24

Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Dec 30, 2015

Download

Documents

Daisy Young
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Special STP Application Cycle for SFY 2016 Projects

ICC and Executive Committee MeetingsSeptember 2015

Page 2: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

STP Applications

• 15 Applications received requesting $22.5 million:– Butler County Engineer (2 applications)– Butler County RTA– Butler County TID– Cincinnati– Cincinnati/Hamilton County – Evendale– Hamilton County Engineer (2 applications)– Harrison (2 applications)– SORTA– Sharonville (2 applications)– Springdale

• Approximately $7.5 million available in Fiscal Year 2016

Page 3: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Butler County Engineer

Federal $688,922Local $172,230Total $861,152

Page 4: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Butler County Engineer

Federal $396,279Local 99,070Total $495,349

Page 5: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Butler County Regional Transit Authority (BCRTA)

• Requesting 4 Replacement Buses– 1 - 35’ bus @ $444,850– 3 - Light Transit Vehicles @ $92,610 each

• Total Project Estimate:– Federal Share $578,144– Local Share $144,536– Total Cost $722,680

• BCRTA provides reliable, effective general public mobility options for the transportation disadvantaged.

Page 6: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Butler County TIDSouth Hamilton Crossing

Federal $5,000,000Local $5,000,000Total $10,000,000

50% Match

Page 7: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

City of Cincinnati Duck Creek Connector

Federal $1,694,200Local $783,300Total $2,477,500

30% Match

Page 8: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

City of Cincinnati/Hamilton County(The Banks Public Partners)

Federal $400,000Local $100,000Total $500,000

Page 9: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Village of Evendale

Federal $487,100Local $505,000Total $992,100

51% Match

Page 10: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Hamilton County EngineerGalbraith Road Bridge

Federal $2,425,380Local $606,345Total $3,031,725

Page 11: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Hamilton County EngineerHopple Street Viaduct

Federal $3,901,423Local $975,355Total $4,876,778

Page 12: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

City of HarrisonHarrison Avenue

Federal $331,474Local $82,868Total $414,342

Page 13: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

City of HarrisonNew Haven Road

Federal $219,680Local $54,920Total $274,600

Page 14: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

SORTA

• Requesting 12 Replacement Buses– 40’ Diesel buses @$475,000 each

• Total project estimate:– Federal Share $4,560,000– Local Share $1,140,000– Total Cost $5,700,000

• Buses will serve both inner city and suburban routes within SORTA’s operating area.

Page 15: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

City of SharonvilleKemper Road

Federal $464,800Local $199,200Total $664,000

30% Match

Page 16: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

City of SharonvilleSharon Road

Federal $250,680Local $167,120Total $417,800

40% Match

Page 17: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

City of SpringdaleSR 4 Southbound Lane Addition

Federal $482,781Local $120,695Total $603,476

Page 18: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

STP Transportation Factors for Highway ApplicationsUp to 45 points

• Safety (accidents per MVM) 1 to 5 points• Positive Impact on Safety 0 to 5 points• Existing Level of Service (LOS) 0 to 5 points• Positive Impact on LOS 0 to 5 points• Average Daily Traffic 0 to 5 points• Freight Volumes 0 to 5 points• Roadway Classification 3 to 5 points• Complete Streets 1 to 5 points• Status of Project 1 to 5 points

Page 19: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

STP Transportation Factors for Transit ApplicationsUp to 45 points

• Impact on Safety & Security 0 to 5 points• Useful Life 0 to 5 points• System Impact 1 to 5 points• Type 6 to 10 points• Time to Implementation 0 to 5 points• Positive Ridership Impact 0 to 10 points• Capital Utilization 1 to 5 points

Page 20: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

STP Planning Factors for All ApplicationsUp to 55 points

• Replacement/Expansion 1 to 5 points• Environmental Justice 0 to 5 points• Strategic Regional Policy Plan 0 to 5 points• Local Planning 0 to 5 points• Air Quality/Energy 0 to 10 points• Local Share 0 to 10 points• Existing Condition 0 to 5 points• Economic Vitality 0 to 5 points• History of Project Delivery 0 to -5 points• Additional Funding Request 0 to -2 points• Intermodal Elements 0 to 5 points

Page 21: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Funding Recommendations

• Hamilton TID $3,750,000 81 points• SORTA (2 buses) $760,000 58 points• BCRTA (3 LTV’s) $222,264 53 points• Springdale - SR 4 $482,781 49 points• Cinti. – Duck Creek $1,694,200 49 points• Sharonville - Sharon Rd $250,680 45 points• Evendale - Reading Rd $487,100 45 points

$7,647,025

Page 22: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Remaining Applications

• Harrison – Harrison Avenue 40 points• Hamilton Co. – Galbraith Rd 38 points• Hamilton Co. – Hopple St Via. 36 points• Harrison – New Haven Road 34 points• Sharonville – Kemper Road 34 points• BCEO – Yankee Road 32 points• BCEO – Hamilton Mason Rd 31 points• Cinti./Hamilton Co. – BANKS 30 points

Page 23: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Resolution 2015-23 Amendment 2A (exempt projects)

Ohio Projects• Butler County - Princeton Road (Butler County Engineer)• Butler County - Liberty Fairfield Road (Butler County Engineer)• Hamilton County - SR 4 SB lane addition (Springdale)• Hamilton County - IR 75 railroad bridge replacement (ODOT)• Hamilton County - Reading Road (Evendale)• Hamilton County - Sharon Road (Sharonville)• Hamilton County - US 22 Sidewalks (DELETED) Sycamore Township

Kentucky Projects• Boone County - US 42 and KY 842 intersection (KYTC)• Kenton County - Electric Alley Pedestrian Improvements (Covington)• Kenton County - Turkeyfoot Road Sidewalks (Lakeside Park)

Transit Projects

Page 24: Special STP Application Cycle for SFY 2016 Projects ICC and Executive Committee Meetings September 2015.

Resolution 2015-24 Amendment 2B (analyzed projects)

Ohio Projects• Butler County TID – South Hamilton Crossing• Cincinnati – Duck Creek Road Extension• ODOT – IR 75 (Phases 1 and 2 of Thru the Valley)