University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji 1 This tutorial stems from the Spatial Analyst Tutorial prepared by ESRI for ArcGIS 10, but it is a simplified and a different one. It is recommended that once you have completed this tutorial, you go through the ESRI’s tutorial and further expand your understanding of the potential of Spatial Analyst. The town of Stowe in Vermont has experienced an increase of families with children and it is considering building a new school. As a citizen advocate for the public interest you are volunteering your GIS knowledge to help community organizations that represent children’s interests to propose a suitable site. To come up with some preliminary alternatives for the school site you have identified three simple criteria: 1. The new school should not be located close to existing schools 2. The new school should be located nearby recreational facilities 3. The new school should be built on suitable land use You have also collected the appropriate GIS datasets that will support these criteria (courtesy of the state of Vermont and prepared by ESRI), and you are now ready to start your analysis. It is also assumed that you have copied the folder ‘sa’ and its files and subfolders somewhere accessible. Step 0 - Enable Spatial Analyst and explore the datasets Start ArcMap and click on menu Customize>Extensions, check Spatial Analyst and close the dialog Extensions. This will load the Spatial Analyst extension. Click on menu Customize >Toolbars and check Spatial Analyst. This will add a few Spatial Analyst functions to the ArcMap interface via a new Toolbar.
17

spatial analyst

May 26, 2017

Download

Documents

sorfil
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

1

This tutorial stems from the Spatial Analyst Tutorial prepared by ESRI for ArcGIS 10, but it is a simplified and a different one. It is recommended that once you have completed this tutorial, you go through the ESRI’s tutorial and further expand your understanding of the potential of Spatial Analyst. The town of Stowe in Vermont has experienced an increase of families with children and it is considering building a new school. As a citizen advocate for the public interest you are volunteering your GIS knowledge to help community organizations that represent children’s interests to propose a suitable site. To come up with some preliminary alternatives for the school site you have identified three simple criteria:

1. The new school should not be located close to existing schools 2. The new school should be located nearby recreational facilities 3. The new school should be built on suitable land use

You have also collected the appropriate GIS datasets that will support these criteria (courtesy of the state

of Vermont and prepared by ESRI), and you are now ready to start your analysis. It is also assumed that

you have copied the folder ‘sa’ and its files and subfolders somewhere accessible.

Step 0 - Enable Spatial Analyst and explore the datasets

Start ArcMap and click on menu Customize>Extensions, check Spatial Analyst and close the dialog

Extensions. This will load the Spatial Analyst extension.

Click on menu Customize >Toolbars and check Spatial Analyst. This will add a few Spatial Analyst

functions to the ArcMap interface via a new Toolbar.

Page 2: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

2

Now click over the red button for the ArcToolbox and take a look at the Spatial Analyst functions

organized in tools and toolsets. There are approximately 170 tools. These tools are not visible if the

Spatial Analyst extension is not loaded.

Now that you have enabled the Spatial Analyst we will add the data collected for our study area.

Close Tool Box and click on button ‘Connect to Folder’ to set a connection with the folder ~\sa

under which you stored the data for this tutorial.

Click on the Add Data button (plus sign icon) and bring all the data into ArcMap. Press shift key,

highlight them all and click on Add Data.

Page 3: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

3

You have added five datasets to ArcGIS. Two of them are in a raster format called grid (elevation

and landuse). The Elevation dataset is a continuous surface grid, the Landuse dataset is a discrete

values grid. ArcGIS draws the data with random symbols. Go over each of the data layers one by

one and explore them. You may want to re-arrange them and/or change symbols and set

transparencies. But you definitely want to view the information in their attribute tables. For this:

Right-click over each layer and Open Attribute Table. Scroll through fields and records to get a feel

for the data.

Save the project in the folder sa and name it sa.mxd.

Page 4: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

4

Step 1 - Set the Analysis Environment

Click on Geoprocessing > Environments.

Click on Workspace.

For Current Workspace navigate to ‘data_sa’ and click Add then OK. This is the workspace where

the data is coming from.

For Scratch Workspace navigate to ‘outputs’ and click Add then OK. This is the workspace where

the project will by default store the new data that you will create during the tutorial.

Click over Geoprocessing > Environments >Processing Extent and for Extent pick ‘Same as layer

elevation’. Click OK.

Page 5: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

5

Click over Geoprocessing > Environments>Raster Analysis and for Cell size pick ‘Same as layer

elevation’. Click OK.

Note: All raster outputs that will be created with this project will have the same cell size as your elevation layer. The elevation grid has a larger cell size (30 meters) than the landuse grid. It is very important to recognize that setting your analysis to the layer with the smaller cell size will not improve the accuracy of your results. Remember a cell is the unit to which the data is aggregated.

