Thermal Shock - Analysis performed to address EPU fluences - criteria met
• Reactor Internal & Core Support Materials - Evaluation performed to address the impact of EPU conditions on aging
effects - no modifications required
• RCPS Materials - Assessment performed to address EPU temperature increases - no
impact
• Leak-Before-Break - Current analysis acceptable for EPU conditions
.... e'1f?'f;';11;ll;i,'ilw;!'i;i!IIIDII~t;~lillliil!il;'1".,i·.·i.·.·.',·,!ll,
36 FPL
37
atrix 1RS-001 Materials and Chemical Engineering
• Protective Coating Systems (Paints) - Evaluation performed to address EPU conditions - no changes
• Flow-Accelerated Corrosion - Program updated to address changes in flow, pressure,
temperature and steam quality
• SG Tube Inservice Inspection - Evaluation performed to addressEPU conditions - no changes
• SG Slowdown System - Evaluation performed to address EPU conditions - no changes
• Chemical & Volume Control System - Evaluation performed to address EPU conditions
• Modified BAM Tank requirements
I=PL
RS-001 Matrix 2 Mechanical and Civil Engineering
• Pipe Rupture Locations & Associated Dynamic Effects - Evaluation performed to address EPU conditions - no changes
• Pressure-Retaining Components & Supports - NSSS Components
• Evaluations performed to address EPU conditions • Includes piping, supports, reactor vessel, CRDMs, reactor coolant
pumps, steam generators and pressurizer • No changes
- BOP Components • Evaluations performed to address EPU conditions • Several BOP component replacements required • Piping acceptable, some support modifications
38 I=PL
RS-001 Matrix 2 Mechanical and Civil Engineering
• RPV Internals & Core Supports - Evaluation performed to address EPU conditions - no
modifications required
• Safety-Related Valves & Pumps - Evaluations performed to address EPU conditions - no
modifications required
• Seismic & Dynamic Qualification - Evaluation performed to address EPU conditions - no
modifications required
• NSSS Design Transients - Evaluation performed to address EPU conditions - minor
changes to selected transients
39 I=PL
RS-OO Matrix 3 Electrical Engineering
• Environmental Qualification of Electrical Equipment - EO equipment evaluated for changes in normal and accident conditions - No equipment replacement required
• Offsite Power System - Grid stability has been evaluated at EPU conditions - Contingencies selected conform to SRP 8.2-111.1.f - Results indicate thermal, voltage and stability performance not degraded
by EPU
• AC Onsite Power System - Evaluation performed to address EPU conditions using ETAP model - Modifications being implemented to improve margin
• DC Onsite Power System - Evaluation performed to address EPU conditions - no modifications required
• Station Blackout - Evaluation performed to address EPU conditions
Increasing time for Alternative AC power from 25 min
40 I=PL.
RS-001 Matrix 4 Instrumentation and Controls
• RP, Safety Features Actuation, 8t Control Systems - Evaluations performed to address EPU conditions - No changes to RPS or ESFAS setpoints - Some control system changes required
• Plant Operability - Detailed transient modeling performed - Some control system changes required
• Pressurizer Component Sizing - Evaluation performed to address EPU conditions - no changes
required
I=PL
RS-001 Matrix 4 Instrumentation and Controls
• MUR/LEFM - Content and format of MUR LR section consistent with RIS
2002-03
- References/links to related EPU LR sections provided where appropriate
- MUR based on Cameron (Caldon) LEFM CheckPlus System and Cameron Topical Reports ER-80P and ER-157P
- Flow elements have been calibrated at Alden Labs using plant specific piping models
42 I=PL
5-001 atrix 5 Plant Systems
• Flood Protection - Evaluation performed to address EPU conditions
required no modifications
• Missile Protection (Internally Generated & Turbine Generator) - Evaluations performed to address EPU conditions - No changes to internal missiles - Updated turbine missile analysis to address EPU conditions and
modified HP and LP turbine steam paths
• Pipe Failures - Evaluation performed to address EPU conditions
modifications required no
