Client: Project Name: Document No.: / Section: Design Data Page: 1 of Design by: Hemant Kale Checked by: Rev: Date: Date: Date: Design Criteria Inlet Parameters 1 Design Flow Minimum Flow = 40000 1666.6667 Average Flow = 80000 3333.3333 Peak factor f = 2 = 160000 6666.6667 2 Population = 275 lpd Population = 290909 3 BOD = 110 gm/c/d BOD load on STP = 32000000 gm/d = 32000 kg/d BODin conc = 400 mg/l 4 = 40 mg/l 5 Suspended Solids* = 0.09 kg/c/d SS load on STP SS*Population = 26182 kg/d SSin conc = 327 mg/l 6 T = 20 7 Elevation above Mean sea Level, Altitude = 100 m 8 Ambient Air Temperature = 25 Outlet Parameters Before Filtration 1 BOD = 10 mg/l 2 TSS = 10 mg/l After Filtration 1 BOD = 5 mg/l 2 TSS = 5 mg/l 3 Ammonia Ne < 1 mg/l 4 Total Nitrogen < 15 mg/l 5 pH = 6.5 to 8.5 6 Coliforms < 100/100ml 7 Salinity < 4000 micromho/cm REFERENCES (1) Design Standard Manual : SPC/DSM Sect 4 ,4.3.4,Pg 18 (2) Design Standard Manual : SPC/DSM Sect 4 ,4.1.5.1,Pg 6 (3) Design Standard Manual : SPC/DSM Sect 1 ,Appendix -2 Sewage Analysis ,Pg 36 (4) KEO/M&E preliminary report of Dec 2004 : Appendix -C , average of Temp recorded Qm m 3 /d m 3 /hr Qa m 3 /d m 3 /hr Peak Flow (1) Qp f * Qa m 3 /d m 3 /hr Flow / capita (1) Qc Qa*1000/Qc BOD load per capita (1) Qa*BODload/capita Si BODload*1000/Qa TKN / Ammonia (3) Ni SSi SS load per capita (2) SSi Temperature (4) o C o C So SSo Se SSe
48

SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Dec 30, 2015

Download

Documents

Hemantk8731

EASY CALCULATION FOR EX AEARTION STP
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client:

Project Name:

Document No.: / /Section: Design Data

Page: 1 of

Design by: Hemant Kale Checked by: Rev:

Date: Date: Date:

Design CriteriaInlet Parameters

1 Design Flow

Minimum Flow = 40000

1666.66667

Average Flow = 80000

3333.33333Peak factor f = 2

= 160000

6666.666672 Population

= 275 lpd

Population = 290909

3 BOD

= 110 gm/c/d

BOD load on STP = 32000000 gm/d= 32000 kg/d

BODin conc = 400 mg/l

4 = 40 mg/l

5 Suspended Solids*

= 0.09 kg/c/dSS load on STP SS*Population = 26182 kg/d

SSin conc = 327 mg/l

6 T = 20

7 Elevation above Mean sea Level, Altitude = 100 m

8 Ambient Air Temperature = 25Outlet Parameters

Before Filtration

1 BOD = 10 mg/l

2 TSS = 10 mg/l After Filtration

1 BOD = 5 mg/l

2 TSS = 5 mg/l3 Ammonia Ne < 1 mg/l4 Total Nitrogen < 15 mg/l5 pH = 6.5 to 8.56 Coliforms < 100/100ml

7 Salinity < 4000 micromho/cmREFERENCES

(1) Design Standard Manual : SPC/DSM Sect 4 ,4.3.4,Pg 18(2) Design Standard Manual : SPC/DSM Sect 4 ,4.1.5.1,Pg 6(3) Design Standard Manual : SPC/DSM Sect 1 ,Appendix -2 Sewage Analysis ,Pg 36(4) KEO/M&E preliminary report of Dec 2004 : Appendix -C , average of Temp recorded

Qm m3/d

m3/hr

Qa m3/d

m3/hr

Peak Flow (1) Qp f * Qa m3/d

m3/hr

Flow / capita (1) Qc

Qa*1000/Qc

BOD load per capita (1)

Qa*BODload/capita

Si BODload*1000/Qa

TKN / Ammonia (3) Ni

SSi

SS load per capita (2)

SSi

Temperature(4) oC

oC

So

SSo

Se

SSe

Page 2: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS
Page 3: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client:

Project Name:

Document No.: / /Section: Inlet works- Screens

Page: 1 of

Design by: Hemant Kale Checked by: Rev:

Date: Date: Date:

Design Flow

Minimum Flow 40000.001666.67 m3/hr 0.46296 m3/s

Average Flow = 80000.00 3333.33 0.92593 m3/s

Peak Flow = 160000.006666.67 1.85185 m3/s

1 Inlet ChannelAssume Water Depth = 1.00 mVelocity at Qp = 1.00 m/sWidth of Channel = 1.85 m

Say = 1.50 m ChecksVelocity at = 0.31 m/s

= 0.62 m/s

1 Screens No of Screen channels = 3.00No of duty Chanels = 2.00No of stand by = 1.00

Flow per channel = 0.23 m3/s= 0.46 m3/s= 0.93 m3/s

PER CHANNEL DETAILSChannel Width =Channel depth =

Vel thro'screens = 1.00 m/s at peak flowBar spacing a = 15 mm Bar width b = 10 mm

Angle of inclination θ = 50 degVert.Liquid Depth dv = 0.75 m

Area of openings = 0.926 Slant areaWidth of openings Wn = 1.235 mNo of Bars n (n*b)+[n+1)*a]=w = 48.8

say = 36 n

= 0.92say = 1 m

Area openings vert. = 0.709

Wn*d = 0.750 Checks At Peak flow

Velocity thro screens Vs = 1.235 m/s

Velocity in channel Vc = 0.74 m/sAt Average Flow

Velocity thro screens Vs = 0.617 m/s

Velocity in channel Vc = 0.37 m/s

at Peak Flow , clean screens = 0.069 m 68.81 mmat 50 % clogging of screens, velocity is doubled Velocity thro screens Vs Vs /0.5 = 2.469

Qm m3/d

Qa m3/dm3/hr

Qp m3/dm3/hr

Qm

Qa

Qm

Qa

Qp

Vs

Aopen Qp / (Vs ) m2

Hence width of channel based on n, Wn

Aopen-v Aopen *Sinθ m2

Cross section of channel, Ca,c/s m2

Qp / (Ca,c/s)

Vs/ (a/(a+b))

Qa / ( Ca,c/s)

