Top Banner
SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 1 ITT PS08037 Versacon Consultants Inc. / 162178 June 2008 1 GENERAL 1.1 Work Included .1 This Division is to be read in conjunction with Instructions to Bidders, General Conditions, Supplementary Conditions and Division 1 - General Requirements 1.2 Drawings and Specifications .1 The intent of the drawings and specifications is to include all labour, products and services necessary for complete work, tested and put in operation. .2 The drawings and specifications are complementary, and what is required by any one is as binding as if required by all. .3 All mechanical drawings are diagrammatic and indicate the general arrangement of systems and work included. Do not scale the drawings. Consult the Architectural and Piping Drawings and details for exact location of fixtures and equipment. .4 Follow drawings as closely as possible in layout work and check drawings of all other trades to verify spaces in which work will be installed. .5 If directed, make without extra cost, reasonable modifications in the layout as needed to prevent conflicts with work of other trades, or for proper execution of the work as required to suit on-site job conditions. .6 If discrepancies or omissions in the drawings or specifications are found, or if intent or meaning is not clear, advise the Consultant for clarification before submitting tender. .7 When clarification has not been obtained or confirmed by addendum the tenders will be presumed to be based upon the interpretation that may be subsequently given by the Consultant after award of contract, in accordance with the provisions of the contract. 1.3 Quality Assurances .1 Regulatory Requirements .1 Conform to the requirements and recommendations of the 2007 City of Vancouver Building By-Law, and the City of Vancouver Plumbing Code, 2007 edition. .2 Do not reduce the quality of work specified and/or shown on the drawings because of the regulatory requirements. .2 Permits, Fees and Certificates .1 Give all necessary notices, obtain and pay for all permits, governmental fees, taxes and other costs in connection with the work, file all necessary drawings, prepare all documents and obtain all necessary approvals of all regulatory bodies having jurisdiction. .2 Obtain all required Certificates of Inspection for the work and deliver same to the Consultant before request for acceptance and final payment for the work. Correct
173

southeast false creek energy center section 15010

Mar 30, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Work Included

.1 This Division is to be read in conjunction with Instructions to Bidders, General Conditions, Supplementary Conditions and Division 1 - General Requirements

1.2 Drawings and Specifications

.1 The intent of the drawings and specifications is to include all labour, products and services necessary for complete work, tested and put in operation.

.2 The drawings and specifications are complementary, and what is required by any one is as binding as if required by all.

.3 All mechanical drawings are diagrammatic and indicate the general arrangement of systems and work included. Do not scale the drawings. Consult the Architectural and Piping Drawings and details for exact location of fixtures and equipment.

.4 Follow drawings as closely as possible in layout work and check drawings of all other trades to verify spaces in which work will be installed.

.5 If directed, make without extra cost, reasonable modifications in the layout as needed to prevent conflicts with work of other trades, or for proper execution of the work as required to suit on-site job conditions.

.6 If discrepancies or omissions in the drawings or specifications are found, or if intent or meaning is not clear, advise the Consultant for clarification before submitting tender.

.7 When clarification has not been obtained or confirmed by addendum the tenders will be presumed to be based upon the interpretation that may be subsequently given by the Consultant after award of contract, in accordance with the provisions of the contract.

1.3 Quality Assurances

.1 Regulatory Requirements

.1 Conform to the requirements and recommendations of the 2007 City of Vancouver Building By-Law, and the City of Vancouver Plumbing Code, 2007 edition.

.2 Do not reduce the quality of work specified and/or shown on the drawings because of the regulatory requirements.

.2 Permits, Fees and Certificates

.1 Give all necessary notices, obtain and pay for all permits, governmental fees, taxes and other costs in connection with the work, file all necessary drawings, prepare all documents and obtain all necessary approvals of all regulatory bodies having jurisdiction.

.2 Obtain all required Certificates of Inspection for the work and deliver same to the Consultant before request for acceptance and final payment for the work. Correct

Page 2: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

installed work as directed by the local Authorized Inspector of the Regulatory body without cost to the Owner.

.3 Standard of Workmanship

.1 Execute all work in a competent manner and present an acceptable appearance when completed.

.2 Employ a competent supervisor to facilitate completion of the work in the required time.

.3 Employ tradesmen fully qualified under Provincial and Municipal Regulations pertaining to the licensing and qualifications of tradesmen for this work.

.4 Arrange and install products to fit properly into designated building spaces.

.5 Unless otherwise specified as shown, install products in accordance with recommendations and ratings of manufacturers.

1.4 Examination

.1 Examine drawings relating to work of all trades and become fully informed as to extent and character of work required and its relation to all other work in project.

.2 Before submitting bid, visit the site and examine the site and space conditions on which the work is in any way dependent for the best workmanship and operation according to the intent of specifications and drawings. Report to the Consultant any conditions that might prevent installing the equipment in the manner intended.

.3 No consideration or allowance will be made for failure to visit the site, or for any alleged misunderstanding of materials to be furnished or work to be done; it being agreed that tender carries with it agreement of items or conditions referred to herein or indicated on the aforementioned drawings.

1.5 Shop Drawings

.1 After receiving approval of Equipment Manufacturers prior to delivery of any material to job site; after the Contractor has previously reviewed stamped and signed same; and sufficiently in advance of requirements six (6) copies of cuts, brochures and charts showing construction, size, arrangement, operating clearance, performance characteristics and capacity of materials and equipment.

.2 Shop drawing review by the Consultant is solely to ascertain conformance to the general design concept. Consultant’s comments are in red.

.3 Responsibility for approval of detail design inherent in shop drawings rests with the Contractor and review by the Consultant shall not imply such approval. Review shall not relieve the Contractor of his responsibility for errors or omissions in shop drawings or for proper completion of the work in accordance with the Contract Documents.

.4 Responsibility for verification and correlation of field dimensions, fabrication processes, techniques of construction and installation and co-ordination of all parts of the work rests with the Contractor.

Page 3: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.5 Notify the Consultant in writing of any deviations in shop drawings from the requirements of the Contractors.

.6 After submittals are stamped “Reviewed” further revisions are not permitted unless resubmitted to the Consultant for further review.

1.6 Project Record Drawings

.1 See Division 1 “Record Documents” for Record Drawing requirements.

.2 Obtain one (1) set of white prints. As the job progresses, mark prints to accurately indicate installed work. Have these prints available for reference at the site.

.3 Prepare record drawings showing the following:

.1 Dimensioned location of all services embedded in the structures.

.2 Dimensioned location of all services left for future work.

.3 All changes to the work due to Change Orders.

.4 All Addendum changes.

.5 All changes to the work during construction.

.6 Location and designation of all items requiring access or service in a hidden location.

.4 Upon completion of the Contract, the Contractor shall submit all marked “As-Built” drawings to the Consultant. The consultant will transfer the “As-Built” information on to AutoCAD drawings for submittal to the Owner.

.5 Final payment will not be made until acceptable project record drawings have been filed with the Consultant.

1.7 Operation

.1 Make available a competent mechanic responsible for the operation of the system and for the instruction of such members of the Owner’s staff as may be designated with regard to the proper operating procedure of all equipment and apparatus forming a part of the system. Allow for a half-day on-site instruction period.

1.8 Maintenance Manuals

.1 See Division 1, Operating and Maintenance Data, for a description of the manual requirements, preparation instructions and binding instructions.

.2 Furnish three printed, indexed, hardbound copies of detailed and complete operating and maintenance instructions for all mechanical equipment and systems installed. Only such information as appears on these printed instructions shall be assumed to have been given to the operating staff. Have the Equipment Manufacturers, Controls Subcontractor, and Commissioning Agent approve these instructions.

Page 4: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

Binder shall be ACCO Canadian Co. Ltd. ACCORING "Customizer" #13401 Binder 216 mm x 275 mm beige, 25 mm, or approved equal.

In addition, provide three copies of CD-ROM’s that contain the complete maintenance manual. The CD-ROM data shall be in Adobe Acrobat or other approved legible format. The data shall be indexed for easy access.

.3 A preliminary copy of the manuals shall be supplied and submitted for approval to Consultant not later than ten (10) working days prior to Substantial Performance. The final manuals shall be supplied prior to the demonstration of the systems to the Owner’s personnel.

.4 Each manual shall contain the following as common requirements:

.1 The manual shall include component and system descriptions, parts lists, maintenance procedures, sequence of operation, wiring schematics and such other relevant information to assist the owner in performing routine maintenance work.

.2 Provide a comprehensive description of the operation of all systems including the function of each item of equipment within a system. Write the description specifically for this project. Provide separate descriptions for heating, ventilating, refrigeration systems, etc. Provide a flow and functional diagram for each system.

.3 Provide as input information to the Owner's computerized Preventative Maintenance System, all P.M. routines and schedules in a separate section of the manual. Reference each task to the specific Equipment Specification Sheet. Information shall include but not limited to:

.1 Description of a daily, weekly, monthly, yearly routine for all systems and significant components.

.2 List of special tools where required.

.3 Statement of the levels of acceptable performances and the range of deterioration. This should apply only in areas that are relevant.

.4 State any hazard to which a tradesman may be exposed when performing PM tasks.

.4 Local source of supply for each item of equipment.

.5 Location of major pieces of equipment.

.6 Operating electrical switchgear schedule with location of each item stated. Include the manufacturer, model and size.

.7 Lubrication schedules and recommended lubricants for all equipment listed.

.8 Equipment drive belt schedule.

.9 Guarantees, warranties and bonds showing:

.1 Name and address of project.

Page 5: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Guarantee commencement date.

.3 Duration of guarantee.

.4 Clear indication of what is being guaranteed and what remedial action will be taken under the guarantee.

.5 Signature and seal of the Contractor

.10 Labeling and identification schedules.

.11 Valve schedule, including location, service, normal position plus location of servicing access panels.

.12 List of all equipment including manufacturer's parts lists, disassembly and reassembly instructions where applicable.

.13 Provide performance curves for all drive motors with indication of the operating point or range.

.14 Provide description of the non-BMS HVAC automatic control systems with approved control diagrams indicating the final control point settings and/or schedules.

.15 Provide a schedule of all verifications or inspections that are to be performed by the Controls Sub-trade during the warranty period. List what is to be done and the approximate time schedule.

.16 Provide integrated wiring diagrams for the mechanical systems. Also include all interlocks and wiring diagrams of purchased equipment.

.17 Include completed Equipment Specification Sheets.

.18 Include reports, inspection certificates, affidavits such as:

.1 Air duct systems balancing report.

.2 Water system balancing report.

.3 Chemical cleaning and treatment report for piping systems.

.4 Air handling and exhaust systems cleaning affidavit.

1.9 Warranty

.1 Refer to "Warranty" in the General Conditions.

.2 The Warranty period shall not be shortened, nor the terms altered, due to the use of the Owner's equipment during construction.

1.10 Temporary Use of Equipment

.1 Make written application for approval to the Consultant for use of the Owner's equipment for any reason prior to the date of Substantial Performance.

Page 6: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 6

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1.11 Fire Separations

.1 Conform to the following requirements to maintain the continuity of fire separations, whether or not shown on the drawings.

.2 Combustible construction that abuts on or is supported by a non-combustible fire separation shall be constructed so that its collapse under fire conditions will not cause the collapse of the fire separation.

.3 Combustible members, fastenings, and the like shall not be used to anchor equipment to a fire separation.

.4 Openings for non-combustible pipes or ducts shall be tightly fitted or fire stopped to prevent the passage of smoke or flame. Be responsible for ensuring that where work passes through a fire separation, the opening shall be plugged with a ULC labeled and approved fire-stopping sealant system to maintain the integrity of the fire separations.

2 PRODUCTS

2.1 Quality of Materials

.1 Furnish new materials, apparatus or products required for the work, of first class quality, delivered, erected, connected up and finished in every detail.

.2 Unless otherwise specified, all products are CSA approved.

.3 All fire protection materials, apparatus or products are approved.

.4 If materials, apparatus or products are not CSA or UL approved, obtain approval of the Authority Having Jurisdiction prior to installation. Pay all applicable charges levied and make all modifications required for approval.

2.2 Specified Equipment Deviations and Approvals

.1 Base all bids on the equipment and material specified. Should bidder desire to use equipment or material of a make other than those specified or approved equal, they shall submit a report in writing at least seven (7) working days prior to close of tenders. An addendum listing any further approved manufacturers will be issued by the Consultant prior to closing of tenders. Propose only standard catalogue products of established manufacturers, of equal quality, finish and durability to those specified.

.2 A bidder may propose the use of equipment not listed in the Approval List, but the tender price must be based on equipment as listed in the Approval List. The Contractor shall show the difference in price between the approved equipment and the proposed equipment as an "Alternate Price".

2.3 Control System Wiring

.1 As applicable, the Contractor is responsible for all control wiring and connections (120 Volt and less) including those between line voltage temperature and humidity controls, safety, limiting and other devices directly related to starters, holding coils, auxiliary contractors, interlocks, relays, etc., as required for the performance of control system and sequence of operation all as specified.

Page 7: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 7

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Provide all wiring and conduit in accordance with the relevant Electrical Codes and in accordance with Division 16, and in no case smaller than #12 AWG for 110 Volt wiring and above.

2.4 Specified Equipment Deviations and Approvals

.1 Base all bids on the equipment and material specified. Should bidder desire to use equipment or material of a make other than those specified or approved equal, they shall submit a report in writing at least seven (7) working days prior to close of tenders. An addendum listing any further approved manufacturers will be issued by the Consultant prior to closing of tenders. Propose only standard catalogue products of established manufacturers, of equal quality, finish and durability to those specified.

.2 A bidder may propose the use of equipment not listed in the Approval List, but the tender price must be based on equipment as listed in the Approval List. The Contractor shall show the difference in price between the approved equipment and the proposed equipment as an "Alternate Price".

2.5 Mechanical Equipment Approval List

.1 The following is a list of manufacturers whose products are approved for installation in the work, providing the product chosen meets with the design characteristics and features of the item where a particular trade name and model is given and installation is described. Conform to space limitations on products which are approved as equal in design characteristics.

(Items marked with an asterisk [*] require shop drawings.)