Now save the project one more time and let’s try to make it look a bit nicer. We will create a hillshade or a

shaded relief of the elevation layer in your project.

Click on ArcToolbox > Surface > Hillshade

Pick Elevation from the Input raster drop down, leave the rest to defaults except for the Z factor.

Enter 0.3048 for the Z factor and click OK.

After a few seconds of watching the status bar you should see this.

Page 6: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

6

And now drag the landuse on top of the hillshade you just created. Go under its Properties and

click the tab Display. Change transparency to 30% and click OK. You should now see smth like

this.

We will not be using the Elevation or the Hillshade any further in this tutorial but they helped us

visualize the town of Stowe a bit better. We are now ready to start our analysis. Time to save the

project again.

Page 7: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

7

Step 2 – Derive new datasets

In this step we will create two new datasets: one showing distance from recreation sites and one showing

distance from schools.

Go in the ArcToolbox > Spatial Analyst Tools > Distance > Euclidean Distance.

For ‘Input raster of feature source data’ pick ‘rec_sites’, leave the rest to default, click OK and

watch the status bar. After a few seconds a new layer must have been added to your project

looking smth like this.

Now repeat the same steps to create the layer showing distance from the schools. You should get smth like

this.

Save your project.

Page 8: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

8

Step 3 – Rank the datasets

The two grids that we just created are continuous surface grids. Their symbology defaulted to 10 classes by

ArcGIS. But that is just a visual representation of the datasets. In this step we will classify these two grid

datasets into 10 spatial categories. These categories will serve as a common measurement amongst them.

Each of these categories (1 to 10) will be defined based on distance from schools or recreation sites. We

will give a value to these distance based rings based on the criteria of our project. The more suitable the

area, the higher its value. Let’s get started.

Reclass school distance grid.

Go in the ArcToolbox > Spatial Analyst Tools > Reclass > Reclassify

For ‘Input raster’ pick EucDist_scho1

For ‘Output raster’ rename the default file to: Recl_schools (you can’t name grid files with more

than 13 characters, if you ask why, the answer trails back to the precursors of ArcGIS)

Click OK and watch the Status Bar.

You will get smth like this.

Click over Properties > Symbology > Color Scheme and pick a continuous scheme that better

represents our classification. Pick it so that the darker the shade the higher the suitability value.

Page 9: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

9

Reclass recreational sites distance grid.

Go in the ArcToolbox > Spatial Analyst Tools > Reclass > Reclassify

For ‘Input raster’ pick EucDist_rec_1

For ‘Output raster’ rename the default file to: Recl_rec

Click over button ‘Reverse New Values’ (as we want higher values for rings closer to the sites)

Click OK and watch the Status Bar.

Once the new grid has been added to your project, change its symbology as you did with the

reclassed distance for schools. The darker the shade the most desirable the location.

Reclass the landuse grid.

Page 10: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

10

We will reclass the landuse based on its use designation. Go in the ArcToolbox > Spatial Analyst

Tools > Reclass > Reclassify.

For ‘Input raster’ pick landuse, for ‘Reclass field’ pick ‘LANDUSE’, for ‘Output raster’ rename the

default file to ‘Recl_land’

Highlight ‘water’ and ‘wetland’ and click button ‘Delete’.

Change New Values as shown in the dialog below.

Now check the ‘Change missing values to NoData’ to set Water and Wetland values to NoData.

Change other symbols to better represent land uses. For ex. Build up (value 3) should be orange,

forests (value 4) dark green and all else somewhere in between.

Click OK, watch for the new layer to be added and Save project.

Once the layer has been added, highlight and right-clik on it to go under Properties > Symbology

and click over button ‘Display NoData as’. Pick color white. This will be your symbol for Water and

Wetlands. Remember, the areas represented by NoData cells are excluded from overlay analysis.

Page 11: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

11

And the map should look similar to this, with Agriculture being the most suitable land use.

Page 12: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

12

Step 4 – Weight and Combine reclassed grids into one suitability map

We will now combine the three reclassified grids to find the most suitable locations. But before, let’s also

set some priorities. Not all of these datasets are equally important. The advocates that you are representing

would like to place more emphasis to proximity to recreational sites making this a more influential criterion.

Therefore, you will give the following weight (or percent influence) to your grids.

Reclassed distance to recreational sites: 0.5 (50%) Reclassed distance to existing schools: 0.2 (20%) Reclassed landuse: 0.3 (30%)

The three grids should look smth like this in your project.