Vc* (a/(a+b))

Head Loss , Hf Vs2-Vc

2/(2*9.81*0.852)

Page 4: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Velocity in channel Vc = 1.48 Hence head loss = 0.273 m 273 mm

Client:

Project Name:

Document No.: / /Section: Inlet works- Grit Removal System

Page: 1 of

Design by: Hemant Kale Checked by: Rev:

Date: Date: Date:

Vs* (a/(a+b))

Page 5: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS
Page 6: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Depth of Channel= DcFree Board FB = 0.5 mHENCE Dc 1.52 m

Say 1 m

2 GRIT Removal systemNo of Grit System 3No of Duty Grit system 2No of Stand by Grit system = 1 m3/hr

Flow per channel = 0.00 m3/s

= 0.00 m3/s

= 0.00 m3/s

Client:

Project Name:

Document No.: / /Section: Design Data

Page: 1 of

Design by: Hemant Kale Checked by: Rev:

Date: Date: Date:

Section: Inlet Works/Biological TreatmentFile:

Design Flow

Average Flow = 80000 3333.33333 0.92593 m3/s

Peak Flow = 160000 6666.66667 1.85185 m3/s4 Anoxic Tank (Anx Tank)

No of Anoxic Tanks = 2 nos

Flow to each Tank Qa = 40000

Influent Ammonia = 40 mg/l

Effluent Ammonia = 1 mg/l

Effluent Nitrates = 8 mg/lMLSS in Aer. Tank X = 3500 mg/l

MLVSS in Anx Tank 0.70 *X = 2450 mg/lD.O in An Tank C = 0.1 mg/l

Denitrification Rate = 0.15 at 20 Deg C

= 0.135 at Field conditions

t = 2.322 hrsSafety Factor f = 1.2

Anx Tank Volume Qa*t*f/24 = 4643.99

R ((Ni-Ne/NO3e)-1)*Qa = 3.88

RAS = 1 100% recycle)

Mixed liquor return = 2.88 = 115000

Hence Provide two Pumps (1 D+ 1S) Each of c capacity = 4791.67

where

Power per unit vol

multiplication factor μ = 1.0087 at 20 Deg C

multiplication factor = 1.000 at Field conditions

= 0.0107Total power required P = 49.677 Kw

dv+FB+Hf

Qm

Qa

Qp

Qa m3/d m3/hr

Qp m3/d m3/hr

m3/d

Ni

Ne

NO3e

Xv Xv / X = 0.7 to 0.8

μdn20 d-1

Denitrif. Rate (6) μdnT μdn20*1.09(T-20)*(1-C) d-1

Anx Tank HRT (7) (Ni-Ne)*24/(Xv * μdnT)

Vanx m3

Recyle Ratio(8)

where R = Overall recycle ratio (Mixed liquor,Qr+Return Sludge,QRAS)

QRAS

Qr (R- QRAS) m3/d

m3/hr

Mixing Requirements per tank (9) (P/Vanx)=0.00094*(μ)0.3*(X)0.298

P/Vanx kw/m3

μT μ(T-20)

P/Vanx

Page 7: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

= 66.680 HpAvailable nearest mixer = 1.50 HpTank DimensionsWidth (C/wall with Aeration Tank ) = 8 m

Depth(based on Hydraulics) = 3.80 mLength = 152.76 msay = 152.80 mVolume = 4645.12 m3

REFERENCES(6) Phosphorus and Nitrogen Removal from Municipal Wastewater- Principles and Practice- Richard Sedlak- Page-20(7) Phosphorus and Nitrogen Removal from Municipal Wastewater- Principles and Practice- Richard Sedlak- Page-19(8) Phosphorus and Nitrogen Removal from Municipal Wastewater- Principles and Practice- Richard Sedlak- Page-25(9) Design &retrofit of wastewater treatment plants for biological nutrient removal- Randall,Barnard, Stensel- Page-118

Page 8: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client:

Project Name:

Document No.: / /Section: Design Data

Page: 1 of

Design by: Hemant Kale Checked by: Rev:

Date: Date: Date:

Section: Biological TreatmentFile:

5 Aeration Tank ( Aer Tank) No of tanksNo of Tanks = 2 nosFlow to each tank Qa = 40000 m3/d

Qp = 80000 m3/d

BODin = 400 mg/l

BODout = 5 mg/l Mixed Liquor Suspended Solids(MLSS), X = 3500 mg/l

Mean Cell Residence Time (MCRT) = 25 days 20-30 range

(also termed as Sludge Retention Time (SRT))

Food to Microorganism ratio, F/M = 0.1 0.05-0.15 range

= 45143 Checks

Mass loading rates = 0.125 kg BOD/kg Xv/d

Vol. loading rate Cv = 0.35 kg BOD/m3/d HRT, t Vaer/Qa = 1.129 d Sudge Recycle

Return sludge conc = 0.8 % = 8000 mg/l 8 kg/m3

Sludge Production( per tank) Sludge Yeild co efficient, Y = 0.6 kg TSS/kg BODremoved

= 790.00 m3/d

= 6510 kg/dSludge produced (11) (Si-So)*Qa*Y/1000 = 9480 kg/d

Sludge Wasting based on SRT = 6320.0 kg/d Take which ever is higher for sludge handling equipment = 9480.0 kg/d

Total sludge = 18960.0 kg/dOxygen Requirement per Tank

=where

= 0.68

Sludge Produced = Yobs*Qa*(Si-So)/1000

Sludge yield =

Sludge decay coeff. = 0.05

= 0.26666667

= 4213.33Hence AOR = 24381.56 kg/dDenitirification credit available ( this is the safety factor)

= 2.86*(Ni-Ne)*Qa/1000 = 4461.6 kg/dHowever only 75 % is considered as available for design = 3346.2 kg/dAOR after considering denitirification credit AOR-Credit = 21035.36 kg/dSafety factor available = 1.16Side water depth SWD = 3.8 mWidth of the tank W = 8.00 mLength of tank L = 1485 m

Volume of AT = 45144.00 m3REFERENCES

(10) Wastewater Engineering Treatment and Resue-Metcalf & Eddy-pg 679 table -8.5 equation 7-60(11) Wastewater Engineering Treatment and Resue-Metcalf & Eddy-pg 693 Equation 8-34

Si

So

θc

d-1

Aer Tank Vol, each ( 10) Vaer =Qa*(Si-So)/(F/M *X) m3

Cm (Si-So)*Qa/(Vaer*X*0.8)

(Si-So)*Qa/(Vaer)

Xr

Sludge Wasting basis (11) Vaer * X/(θc*Xr)