.2 GENERAL

.1 Piping Hangers

.1 Grinnell, Myatt

.2 Gate, Globe, Check, Ball, Plug Valves

.1 Crane, Jenkins, Toyo, Red-White, Nibco, Rockwell, Kitz, Apollo

.3 Mechanical Joints

.1 Victaulic

.4 *Access Doors

.1 Acudor, Milcor, Maxam, Mifab

.5 *Water Pressure Reducing Valves

.1 Watts

.6 Pressure Gauges

.1 Trerice, Marsh, Weksler, Weiss

Page 8: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 8

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.7 Thermometers

.1 Trerice, Marsh, Weksler, Weiss

.8 *Pumps

.1 Armstrong, Bell and Gossett, Grundfos

.9 Balancing Valves

.1 Armstrong, Tour & Andersson, Bell & Gossett

.3 NOISE, VIBRATION, AND SEISMIC CONTROL

.1 *Vibration Isolation

.1 Mason, Vibron, Vibro-Acoustics, Vibrex, CalDyn, Amber Booth, Korfund

.2 Flexible Duct

.1 Thermaflex, Wiremold

.3 *Pipe Restraints

.1 Trelleborg

.4 HEATING & VENTILATING

.1 *Fire Dampers

.1 Ruskin, Nailor Industries, National Controlled Air

.2 *Grilles, Registers, Diffusers

.1 Price, Titus, Nailor-Hart

.3 *Duct Sealant

.1 Flexmaster, Multi-Purpose, Robson's Duct Seal, Ticki-Tuff

.4 Flexible Duct

.1 Thermaflex, Wiremold

.5 Air Handling Units

.1 Trane, McQuay, Engineered Air

.6 *Coils

.1 McQuay, Trane, Carrier, Engineered Air, Witt, York

.7 *Air Filters

Page 9: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 9

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.1 Camfil Farr, A.A.F

.8 *Water Treatment

.1 Grace Dearborn, Pace

.9 Air Vents

.1 Hoffman, Maid-O-Mist, Taco

.10 *Fans

.1 Loren Cook, Greenheck, Penn

.11 *Roof, & Inline Fans

.1 Loren Cook, Penn, Delhi, Greenheck

.12 *Centrifugal Fans

.1 Northern Blower, Twin City, Greenheck, Trane, Chicago, Loren Cook

.13 *Louvres

.1 Airolite, Penn Airstream, West Vent, Alumavent, Ruskin, Nailor Industries

.14 *Silencers:

.1 VAW, Woods, Vibron, Vibro-Acoustics, Wisp-Air

.15 *Electric Heaters:

.1 Ouellet, Chromalox

.5 PLUMBING

.1 Stops

.1 Dahl, Brasscraft, Watts

.2 *Floor Drains, Hose Bibbs

.1 Zurn, Ancon, Enpoco, Mifab Clean-outs, Trap Primers, Water Hammer Arrestors Roof Drains

.3 *Backflow Preventers

.1 Watts, Febco, Cla-Val, Beeco

.4 *Plumbing Brass

.1 Teck (Cambridge Brass)

Page 10: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 10

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.5 *S. S. Sinks

.1 Aristaline, K.I.L., AMI

.6 *Fixtures

.1 Caroma, Crane, American Standard

.7 *Toilet Seats

.1 Caroma, Moldex, Olsonite, Beneke, Centoco

.8 *Mixing Valves

.1 Powers, Symmons, Acorn

.9 *Thermostatic Mixing Valves

.1 Lawler

3 EXECUTION

3.1 Co-ordination

.1 Give full co-operation to those doing work under other contracts and furnish in writing, with copies to the Consultant, any information necessary to permit the work of other contracts to be installed satisfactorily and with least possible interference or delay.

.2 If work is installed before co-ordination with other trades or so as to interfere with work of other trades, make necessary changes in the work to correct the conditions without extra charge.

3.2 Accessibility

.1 Locate all equipment which must be serviced, operated or maintained in fully accessible positions, with minimum interference and maximum usable space. Make minor deviations from drawings to allow for better accessibility, but obtain prior approval for changes of magnitude or changes involving extra cost.

.2 Be responsible for supplying and installing all access panels in the ceiling, wall, partitions, etc., where openings are necessary for the proper servicing or removal of equipment covered by these drawings and specifications. Construct panels of metal and of the type required by the construction of the ceilings, walls, partitions, etc., in which they are located. Access panels shall be fire rated when installed in fire separations. Determine the location subject to the approval of the Consultant. Access panels are specified in Section 15050.

3.3 Scaffolding, Rigging, Hoisting

.1 Furnish all scaffolding, rigging and hoisting necessary for erection of any equipment and apparatus.

.2 Take precautions not to overload the structure in any manner nor provide inadequate scaffolding and rigging so as to endanger the safety of personnel on the site whether under this Contractor's employ or otherwise.

Page 11: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15010 AND SEWAGE PUMP STATION BASIC MECHANICAL REQUIREMENTS PAGE 11

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

3.4 Cutting & Patching

.1 Furnish and locate all sleeves and inserts required before the floor and walls are built, or be responsible for the cost of the cutting and patching required or for pipes where sleeves and inserts were not installed, or where incorrectly located, or where they have to be relocated due to conflict with other parts of the overall project.

.2 Do not cut structural members without the prior approval of the Consultant.

3.5 Waterproofing

.1 Obtain approval for the installation method employed where any work pierces waterproofing concrete and waterproofing. Furnish all necessary grout rings, sleeves, caulking, counter flashing and flashing required to make openings through walls, floors, etc., absolutely watertight. This applies to, but is not restricted to ducts, grilles, pipes, etc.

3.6 Protection

.1 Protect the work and material of all other Sections from damage and make good all damage thus caused, to the satisfaction of the Consultant.

3.7 Cleaning

.1 Any dirt, rubbish, or grease on walls, floors or fixtures for which this Division is responsible must be removed and the premises left in first class condition in every respect.

.2 Clean all mechanical piping and equipment and leave in a condition to receive paint.

3.8 Painting

.1 Painting, if any, and unless otherwise specified, shall be by the Painting Contractor.

.2 All equipment to be factory primed and painted before being shipped to the site. Make good all damage to factory finish prior to acceptance and in general this means a complete repaint over the factory finish. Unmatched patching is not acceptable.

.3 Be responsible for advising the Painting Contractor as to the colours of the piping, etc.

3.9 Equipment Lubrication

.1 Maintain equipment placed in operation before the completion of the contract and adequately lubricate in accordance with the Manufacturer's Instructions.

.2 Make the lubricating and oiling positions for all equipment supplied and installed under this Division fully accessible.

.3 Before the system is accepted, re-lubricate all equipment in accordance with the Manufacturer's Instructions.

END OF SECTION

Page 12: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15050 AND SEWAGE PUMP STATION BASIC MECHANICAL MATERIALS AND METHODS PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Scope of Work

.1 Execute all work and furnish all products as specified herein and in accordance with the contract documents.

1.2 Work Included

.1 Access Doors

.2 Hangers and Supports

.3 Valves, Strainers, Air Vents

.4 Motors

.5 Pressure Gauges and Thermometers

1.3 Welding

.1 All welding must be done in accordance with the regulations of the Boiler Inspection Branch. All field welding must be in accordance with the procedures of CSA-W55.3-1965 and CSA-W117.2-94 and the current edition of ASME Code for Power Piping.

.2 Welding must be performed by welders fully qualified and licenced by Provincial Authorities.

2 PRODUCTS

2.1 Pipe Hangers

.1 Use adjustable pipe rolls with pipe or washer spacers on exposed threaded stands for all piping supported from below.

.2 Use adjustable swivel solid ring type hangers for pipes up to 40 mm (1 1/2"). Use adjustable wrought clevis type hangers for pipes 50 mm (2") to 75 mm (3") diameter. Use adjustable swivel roller type for pipes 100 mm (4") and over.

.3 Use the following schedule of hanger rods:

.1 10 mm (3/8") rod for pipes up to 50 mm (2") diameter

.2 12 mm (1/2") rod for 65 mm (2 1/2") and 75 mm (3") diameter

.3 16 mm (5/8") rod for 100 mm (4") diameter

.4 20 mm (3/4") rod for 150 mm (6") diameter

.5 22 mm (7/8") rod for 200 mm (8") to 300 mm (12") diameter

.4 Unless specifically noted otherwise on the drawings, support all piping with hangers spaced as follows:

Page 13: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15050 AND SEWAGE PUMP STATION BASIC MECHANICAL MATERIALS AND METHODS PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.1 2.1 m (7 feet) for piping - 32 mm (1 1/4") diameter and smaller

.2 3.0 m (10 feet) for piping – 40 mm (1 1/2") diameter to 65 mm (2 1/2") diameter

.3 3.6 m (12 feet) for piping – 75 mm (3") diameter and larger

.5 Provide all auxiliary supporting steel and accessories for hanger installation to facilitate connection to the structural steel members provided by other trades.

.6 Apply 2 coats of primer paint on all unpainted hanger hardware and supporting steel and leave in a condition to receive paint.

.7 For seismic bracing and support of pipes, see Section 15070, Seismic Control.

.8 Install hanger rods vertical without bends or offsets such that finished piping is aligned correctly both with respect to line and grade.

.9 Where groups of pipes are run together, a fabricated hanger may be used with separate rolls for each pipe.

.10 Secure all hanger rods directly to the building structure by means of inserts or clamps. Do not support from other pipes and ducts. Give all hangers and rods, etc., two heavy coats of primer paint before concealing.

.11 Support vertical piping at its base by hangers placed as near as possible to the horizontal pipe to which it is connected.

Provide supports at each floor using iron brackets and pipe clamps. Use 10 mm (3/8") MS plates as pads or anchored into vertical concrete for connections of brackets on floor levels.

.12 Use pipe saddles in conjunction with all pipe supports on insulated piping with the exception of pipe where insulation includes a vapour barrier.

.13 See Section 15080 for support of piping where insulation includes a vapour barrier.

2.2 Strainers

.1 Strainers 50 mm (2”) and under shall be screwed ends Red & White, Toyo Figure 380, Kitz 15, 1034 kPa Y pattern body, stainless steel screen.

.2 Strainers over 50 mm (2”) shall be flanged ends Red & White, Toyo Figure 381A, Kitz 80, 1034 kPa Y pattern body, stainless steel screen 3 mm (1/8") perforations and minimum 20 mm (3/4") gate valve and cap installed on drain fitting.

2.3 Air Vents

.1 Furnish air vents complete with air chambers and isolating valves to properly vent all systems and equipment as indicated and as specified herein. Arrange vents to vent all high points in the system. Connect all vents to the nearest accessible drain with 6 mm (1/4") or 5 mm (3/16") (depending on the size of the vent) copper tubing. Carry the vent drain lines to the nearest accessible drain and label as to the vent they serve.

.2 Use manual key operated vents on radiation, and radiant panels.

Page 14: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15050 AND SEWAGE PUMP STATION BASIC MECHANICAL MATERIALS AND METHODS PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.3 Automatic air vents shall be Maid-O-Mist No. 75 installed with isolating gate valve, 1034 kPa (150 psi) water rating.

.4 Air vents shall be installed to properly vent all systems, equipment, unit heaters, convectors and radiant panels.

2.4 Access Doors

.1 Provide access doors for the servicing of balance dampers, valves and equipment and to give access to pipe cleanouts as required and/or shown.

.2 Access doors to be constructed from 2.7 mm steel and be complete with concealed spring hinge and a screwdriver cam lock. All doors to be installed flush with the finished walls and/or ceilings.

.3 Access doors installed in tile finishes to be polished stainless steel. Access doors installed in plaster, drywall or cement finishes to be prime coated.

.4 Access doors sizes to be 300 mm x 300 mm (12”x12”) for hand access and 450 mm x 600 mm (18”x18”) for entry access unless otherwise noted on drawings or specified elsewhere.

.5 Access doors in fire rated walls or ceiling assemblies shall be fire-rated to match or exceed the rating of the wall or ceiling.

.6 Access doors shall be equal to Mifab UA with internal angle bracket.

2.5 Hangers & Supports

.1 Furnish all hangers, supporting steel, etc., for the mounting and hanging of all mechanical equipment supplied unless otherwise specified.

.2 Size supports, hangers, etc., suitable for supporting the weight of the equipment without subjecting the building structure or the supports to undue stress.

.3 Use new materials only for supporting steel, free of rust, installed in a workmanlike and neat manner. Prime hangers, rods and support steel and leave in a condition to receive paint. Instead of prime coating, rods may be cadmium plated and hangers may be galvanized.

2.6 Valves

.1 Where possible, valves are to be of one manufacturer, with manufacturer's name, pressure rating and size clearly marked on body.

.2 Use O.S. & Y. design on all valves 100 mm (4") and larger unless specifically noted otherwise.

.3 Provide valves with hand wheels accessible for operation.

.4 Valves on domestic and process hot and cold water service piping to be as follows:

.1 Ball Valves - 1034 kPa (150 psi) for shut-off.

.1 Solder end 50 mm (2”) and smaller - Red-White 5049A, Kitz 58.

Page 15: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15050 AND SEWAGE PUMP STATION BASIC MECHANICAL MATERIALS AND METHODS PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Screwed ends 50 mm (2”) and smaller - Red-White 5044A, Kitz 59.

.3 Provide memory stop when used for balancing.

.2 Gate Valves - 860 kPa (125 psi) for shut-off.

.1 Flanged ends 65 mm (2-1/2”) and larger - Red & White, Toyo 421A, Kitz 72.

.3 Globe Valves - 860 kPa (125 psi) for throttling, by-pass and make-up.

.1 Solder ends 50 mm (2”) and smaller - Red & White, Toyo 212, Kitz 12

.2 Screwed ends 50 mm (2”) and smaller - Red & White, Toyo 220, Kitz 03.

.3 Flanged ends 65 mm (2-1/2”) and larger - Red & White, Toyo 400A, Kitz 76.

.4 Check Valves - 860 kPa (125 psi) for horizontal installation.

.1 Screwed ends 50 mm (2”) and smaller - Red & White, Toyo 236, Kitz 22.

.2 Flanged ends 65 mm (2-1/2”) and larger - Red & White, Toyo 435A, Kitz 78.

.5 Balancing Valves - 1720 kPa (250 psi) - Armstrong CBV / Tour and Anderson.

.6 Pressure Reducing Valves - 860 kPa (125 psi), see drawings for capacities.

.1 50 mm (2”) and smaller - Watts, Singer.

.2 65 mm (2-1/2”) and larger - Clayton, Singer.

.5 Valves on heating water piping to be as follows:

.1 Ball Valves - 1034 kPa (150 psi) for shut-off.

.1 Solder end 50 mm (2”) and smaller - Red-White 5049A, Kitz 58.

.2 Screwed ends 50 mm (2”) and smaller - Red-White 5044A, Kitz 59.

.3 Provide memory stop when used for balancing.