Reclassed landuse Reclassed distance to recreational sites Reclassed distance to schools

Go now in ArcToolbox > Spatial Analyst Tools > Overlay > Weighted Sum

For ‘Input rasters’ bring all three grids one by one and for ‘Output raster’ rename default file name

to suitmap.

Under ‘Weight’ enter weight coefficients as shown in the dialog below and click OK.

Page 13: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

13

After the process runs and the suitability grid gets added to your project, chances are that its legend has

defaulted into lighter colors for higher values. Let’s reverse that by going under Properties > Symbology >

Color Scheme and pick a color ramp that uses darker shades for higher values (map below was created by

picking the 7th ramp in the raw, you can pick anyone you like).

As it can be seen by the legend the highest value in this grid is 9.2. Please also note that this grid is a

continuous surface grid. Try to open its attribute table. The menu ‘Open Attribute Table’ is disabled.

We will now select out only those areas (cells) that have a value of 9 - 9.2.

At the Spatial Analyst toolsets go under Map Algebra > Raster Calculator.

Build the query as shown in the Raster Calculator dialog below, rename default output file to

‘topsuitmap’ and click OK.

suitmap

High : 9.2

Low : 3.4

Page 14: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

14

Once a new grid has been added, change its symbol for value 0 to a hollow symbol and its symbol for value

1 to red (double click on symbol). The red area now shows the top suitable locations.

Although we see graphically where the best locations are, we do not know at this point whether there is

enough land to build a school. Our next steps are about finding just that.

Highlight/Right-click over the layer ‘topsuitmap’ and open it’s Attribute Table. You can now see that

the menu ‘Open Attribute Table’ is enabled, which means that the grid is a discrete grid.

In the attribute table the field Count stores the number of cells with a particular value. We see that

we have 1,971 cells in the red area. But what does this mean?

We know that the cell size of our Analysis Environment is 30 meters x 30 meters (to double check, go

under the tab Source of the Properties of the layer ‘elevation’). This means that each cell has an area of

900 square meters. By multiplying cell counts with the area of one cell we can find our total area. We will

now add a new field to the attribute table to calculate and store the total area.

Click over the top left button of your Table dialog and click on Add field menu.

Page 15: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

15

In the Add Field dialog, enter Acres for Name, pick Long Integer for Type and click OK.

Right click over the new field Acres and click over Field Calculator.

Enter the expression shown in the dialog below to calculate area in square meters and click OK.

Page 16: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

16

Right click again over the field Acres and click over Field Calculator. You will now convert square meters to

Acres knowing that 1 square meter = 0.000247105381 acres.

This time enter the expression: [ACRES] *0.000247105381 and click OK.

We can now see that there are 438 acres in the red area.

Let’s now zoom in closer to the red area. We can see that some of the cells are not contiguous and

therefore will not be of much use to us. So our next and last step in this project is to try to filter out as much

as we can the scattered small areas that are represented by one, two or more cells.

At the Spatial Analyst toolsets go under Generalization > Majority Filter. This function replaces cells

based on the majority value in their immediate surrounding cells. If one of our red cells is

surrounded mostly be cells with a lower value, this means that we do not much need that cell for

our school (too small area) and that we can safely assign it the same value as the majority of the

surrounding cells.

For Input Raster pick ‘topsuitmap’, for Output Raster rename default file name to ‘lastsuitmap’.

For Number of neighbors to use, pick FOUR, for Replacement threshold pick HALF.

Click OK.

Page 17: spatial analyst

University of Florida, School of Landscape Architecture and Planning, URP4273, Prepared by Juna Papajorgji

17

After the ‘lastsuitmap’ grid is added to the project, as you did with the ‘topsuitmap’, change its symbology to

look similar to the map below.

You can now see how we eliminated most of the scattered cells. Please note that this process can be

repeated again with the yellow areas to eliminate some more scattered cells. You can also look at the

attribute table of the ‘lastsuitmap’ grid (yellow area) to see the acreage we lost as compared to the

‘topsuitmap’ grid.

At this point your job as a GIS professional is done. This is just a preliminary stage in the process of

locating a new school. Site specific analysis will now be conducted by urban planners and then public

participation will be sought prior to making a final decision.

This tutorial ends here, but your work should continue. A useful follow up exercise could be to automate

this entire process via the Model Builder. The Model Builder can convert the sequences in this process into

a model. Once you have built a model, you can easily rerun this entire process with new data (when you

find better ones), with modified variables (such as for the weight and classes that we used), and you can

therefore optimize your results and/or also offer several alternate results for consideration.