((Vaer *X)/(1000))/θc

Actual Oxygen Requirements, AOR, kg/d (12) (Qa*(Si-So)/(1000*f)-1.42*Px +4.33*(Qa*(Ni-Ne)/1000)

BOD5 to BODL factor, f

Px

Yobs Y/(1+ Kd*θc)

Kd

Yobs

Px

Credit of O2 ,released per kg of Ammonia denitrified

Vaer

Page 9: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

(12) Wastewater Engineering Treatment and Resue-Metcalf & Eddy-pg 683 Equation 8-17

Page 10: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client:

Project Name:

Document No.: / /Section: Design Data

Page: 1 of

Design by: Hemant Kale Checked by: Rev:

Date: Date: Date:

Section: Biological TreatmentFile:

6 Secondary ClarifierNo of Clarifiers = 2Flow to each tank Qa = 40000 m3/d

Qp = 80000 m3/d

Overflow rate at Qa = 10 8-16 is the range

Overflow rate at Qp = 32 24-32 is the rangeSide water Depth SWD = 3.5 m 3.5 to 6 m

Area of each clarifier Qp/OFRp = 2500Dia of the clarifier d = 56.42 m

say = 9.50 m

area at rounded off dia = 70.85

Vol. of clarifier A * SWD = 247.96 Checks

OFR at Qa OFRa = 564.60 ok Hydraulic Retention Time, t

at Qa = 0.1 hr

at Qp = 0.1 hr

164.7 at average flow

= 247.0 at peak flow Clarifiers Dimensions Diameter = 9.50 m SWD = 3.5 m

7 Continuos Backwash FiltersQpeak = 160000

Filter Size ( each cell) L = 2.16 mW = 2.16 m

No of Cells) N = 4 Total filtration area = 18.6624 m2

Filtration rate at Qp = 357.225 m3/m2/hr 8 CCT inlet chamber

HRT at Qpeak flow = 90 secVolume = 166.666667 m3Depth = 1.5

Area = 111.111111 m2Length = 2 mWidth = 56 m

9 Chlorine Contact TankNo of Tanks = 2HRT in tanks at Qp = 30 minutes (15 to 45 at Qp)Volume of each tank = 1666.66667 m3SWD = 1.5 mLength to width ratio L: W ratio = 2Width W = 24.00 mLength L = 48.0 m

OFRa m3/m2/d

OFRp m3/m2/d

Acl m2

m2

Vcl m3

Qa/Acl m3/m2/d

Vcl*24/Qa

Vcl*24/Qp

Solid loading Rate SLR = (Qa+QRAS)*X/(24*1000*Acl) = kg/m2/hr

kg/m2/hr

Page 11: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client:

Project Name:

Document No.: / /Section: Design Data

Page: 1 of

Design by: Hemant Kale Checked by: Rev:

Date: Date: Date:

Section: Biological TreatmentFile:

Tank dimensions

Length = 48.0 mWidth = 24.00 m

SWD = 1.5 mFB = 0.55 m

10 Sludge Holding TankSludge Wasted /d WAS = 18960 kg/d

Sludge Wasted /d WAS/(Sp Gr *Conc) = 2301.0 m3/d However handling rate based on 7day sludge handled in 5 d = 3221 m3/d

Hydraulic Retention Time, t = 1.5 days

= 4832 m3 Sludge concentration after before desludging = 1.2 % 12 kg/m3

Sludge volume to Dryings Beds = 1533.98 m3/d

Sludge Holding Tank decant = 766.99 m3/d SWD = 3 Length = 40.1 Width = 40.1 Area of Tank = 1610.68

Solids Loading rate = 16.48 kg/m2/d Depth based of HRT = 3.0 m Depth required for 1.2 % conc = 1.3

Available extra depth ( min. = 1.2 % conc depth) = 1.7 mFree Board = 0.5 m

Tank Dimensions Length = 40.1 m

Width = 40.1 mSWD = 3.0 mTotal Depth = 3.5 m

11 Sludge Drying Beds (SDB)

Sludge Volume = 1534.0 m3/d Approach -1 based on Solids loading

Solids loading rate SLR = 75 kg/m2/yr 50-100 kg/m2/yr

Area of SDB WAS*365/SLR = 92272.00 m2Depth of Sludge d = 0.225 m

Volume of beds = 20761 m3

Hyd.Retention Time t = 13.5 dCheckArea/person Area/Population = 0.317 m2/personDivide area into equal area + add 2 beds( 1 as under excavation+ I stand by)Length of each bed L = 21.85Width of each bed W = 14.16No of beds = 298.23Hence provide working no of beds = 6 noTotal no of Beds = 10Drying Period = = 0.27 days

Solids concentration after drying = 30 %Volume of solids after drying = 61.36 m3

Vwas

Sludge holding Tank Volume, Vsl

Vsl

Vwas-Vsl

Vsl

Asdb

Vbeds Asdb*d

Vbeds / Vsl

Page 12: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Filtrate considering no evaporation losses = 1472.62 m3/d

Client:

Project Name:

Document No.: / /Section: Design Data

Page: 1 of

Design by: Hemant Kale Checked by: Rev:

Date: Date: Date:

Section: Biological TreatmentFile:

12 Equipment sizing for Each aeration tank

AOR, 24381.6 kg/d

= AOR*Csw / α *(β*Fa*C'sw-C)(1.024)^(T-20) Where

α 0.60 0.4-0.8 range

Salinity surface tension factor β 0.95 0.7-0.98

Fa 1-(altitude/9450) 1.0Temp.correction factor at field cond. 1.024(T-20) 1.0Min.DO maintained in Aer.Tank C 2.0 mg/l

C'sw 9.1 mg/l O2 sol.in tap water at 20 deg C, Csw 9.08 mg/l SOR 56463.7 kg/d 0.43 (AOR/SOR) Side water depth in Aer Tank SWD 3.8 m Diffuser location from tank bottom d 0.25 m from vendor Diffuser submergence depth d1 SWD-d 3.55 m Air flow per diffuser 4.5 m3/hr from vendor Diffuser eff. per m submergence % 6.5 % from vendor Oxygen content in Air % 21% Diffuser effeciency % 23.1 %

Air density at filed conditions 1.206 kg/m3

Air required, filed conditions 966071.4 m3/d safety factor in order to get over all SF of 1.5 1.29

Air required , m3/hr 52092.8no of working blowers 1.0Air required ,m3/hr 52092.8

Air required, Nm3/hr 47722.6ChecksAir per m3 of tank volume blower capaity/ tank volume 1.15 0.6 -0.9 is the range

12 Power Required for Blowers Effeciency 0.85WRT1/eff = 6052.5529

Inlet pressure (absolute) = 1.01 atms Outlet pressure (absolute)= 1.39 atms

Power required 761.096451 HP Next available 25 HP

Margin = 0.03284735

13 Aeration Requirment for Sludge Holding TankVolume of sludge Holding Tank = 4832 m3Mixing power required = 30 kw/1000 m3 ( range 20-40)Required Kw = 144.96 KwAvailable next Kw = 4 Kw

14 Mixer for Chlorine MixingVolume = 168 m3Gt = 45000G = 500Watts = 42000

O2 under standard conditions of 20OC, SOR, kg/d

O2 Transfer correction factor

O2 Sol.Correc.factor,at field elev.