.2 Gate Valves, NPS 2-1/2 to 12: Flanged iron body, bronze trimmed and bolted bonnet, Kitz 72, Toyo 421A

.3 Plug Cocks, NPS 1/2 to 2: Class 150 150 psi bronze, lubricated plug cocks, screwed, Rockwell 614.

.4 Swing Check Valves, NPS 1/2 to 2: Class 125 125 psi bronze body, screwed ends, swing disc, screw in cap, bronze disc, regrindable seat, Kitz 22, Toyo 236.

.5 Swing Check Valves, NPS 2-1/2 to 12: Class 125, 125 psi cast iron body, F.F. flanged, renewable seat, bronze disc, bolted cap, Kitz 78, Toyo 435A.

Page 16: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15050 AND SEWAGE PUMP STATION BASIC MECHANICAL MATERIALS AND METHODS PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.6 Swing Check Valves, NPS 2 to 4: Class 125, 125 psi grooved end, malleable or ductile iron body, aluminum bronze, or stainless steel discs, stainless steel spring, stainless steel shaft, EPDM seat, Victaulic 712, Mueller "LocXend" 74G.

.7 Silent Check Valves, NPS 1/2 to 2: Class 125, 125 psi, bronze body, screwed ends, brass seat ring, brass inner valve, S.S. spring (heavy duty spring in vertical down flow application), Singer 475, Apollo 61-100.

.8 Silent Check Valves, NPS 2-1/2 to 12: Class 125, 125 psi, high tensile iron or semi-steel body, flanged ends, bronze trim, S.S. spring (heavy duty spring in vertical down flow application), Singer 480 to NPS 3, Singer 485 for NPS 4 to 12, Mueller 105 MAP.

.9 Balancing Valves - 1720 kPa (250 psi) - Armstrong CBV / Tour and Anderson.

.6 Valves on chilled water piping to be as follows:

.1 Ball Valves - 1034 kPa (150 psi) for shut-off.

.1 Solder end 50 mm (2”) and smaller - Red-White 5049A, Kitz 58.

.2 Screwed ends 50 mm (2”) and smaller - Red-White 5044A, Kitz 59.

.3 Provide memory stop when used for balancing.

.2 Gate Valves, NPS 1/2 to 2: Threaded bronze body, rising stem solid wedge, Kitz 24, Toyo 293

.3 Gate Valves, NPS 2-1/2 to 12: Flanged iron body, bronze trimmed and bolted bonnet, Kitz 72, Toyo 421A

.4 Globe Valves, NPS 1/2 to 2: Threaded bronze body, screwed over bonnet, renewable composition disc, Kitz 09, Toyo 221.

.5 Globe Valves, NPS 2-1/2 to 12: Flanged cast iron body, bronze trim, OS&Y bolted bonnet, bronze disc and seat ring, Kitz 76, Toyo 400A.

.6 Butterfly Valves, NPS 2-1/2 to 12: Class 150, semi-steel body with stainless steel or bronze disc an stainless steel stem replaceable rubber seat, wafer body, loccking handle, gear operators over NPS 6, DeZurik 632W, Victaulic Series 700, Kitz 6122EL, Kitz 6122EG, Mueller "LocXend" 59G.

.7 Plug Cocks, NPS 1/2 to 2: Class 150 150 psi bronze, lubricated plug cocks, screwed, Rockwell 614.

.8 Swing Check Valves, NPS 1/2 to 2: Class 125 125 psi bronze body, screwed ends, swing disc, screw in cap, bronze disc, regrindable seat, Kitz 22, Toyo 236.

.9 Swing Check Valves, NPS 2-1/2 to 12: Class 125, 125 psi cast iron body, F.F. flanged, renewable seat, bronze disc, bolted cap, Kitz 78, Toyo 435A.

.10 Swing Check Valves, NPS 2 to 4: Class 125, 125 psi grooved end, malleable or ductile iron body, aluminum bronze, or stainless steel discs, stainless steel spring, stainless steel shaft, EPDM seat, Victaulic 712, Mueller "LocXend" 74G.

Page 17: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15050 AND SEWAGE PUMP STATION BASIC MECHANICAL MATERIALS AND METHODS PAGE 6

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.11 Silent Check Valves, NPS 1/2 to 2: Class 125, 125 psi, bronze body, screwed ends, brass seat ring, brass inner valve, S.S. spring (heavy duty spring in vertical down flow application), Singer 475, Apollo 61-100.

.12 Silent Check Valves, NPS 2-1/2 to 12: Class 125, 125 psi, high tensile iron or semi-steel body, flanged ends, bronze trim, S.S. spring (heavy duty spring in vertical down flow application), Singer 480 to NPS 3, Singer 485 for NPS 4 to 12, Mueller 105 MAP.

.13 Balancing Valves - 1720 kPa (250 psi) - Armstrong CBV / Tour and Anderson.

2.7 Pressure Gauges and Thermometers

.1 As applicable, furnish pressure gauges on both the upstream and downstream side of all pumps, chiller evaporator and chiller condenser inlet and outlet and where shown on the drawings.

.2 Pressure gauge characteristics:

.1 Gauges, Bourden tube type constructed with phosphor bronze tube silver soldered to socket and tip or low pressure bellows type as required for special applications.

.2 Gauges, accurate to 1% of the scale range.

.3 Movement, stainless steel rotary type with nickel silver shaft and pinion gear.

.4 Pointer black finished brass, micrometer type. Face, enamel white with black numerals.

.3 All pressure gauges, installed with bar stock needle design isolation valves and snubbers, suitable for service pressure.

.4 Dial size 100 mm (4") diameter.

.5 Scale range to suit particular application, normal operating pressure to read 50% of full scale.

.6 Dual PSI and kPa reading scale.

.7 Turret type polypropylene case with threaded bezel ring and unbreakable glass.

.8 Provide oil filled gauges in corrosive atmospheres and/or severe vibrating conditions.

.9 As applicable, furnish thermometers on both the entering and leaving side of all mixing valves, heat exchangers, chilled water supply and return, condenser water supply and return piping.

.10 Thermometer characteristics:

.1 Dial size 100 mm (4”) diameter with double strength glass window.

.2 Adjustable brass pointer and movement, copper bulb and cast aluminum casing.

.3 Medium and range to suit particular application, normal operating temperature to read 50% of full scale.

Page 18: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15050 AND SEWAGE PUMP STATION BASIC MECHANICAL MATERIALS AND METHODS PAGE 7

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

Scale Range: Heating water 20°C to 130°C

Chilled water 0°C to 50°C

Glycol 0°C to 130°C

.4 Furnish all thermometers with separable wells.

.5 Dual F and C reading scale.

.6 Adjustable angle mounting.

.7 Vapour actuated.

2.8 Drive Guards

.1 Fit all exposed drive assemblies with guards.

.2 Make guards demountable to facilitate access for servicing.

3 EXECUTION

3.1 Sleeves

.1 Furnish sleeves for all piping passing through partitions, floors, walls, etc. as specified herein.

.2 Use 24 gauge galvanized steel for sleeves through walls, floors, etc., and schedule 40 black iron sleeves through all reinforced concrete beams, and other locations. Centre all piping in their respective sleeves.

.3 Extend sleeves 25 mm (1") either side of all floors, partitions, etc., through which they pass, except for floor sleeves into potentially wet areas such as washrooms, etc., where sleeves extend 50 mm (2") above the finished floors. Caulk pipes into potentially wet areas for full depth to prevent leakage.

.4 Use sleeves 12 mm (1/2") clear of the insulation on insulated pipes. Caulk pipes full depth with non-combustible material. Use light gauge sheet metal covers to protect insulation from caulking.

.5 Fit a minimum of 3 centering fins welded to the pipe on steam risers passing through floor sleeves.

.6 Where pipes pass through an outside wall, equipment room wall, or fire separation, the space between the pipe and sleeves must be filled with an approved fire stop caulking compound and made watertight and airtight.

.7 Core sleeves in locations approved by the Engineer if sleeves are required in precast or cast-in-place concrete and these have not been provided. Locate sleeves in these holes and cement in place to provide the extensions of 25 mm or 50 mm (1" or 2") as previously stated.

Page 19: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15050 AND SEWAGE PUMP STATION BASIC MECHANICAL MATERIALS AND METHODS PAGE 8

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

3.2 Escutcheon Plates

.1 Furnish heavy chromium plated solid type escutcheon plates on all exposed piping where passing through wall, floors, partitions, etc. Design of escutcheon plates must cover sleeves extending 50 mm (2") above the floor, completely hiding the sleeve. Plates to be B&C #10.

3.3 Piping Inspection and Tests

.1 Provide all materials, labour, plant and equipment necessary for tests as specified herein.

.2 Notify the Engineer and/or the governing authority of all tests at least 48 hours in advance and conduct all tests to their satisfaction. Repeat tests if required until the system is shown to be leak tight and in proper working condition.

.3 Conduct tests before piping is concealed or insulated. Test underground piping prior to backfill as applicable.

.4 Test all piping, with the exception of atmospheric vents, hydraulically to 1-1/2 times the operation pressure but not less than 860 kPa (125 psi). Remove and protect all components such as control valves which are not designed for the test pressure. Prove piping without pressure drop for a period of 24 hours with a hydraulic test.

.5 Carry out a hammer test with a 1.4 kg (3 lb.) pound hammer around each weld. No caulking is permitted.

3.4 Access Doors

.1 Install access doors in accordance with architectural requirements.

3.5 Connections

.1 Make all connections to the mains with branches and with radiant panels, etc., so that free and continuous circulation of water in the whole apparatus will be obtained at all times and under all circumstances.

.2 Equip piping with cast bronze copper-to-iron connectors at all points where these metals are joined in the system.

3.6 Thermometers

.1 Install all thermometers, including pockets, as shown on the drawings.

.2 Install all thermometers, as noted under items of equipment as specified.

.3 Ensure that all thermometers, as far as practical, are of one manufacturer and of matching pattern.

3.7 Pressure Gauges

.1 Install all pressure gauges, as shown on the drawings.

.2 Install all pressure gauges, as noted under items of equipment as specified.

Page 20: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15050 AND SEWAGE PUMP STATION BASIC MECHANICAL MATERIALS AND METHODS PAGE 9

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.3 Ensure that all pressure gauges, as far as practical, are of one manufacturer and of matching pattern.

3.8 Hangers & Supports

.1 Install hangers and supports in accordance with manufacturer's recommendations and in accordance with the codes minimum requirements.

.2 Furnish all hangers, supporting steel, etc., for the mounting and hanging of all mechanical equipment supplied unless otherwise specified.

.3 Size supports, hangers, etc., suitable for supporting the weight of the equipment without subjecting the building structure or the supports to undue stress.

END OF SECTION

Page 21: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15055 AND SEWAGE PUMP STATION CLEANING AND CHEMICAL TREATMENT PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Scope of Work

.1 Execute all work and furnish all products as specified herein and in accordance with the contract documents.

1.2 Work Included

.1 Cleaning of the new domestic water and process water distribution system.

.2 Cleaning and chemical treatment of the new heating water and chilled water piping system.

.3 Supply and installation of glycol handling equipment and glycol fluid.

1.3 Submittals

.1 Provide written report containing log and procedure of system cleaning, giving times, dates, problems encountered and condition of water.

2 PRODUCTS

2.1 System Cleaner

.1 Use a Sodium Metasilicate, Sodium Nitrite and a wetting agent compound which in solution removes grease and petroleum products. Concentration level to be determined by the Water Treatment Specialist. Compound to be equal to Pace Chemicals Purgex L-24.

2.2 System Treatment

.1 Provide sufficient chemicals to bring the system up to the same chemical concentration as was at the beginning of the project.

.2 Chilled Water System Treatment: Use a Borated Nitrite-Molybdate based corrosion inhibitor. Maintain levels at 200 to 400 ppm. (PACE Chemicals Ltd. - BAR COR CWS-91). Note: The use of Nitrite only, Molybdate only or Sulphite only will not be accepted.

2.3 Glycol System

.1 Charge the chilled water system with 30% solution of inhibited propylene glycol equivalent to DOWFROST.

2.4 System Equipment

.1 Bypass Pot Feeder

.1 The chilled water heating system shall have a by-pass chemical pot feeder with a 7.6 litre capacity. It shall be constructed of heavy duty cast iron or welded steel, be suitable for 1380 kPa (200 psi) working pressure, and be complete with quick opening cap and 20 mm NPT connections. Isolating valves shall be installed on the inlet, outlet, and drain.

Page 22: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15055 AND SEWAGE PUMP STATION CLEANING AND CHEMICAL TREATMENT PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Sidestream Filter

.1 The chilled water heating system shall have a sidestream filter housing of steel construction using a 250 mm x 30 micron filter cartridge, with a minimum flow rate of 0.58 litres/second. A flow indicator shall be installed in conjunction with the sidestream filter. Connections shall be 20 mm NPT and all isolating valves shall be installed in accordance with the manufacturer’s instructions. Provide ten (10) filter cartridges.

.3 Totalizing Make-up Water Meter

.1 Cast bronze body, 20 mm NPT connections, thermoplastic rotor and gear train, rated at 1200 kPa (175 psi) maximum operating pressure.

2.5 Glycol System Equipment

.1 Tank

.1 205 litre cylindrical, polyethylene tank with hinged poly cover, steel support stand with all required connections and agitator bracket. (Neptune Model 45PT-159)

.2 Agitator

.1 Direct drive, 1725 rpm, 1/4 HP, 115/1/60 VAC c/w 316 stainless steel shaft and propeller (Neptune Model A-2). Mixer mounts to bracket supplied as part of tank stand.

.3 Pump

.1 Hand operated fill pump, diaphragm style, 250 kPa (85 ft.) minimum head, 20 mm NPT connections, equivalent to Monarch L-30A.

.4 Pipe & Fittings

.1 Pump suction shall be piped using 20 mm S40 PVC pipe and S80 PVC fittings. A 20 mm PVC ball valve and Y-Strainer shall be provided in the pump suction. The pump discharge shall be piped using 20 mm S80 PVC pipe and fittings. A 20 mm PVC ball valve and check valve shall be provided in the pump discharge line. Supply a 65 mm pressure gauge (0-600 kPa range) in the discharge piping.

2.6 Test Kits

.1 Provide test kits to determine proper systems treatment, including but not limited to the following:

.1 Closed System Test Kit

.1 To determine proper level of Borated Nitrite and Molybdate in closed system treatment. (PACE Chemicals Test Kit # 104).