43 I=PL
5-001 Matrix 5 Plant Systems
• Fire Protection - Evaluation performed to address EPU conditions - no modifications
required
• Pressurizer Relief Tank - Evaluation performed to address EPU conditions - no modifications
required
• Fission Product Control - Fission Product Control Systems & Structures
• Evaluation performed to address EPU conditions - no modifications required
- Main Condenser Evacuation System • Evaluation performed to address EPU conditions - no modifications
required
- Turbine Gland Sealing System • Evaluation performed for EPU conditions
44 I=PL
45
RS-001 Matrix 5 Plant Systems
• Component Cooling & Decay Heat Removal - Evaluations performed for increased EPU heat loads on the
following systems: • Spent Fuel Pool Cooling & Cleanup System
- Full core off-load and partial core off-load cases analyzed - Acceptance criteria met
• Station Service Water System (ICW) - No modifications required
• Reactor Auxiliary Cooling Water Systems (CCW) - No modifications required
• Ultimate Heat Sink - No modifications required
• Auxiliary Feedwater System - No modifications required
I=PL
RS-001 Matrix 5 Plant Systems
• Balance-af-Plant Systems - Evaluations performed and modifications required for the
following systems: . • Main Steam - MSIV actuator upgrade • Main Condenser - tube staking • Turbine Bypass - steam bypass capacity increase • Condensate & Feedwater
- LEFM installation - FW pump & HD pumps upgrades - High pressure FW heater - Valve upgrades (FW control and heater drain)
• Waste Management Systems - Evaluations performed to address EPU conditions for the
following systems - no modifications required: • Gaseous Waste Management System • Liquid Waste Management System • Solid Waste Management System
46 I=PL.
RS-001 Matrix 5 Plant Systems
• Additional Considerations - EDG Engine Fuel Oil Storage &Transfer System
• Evaluations performed to address EPU conditions - no modifications required
- Light Load Handling System (Related to Refueling) • Evaluations performed to address EPU conditions - no modifications
required
47 I=PL
RS-001 Matrix 6 Containment Review
• Primary Containment Functional Design - Containment response evaluated to address EPU conditions - Containment design pressure and temperature limits are met
• Subcompartment Analyses - Containment response evaluated to address EPU conditions - no
changes
• Mass & Energy Release - EPU releases calculated for LOCA and secondary system pipe
ruptures
• Combustible Gas Control in Containment - Evaluation performed to address EPU conditions - no
modifications required
I=PL
RS-001 Matrix 6 Containment Review
• Containment Heat Removal - Analyses performed to address EPU heat loads, no modifications
required
• Pressure Analysis for ECCS Performance - Minimum pressure analysis performed at EPU conditions and
10 CFR 50.46 acceptance criteria met
I=PL.
RS-001 Matrix 7 Habitability, Filtration and Ventilation
• Evaluations performed to address EPU conditions for the following systems - no modifications required: - Control Room Habitability System
- ESF Atmosphere Cleanup
- Spent Fuel Pool Area Ventilation System
- Auxiliary, Radwaste & Turbine Areas Ventilation Systems
• Containment Ventilation Systems - Modification to the continuous containment purge system to allow
for online containment purge
50 I=PL
RS-001 Matrix 8 Reactor Systems
• Fuel System Design - Areva Advanced CE14 HTP fuel design
- Fuel analyzed at EPU conditions and acceptance criteria met
• Nuclear Design· - Analyzed at EPU conditions and fuel design limits not exceeded
• Thermal & Hydraulic Design - Analyzed at EPU conditions and acceptance criteria met
I=PL
RS-001 Matrix 8 Reactor Systems
• Emergency Systems - Functional Design of CR Drive System
• Evaluation performed to address EPU conditions -no modifications required
- Overpressure Protection During Power Operation • Analyses performed to address EPU conditions - no modifications
required
- Overpressure Protection During Low Temperature Operation
• Evaluation performed to address EPU conditions • Modify LTOP enable temperature for heatup
- Residual Heat Removal System • Evaluation performed to address EPU conditions - no modifications