O2 sol.in tap water(field temp,)

SOR/(air density*O2 %*Diff Eff)

Page 13: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Kw = 42.00

Page 14: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

System CurveDia Velocity Area

Suction Dia 0.15 m 1.5 0.017672Discharge Dia 0.1 m 2.4 0.007854Qs 0.026507Qd 0.01885

LossesÑH

Pd Atm 10Ps Atm 10hs suction head 5hd discharge head 15Friction losses

Flowratel/s Total Head

0 10.005 12.22

10 18.8715 29.9620 45.4825 65.4430 89.8335 118.6640 151.9245 189.6250 231.7555 278.3260 329.3365 384.7670 444.6475 508.9580 577.69

[(Pd-Ps)/rg]+(hd-hs)+[(Vd2-Vs2)/2g]+Friction lossed

l/s 0 5 10 15 20 25 30 350.00

20.00

40.00

60.00

80.00

100.00

120.00

140.00

160.00

Total Head

Total Head

Page 15: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Suction Qty K Length Head loss fBellmouth 1 0.05090deg Bend 1 0.400Straight Pipe 1.5Isolation valve 1 0.450Straight Pipe 190 Def bend 1 0.400

1.300 2.5DischargeStraight Pipe 1Isolation Valve 0.4590deg Bend 0.4Straight Pipe 290deg Bend 0.4Straight Pipe 1NRV 0.3Straight Pipe 100Gate valve Pipe exit 1

2.55 104

Vd Vs Term-1 Term-2 Term-3 Term-4 fittings0.00 0.00 0 10 0.00 0.00 ###0.64 0.28 0 10 0.02 2.20 ###1.27 0.57 0 10 0.07 8.80 ###1.91 0.85 0 10 0.15 19.81 ###2.55 1.13 0 10 0.27 35.22 ###3.18 1.41 0 10 0.41 55.02 ###3.82 1.70 0 10 0.60 79.23 ###4.46 1.98 0 10 0.81 107.85 ###5.09 2.26 0 10 1.06 140.86 ###5.73 2.55 0 10 1.34 178.28 ###6.37 2.83 0 10 1.66 220.10 ###7.00 3.11 0 10 2.01 266.32 ###7.64 3.40 0 10 2.39 316.94 ###8.28 3.68 0 10 2.80 371.96 ###8.91 3.96 0 10 3.25 431.39 ###9.55 4.24 0 10 3.73 495.22 ###

10.19 4.53 0 10 4.24 563.45 ###l/s 0 5 10 15 20 25 30 350.00

20.00

40.00

60.00

80.00

100.00

120.00

140.00

160.00

Total Head

Total Head

Page 16: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Nitrification

ConcentrationFrom to

Total N 20 85Organic 8 35Free Ammonia 12 50

Temp 20

NO3-N at outlet 5

inlet TKN 40

Outlet Ammonia,N 1

Kn 1

BODin So 400

BODout Se 10

MLSS 3500

Flow 1500

Inlet Solids 327

Outlet Solids 20

=

=

Safety factor (1.5 to 2.5) =

=

=

By Monod equn =

Organic removal rate

=

HRTn

DenitrificationNet yield of TSS, kg/ kg of BOD removed, 75 % VSSMlvss/MlssOrganic nitrogen content of cells (MLVSS)Soluble TKN,mg/lSoluble TKN,mg/lTKN to be nirtified mg/l

kg/d

μ N15 μ N10 + (20-t/20-10 *(μ N20-μ N10))

Minimum SRT θmc (KN+N/ μ NT *N)

Design SRT θmc

Design Nitrifier Growth rate,μ N

Design Nitrifier Growth rate,μ b 1/θdc =Yb*qb-Kd

Yb = Heterotrophic yield coefficient, Kg VSS sysnthesized /Kg BOD removed

Kb = Endogenous decay co eff.,d-1

μ b = Heterotrophic growth rate ,d-1

qb =rate of substrate BOD to Kg VSS removal, Kg BOD removed/Kg VSS.d

q DN

Page 17: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Mlvss required in the DN reactorMlvss in mg/litVolume of denitrifying reactor

Volume required for nitrification

=

t =f =

Qa*t*f/24 =R ((Ni-Ne/NO3e)-1)*Qa =

=

=capacity =

where

μ = 1.0087 at 20 Deg C

μdnT μdn20*1.09(T-20)*(1-C)

(Ni-Ne)*24/(Xv * μdnT)

Vanx

QRAS

Qr (R- QRAS)

(P/Vanx)=0.00094*(μ)0.3*(X)0.298

P/Vanx kw/m3

Page 18: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Temp10 0.320 0.6530 1.2

0.3 at 20 Deg C

6.67 d

2

13.33 d

0.075 d

0.15 d

0.65

0.05

0.192307692

0.724285714 d

17.38285714 hr

0.65

0.7

0.07

27.5785

1.44

21.1385

31.70775

0.073002141

μ Nd-1

d-1

θc

Page 19: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

434.3400002 kg

2450

177.2816327 m3

1086.428571

6.42

10000000000

1.425823E-120.0915378411

at 20 Deg C

Page 20: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 1 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section: Head LossFile:

Design Criteria

Inlet Parameters1 Design Flow

Average Flow = 80000 3333.33333 0.925926 m3/s

= 160000 6666.66667 1.851852 m3/s =2 Chlorine Contact Tank water level = 63.3 63.3

3 Inlet chamber to CCT Weir width = 0.40 m

Qpeak = 1.851852 m3/s No of CCT = 2 Flow to each = 0.925926

Head over weir = 1.173 64.52279Top of weir level = 63.35 63.3Level in inlet chamber = 64.523