.2 Glycol System Specific Gravity Test Kit

.1 To determine freezing point of glycol systems. To contain a 300mm specific gravity hydrometer equivalent to Kessler Model 8350 with scale range of 1.000

Page 23: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15055 AND SEWAGE PUMP STATION CLEANING AND CHEMICAL TREATMENT PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

-1.110 at .001 specific gravity increments. Provide a chart showing the specific gravity of the specified solution by volume, at a specified temperature.

3 EXECUTION

3.1 Cleaning and Chlorination of Potable Water Piping

.1 All domestic water piping shall be thoroughly flushed so that it is free from scale, sediment, construction debris etc.

.2 On completion of installation and testing of the potable water systems, pre-flush, chlorinate with Sodium Hypochlorite to AWWA C-601 specifications and let stand for 24 hours. Thoroughly flush again until flush water meets AWWA standards.

.3 Retain an independent inspection firm to supervise and inspect the chlorination and flushing procedures and perform chemical tests as required.

.4 Submit to the Consultant, a certificate from the testing firm that states that the chlorination and flushing have been successfully carried out.

.5 Acceptable Firms: PACE Chemicals Ltd., Betz Dearborn.

3.2 Pre-operational Cleaning and Chemical Treatment – Heating Water and Chilled Water Piping Systems

.1 All new heating piping systems and chilled water systems shall be chemically cleaned and flushed before water treatment is added. This includes partial or complete filling for pressure testing.

.2 After all components of the new piping system have been pressure tested and proven to be in full operational condition and leak-free, flush the entire system with fresh, clean make-up water to remove loose mill scale, sediment, and construction debris.

.3 Provide drain connections to drain system in one hour.

.4 Install totalizing water meter to record capacity in the system.

.5 After the initial flushing has been completed, clean all strainer screens.

.6 System pumps may be used for cleaning, provided that pumps are dismantled and inspected, worn parts repaired with new gaskets and seals installed. Submit used seals.

.7 Add cleaner to the system at concentration levels recommended by the Water Treatment Specialist.

.8 Circulate water for 48 hours. After cleaning, drain system as rapidly as possible. Flush system by opening drain valves and opening bypass valve on water make-up to system. Continue flushing until tests show pH, Iron, TDS and Chloride levels of water leaving system are the same as entering system. Refill and immediately add water treatment to proper level.

3.3 Glycol System

.1 Label all drain valves with "GLYCOL - DO NOT DRAIN".

Page 24: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15055 AND SEWAGE PUMP STATION CLEANING AND CHEMICAL TREATMENT PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Pre-mix solution in mixing tank, demonstrate specific gravity of solution to Owner and charge system using feed pump. After system has been filled, check specific gravity of solution in each system. Leave mixing tank filled with specified glycol solution. Secure cover lid.

END OF SECTION

Page 25: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15070 AND SEWAGE PUMP STATION MECHANICAL SOUND, VIBRATION & SEISMIC CONTROLS PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Description

.1 Provide vibration isolation for the fans, pumps, and on piping and ductwork, as shown on the drawings or as indicated herein. For equipment less than 0.375 kW (1/2 hp), provide neoprene grommets at the support points.

.2 Provide earthquake restraining devices for resiliently mounted equipment, where indicated.

.3 Provide flexible connections for all ductwork connections to fans on plenums.

.4 Provide flexible conduit connections for all electrical connections to isolated equipment.

.5 Ensure isolation systems have a natural frequency no higher than one-third of the lowest forcing frequency.

.6 Provide all horizontal piping larger than 65 mm (NPS 2-1/2), with earthquake restraints, unless the piping is rigidly suspended within 300 mm (12”) of the structure.

.7 All seismic restraints shall be designed for a Post Disaster importance factor.

1.2 Qualifications

.1 All seismic restraining devices shall be supplied by an approved supplier with the exception of seismic restraining devices which are factory installed and are standard equipment with the machinery.

.2 The supplier shall obtain all relevant equipment information and shall provide the Consultant with shop and placement drawings for all seismic restraining devices for review, before materials are ordered. The supplier shall include details of seismic restraining device attachment to both the base and the structure.

.3 The supplier shall provide, for the Consultant's approval, a statement on all factory installed seismic restraining devices, advising as to any deviations in the factory installed equipment from the requirements of the Section.

.4 The submittals shall bear the seal and signature of a Professional Engineer registered to practice in British Columbia.

.5 The work shall be carried out in accordance with the specification and, where applicable, in accordance with the manufacturer's instructions and only by workmen experienced in this type of work.

1.3 Shop Drawings

.1 Submit shop drawings in accordance with the General Conditions and Supplementary General Conditions.

.2 Prepare shop drawings after obtaining all relevant equipment data and information.

Page 26: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15070 AND SEWAGE PUMP STATION MECHANICAL SOUND, VIBRATION & SEISMIC CONTROLS PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.3 Submit shop drawings for all vibration isolation elements, and seismic restraining devices, and placement drawings. Include details of attachments to the building structure.

.4 Include with the shop drawing submittal a statement of review of all isolators and restraining devices factory installed, detailing deviations from the requirements of this Section of the Specification.

1.4 Work of Others

.1 Install vibration breaks of a material and in a location suitable to the Mechanical Consultant on all ductwork connected to isolated equipment.

.2 Make all electrical connections to isolated equipment with a flexible conduit suspended in a circular hanging loop.

.3 Where isolated piping connected to noise generating equipment is routed from the mechanical room through plumbing chases or other openings, position isolated piping to avoid contact with the structure, future framing, gypsum wallboard and other finishes which may radiate noise. Submit proposed details to meet this requirement.

1.5 Extent of Work - Isolators

.1 Provide vibration isolation on all motor driven fans regardless of power rating and all other motor driven equipment over 0.375 kW (0.5 hp), plus associated piping and ductwork shown on the drawings or indicated herein.

.2 All spring isolators shall be "open spring" unless otherwise stated. Closed spring isolators shall only be used where specified. The exception to this clause being seismically rated housed spring isolators such as Mason type SSLFH.

.3 The required static deflection of isolators for motor driven fans of less than 0.35 kW (0.5 hp) is 5 mm (3/16”).

.4 Neoprene isolators shall be used for deflections 5 mm (3/16”) and under.

1.6 Extent of Work - Restraining Devices

.1 All resiliently mounted equipment including piping and ductwork shall be provided with seismic restraining devices (snubbers). All isolated equipment shall have a minimum of four seismic restraints. Restraints shall be located as close as possible to the isolators, or incorporated in the isolator.

.2 All snubbers shall be adjusted to maintain clearances between 3 mm (1/8”) and 6 mm (1/4”) under normal operating conditions of the equipment.

.3 Isolated suspended equipment including piping shall be restrained using a slack cable restraint system designed by a Professional Engineer, or other means acceptable to the Consultant.

1.7 Samples

.1 Samples of materials required to complete the work of this Section shall be submitted on request to the Consultant for inspection and approval.

Page 27: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15070 AND SEWAGE PUMP STATION MECHANICAL SOUND, VIBRATION & SEISMIC CONTROLS PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

2 PRODUCTS

2.1 Isolators

.1 All vibration isolation equipment is to be supplied by one approved supplier with the exception of isolators which are factory installed and are standard equipment with the machinery.

.2 All isolators are to be of the following types, supplied by the manufacturers named, or other acceptable manufacturers listed:

.1 Type 1: Rubber/neoprene-in-shear isolators capable of a vertical upward load equal to 3 times the normal load capacity of the isolators, unless provision is made to minimize vertical shock loading. Select the isolators for a 5 mm (3/16”) minimum static deflection, and bolt down. In the case of rubber isolators, provide protection in the design of the isolator to avoid contact of the rubber element to oil in the mechanical room. Design is based on Trelleborg Type RAEM with stops, approved equal - Mason SSLFH.

The Consultant shall be provided with the following test data to prove the performance of the neoprene isolators:

.1 A data sheet listing all the ASTM test results.

.2 Load deflection curves for the isolator indicating the deflection to full compression for both laterally restrained and unrestrained isolators.

.3 The measured dynamic stiffness of the isolators over the design range.

.2 Type 2: Marine spring mounts complete with levelling devices, adjustable side dampers, minimum 6 mm (1/4”) thick neoprene sound pads, and zinc chromate plated hardware. With snubbers correctly adjusted, the isolator is to be capable of withstanding a horizontal load equal to four times the vertical loading on the isolator. Sound pads shall be sized for a minimum deflection of 1.2 mm (1/16”) and shall meet the requirements for neoprene isolators.

Select marine mounts for a minimum 25 mm (1”) deflection, and bolt down using neoprene grommets. Design is based on Vibron VMR-2, approved equal - Mason SSLFH.

.3 Type 3: Neoprene/steel/neoprene pad isolators, manufactured from "bridge bearing quality neoprene", as defined by CSA Standard CAN3-S6-M78 Section 11.10. The height of the ribs shall not exceed 0.7 times the width of the rib. Steel interlayers shall be used to distribute the load in a multilayered unit. Select type 3 pads for a 3 mm (1/8”) static deflection or greater. Bolt down equipment mounted on neoprene pad isolators using neoprene grommets.

.4 Type 4: Spring or neoprene hangers designed to avoid binding. Springs shall be stable under operating conditions. Hangers shall be capable of a 10-degree misalignment without binding unless otherwise specified. Design is based on Vibron Series VH, approved equal - Mason HD, HS.

.3 Provide test data to confirm the quality and performance of isolators if requested.

Page 28: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15070 AND SEWAGE PUMP STATION MECHANICAL SOUND, VIBRATION & SEISMIC CONTROLS PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.4 Select isolator at the supplier's optimum recommended loading, and do not load beyond the limit specified in the manufacturer's literature.

.5 Design springs in accordance with the Society of Automotive Engineers' Handbook Supplement 9 entitled "Manual on Design and Application of Helical and Spiral Springs - SAE - 1975".

.6 Springs are to be "iso-stiff" (kx/ky = 1.0 to 1.5) with a working deflection between 0.3 and 0.6 of solid deflection.

.7 Provide hot dipped galvanized housings and neoprene coated springs, for all spring isolators located out of doors. Drill spring cup base for drainage. All bolts shall be cadmium plated.

.8 For all electrical connections to isolate equipment, provide flexible conduit suspended in a semi-circular hanging loop for 25 mm (1") conduit and smaller or Crouse-Hinds EC couplings for larger conduit.

2.2 Flexible Duct Connectors

.1 Provide flexible duct connectors of Durodyne with Durolon fabric.

2.3 Vibration Levels of Rotating Equipment

.1 The vibration velocity amplitude measured on the bearing housing of all equipment shall not exceed 1.5 mm/sec.

2.4 Seismic Restraints

.1 The restraints shall be designed to handle the appropriate Vp force calculated in clause 4.1.8.17 (1) of the 2007 City of Vancouver Building By-Law and the 2006 BC Building Code. In this case, calculations bearing the seal of a Professional Engineer must be submitted with the shop drawings to demonstrate compliance with the Code.

.2 All elastomer elements within the restraint shall be bridge bearing neoprene satisfying the requirements of this Section.

.3 Test data shall be provided to the Consultant, showing the load deflection curves up to 1.5 times the rated capacity of the restraint, and certifying that neither the neoprene elements nor the snubber body sustained any obvious deformation after the release of the load.

.4 All attachment points and fasteners shall be capable of withstanding a load of three times the sized capacity of the seismic restraint.

.5 Slack cables shall be sized to withstand the calculated earthquake loading on the isolated equipment, with a safety margin of 4. Slack cable restraint systems shall be Vibron, Mason, or other approved.

3 EXECUTION

3.1 Isolators and Hangers

.1 Submit samples of materials required to complete the work of this Section for inspection and review if and when requested.

Page 29: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15070 AND SEWAGE PUMP STATION MECHANICAL SOUND, VIBRATION & SEISMIC CONTROLS PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 The work shall be carried out in accordance with the Specifications and, where applicable, in accordance with the manufacturer's instructions and only by workmen experienced in this type of work.

.3 All equipment mounted on vibration isolators shall have a minimum clearance of 50 mm (2”) to other structures, piping, equipment, etc.

.4 Any floor mounted equipment rotating at less than 1170 RPM shall be isolated on Type 2 isolators.

.5 Under equipment mounted on Type 2 mounts, neoprene/steel/neoprene (Type 3) pads shall be provided adjacent to the springs, selected for the manufacturer's optimum loading, and shimmed to be just clear of the base of the equipment under operating conditions. These pads shall be bolted to the floor slab, and the top of the bolt shall be below the top of the pads. These pads are to minimize rocking of the equipment in the event of an earthquake, and can be deleted if other provision is designed into the isolator to minimize rocking.

.6 Equipment mounted on a slab on grade and in-line pumps are to be mounted on Type 3 neoprene/steel/neoprene sandwich pads.

.7 Provide Type 4 spring hangers selected for a minimum static deflection of 25 mm (1") on all ceiling hung fans.

.8 Provide neoprene or spring hangers (Type 4) on all piping connected to isolated equipment. The use of spring or neoprene as the piping isolation element is to be consistent with the method of isolation of the equipment to which the piping is connected - e.g. spring hangers on piping connected to equipment isolated on springs. The deflection shall be the same as specified for the equipment.

.9 Install hangers midway down the hanger rod in order that the hangers are self-aligning. All hangers shall be installed without binding.

.10 Adjustable, horizontal stabilizers on closed spring isolators shall be adjusted so that the side stabilizers are clear under normal operating conditions.

3.2 Duct Connections to Isolated Equipment

.1 For flexible duct connections provide a metal to metal gap of 50% of the fabric width when the equipment is not running, and fabric widths as follows:

.1 Centrifugal fans up to 600 mm (24”) dia. - 75 mm (3”)

.2 Cabinet fans - 75 mm (3”)

.3 Centrifugal fans - mounted on neoprene isolators 75 mm (3”) - All other applications, unless otherwise specified 150 mm (6”)

.2 Stabilizing springs to be provided limiting movement at flexible connections to 25% of fabric width under steady state and 40% at start up.

Page 30: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15070 AND SEWAGE PUMP STATION MECHANICAL SOUND, VIBRATION & SEISMIC CONTROLS PAGE 6

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

3.3 Seismic Restraints

.1 Provide slack cable restraints on the fans, connected to the fans at the point of vertical support (4 points). Orient the restraint wires at approximately 90 degrees to each other (in plan), and tie back to the ceiling slab at approximately 45 degrees to the slab. Select the restraints for a L/g earthquake loading (i.e. each wire shall have a working load capacity equal to the weight of the fan). Select the anchors in the concrete for a load equal to the weight of the fan at a 45 degree pull.