required
52 I=PL
RS-001 Matrix 8 Reactor Systems
• Non LOCA Analysis Codes - S-RELAP5 code utilized for transient analysis
- RODEX2 code utilized to model fuel rod
•
- XCOBRA-IIIC code used to calculate fuel assembly flow and enthalpy
All Codes approved for use on St. Lucie Unit 1
I=PL
RS-001 Matrix 8 Reactor Systems
• Non LOCA Analyses • All events analyzed/evaluated at EPU conditions and
specific acceptance criteria met - Increase in Heat Removal by the Secondary System
• Decrease FW Temp, Increase FW Flow, Increase Steam Flow, & Inadvertent Opening of SG Relief or Safety Valve
- Steam System Piping Failures Inside & Outside Containment - Decrease in Heat Removal by the Secondary System
• Loss of External Load
- Loss of AC Power to the Station Auxiliaries - Loss of Normal Feedwater Flow - Feedwater System Pipe Breaks - Loss of Forced Reactor Coolant Flow
FPL 54
RS-001 Matrix 8 Reactor Systems
• Non LOCA Analyses (continued) - RCP Rotor Seizure
- Uncontrolled CR Assembly Withdrawal from Subcritical or Low Power Startup Condition
- Uncontrolled CR Assembly Withdrawal at Power
- Control Rod Misoperation
- CVCS Malfunction
- Spectrum of Rod Ejection Accidents
- Inadvertent Opening of Pressurizer PRV
- SG Tube Rupture
- Anticipated Transients Without Scrams
55 I=PL
RS-001 Matrix 8 Reactor Systems
• Small Break Loss of Coolant Accident (LOCA) - Performed using Areva Appendix K model - Credited increased SIT pressure - All acceptance criteria met
• Large Break Loss of Coolant Accident (LOCA) - Performed using Areva realistic LBLOCA methodology - All acceptance criteria met
• Post-LOCA Long-term Cooling - Performed using Westinghouse post-LOCA LTC model - Consistent with methodology used for Waterford to address Staff
concerns - Minimum hot leg injection flow increased from 190 gpm to 250
gpm
56 I=PL
5-001 Matrix 8 Reactor Systems
• Fuel Storage - New Fuel Storage
• Analyzed at 4.6 weight percent enrichment {planar averagS?} • All acceptance criteria met
- Spent Fuel Storage • Analyzed at 4.6 weight percent enrichment {planar averagS?} • All acceptance criteria met
- Analyses available
• Additional Reactor Systems - Loss of Residual Heat Removal at Midloop
• Evaluated for higher EPU decay heat load • Developed new time to boil curves
- Natural Circulation Cooldown • Analyzed at EPU conditions • All acceptance criteria met
57 I=PL
RS-001 Matrix 9 Source Term and Radiological Consequences
• Source Terms for Radwaste Systems Analyses - Source term revised for EPU conditions
• Radiological Consequences Analyses Using Alternate Source Terms - AST previously approved for St. Lucie 1
- Events analyzed for EPU using same methodology
• Waste Gas Decay Tank Rupture - Analysis performed for EPU conditions
- Dose limits consistent with BTP 11-5
58 I=PL
RS-001 Matrix 10 Health Physics
• Occupational & Public Radiation Doses - Doses determined at EPU conditions
- Results acceptable, no modifications required
59 I=PL
RS-001 Matrix 11 Human Performance
• Programs, procedures, training and plant design features related to operator performance evaluated to address EPU conditions
• Evaluation responds to NRC questions regarding changes to: - Emergency & Abnormal Operating Procedures
- Operator Actions Sensitive to Power Uprate
- Control Room Controls, Displays and Alarms
- Safety Parameter Display System
- Operator Training Program and Simulator
60 r=PL
RS-001 Matrix 12 Power Ascension and Testing Plan
• Approach to EPU Power Level & Test Plan - Test plan includes:
• Augmented start-up testing from hot zero power to current 100% power level
• Incremental power ascension from current 1000/0 power level to EPU conditions
• Post modification testing • Additional testing (e.9., vibration monitoring)
- Compared EPU testing plan to original start-up testing Numerous transients evaluated using CENTS model Consistent with SRP 14.2.1, Generic Guidelines for EPU Testing Programs
61 I=PL
RS-001 Matrix 13 Risk Evaluation
• Risk Evaluation of EPU - PRA models updated for EPU conditions
- Additional hardware modifications and human actions being evaluated to reduce EPU effects
62 I=PL