4 Filter outlet chamber To CCT inlet chamber

Manning's formula Depth of water in full pipe D at QavgDepth of water partially full pipe d d/D = 0.7 0.7

= 0.85 0.85Q = 1.851852 m3/s 0.925926Qf = 2.178649 m3/s 1.089325

Velocity in pipe when full = 0.75 m/s 0.75Dia of pipe at above velocity, D = 1.923 m 1.360Choose dia = 0.3 m 0.3Velocity at chossen dia = 30.837 m/s 15.419Manning's constant n = 0.0133 0.0133Wetted perimeter, R = 0.075 m 0.075Slope S = 5.410925 541.092 % 1.352731 135.273Fitting Factor Qty Elbow-90 34 2 = 20.4 20.4Elbow-45 14 0 0 0Radial T 22 0 0 0Tee 54 0 0 0Taper 22 0 0 0Straight pipe length = 40 32Toatl length of pipe = 60.4 52.4Drop in levels based on slope = 326.820 m 70.883Other losses Qty k factor

Exit 1 1 = 48.468 m 12.117Entry 1 0.5 = 24.234 m 6.058Valves 0 1 = 0.000 m 0.000

Total head loss = 399.521 m 463.171 89.058Level in filter outlet chamber = 463.171 m 64.523 89.210(as thumb rule pipe dia ODis added to 89.510

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Peak Flow (1) Qp m3/d m3/hr

H=(0.55*Qa/W)^0.66

V=1/n*R2/3*S1/2

at above condition Q/Qf

Page 21: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 2 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section:Head LossFile:

Design Flow

Average Flow = 80000 3333.33333 0.925926 m3/s

Peak Flow = 160000 6666.66667 1.851852 m3/s

5 Filter to Filter outlet chamberWeir width = 2.16 m No of weirs = 2 mTotal weir width = 4.32Qpeak = 1.851852 m3/s

Head over weir = 0.385 msay = 0.05 m 463.321

Top of weir level = 463.171 463.171Free fall = 0.1

Level of water in Filter = 463.3216 Head Loss across the Filters

Filter Size ( each cell) L = 2.16 mW = 2.16 m

No of Cells) N = 4Total filtration area = 18.6624 m2Solids into Filter = 10 mg/lSolids out of Filter = 5 mg/lSolids captured = 400 kg/dSollid capture = 1.5 kg/m3/dHead Loss across the Filters = 14.29 mAdd = 0.15 m 477.761Total head loss = 14.44 m 463.321Level in Inlet chamber of the Filter = 477.76

7 Head loss from Outlet chamber of Secondary Clarifier to Inlet Chamber of Filtera Individual S/Clarifiers to Commom headerNo of clarifiers = 2 2

Manning's formula Depth of water in full pipe D AT QavgDepth of water partially full pipe d d/D = 0.7 0.7

= 0.85 0.85Q = 0.925926 m3/s 0.462963Qf = 1.089325 m3/s 0.544662

Velocity in pipe when full = 0.75 m/s 0.75Dia of pipe at above velocity, D = 1.360 m 0.962Choose dia = 0.2 m 0.2Velocity at chossen dia = 34.692 m/s 17.346Manning's constant n = 0.0133 0.0133Wetted perimeter, R = 0.05 m 0.05Slope S = 11.79068 1179.068 % 2.94767

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Qp m3/d m3/hr

H=(0.55*Qa/W)^0.66

V=1/n*R2/3*S1/2

at above condition Q/Qf

Page 22: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 3 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section: Head LossFile:

Fittings Factor Qty Elbow-90 34 2 = 13.6Elbow-45 14 1 2.8

Radial T 22 0 0Tee 54 1 10.8Taper 22 0 0Straight pipe length = 22Toatl length of pipe = 49.2Drop in levels based on slope = 580.101 mOther losses Qty k factor

Exit 0 1 = 0.000 mEntry 1 0.5 = 30.671 mValves 0 1 = 0.000 m

Total head loss = 610.772 m

b Head loss through Common Pipe

Manning's formula Depth of water in full pipe D Depth of water partially full pipe d d/D = 0.7 0.7

= 0.85 0.85 Q = 1.851852 m3/s 0.925926 m3/sQf = 2.178649 m3/s 1.089325 m3/s

Velocity in pipe when full = 0.75 m/s 0.75 m/sDia of pipe at above velocity, D = 1.923 m 1.360 mChoose dia = 0.3 m 0.3 m

Velocity at chossen dia = 30.837 m/s 15.419 m/sManning's constant n = 0.0133 0.0133Wetted perimeter, R = 0.075 m 0.075 mSlope S = 5.410925 541.092 % 1.352731 135.273Fitting Factor Qty Elbow-90 34 2 = 20.40 20.40Elbow-45 14 1 4.20 4.20Radial T 22 1 6.60 6.60Tee 54 1 16.20 16.20Taper 22 0 0.00 0.00Straight pipe length = 50 50Toatl length of pipe = 97.4 97.4Drop in levels based on slope = 527.024 m 131.756 mOther losses Qty k factor

Exit 1 1 = 48.468 m 12.117 mEntry 0 0.5 = 0.000 m 0.000 mValves 1 1 = 48.468 m 12.117 m

Head loss thro'common header = 623.959 m 155.990 mHead loss- S/C outlet chamber to filter inlet = 1234.732 155.990

say = 1234.700 m 0.5 mLevel in Inlet chamber of the Filter = 477.76 1712.461 0.00 0.500Level in Outlet chamber of the clarifer = 1712.46 477.761 0.50

Project Name: Raising Capacity of Gayathi STP-Phase-II

V=1/n*R2/3*S1/2

at above condition Q/Qf

Page 23: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 4 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section: Head LossFile:

Design Flow

Average Flow = 80000 3333.33333 0.925926 m3/s

Peak Flow = 160000 6666.66667 1.851852 m3/s

Qras Qras = 80000 3333.33333 0.925926 m3/s8 Outlet Chamber of the S/Clarifier 1713.06 Launder Top level Head loss D/S = 1234.7 m

Pipe dia = 0.2 m 1712.461 1712.461 Water LevelInvert level of chamber = 477.56 IL of IL of chamberS/C launder invert level = 1712.46 S/C laund 477.56

Launder Depth = 0.6 m ChamberTop of concrete of launder = 1713.06

9 Head over the V notch Q= 8/15*Cd*tanθ/2*√2*9.81*H5/2 Launder width = 0.4 m Circumference of the each clarifier = 27.33 m C/C distance of V notch = 0.15 m No of notches = 182 n 1713.11 Weir plate Level Qpeak /per V notch Q = 0.005088 m3/s Angle of V notch θ = 90.00 deg 1713.17 water Level in V notch