.2 On piping systems, provide transverse slack cable restraints at a maximum spacing of 12 metres (40 ft.) and longitudinal restraints at 24 metres (80 feet) maximum spacing, or as limited by anchor/slack cable performance. The loading and installation requirements are the same as specified above for the fans. Vary by 10% to 30% the adjacent spacing of restraints on a piping run to avoid coincident resonances.

.3 Transverse bracing for one pipe section may also act as longitudinal bracing for the pipe connected perpendicular to it provided the bracing is installed within 600 mm (24”) of the elbow or tee and if the connected pipe is the same or smaller in size. Do not use branch lines to restrain main lines.

.4 Provide flexibility in piping joints or sleeves where pipes pass through building seismic or expansion joints.

.5 At vertical pipe risers, wherever possible, support the weight of the riser at a point or points above the centre of gravity of the riser. Lateral guides shall be provided at the top and bottom of the riser, and at intermediate points not to exceed 9 metres (30 ft.) on centre, with guide clearance not exceeding 3 mm (1/8”). Adjacent spacing of restraints on a piping run shall vary by 10% to 30% to avoid coincident resonances.

END OF SECTION

Page 31: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15075 AND SEWAGE PUMP STATION MECHANICAL IDENTIFICATION PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Scope of Work

.1 Execute all work and furnish all products as specified herein and in accordance with the contract documents.

1.2 1.2 Work Included

.1 Labeling

.2 Flow Arrows

.3 Banding

1.3 Quality Assurances

.1 Standards of Workmanship

.1 Execute all work in a competent manner and present an acceptable appearance when completed.

.2 Unless otherwise specified as shown, install products in accordance with recommendations of manufacturers.

2 PRODUCTS

2.1 Quality of Materials

.1 Furnish new materials, apparatus or products required for the work, of first class quality, delivered, installed and finished in every detail.

3 EXECUTION

3.1 Systems and Equipment Identification

.1 Supply and install black lamicoid identification plates with 15 mm high white letters on all equipment forming a part of this Contract. Attach plates to the equipment with sheet metal screws or bolts and nuts (adhesive will not be acceptable).

.2 Provide data dots on the ceiling to locate serviceable equipment. Use the hospital dot colour system.

3.2 Piping Identification

.1 At the completion of the work, provide self-stick pipe markers as manufactured by Craftmark, Revere-Seton, or other approved with flow arrows and symbol letters designating the pipe service on all piping forming a part of this Division. Use contrasting colour to the piping on which it is stenciled. Locate arrows and symbols as follows:

.1 Immediately adjacent to all equipment, control valves, etc., to which the piping is attached.

Page 32: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15075 AND SEWAGE PUMP STATION MECHANICAL IDENTIFICATION PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Immediately adjacent to and on each side of partitions, walls, floors, ceilings, etc., through which the piping passes.

.3 A maximum of every 6 m in all other locations regardless of whether the pipe is concealed or exposed except in shafts.

.4 One connection at each Tee.

.2 Locate all arrows and symbols together in a visible location and in an orderly manner.

.3 Use symbols as specified in 'Painting' of this Division. Where two or more different pressures or temperatures occur in any medium, stencil on the pressure or temperature contained therein in addition to the symbol or as otherwise shown on the Labeling and Banding Schedule.

.4 Stencil ductwork with zone or system identification and flow arrows at 10 m intervals and on both sides of walls. Colour is black, or white on a black background at least 25 mm high. Do not band sanitary and vent piping outside mechanical rooms or within concealed spaces.

.5 For pipe sizes 20 mm and smaller, use 64 mm long x 25 mm tubing markers.

.6 For pipe sizes 25 mm to 65 mm, use 200 mm long x 40 mm pipe markers with 20 mm high letters.

.7 For pipe sizes 65 mm to 150 mm, use 350 mm long x 57 mm pipe markers with 32 mm high letters.

.8 Provide all valves with a plastic tag with black stamped numbers secured to it with a non-ferrous strap. This is to apply to all valves except those located on radiators, convectors, unit heaters, and "Dead End" services, if the valves are located in proximity to the equipment or system being served. Furnish a directory consisting of a typewritten valve list showing the tag number, the location of the valve and its use. These lists are to be included in the operating and maintenance instruction book.

.9 The identification symbols and colours for piping, as applicable, are as follows based on the requirements of CAN/CGSB – 24.3-92 and ANSI A13.1-1981.

Service Basic Colour (Background)

Secondary Colour (Lettering)

Legend

Chilled Water Green White Chilled, CHWS or CHWR

Condenser Water Green White Condenser, CWS or CWR

Heating Water Supply Yellow Black Hot Water Supply

Heating Water Return Yellow Black Hot Water Return

Process Hot Water Yellow Black Process Hot Water

Process Cold Water Green White Process Water

Page 33: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15075 AND SEWAGE PUMP STATION MECHANICAL IDENTIFICATION PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

Domestic Hot Water Yellow Black Domestic Hot Water

Domestic Cold Water Green White Domestic Cold Water

Sprinkler Red - Sprinkler

.10 Colours applied shall confirm to CGSB 1-GP-12 1965, as follows:

.1 Yellow 505-111

.2 White 513-101

.3 Black 512-101

.4 Orange 508-101

.5 Green 403-301

.6 Red 509-101

.7 Aluminum 515-101

.8 Purple 511-103

.9 Blue 502-105

.11 Where two or more different pressures or temperatures occur in any medium, apply a label with the pressure or temperature contained therein in addition to the symbol. Symbols are applied adjacent to all flow arrows specified in the Systems Identification Clause of this Division.

END OF SECTION

Page 34: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15080 AND SEWAGE PUMP STATION MECHANICAL INSULATION PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Scope of Work

.1 Perform work by Journeymen Insulators skilled in this trade.

.2 Apply insulation in a workmanlike manner so that the finished product is uniform in diameter, smooth in finish, pleasing to the eye with all longitudinal seams placed as to be invisible.

.3 Apply insulation to piping and equipment only after all tests have been successfully made.

.4 Be responsible for ensuring that sufficient space is provided to allow proper installation of insulation.

.5 Wherever possible, apply coverings to piping and equipment containing liquids or vapours of operating temperature different from ambient with the equipment at operating conditions. Consult the Engineer prior to applying insulation to pipe, ductwork or equipment where extreme thermal movement is anticipated. Make good any separation of joints or cracking of the insulation due to the thermal movement or poor workmanship.

.6 As applicable, use the local "Insulation Contractors Association Standards Manual" as the basis of determining material specification if not contained herein. Use materials with a flame spread rating of not more than 25 and a smoke developed rating of not more than 50 when determined in accordance with ASTM E-84, ULC C723, ULI 723, or NFPA 255.

.7 Comply with ASHRAE Standard 90.1.

2 PRODUCTS

2.1 Pipe Insulation

.1 Pipe insulation in concealed areas is ULC approved 80 kg/m3 (5 lb/ft3) density moulded sectional glass fibre complete with vinyl coated foil-kraft laminated vapour barrier jacket reinforced with an open mesh fiberglass scrim fabric, to CAN-ULC-S102.2-M88.

.2 Cold pipe insulation in exposed areas is ULC approved 80 kg/m3 (5 lb/ft3) density moulded sectional glass fibre preformed pipe insulation complete with vinyl coated foil-kraft laminated vapour barrier jacket reinforced with an open mesh fiberglass scrim fabric, K=0.24 at 24°C, to CAN-ULC-S102.2-M88.

.3 Hot pipe insulation in exposed areas is ULC approved 80 kg/m3 (5 lb/ft3) density moulded sectional glass fibre preformed pipe insulation, to CAN-ULC-S102.2-M88, covered with jacket.

.4 Domestic and process water pipe insulation thickness:

.1 12 mm (1/2”) for cold water pipe sizes up to 50 mm (2”)

.2 25 mm (1”) for hot water pipe sizes up to 50 mm (2”)

.3 25 mm (1”) for cold water pipe sizes 65 mm (2-1/2”) and larger

Page 35: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15080 AND SEWAGE PUMP STATION MECHANICAL INSULATION PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.4 40 mm (1-1/2”) for hot water pipe sizes 65 mm (2-1/2”) and larger

.5 12 mm (1/2”) for hot and cold-water runouts up to 3.6 metres (12 ft.) in length.

.5 Heating water pipe insulation:

.1 37 mm (1-1/2”) for pipe sizes up to 50 mm (2”)

.2 50 mm (2”) for pipe sizes 67 mm to 150 mm (2-1/2" to 6")

.3 25 mm (1”) for runouts up to 3.6 metres (12 ft.) in length.

.6 Chilled water pipe insulation thickness:

.1 12 mm (1/2”) for pipe sizes up to 50 mm (2”)

.2 25 mm (1”) for pipe sizes 65 mm (2-1/2”) and larger

.7 Storm piping insulation is 25 mm thick.

.8 Comply with CGSB 51-GP-9 standards and the City of Vancouver Energy Use By-Law.

2.2 Tanks and Equipment Insulation

.1 Tanks and equipment insulation is 40 mm [1 1/2"] thick UL approved glass fibre rigid type having a thermal conductivity of 0.25 BTU-in/hr-sq ft-F @ 38C density. Comply with CGSB 51-GP-10 and 51-GP-11 standards.

2.3 Duct Insulation

.1 External duct insulation is ULC approved, 16 kg/m3 (1 lb/ft3) density glass fibre faced flexible blanket type with foil faced laminated vapour barrier jacket reinforced with an open mesh, fiberglass, scrim fabric. Insulation is 25 mm [1”] thick for ductwork within the building. Insulation is 50 mm thick for ductwork carrying outdoor air in heated areas or ductwork carrying heated air in unheated areas.

.2 Acoustic and internal rectangular duct insulation is UL approved, 32 kg/m3 (2 lb /ft3) density glass fibre semi-rigid type with black coated mat on air stream surface. Insulation is 50 mm [2”] thick unless otherwise noted. Insulation shall be high velocity type suitable for 6000 fpm air velocity and equal to Owens Corning Aeroflex PLUS Type 200 Acoutical Duct Liner. Knauf Duct Liner is an approved equal.

.3 Comply with CGSB 51-GP-10 and 51-GP-11 standards.

2.4 Fire Stopping

.1 Fire stopping and smoke seal systems shall utilize asbestos free materials and systems capable of maintaining an effective barrier against flame, smoke, and gases in compliance with the requirements of CAN4-S115-M85, or ULI 14/79 and ASTM 814, and not to exceed opening sizes for which they are intended.

Page 36: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15080 AND SEWAGE PUMP STATION MECHANICAL INSULATION PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Service Penetration Assemblies shall be certified by ULC in accordance with CAN4-S115-M85 and listed in ULC Guide No. 40 U19 or ULI 1479 and ASTM 814 and listed in the ULI Guide.

.3 Fire resistance rating of the installed firestopping assembly shall be not less than the fire resistance rating of surrounding floor and wall assemblies as indicated.

.4 Approved firestopping systems:

.1 Dow FS 2000/2001

.2 Tremco Fyre-Sil Self Leveling.

.5 Primers shall be to the manufacturer’s recommendation for the specific material, substrate, and end use.

.6 Damming and back-up materials, supports, and anchoring devices shall be to the manufacturer’s recommendations and in accordance with the tested assembly being installed as acceptable to authorities having jurisdiction.

.7 Sealants for vertical joints shall be non-sagging.

3 EXECUTION

3.1 General

.1 Install all insulation uninterrupted through sleeves, wall, floors, etc. Where insulated pipes pass through fire separation, butt insulation up to the approved fire proofing sealant and provide a vapour barrier seal.

.2 Increase insulation diameters to accommodate trace heated piping and fittings, etc. in unheated areas.

.3 Ensure the integrity of the vapour barrier is not destroyed.

3.2 Pipe Insulation

.1 Plumbing Pipes, Fire Protection Pipes, Fitting and Valves

.1 Insulate the following piping and/or fittings unless otherwise noted:

.1 Domestic and process cold water

.2 Domestic hot water

.3 Roof drain hoppers and storm piping within building

.4 All drains, lines, stacks in unheated areas

.5 Water valves, flanges and strainers

.2 Do not insulate the following piping and/or fittings unless otherwise noted:

.1 Soil stacks, vents, etc.

Page 37: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15080 AND SEWAGE PUMP STATION MECHANICAL INSULATION PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Unions

.3 Flexible connections or expansion joints unless noted on the drawings

.4 Check valve covers

.5 Strainer leg and bucket covers

.2 Heating Pipe Fittings and Valves

.1 Insulate the following piping unless otherwise noted:

.1 Heating water piping

.2 Do not insulate the following unless otherwise noted:

.1 Relief piping

.2 Drain lines

.3 Insulate the following fittings if the pipe is insulated:

.1 Elbows

.2 Tees

.3 Reducers

.4 Valve bodies on valves and check valves over 65 mm [2 1/2"]

.5 Flanges

.6 Strainers

.4 Do not insulate the following fittings even if pipe is insulated:

.1 Valves 65 mm [2 1/2"] and under

.2 Valve bonnets

.3 Unions

.4 Strainer leg covers and bucket covers

.5 Flexible connections

.6 Expansion joints

.7 Check valve covers

.8 Section of pipe through sleeve in fire separation.

.3 Chilled Water Pipe Fittings and Valves

Page 38: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15080 AND SEWAGE PUMP STATION MECHANICAL INSULATION PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.1 Insulate the following piping unless otherwise noted:

.1 Chilled water piping

.2 Do not insulate the following unless otherwise noted:

.1 Relief piping

.2 Drain lines

.3 Insulate the following fittings if the pipe is insulated:

.1 Elbows

.2 Tees

.3 Reducers

.4 Valve bodies on valves and check valves over 65 mm [2 1/2"]

.5 Flanges

.6 Strainers

.4 Do not insulate the following fittings even if pipe is insulated:

.1 Valves 65 mm [2 1/2"] and under

.2 Valve bonnets

.3 Unions

.4 Strainer leg covers and bucket covers

.5 Flexible connections

.6 Check valve covers

.7 Section of pipe through sleeve in fire separation.

.4 Application - Hot Piping - Above 32°C

.1 Piping

.1 Hold pipe covering without integral jacket in place with insulation fastenings at not less than 300 mm [12”] centres. Hold pipe covering with integral jacket in place by stapling the flap on 75 mm [3”] centres.

.2 Fittings

.1 Insulate fittings with sections of the pipe covering mitered to fit tightly, or insulating cement, or with tightly placed flexible insulation covered with

Page 39: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15080 AND SEWAGE PUMP STATION MECHANICAL INSULATION PAGE 6

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

reinforcing membrane stapled in place. Apply hard coat finishing cement over insulating cement.

.3 Valves, Strainers

.1 Insulate valve bodies and strainers with insulating cement, or fitted pipe coverings, or mitered blocks all to thickness of adjacent pipe covering or insulate with tightly placed flexible insulation covered with reinforcing membrane stapled in place. Leave drains, blow-off plugs and caps uncovered. Apply hard coat finishing cement over insulating cement.

.4 Flanges

.1 Insulate flanges with oversized pipe covering or mitered blocks to thickness of the adjacent pipe covering.

.5 .5 Insulation Termination Points

.1 Terminate insulation 75 mm [3”] from fittings to provide working clearance and bevel insulation at 45-degree angle.

.5 Application - Cold Piping - Below 15°C

.1 Piping

.1 Apply pipe covering with integral vapour barrier jacket to piping and hold in place by securing the jacket flap. Seal all flaps and butt strips with Childers CP-85 vapour barrier coating adhesive or alternatively secure with staples and cover with a heavy brush coat of the same barrier coating.

.2 Fittings

.1 Insulate fittings with sections of the pipe covering mitered to fit tightly, or strips of flexible insulation, then apply reinforcing membrane embedded in barrier coating.

.3 Valves, Strainers

.1 Insulate valve bodies, bonnets and strainers with insulating cement, or fitted pipe coverings; or mitered blocks all to the thickness of adjacent pipe covering, and then apply reinforcing membrane embedded in barrier coating. Alternately, insulate with tightly placed flexible insulation covered with reinforcing membrane stapled in place and cover with a barrier coating. Leave drains, blow-off plugs and caps uncovered. Apply hard coat finishing cement over insulating cement.

.4 Flanges

.1 Insulate cold flanges with oversized pipe covering or mitered blocks to the thickness of the adjacent pipe covering then apply reinforcing membrane embedded in barrier coating.

.5 Hangers

Page 40: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15080 AND SEWAGE PUMP STATION MECHANICAL INSULATION PAGE 7

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.1 Use 12 gauge galvanized sheet metal sections of suitable length between the hanger and the pipe. Do not use saddles for this application.

.6 Pipe Insulation Finishes

.1 Unless otherwise specified, recover all insulated exposed piping with 270 g/m2 canvas, secured and finished with 2 coats of fire retardant anti-fungicide lagging adhesive. Non-antifungus type adhesives are unacceptable. Canvas must be labelled by ULC to be less than 50 smoke developed rating and less than 25 flame spread rating. PVC jacket and fitting covers with a flame spread rating of less than 25 and a smoke developed rating of less than 50 may be used instead of canvas jacket.

.2 Upon completion of finished insulation, paint the entire insulated surface with Childers CP-52 fire retardant, anti-fungicide coating.

.3 For insulated piping in outdoor locations, apply Childers aluminum jacketing, 0.4 mm thick with 5 mm corrugations and factory applied moisture barrier continuously laminated across full width of the jacketing. Fasten jacket using straps approximately 150 mm on centre.

.4 Over insulated fittings, valve bodies, valve bonnets, strainers and flanges apply metal jacket or preformed metal fittings to provide a complete jacket system. Secure with necessary fastenings.

.5 Seal all jacketing weathertight.

3.3 Ductwork Insulation

.1 Ductwork & Plenum Casing (External)

.1 Insulate the following ductwork and components externally unless otherwise noted:

.1 Supply air ducts for systems HVAC-103 (Heat Pump Area), HVAC-104 (Electrical Room), and HVAC-106 (Office).

.2 Outdoor air intake ductwork shown on drawing M103.

.3 Do not externally insulate ductwork that is internally insulated.

.2 Ductwork & Plenum Casing (Internal)

.1 Insulate the following ductwork and components internally unless otherwise noted:

.1 Ductwork shown on the drawings as acoustically lined.

.2 Outdoor air intake ductwork in the mechanical room up to an including the mixing box, unless the mixing box is supplied with the unit.

.3 The sides and ceiling of the outdoor air intake tunnel and the exhaust air tunnel.

.3 Application - Flexible Insulation - (External)

Page 41: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15080 AND SEWAGE PUMP STATION MECHANICAL INSULATION PAGE 8

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.1 On round ducts and on rectangular ducts, under 750 mm [30”] in width, no preparation is necessary. On rectangular ducts 750 mm [30”] or more in width, apply to bottom surface mechanical fasteners at approximately 450 mm [18”] centres. Apply insulation with vapour barrier to the outside. Seal all joints or flanges with vapour barrier tape secured with vapour barrier adhesive. Where mechanical fasteners penetrate the vapour barrier, apply vapour barrier tape or cover with heavy coating of vapour barrier adhesive.

.4 Application - Internal – (Acoustically Lined)

.1 Fix mechanical fasteners to both horizontal and vertical surfaces at approximately 300 mm centres each way. In addition, apply to all interior sides a minimum of 90% coverage of fire retardant adhesive complying with ASTM C916. Cut insulation material to required size and apply to interior of duct and/or plenum with horizontal surfaces overlapping vertical surfaces and edges sealed and tightly butted together. All transverse joints and all exposed leading edges shall be coated. Secure insulation by impaling on mechanical fasteners. Where mechanical fasteners penetrate factory finish and at all joints, apply a seal coating. On duct systems having air velocities between 10 m/s and 30 m/s [2000 fpm and 6000 fpm], reinforce the joints with seal coating and reinforcing membrane.

.2 Use metal corners extending a minimum of 50 mm [2”] along the leading edge of duct liners to eliminate any possibility of uplift.

.5 Duct Insulation Finishes

.1 No further recovering or finishes are required on concealed ductwork unless otherwise specified.

.2 Insulated ductwork that is located outdoors shall have a double sheet metal wall construction with 50 mm [2”] thick insulation.

3.4 Fire Stopping

.1 Install fire stopping in accordance with manufacturer’s instructions and in accordance with ULC certification.

.2 Where longitudinal pipe motion is anticipated, increase sleeve size to allow sealant to accommodate motion.

.3 Tool or trowel exposed surfaces to a neat finish.

.4 Remove excess compound promptly as work progresses and upon completion.

.5 Do not cover materials until proper curing has taken place.

.6 Remove temporary dams after initial set of firestopping and smoke seal materials..

END OF SECTION

Page 42: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15100 AND SEWAGE PUMP STATION BUILDING SERVICES PIPING PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 May 2008

1 GENERAL

1.1 Work Included

.1 Furnish all labour and materials, services and equipment required for the installation of additions, removals, and modifications to the existing building services piping system to form complete operable systems as shown on the drawings and specified herein.

.1 Drainage system including all vents, piping, etc., with all necessary connections to not-in-contract equipment.

.2 Foundation drainage system including all piping, foundation drainage

.3 Domestic hot water and cold water systems, piping, valves, etc., with all necessary connections to not-in-contract equipment.

.4 Process hot water and cold water systems, piping, valves, etc., with all necessary connections to not-in-contract equipment.

.5 Chilled water system, piping, valves, etc., with all necessary connections to not-in-contract equipment.

.6 Condenser water systems, piping, valves, etc., with all necessary connections to not-in-contract equipment.

.7 Refrigerant relief piping.

.8 Heating water system, piping, valves, etc., with all necessary connections to not-in-contract equipment.

.9 Installation of pressure sensors and temperature wells in new and existing piping in locations designated by Section 15900 Controls.

1.2 Related Work

.1 Basic Mechanical Requirements Section 15010

1.3 General Requirements

.1 Install all plumbing systems to the requirements and standards of the 2007 City of Vancouver Building By-Law and the authority having jurisdiction.

1.4 Welding

.1 All welding must be done in accordance with the regulations of the Boiler Inspection Branch. All field welding must be in accordance with the procedures of CSA-W55.3-1965 and CSA-W117.2-94 and the current edition of ASME Code for Power Piping.

.2 Welding must be performed by welders fully qualified and licenced by Provincial Authorities.

Page 43: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15100 AND SEWAGE PUMP STATION BUILDING SERVICES PIPING PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 May 2008

2 PRODUCTS

2.1 Drainage and Vent Pipe and Fittings

.1 Storm and Sanitary piping:

.1 Class 4000 mechanical joint cast iron soil pipe and fittings to CAN/CSA B70.

.2 DWV copper drainage pipe with cast brass and/or wrought copper drainage fittings.

.2 Sanitary and storm piping within concrete slab:

.1 DWV copper drainage pipe with cast brass and/or wrought copper drainage fittings.

.2 DWV ABS or PVC drainage pipe with solvent weld ABS or PVC fittings.

.3 Foundation Drainage Piping (FTD):

.1 Foundation drainage piping and fittings shall be standard duty PVC SDR 35 with two rows of 1/2" diameter holes 120° radially, holes facing downward, with solvent weld joints.

.2 Provide cleanouts where shown on the drawings and as required to permit cleaning of the piping. Extend cleanout to grade level and provide access to fittings as follows:

.3 Cleanouts in cast-in-place concrete, paving or pavers to be Zurn ZXN 1612.

.4 Cleanout in landscaped areas to be PVC screwed pipe plubs with 12”x12”x6” thick concrete surround.

2.2 Domestic Water Piping

.1 Piping 75 mm [3”] diameter and smaller inside building:

.1 Certified type 'K' hard drawn copper tubing with cast brass and/or wrought copper streamline fittings.

.2 Piping 100 mm [4”] diameter and larger inside building:

.1 Centrifugal spun ductile iron pipe, thickness Class 3 and fittings to ASA-A21.51-1976, suitable for mechanical joint couplings.

2.3 Heating Water Piping

.1 Pipe material is steel to ASTM A-53, grade B, ERW, schedule 40. Alternatively, for piping 50 mm and smaller, certified type 'K' hard drawn copper tubing with cast brass and/or wrought copper streamline fittings.

.2 Fittings are 150 psi malleable iron screwed up to 50 mm [2"] and butt welded, long radius to match ASTM A-234 Grade B for 65 mm [2 1/2"] and over.

.3 Flange stud bolts to ASTM A-193, Class 37 2CP Hex nuts with ASTM A-194 Class 2H asbestos gaskets 1.6 mm [1/16"] thick.

Page 44: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15100 AND SEWAGE PUMP STATION BUILDING SERVICES PIPING PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 May 2008

2.4 Chilled Water Piping, Condenser Water Piping

.1 Pipe material is steel to ASTM A-53, grade B, ERW, schedule 40.

.2 Fittings are 150 psi malleable iron screwed up to 50 mm [2" NPS] and Victaulic grooved fitting system, long radius to match ASTM A-234 Grade B for 65 mm [2 1/2" NPS] and over.

.3 Flange stud bolts to ASTM A-193, Class 37 2CP Hex nuts with ASTM A-194 Class 2H gaskets 1.6 mm [1/16"] thick.

2.5 Refrigerant Relief Piping

.1 Pipe material is steel to ASTM A-53, grade B, ERW, schedule 40, or lightwall piping equal to Western Tube & Conduit Hi-Flow. The existing piping material removed by the demolition work may be reused for this piping.

.2 Fittings are 150 psi malleable iron screwed up to 50 mm [2" NPS] and Victaulic grooved fitting system, long radius to match ASTM A-234 Grade B for 65 mm [2 1/2" NPS] and over.

2.6 Joints

.1 Cast Iron Soil Pipe:

.1 MJ to be stainless steel or cast iron clamp type with neoprene gasket to CGSB 77-GP-2M.

.2 Pipe and couplings to be of the same manufacturer.

.2 Copper Pipe:

.1 Joints on pipe to be made using lead-free solder.

.2 Cut copper pipe square with hacksaw and guide or pipe cutting tool. Remove all burrs and slivers.

.3 Make joints with solder as specified using non-corrosive flux. Clean pipe fittings with steel wool over the whole tack surface before applying flux.

.4 Victaulic groove fittings may be used for 50 mm and larger copper pipe.

.3 Threaded Joints:

.1 Conform to American Standard taper pipe thread.

.2 Use approved type of pipe jointing lubricant on male threads only. Remake all leaking joints with new materials. Do not use caulking compounds.

.4 .Mechanical Joint Couplings:

.1 All grooved end fittings to be of the same manufacturer (e.g., Victaulic).

.5 Install cast bronze couplings when dissimilar pipes are joined. Couplings to be same size as piping.

Page 45: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15100 AND SEWAGE PUMP STATION BUILDING SERVICES PIPING PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 May 2008

.6 Install cast bronze couplings when dissimilar pipes are joined. Couplings to be same size as piping.

2.7 Pipe Supports

.1 Hangers for pipe sizes 12 mm [1/2”] through 65 mm [2-1/2”] to be adjustable wrought ring malleable nut steel band, as Grinnell 97. For copper piping hangers to be plastic coated as Grinnell 97C.

.2 Use wrought clevis hangers for piping 75 mm [3”] diameter and over.

.3 Support vertical piping by means of riser clamps as Grinnell 261. For copper pipe clamps to be plastic coated as Grinnell 261C. Use guides to maintain alignment where necessary.

.4 Support horizontal soil pipe by means of hangers as previously specified at the hub end of each length.

.5 Support vertical soil pipes by means of iron pipe hooks or rings placed immediately below the hub of each length and securely fastened to adjoining walls.

.6 On insulated piping where the insulation is called to have continuous vapour barrier, install oversized hangers and insulation protection shields, with shield gauge and length as recommended by manufacturer. Shield to be as Grinnell Fig. 167.

.7 Do not use perforated hanger straps.

2.8 Pipe Sleeves

.1 Pipe sleeves to be 0.625 mm thick galvanized sheet steel.

.2 Fit sleeves flush on either sides of wall through which they pass, extend sleeves through floors 50 mm [2”] above finished floor.

.3 Make sleeves large enough to accommodate uncompressed insulation on the piping where applicable, otherwise where passing through walls make sleeves minimum 6 mm [1/4”] clear of the piping. Caulk full depth of sleeves with an approved sealant.

2.9 Cleanouts

.1 Cleanouts to be full size for pipe up to 100 mm [4”] and not less than 100 mm [4”] on larger pipe.

.2 Cleanouts on vertical stacks to be Zurn Z-1445-3 with access panel on concealed stacks.

.3 Cleanouts in finished floors to have removable covers, the cover to match surrounding finish, e.g., Zurn ZN-1400-5 for tiled floors.