Coefficient of discharge Cd = 0.61 Head over the V notch = 0.10 m 104 mm Water Level in V notch = 1713.166

10 Side water depth of clarifier SWD = 3.5 m Hopper top level = 1709.67

11 Aeration Tank outlet to each S/Clarifier

Manning's formula Depth of water in full pipe D

Depth of water partially full pipe d d/D = 0.7 0.7

= 0.85 0.85Q = 1.389 m3/s 0.926

Qf = 1.634 m3/s 1.089

Velocity in pipe when full = 0.750 m/s 0.750Dia of pipe at above velocity, D = 1.666 m 1.360Choose dia = 0.3 m 0.3 Velocity at chossen dia = 23.128 m/s 15.419Manning's constant n = 0.0133 0.0133Wetted perimeter, R = 0.075 m 0.075Slope S = 3.043645 304.365 % 1.352731Fitting Factor Qty Elbow-90 34 3 = 30.60 30.60Elbow-45 14 1 4.20 4.20Radial T 22 0 0.00 0.00Tee 54 0 0.00 0.00Taper 22 0 0.00 0.00Straight pipe length = 35 35Total length of pipe = 69.80 69.80Drop in levels based on slope = 212.446 m 0.944

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Qp m3/d m3/hr

m3/hr

V=1/n*R2/3*S1/2

at above condition Q/Qf

Page 24: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 5 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section:Head LossFile:

Average Flow = 80000 3333.33333 0.925926 m3/s

Peak Flow = 160000 6666.66667 1.851852 m3/s

Qras Qras = 80000 3333.33333 0.925926 m3/s

Other losses Qty k factorExit 1 1 = 27.263 mEntry 1 0.5 = 13.632 mValves 1 1 = 27.263 m

Head loss thro'common header = 280.604 m Head loss- AT outlet to S/Clarifier = 280.604 m say = 280.604 m 1993.770 Level in S/clarifier = 1713.17 1713.166 Level in Outlet of AT = 1993.77

12 Level in Aeration Tank Weir width = 0.60 m Q(Qpeak+Qras) = 2.778 m3/s

No of AT = 2.000 nos Flow to each = 1.389 m3/s

Head over weir = 1.173 m 1994.992Allow for free Fall = 0.05 m 1993.77Top of weir level = 1993.770Water Level in Aeration tank = 1994.992Bottom Level of AT at center of tank = 1991.192 1994.905 1991.192 1987.480

Bottom Level of AT at OUTLET = 1987.480 U/stream centre d/s stream Bottom level of AT c/wall with Anoxic Tank = 1994.905

13 Anoxic Tank to Aeration TankProvide opening bewteen An Tk and Ae Tank

Width = 400 mmHeight = 400 mmArea = 0.16 m2

Q(Qavg+Qras+Qir) per tank = 195000 m3/d 8125.00 2.26 m3/s

Q(Qpeak+Qras+Qir) per tank = 235000 m3/d 9791.67 2.72 m3/sVelocity at (Qavg+Qras+Qir) per tank = 14.106 m/s m3/sVelocity at (Qpeak+Qras+Qir) per tank = 16.999 m/sVelocity head at max velocity = 14.729 m ### mmLevel in Aeration Tank = 1994.992 2009.72 1994.99Level in Anoxic Tank = 2009.721

1994.905 1994.905Anoxic Aeartion

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Qp m3/d m3/hr

m3/hr

H=(0.55*Qa/W)^0.66

m3/hr

m3/hr

Page 25: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 6 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section:Head LossFile:

Average Flow = 80000 3333.33333 0.925926 m3/s

Peak Flow = 160000 6666.66667 1.851852 m3/s

14 Distribution Box to Anoxic Tank Tank

Manning's formula Depth of water in full pipe D Depth of water partially full pipe d d/D = 0.7

= 0.85 Q = 1.389 m3/sQf = 1.634 m3/s

Velocity in pipe when full = 0.750 m/s Dia of pipe at above velocity, D = 1.666 m Choose dia = 0.25 m Velocity at chossen dia = 33.304 m/s Manning's constant n = 0.0133 Wetted perimeter, R = 0.0625 m Slope S = 8.0579 805.790 % Fitting Factor Qty

Elbow-90 34 2 = 0.00Elbow-45 14 0 0.00

Radial T 22 0 0.00Tee 54 0 0.00Taper 22 0 0.00Straight pipe length = 0Total length of pipe = 0.00

Drop in levels based on slope = 0.000Other losses Qty k factor

Exit 0 1 = 0.000 mEntry 0 0.5 = 0.000 mValves 0 1 = 0.000 m

Toatl Head loss = 0.000 Head loss- D/Box to Anoxic Tank = 0.000 m

say = 0.000 m 1994.992Level in Anoxic Tank = 2009.72 2009.721Level in Distribution Box = 1994.992

15 Distrbution BoxWeir width = 1.00 m Qpeak = 1.389 m3/s

Head over weir = 0.837 m Allow for free Fall = 0.1 mWorst case when flow is full and I stream closed 1995.930Head over weir = 1.012 1994.992 Top of weir level = 1995.092 Level of water over weir = 1995.930Depth of flow in Box = 0.500 1994.592 Bottom Level of Box = 1994.592

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Qp m3/d m3/hr

V=1/n*R2/3*S1/2

at above condition Q/Qf

H=(0.55*Qa/W)^0.66

Page 26: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 7 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section:Head LossFile:

Average Flow = 80000 3333.33333 0.925926 m3/s

Peak Flow = 160000 6666.66667 1.851852 m3/s

16 Grit Chammber To Distribution Box

Manning's formula Depth of water in full pipe D Depth of water partially full pipe d d/D = 0.7

= 0.85 Q = 1.852 m3/sQf = 2.179 m3/s

Velocity in pipe when full = 0.750 m/s Dia of pipe at above velocity, D = 1.923 m Choose dia = 0.3 m Velocity at chossen dia = 30.837 m/s Manning's constant n = 0.0133 Wetted perimeter, R = 0.075 m Slope S = 5.410925 541.092 % Fitting Factor Qty

Elbow-90 34 2 = 20.40Elbow-45 14 0 0.00

Radial T 22 0 0.00Tee 54 0 0.00Taper 22 0 0.00Straight pipe length = 25Total length of pipe = 45.40