.4 Cleanouts in unfinished concrete floors to be Zurn Z-1410-2 with clamping collars on units located in waterproofed floors.

Page 46: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15100 AND SEWAGE PUMP STATION BUILDING SERVICES PIPING PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 May 2008

2.10 Floor Drains

.1 Supply and install floor drains in the location and to the size as shown on the drawings and specified herein.

.2 FD-A (Gutter Drain) – Zurn ZXN-415-H-90 152 mm x 152 mm heavy duty floor drain with Dura-coated cast iron body and grate and side outlet.

.3 FD-B – Zurn Z-536 heavy-duty floor drain with 203 mm diameter cast iron strainer.

.4 FD-C - Zurn ZN-415-B-P with nickel bronze strainer, trap and trap primer connection.

.5 AD-A (Area Drain) – Zurn Z509 heavy duty floor drain with 305 mm diameter cast iron strainer, and combination membrane clamp and frame.

2.11 Lead Flashings

.1 Supply and install 25 kg/sq. m. [5 lb/sq. ft.] sheet lead flashings to cleanouts and floor drains. Secure flashings to flashing clamps and extend 300 mm [12”] beyond the edge of the fittings.

2.12 Trap Primers

.1 Supply and install trap primer piping to all floor drains with primer connections to maintain trap seal. Terminate piping adjacent the floor drain for drains installed in suspended floor slabs. Terminate the piping 300 mm above the floor adjacent the nearest wall in a location approved by the Consultant for drains installed in slab-on-grade floors.

3 EXECUTION

3.1 Piping General

.1 Install all piping approximately as shown, conceal piping except in unfinished portions of the building such as pipe spaces, mechanical rooms, etc., unless otherwise approved. Group all piping and run equidistant and parallel to walls, partitions, building lines, etc. Do not cover any piping, fittings or work of any kind before it is examined and approved by the Consultant.

.2 Align and support all piping properly; under no circumstances may any piping load be transferred to the equipment. Make all equipment connections so as to allow disassembly of the piping for equipment removal and maintenance.

3.2 Plumbing Piping

.1 Use DWV copper pipe and fittings as specified, for piping in confined areas (walls, shafts, etc.) when there is insufficient clearance for a hub type pipe and/or as marked on the drawing even if the piping is over 75 mm [3”] diameter.

.2 Grade waste piping, except as specifically noted on the drawings, at 2%. Arrange all vents to drain back to the connected waste lines.

3.3 Flushing of Systems

.1 Thoroughly flush all piping systems with clean fresh water to remove all scale sediment, etc., as soon as possible after completing the system.

Page 47: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15100 AND SEWAGE PUMP STATION BUILDING SERVICES PIPING PAGE 6

ITT PS08037 Versacon Consultants Inc. / 162178 May 2008

.2 Cap or plug all piping, which is to be left disconnected to prevent the entry of foreign material.

3.4 Cleanouts

.1 Supply and install cleanouts in all sanitary piping at the base of every stack and at all changes of direction and as indicated on the drawings, and as required by local codes.

.2 Generally locate cleanouts at intervals not exceeding 15 metres on horizontal drains up to and including 100 mm [4”] diameter and 30 metres [100 ft.] on horizontal drains exceeding 100 mm [4”] diameter.

.3 Extend all cleanouts so that the opening is readily accessible and has sufficient clearance for effective rodding and clearing.

.4 Provide hub adaptor when mechanical joint cast iron pipe is used.

3.5 Tests and Inspection

.1 Supply all labour, materials and equipment necessary for all tests. All tests are subject to inspection.

.2 Tests on plumbing systems to consist of pressure tests. Use soap on all joints being pneumatically tested.

.3 Correct all leaks by remaking the joints and retest the system until no leaks are observed.

.4 Notify the Consultant and the authority having jurisdiction at least 48 hours in advance before commencing any tests.

.5 Tests to be as follows:

.1 All sanitary waste and storm drains - hydraulic 35 kPa for 30 minutes.

3.6 Miscellaneous Metals

.1 Unless otherwise indicated, install all miscellaneous metals required by this Section as shown on the drawings and specified herein. This includes but is not limited to all steel and angle iron required for support and anchoring of piping.

.2 All steel to be in accordance with CSA G40.21 or with ASTM Specification A36.

.3 The design, fabrication and erection of miscellaneous metals to be in accordance with CSA S16 and supplements.

.4 Arc welding to be in accordance with CSA W47, W55 and W59.1.

.5 All steel to receive two coats of shop primer. At the completion of all field welding, touch-up primer and make good. Shop primer to be ready mixed oil alkyd paint for use as a primer on structural steel in accordance with the requirements of CGSB 1-GP-140.

END OF SECTION

Page 48: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15200 AND SEWAGE PUMP STATION CRANE AND HOISTS AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM PAGE 1

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1 GENERAL

1.1 Scope of Work

.1 This section includes the supply, assembly, installation and testing the following:

.1 Two (2) tonne under running traveling crane;

.2 The single girder under running crane shall be installed over the sewage pumps and the monorail shall be installed in the future pressure filter area both as shown or indicated on the pump room area drawings.

.3 Structural requirements and component sizes are shown on the structural drawings. Refer to structural drawings for structural requirements.

1.2 Related Work

.1 Metal Work Division 5

.2 Painting Division 9

1.3 Shop Drawings

.1 Submit shop drawings in accordance with the Contract Documents and Division 1 requirements.

.2 Include complete technical information, and detailed dimensional drawings showing required clearances and minimum distances from rail to hook.

.3 Shop drawings to be signed and sealed by a qualified structural engineer currently registered and in good standing with the professional engineers in the Province of British Columbia (APEGBC).

2 PRODUCTS

2.1 Runways

.1 Runways shall be of standard structural steel sections to G40.21 – 44 W. Fabricate and mount as detailed on the structural drawings.

2.2 Under Running Crane

.1 Supply and install one only single girder under running crane with a minimum capacity of two (2) tonne. The under running crane and hoist shall be sized to suit dimensions on the drawings.

.2 The crane shall be equipped with end trucks.

.3 The crane end trucks shall be equipped for hand geared bridge travel. The drive chain shall be located over the concrete floor walkway as shown on the drawings.

Page 49: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15200 AND SEWAGE PUMP STATION CRANE AND HOISTS AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM PAGE 2

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.4 The hand geared bridge travel shall be accomplished with an endless chain free hanging between 300-500 mm above pump room floor level. The chain wheel shall be equipped with guides to minimize “gagging” of the chain when rapidly handled.

.5 The under running crane complete with end trucks and joists shall meet all the requirements of CSA B1967 CMAA Specification No. 70 and maximum rated load, deflection shall not exceed 1/600 of the span.

.6 Standard of Acceptance 2 tonne CANCO hand geared single girder under running Crane with M3CB020-20 Hoist complete with chain bucket (20 feet of chain) and Mono Tsg 2020 Trolley.

2.3 End Trucks for Overrunning Bridge Crane

.1 The under running crane shall be fitted with end trucks not exceeding 1800 mm in overall length.

.2 The crane shall have double flanged alloy steel wheels hardened to 75-425 BHN. Bearings shall be factory grease packed with sufficient reservoir to eliminate the need for field servicing.

.3 End trucks shall have AGMA specification gearing drive for two wheels. Trucks shall have restraining lugs to limit drop to 25 mm in the event of axle or wheel failure.

.4 The drive cross shaft, with chain drive wheel, shall be supported by lubricated ball bearings and so designed that wheel rotation differential does not exceed one degree at maximum rated load, regardless of load location. See item 2.4

.5 The girder shall be designed to CMAA and AISC specifications and, to maximum rated load, deflection shall not exceed 1/600 of the span.

.6 The end trucks shall be fitted with two neoprene bumper stops mounted on the sides at each end of the truck to permit maximum travel along the runway beams.

.7 The wheels of the end trucks shall be suitable for operating on S250 x 38 runway beams (confirm with structural drawings).

2.4 Geared Trolley Hoist for under running Bridge Crane

.1 Mounted under the crane girder beam shall be a trolley and hoist.

.2 The trolley shall be adjusted to suit the size of crane girder, have anti -friction bearings on each wheel and be chain and gear drive – See Paragraph 2.02.

.3 The integral hoist shall be chain and gear driven with automatic overload protection feature. Chain pull required to raise the maximum rated load shall not exceed 24 kg. The brake shall be fully enclosed and not require lubrication.

.4 The load chain shall be equipped with a swivel and latch type hook. Sufficient load chain shall be provided to permit the eye of the hook to travel at least 6.0 metres below the hoist.

.5 Provide M3C020-20 hoist, or approved equal, rated capacity 2 tonnes.

Page 50: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15200 AND SEWAGE PUMP STATION CRANE AND HOISTS AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM PAGE 3

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.6 Provide Mono Tsj 2020 Trolley rated capacity 2 tonnes.

2.5 Painting

.1 All fabricated crane components, hoists and trolleys shall be sand blasted and factory coated with one coat of rustoleum primer and two coats of machinery enamel (International Paints B256 – extra caution orange). Two litres of touch up enamel shall be supplied with the cranes. Capacities shall be clearly indicated on hoists, crane and both monorails. The crane shall be marked “capacity 2 tonne”.

3 EXECUTION

3.1 Runways

.1 Runway beam operating surfaces shall be straight, parallel, level and at the same elevation. The centre to centre distance shall be within a tolerance of plus or minus 3 mm.

.2 Welding shall be completed by certified welders and in accordance with applicable standards. All welds shall be ductile, have good penetration free of cracks and undercuts and shall manifest workmanlike appearance.

3.2 Crane and Hoist

.1 Erection shall be in accordance with manufacturer’s instructions and stamped shop drawings

END OF SECTION

Page 51: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15300 AND SEWAGE PUMP STATION FIRE PROTECTION PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Work Included

.1 Wet and dry sprinkler systems as shown on the drawings including all piping, sprinkler heads, valves, water motor gongs, flow switches, air compressors, tamper switches, hangers and supports, system drains, fire department connection, inspectors test connections and all other accessories as required.

.2 Connect to incoming water mains as shown on the drawings.

1.2 General Requirements

.1 All labour and materials to be in accordance with the requirements of NFPA 13 (1999) and the Authority Having Jurisdiction.

.2 Submit working drawings and hydraulic calculations to the Consultant for review prior to submitting to the Authority Having Jurisdiction.

.3 Installation shall not commence until the working drawings and hydraulic calculations have been reviewed and accepted by the Authority Having Jurisdiction.

.4 It is specifically understood that all items of work and systems be furnished and installed complete in all details, including all necessary specialties and other appurtenances.

1.3 Quality Assurance

.1 Sprinkler systems and all equipment shall be installed by qualified contractors licensed and regularly engaged in the installation of automatic fire sprinkler equipment.

.2 Employ on the site at all times a competent superintendent who shall be responsible for the progress and execution of the work. Workmanship to be of the best standard practice as stipulated by the ASTM, NFPA and ANSI recommendations.

.3 All sprinklers, valves, fittings, gauges, pipe hangers, and other accessories to be of a type which is listed or labelled by Underwriters Laboratories of Canada (ULC). Use of such materials and equipment shall conform to all requirements and limitations of their listings. If suitable ULC listed or labelled products are not available, products listed by other testing agencies (FM, ULC, Warnock Hersey, etc.) may be used with the prior written approval of the FCC.

2 PRODUCTS

2.1 Piping

.1 Piping to be new schedule 40 standard weight, Allied XL threadable lightwall pipe, or type L copper. Other types may be used if listed for this service by ULC, ULI, or FM.

.2 Fittings to be new 860 kPa [125 psi] cast iron or 1030 kPa [150 psi] malleable iron, approved for use in fire protection systems.

.3 All pipe and fittings in the Wet Well area and the Odour Control Room are to be galvanized.

Page 52: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15300 AND SEWAGE PUMP STATION FIRE PROTECTION PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.4 Screwed pipes to have threads cut to American standard pipe thread.

.5 Install piping in a uniform manner, direct as possible. Install piping to provide proper slope where required. Install sprinkler piping in such a manner that the entire system may be drained at a central point if possible. Where piping cannot be pitched to a central point, provide drainage facilities for such portions of the system as may be required to permit adequate drainage.

.6 Where applicable, with exception of branch piping, joints and straight runs of steel piping may be flanged, screwed or rubber gasketed-grooved type, Victaulic, Couplox, or approved equal. Shop welding, in conformance with NFPA #13, may be used. Note that on rubber gasketed-grooved type joints, all fittings and couplings are to be of the same manufacturer throughout.

.7 Install all branch piping with screwed fittings except as noted.

.8 Provide suitable test and drainage piping, valves and fittings on sprinkler systems as required by NFPA #13.

2.2 Sprinkler Heads

.1 Sprinkler heads shall be as specified below. All automatic water spray heads are to be of the latest design as listed and approved by ULC, with standard 12 mm [1/2”] orifice.

.1 Finished areas with ceilings, provide quick response chrome plated Reliable F-1 adjustable recessed flush pendent heads.

.2 Finished areas without ceilings, provide quick response chrome plated brass upright heads.

.3 Unfinished areas (attic, etc.) provide quick response standard brass upright or pendent heads.

.4 Unfinished areas, Plant, Service and Shop Areas, Mechanical Rooms provide standard brass quick response upright or pendent heads.

.5 Wet Well, Odour Control Room, and cold concealed areas, provide quick response standard brass upright or dry pendant heads.

2.3 Valves

.1 All valves to be Underwriter’s Laboratories Canada listed for 1200 kPa [175 psi] working pressure on sprinkler and standpipe systems.

.2 All valves to be plainly marked with the manufacturer's name and trademark, the size of the valve and the ULC or FM identification marks.

.3 All control valves installed to be O.S. & Y. or ULC approved butterfly type and be complete with approved type supervisory switches.

.4 Gauge control valves to be bronze body needle type with inspector's test connection and plug.

.5 It is the responsibility of this section to supply and install all valve supervisory switches.

.6 Wiring from supervisory switches to annunciator panel, etc., electrical division.

Page 53: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15300 AND SEWAGE PUMP STATION FIRE PROTECTION PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

2.4 Alarm Check Valves

.1 Alarm check valves to be complete with 50 mm [2”] diameter drain, excess pressure pump, pressure switch and water pressure gauges. Excess pressure pump to be as Albany Model CEP 67, 1/3 hp motor, 110V single phase.

.2 Dry System alarm check valve to be iron body, bronze trim, complete with quick opening device if needed, and all accessories, interconnecting piping and subassembly valves and other necessary appurtenances required for complete installation.