Drop in levels based on slope = 245.656 Other losses Qty k factor

Exit 1 1 = 48.468 mEntry 1 0.5 = 24.234 mValves 0 1 = 0.000 m 2314.287

Toatl Head loss = 318.357 say = 318.357 m Grit 1995.930

Level in Grit Channel = 2314.29 Channel

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Qp m3/d m3/hr

V=1/n*R2/3*S1/2

at above condition Q/Qf

Page 27: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 1 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section: Head LossFile:

Design Criteria

Inlet Parameters1 Design Flow

Average Flow = 80000 3333.33333 0.925926 m3/s

= 160000 6666.66667 1.851852 m3/s

RAS flow = 80000 3333.33333 0.925926 m3/s

IR flow = 230000 9583.33333 2.662037 m3/sNo of streams = 2

Anoxic Mixer

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Peak Flow (1) Qp m3/d m3/hr

m3/d m3/hr

m3/d m3/hr

Page 28: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 2 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section:Head LossFile:

Design Flow

Average Flow = 80000 3333.33333 0.925926 m3/s

Peak Flow = 160000 6666.66667 1.851852 m3/s

5 Filter to Filter outlet chamberWeir width = 2.16 m No of weirs = 2 mTotal weir width = 4.32Qpeak = 1.851852 m3/s

Head over weir = 0.385 msay = 0.05 m 0.100

Top of weir level = 0.000 0.000Free fall = 0.05

Level of water in Filter = 0.1006 Head Loss across the Filters

Filter Size ( each cell) L = 2.16 mW = 2.16 m

No of Cells) N = 4Total filtration area = 18.6624 m2Solids into Filter = 10 mg/lSolids out of Filter = 5 mg/lSolids captured = 400 kg/dSollid capture = 1.5 kg/m3/dHead Loss across the Filters = 14.29 mAdd = 0.2 m 14.600Total head loss = 14.50 m 0.100Level in Inlet chamber of the Filter = 14.60

7 Head loss from Outlet chamber of Secondary Clarifier to Inlet Chamber of Filtera Individual S/Clarifiers to Commom headerNo of clarifiers = 2

Manning's formula Depth of water in full pipe D Depth of water partially full pipe d d/D = 0.7

= 0.85 Q = 0.925926 m3/sQf = 1.089325 m3/s

Velocity in pipe when full = 0.75 m/sDia of pipe at above velocity, D = 1.360 mChoose dia = 0.2 mVelocity at chossen dia = 34.692 m/sManning's constant n = 0.0133Wetted perimeter, R = 0.05 mSlope S = 11.79068 1179.068 %

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Qp m3/d m3/hr

H=(0.55*Qa/W)^0.66

V=1/n*R2/3*S1/2

at above condition Q/Qf

Page 29: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 3 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section: Head LossFile:

Fittings Factor Qty Elbow-90 34 0 = 0Elbow-45 14 0 0

Radial T 22 0 0Tee 54 0 0Taper 22 0 0Straight pipe length = 20Toatl length of pipe = 20Drop in levels based on slope = 235.814 mOther losses Qty k factor

Exit 0 1 = 0.000 mEntry 1 0.5 = 30.671 mValves 0 1 = 0.000 m

Total head loss = 266.484 m =

b Head loss through Common Pipe

Manning's formula Depth of water in full pipe D Depth of water partially full pipe d d/D = 0.7

= 0.85 Q = 1.851852 m3/sQf = 2.178649 m3/s

Velocity in pipe when full = 0.75 m/sDia of pipe at above velocity, D = 1.923 mChoose dia = 0.3 m

Velocity at chossen dia = 30.837 m/sManning's constant n = 0.0133Wetted perimeter, R = 0.075 mSlope S = 5.410925 541.092 %Fitting Factor Qty Elbow-90 34 1 = 10.20Elbow-45 14 0 0.00Radial T 22 1 6.60Tee 54 0 0.00Taper 22 0 0.00Straight pipe length = 20Toatl length of pipe = 36.8Drop in levels based on slope = 199.122 mOther losses Qty k factor

Exit 1 1 = 48.468 mEntry 0 0.5 = 0.000 mValves 1 1 = 48.468 m

Head loss thro'common header = 296.057 m Head loss- S/C outlet chamber to filter inlet = 562.542

say = 0.5 m 15.100Level in Inlet chamber of the Filter = 14.60 14.600Level in Outlet chamber of the clarifer = 15.10

Project Name: Raising Capacity of Gayathi STP-Phase-II

V=1/n*R2/3*S1/2

at above condition Q/Qf

Page 30: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 4 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section: Head LossFile:

Design Flow

Average Flow = 80000 3333.33333 0.925926 m3/s

Peak Flow = 160000 6666.66667 1.851852 m3/s

Qras Qras = 80000 3333.33333 0.925926 m3/s8 Outlet Chamber of the S/Clarifier 15.70 Launder Top level Head loss D/S = 0.5 m

Pipe dia = 0.3 m 15.100 15.100 Water LevelInvert level of chamber = 14.30 IL of IL of chamberS/C launder invert level = 15.10 S/C laund 14.30

Launder Depth = 0.6 m ChamberTop of concrete of launder = 15.70

9 Head over the V notch Q= 8/15*Cd*tanθ/2*√2*9.81*H5/2 Launder width = 0.4 m Circumference of the each clarifier = 27.33 m C/C distance of V notch = 0.15 m No of notches = 182 n 15.75 Weir plate Level Qpeak /per V notch Q = 0.005088 m3/s Angle of V notch θ = 90.00 deg 15.80 water Level in V notch

Coefficient of discharge Cd = 0.61 Head over the V notch = 0.10 m 104 mm Water Level in V notch = 15.804

10 Side water depth of clarifier SWD = 3.5 m Hopper top level = 12.30

11 Aeration Tank outlet to each S/Clarifier

Manning's formula Depth of water in full pipe D

Depth of water partially full pipe d d/D = 0.7

= 0.85 Q = 1.389 m3/s

Qf = 1.634 m3/s

Velocity in pipe when full = 0.750 m/sDia of pipe at above velocity, D = 1.666 mChoose dia = 0.25 mVelocity at chossen dia = 33.304 m/sManning's constant n = 0.0133Wetted perimeter, R = 0.0625 mSlope S = 8.0579 805.790 %Fitting Factor Qty Elbow-90 34 3 = 25.50Elbow-45 14 0 0.00Radial T 22 0 0.00Tee 54 0 0.00Taper 22 0 0.00Straight pipe length = 20Total length of pipe = 45.50Drop in levels based on slope = 366.634 m

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Qp m3/d m3/hr

m3/hr

V=1/n*R2/3*S1/2

at above condition Q/Qf

Page 31: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 5 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section:Head LossFile:

Average Flow = 80000 3333.33333 0.925926 m3/s

Peak Flow = 160000 6666.66667 1.851852 m3/s

Qras Qras = 80000 3333.33333 0.925926 m3/s

Other losses Qty k factorExit 1 1 = 56.533 mEntry 1 0.5 = 28.266 mValves 0 1 = 0.000 m

Head loss thro'common header = 451.433 m Head loss- AT outlet to S/Clarifier = 451.433 m say = 0.3 m 16.104 Level in S/clarifier = 15.80 15.804 Level in Outlet of AT = 16.10

12 Level in Aeration Tank Weir width = 0.60 m Q(Qpeak+Qras) = 2.778 m3/s

No of AT = 2.000 nos Flow to each = 1.389 m3/s

Head over weir = 1.173 m 17.327Allow for free Fall = 0.05 m 16.10Top of weir level = 16.104Water Level in Aeration tank = 17.327Bottom Level of AT at center of tank = 13.527 17.240 13.527 9.815

Bottom Level of AT at OUTLET = 9.815 U/stream centre d/s stream Bottom level of AT c/wall with Anoxic Tank = 17.240

13 Anoxic Tank to Aeration TankProvide opening bewteen An Tk and Ae Tank

Width = 400 mmHeight = 400 mmArea = 0.16 m2

Q(Qavg+Qras+Qir) per tank = 195000 m3/d 8125.00 2.26 m3/s

Q(Qpeak+Qras+Qir) per tank = 235000 m3/d 9791.67 2.72 m3/sVelocity at (Qavg+Qras+Qir) per tank = 14.106 m/s m3/sVelocity at (Qpeak+Qras+Qir) per tank = 16.999 m/sVelocity head at max velocity = 14.729 m ### mmLevel in Aeration Tank = 17.327 32.06 17.33Level in Anoxic Tank = 32.056

17.240 17.240Anoxic Aeartion

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Qp m3/d m3/hr

m3/hr

H=(0.55*Qa/W)^0.66

m3/hr

m3/hr

Page 32: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Client: ABU DHABI MUNICIPALITY Ref/RFS:

Calc Sheet No.: / /Rev:

Drawings:Page: 6 of

Design: Hemant Kale Date:

Structure:Checked: Date:

Section:Head LossFile:

Average Flow = 80000 3333.33333 0.925926 m3/s

Peak Flow = 160000 6666.66667 1.851852 m3/s

14 Distribution Box to Anoxic Tank Tank

Manning's formula Depth of water in full pipe D Depth of water partially full pipe d d/D = 0.7

= 0.85 Q = 0.926 m3/sQf = 1.089 m3/s

Velocity in pipe when full = 0.750 m/s Dia of pipe at above velocity, D = 1.360 m Choose dia = 0.2 m Velocity at chossen dia = 34.692 m/s Manning's constant n = 0.0133 Wetted perimeter, R = 0.05 m Slope S = 11.79068 1179.068 % Fitting Factor Qty

Elbow-90 34 2 = 13.60Elbow-45 14 0 0.00

Radial T 22 0 0.00Tee 54 0 0.00Taper 22 0 0.00Straight pipe length = 20Total length of pipe = 33.60

Drop in levels based on slope = 396.167Other losses Qty k factor

Exit 1 1 = 61.342 mEntry 1 0.5 = 30.671 mValves 0 1 = 0.000 m

Toatl Head loss = 488.179 Head loss- D/Box to Anoxic Tank = 488.179 m

say = 0.4 m 32.856Level in Anoxic Tank = 32.46 32.456Level in Distribution Box = 32.86

15 Distrbution BoxWeir width = 1.00 m Qpeak = 0.926 m3/s

Head over weir = 0.641 m Allow for free Fall = 0.05 mWorst case when flow is full and I stream closed 33.547Head over weir = 1.012 32.856 Top of weir level = 32.906 Level of water over weir = 33.547Depth of flow in Box = 0.500 32.406 Bottom Level of Box = 32.406

Project Name: Raising Capacity of Gayathi STP-Phase-II

Qa m3/d m3/hr

Qp m3/d m3/hr

V=1/n*R2/3*S1/2

at above condition Q/Qf

H=(0.55*Qa/W)^0.66

Page 33: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Head loss Calculation Raw sewage Pumping ABV ROCK SITE -5

BY HRK

hf=6.82*(V/C)^1.85*L/D^1.167PIPE LENGTH 160.00 160.00FLOW , m3/d 4500 4500m3/hr 187.50 187.50m3/s 0.05 0.05PIPE DIAMETER, mm 300 300PIPE DIAMETER, m 0.30 0.30AREA 0.07 0.07VELOCITY , m/s 0.74 0.74C 100.00 140.00V/C^1.85 0.0 0.0L/D^1.167 652.11 652.11HEAD LOSS, hf m 0.50 0.27HEAD LOSS PIPE FITTINGS

Quantity K values K * V^2/2gVALVES 1.00 0.19 0.0052629Check Valves 1.00 0.6 0.0166198ELBOWS 3.00 0.28 0.0232677TEES 0.00 0.7 0ENTRANCE 1.00 1 0.0276996EXIT 1.00 0.75 0.0207747Head loss through fittings 0.0936248Head Loss in meters thr pipe and fittings 0.60add 10 % extra 0.66Static Head 0Total Head Loss 0.66

Page 34: SPREADSHEET FOR ACTIVATED SLUDGE PROCESS

Qa 4148.6 m3/dPeak factor 3.41Peak flow 14146.73 m3/d

0.163735 m3/s

1 Mechanical Bar ScreenFlow 4148.60 m3/dClear spacing 25.00 mmScreening Removed 20.00 m3/mldQuantity of Screenings 0.08 m3/dScreenings bin with storage of 7.00 daysVolume of Bin 0.58 m3

2 Approach & flow through velocitiesMax. Vel. At feed channel 1.00 m/sMax. Vel. at screen face 1.00 m/s

Approach velocityClear spacing 25.00 mmThickness of bars 6.00 mmFlow through screen Velcoity Vsc 0.90 m/sAproach velocity V1 0.73 m/sHead loss Vsc^2-V1^2/2*g*Cd^2 0.02 mH1 20.46 mm

Downstream depth of flow 262 mmDepth U/S of screen Yc 282.46

0.28 mClear width of Screen Wsc 0.64 mRequired Screen width 0.80 mFree Board at Qpeak 0.35 mTotal depth 0.63 m

For Screens 50 % blockedFlow area =