2.5 Water Flow Switches

.1 Provide and install water flow switch to each sprinkler system as shown on the drawings.

.2 Flow switches to be connected to an alarm system in such a manner that operation of one sprinkler will actuate the alarm system and the location of the operated switch indicated on the annunciator or register.

.3 Wiring from water flow switches to annunciator panel and the supply and installation of panel is by Electrical Division.

2.6 Siamese Connections

.1 Provide appropriately labelled wall type Siamese fittings consisting of rough brass body with polished swivels, caps and chains, at locations indicated on the drawings. Units to have 65 mm [2-1/2”] B. C. Fire Marshall threads and shall be ULC listed and approved. Wall plates to be chrome plated finish as N.F.E. Model #229 angle body. Submit shop drawings for the Siamese fitting.

2.7 Pressure Gauges

.1 Furnish and install ULC approved pressure gauges on both the upstream and downstream side of all pumps and where shown on the drawings. Unless otherwise noted, gauges are to be as Marsh Type 8 or approved equal.

.2 Gauge characteristics to be as follows:

.1 Standard brass case construction.

.2 Bourden tube type, of seamless copper alloy with brass tip and socket.

.3 Accurate to + 2% over the dial range.

.4 Movement to be of special hard brass.

.5 All gauges to be installed with isolation valves and snubbers.

.6 Dial to be 65 mm [2-1/2”] diameter, minimum.

2.8 Air Compressors

.1 Supply and install air compressors, approved for use in sprinkler systems and ULC approved, in the locations as shown on the drawings.

Page 54: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15300 AND SEWAGE PUMP STATION FIRE PROTECTION PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Compressors to be sized in accordance with the requirement of NFPA #13.

3 EXECUTION

3.1 Installation

.1 Use materials that bear the manufacturer's identification mark in addition to all other markings required by the specifications.

.2 Install all piping parallel to building walls and at a height so as not to obstruct any portion of a window, doorway, stairway, or passageway and to clear building ductwork, heating, cooling and plumbing piping.

.3 Provide and keep up to date, a complete set of project record drawings in accordance with the "Basic Mechanical Requirements", Section 15010.

.4 Report to the Consultant when structural difficulties or the equipment and work of other trades interfere with the location of this work. Minor deviation of piping from the locations shown on working drawings may be made in the field, shown on the project record drawings and reported to the Consultant later, provided such minor relocations do not interfere with the existing conditions, nor with the intended use of the space involved, nor with the system design intent.

.5 All tests and adjustments required by NFPA 13, Chapter 8 shall be performed. Copies of completed Aboveground and Underground Contractor’s Material and Test Certificates shall be delivered to the FCC at least two full working days prior to the building takeover inspection.

.6 Supply and install cabinet containing spare sprinkler heads corresponding to the types and temperature ratings as installed in the building. Cabinet to be located as indicated on site and shall include sprinkler wrench suitable for each head type. Provide a minimum of six spare heads for each type of head installed.

3.2 Pipe Supports

.1 Hangers to be ULC listed and as approved by NFPA for use on fire protection systems.

.2 Rod sizes to be as follows:

.1 Piping up to 100 mm [4”] diameter - 9 mm [5/16”] diameter rod

.2 Piping 125 mm and 150 mm [5” and 6”] diameter - 12 mm [1/2”] diameter rod

.3 Piping 200 mm [8”] diameter and over - 18 mm [3/4”] diameter rod

.3 Space hangers for horizontal piping in accordance with the following:

.1 Pipe sizes 25 mm and 32 mm [1” and 1-1/4”] - 3.0 metres [10 ft.] apart maximum

.2 Pipe sizes 37 mm to 100 mm - 3.6 metres [12 ft.] apart maximum

.3 Pipe sizes 125 mm [5”] and over - 4.5 metres [15 ft.] apart maximum

.4 Install hanger rods vertical, without bends or offsets, so that finished piping is aligned correctly both with respect to line and grade.

Page 55: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15300 AND SEWAGE PUMP STATION FIRE PROTECTION PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.5 Secure all hanger rods directly to the building structure by means of inserts or clamps. Do not support from other pipes and ducts.

.6 Support vertical piping at its base by hangers placed as near as possible to the horizontal pipe to which it is connected. Provide pipe supports at each floor using iron brackets and pipe clamps.

3.3 Earthquake Protection

.1 Supply and install sway bracing to all cross-mains, loops 50 mm [2”] in diameter and larger, all feed mains and risers.

.2 Bracing on piping to be as follows:

.1 Two way bracing on horizontal piping spaced a maximum 12 metres [40 ft.] apart.

.2 Two way bracing at the corners of loops 50 mm [2”] in diameter and larger.

.3 Four way bracing at the top of risers.

.3 All bracing to be in accordance with the requirements of NFPA 13.

3.4 Flushing Systems

.1 Flush all piping prior to making final connections to remove all dirt and foreign matter. Run discharge to sewer.

3.5 Performance

.1 The Contractor is responsible for layout of piping and sprinkler heads as approved on working drawings.

.2 The Contractor to hydraulically design system to perform in accordance with the following:

.1 All areas except office areas:

.1 Ordinary Hazard, Group 2

.2 Office Areas:

.1 Light Hazard

.3 Hydraulic calculations are to include for 20% more in volume than the total sprinkler demand and 10% more pressure at the base of the riser required by Authority Having Jurisdiction.

.4 Hydraulic calculations and working drawings to be presented in a manner acceptable to NFPA 13. Contractor to note all requirements of NFPA 13.

.5 The Contractor shall test the system flow to provide the final data for the sprinkler system design and shall report the results of the flow test to the Consultant.

Page 56: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15300 AND SEWAGE PUMP STATION FIRE PROTECTION PAGE 6

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

3.6 Tests and Inspections

.1 Supply all labour, materials and equipment necessary for all tests. All tests are subject to inspection, Consultant or his representative shall witness tests.

.2 Notify the Consultant and the authority having jurisdiction, at least 48 hours in advance, before commencing any tests.

.3 Hydraulically test all wet and dry sprinkler systems and standpipe systems at not less than 1380 kPa [200 psi] for 2 hours in the manner as prescribed in NFPA 13 and 14 respectively, with no leakage.

.4 Hydrostatically test all new outside protection yard piping at not less than 1380 kPa [200 psi] for 2 hours. Test procedures and permissible leakage for joints, valves and hydrants are as prescribed in NFPA 24.

.5 Where the static pressure exceeds 1030 kPa [150 psi], increase the test pressure in all of the above to 340 kPa [50 psi] in excess of the actual maximum static pressure.

.6 If the test leakage in any section is greater than that permitted by the NFPA, locate and repair the defective joints of pipe until the leakage is within the permitted allowance.

END OF SECTION

Page 57: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15400 AND SEWAGE PUMP STATION PLUMBING FIXTURES AND EQUIPMENT PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Work Included

.1 Furnish all labour and materials, services and equipment required for the installation a complete operable plumbing system as shown on the drawings and specified herein.

1.2 Related Work

.1 Basic Mechanical Requirements Section 15010

.2 Mechanical Insulation Section 15080

.3 Building Services Piping Section 15100

1.3 General Requirements

.1 Install all plumbing systems to the requirements and standards of the 2007 City of Vancouver Building By-law.

2 PRODUCTS

2.1 Fixtures

.1 All fixtures to be free from flaws or blemishes with surfaces clear, smooth and bright and have dimensional stability.

.2 Exposed trim, supplies, traps, tubing, escutcheons and valves to fixtures to be chrome plated, unless otherwise noted.

.3 Materials to be as follows:

.1 Stainless steel fixtures to CSA B45.4-1975 Class II, Type 316 in accordance with CSA G110.6-1968.

.2 Plumbing fittings to CSA B125-1975.

.4 Water Closet WC-1

.1 Caroma “Sydney 270” 431 mm high vitreous china elongated syphon jet bowl, dual flush 6/3 LPF, with bolt-down lid, 37 mm top spud and bolt caps.

.2 Caroma solid plastic white toilet seat with open front for elongated rim and with lid.

.5 Lavatory L-1

.1 American Standard 0955 000 “Murro” Universal Access vitreous china lavatory with overflow and with single supply opening.

.2 Zurn carrier to suit lavatory.

Page 58: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15400 AND SEWAGE PUMP STATION PLUMBING FIXTURES AND EQUIPMENT PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.3 Delta 22T601 single hole lavatory faucet in chrome finish with lever handle and 0.5 USGPM spray outlet.

.4 Open grid strainer and chrome plated 32 mm offset drain with chrome plated cast brass P-trap.

.5 10-mm supplies with Dahl mini-ball valve angle stops, chrome plated flexible risers and escutcheons.

.6 Sink S-1

.1 Aristaline QDL2031/8 double bowl ledge back stainless steel sink, with two 410 mm x 360 mm x 200 mm deep bowls, with two supply openings 102 mm on centre, 89 mm crumb cup strainer, 37 mm “P” trap assembly.

.2 American Standard #GV 2021.600 kitchen sink faucet in chrome finish with single lever handle and water economy aerator, less escutcheon plate.

.3 10-mm supplies with Dahl mini-ball valve angle stops, chrome plated flexible risers and escutcheons.

.7 Shower SH-1

.1 Delta 11T5153 handshower with wall fitting, pressure balanced shower valve with 57 mm blade handle, 610 mm combination slide and grab bar.

.2 ZN 415- P-6 floor drain, with trap primer connection FD-1.

.8 Emergency Eye Wash EW-1

.1 Guardian Equipment G1814/BC/TMV eyewash with spray head assembly, valve, stainless steel bowl, stainless steel bowl cover, mounting bracket, and TMV G3600 thermostatic mixing valve mounted in a stainless steel box.

2.2 Electric Hot Water Heater DHWT-1

.1 Electric water heater to be Rheem Fury RR415T, 175 litre capacity, 3.0 kW, 208/1/60 power supply. Tank to be glass lined, fibreglass insulated, with anode rod, automatic temperature control, and six year warranty on tank. Install ASME rated temperature and pressure relief valve on tank and pipe outlet full size to drain. Provide vacuum relief valve for the tank.

2.3 Washdown Hot Water Tank

.1 AO Smith HD 54-1000, 1371 x 2667 mm long, glass lined storage tank with immersion bundle NW6-96, 277 litres per hour recovery using 4.9 l/s (78 gpm) of 82C heating water.

2.4 Expansion Tank ET 1

.1 ASME rated 1030 kPa [150 psi] precharged steel expansion tank with heavy duty diaphragm. The tank shall have a top NPT system connection, NPT drain, and a .302-32 charging valve connection. Provide 12 mm valved drain connection piped to the nearest floor drain, and pet cock on the top of the tank. Total tank volume shall be 7.5 litre [2.0 gal]. Tank is Therm-X-Trol model ST-5 or other approved.

Page 59: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15400 AND SEWAGE PUMP STATION PLUMBING FIXTURES AND EQUIPMENT PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

3 EXECUTION

3.1 Plumbing Fixtures

.1 Install concealed water supply piping to plumbing fixture supplies using cast brass 90-degree drop ear elbows or drop ear tees as the piping design dictates. Provide blocking within the concealed space and secure elbows and tees to blocking using brass screws.

.2 Supply and install all hangers, supports, brackets, reinforcement, 14 gauge thick steel backup plates, etc., for the proper installation and support of such fixtures and their respective supply fitting.

.3 Where plumbing fixtures come in contact with wall and/or floor, seal joints with Dow Corning 780 building sealant, made watertight and beaded smooth in a neat workmanlike manner.

.4 Install shower bases and shower cabinets on a mortar bed with polyethylene sheet between the mortar and the shower base.

3.2 Equipment

.1 Install equipment in accordance with manufacturer’s recommendations.

3.3 Miscellaneous Metals

.1 Unless otherwise indicated, install all miscellaneous metals required by this Section as shown on the drawings and specified herein.

.2 All steel to be in accordance with CSA G40.21 or with ASTM Specification A36.

.3 The design, fabrication and erection of miscellaneous metals to be in accordance with CSA S16 and supplements.

.4 Arc welding to be in accordance with CSA W47, W55 and W59.1.

.5 All steel to receive two coats of shop primer. At the completion of all field welding, touch-up primer and make good. Shop primer to be ready mixed oil alkyd paint for use as a primer on structural steel in accordance with the requirements of CGSB 1-GP-140.

END OF SECTION

Page 60: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 1

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1 GENERAL

1.1 Description

.1 The work of this section includes the installation of sewage piping, valves systems and related equipment to be installed in the sewage pump room only.

.2 Piping covered under this section extends through the pump station concrete walls and connects with other piping systems which are not included in this section. Refer to other sections for continuation of sewage piping systems beyond the pump room.

.3 Other process piping systems are also installed in the pump room and are not included in this section. Refer to the contract documents and other sections for other piping or related systems.

1.2 Work Included

.1 The work of this section includes but is not limited to the items generally described following:

.1 Supply and installation of sewage pump suction and discharge piping complete with valves and related equipment. Suction piping extends into the pump station wet wells.

.2 Supply and installation of miscellaneous station piping, valves and related equipment.

.3 Supply and installation of sump pumps and discharge piping installed in the pump room.

.4 Co-ordination with pumping equipment installations in the Pump Room and Wet Well Area. See Section 15600 “Pump Station Sewage Pumps”.

.5 Coordination with Division 16 work to ensure all equipment is wired, connected.

.6 Supply and installation of all other mechanical items, equipment and components required or necessary to provide a complete working installation.

.7 Testing and commissioning of all piping & pumping systems and all related mechanical and electrical equipment and appurtenances. Testing and commissioning to be in co-ordination with other related work including Division 15 mechanical work and Division 16 electrical work.

1.3 Shop Drawings

.1 Provide shop drawings for all equipment covered in this section including piping, valves, couplings, fittings, pipe supports, brackets, fasteners and other equipment.

.2 Submit mill certificates for all steel pressure piping showing mechanical and chemical properties and indicating compliance with steel pipe specification requirements.

.3 Shop drawings to Division 1 Requirements.

Page 61: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 2

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1.4 Related Work

.1 Forcemain and Buried Piping Division 2

.2 Metals Division 5

.3 Sewage Pumping Equipment Section 15600

.4 Electric Valve Actuators Section 15850 and 15860

.5 Slide Gates Section 15800

.6 Screens Section 15900

.7 Mechanical Equipment Division 15

.8 Electrical Equipment Division 16

2 PRODUCTS

2.1 Steel Pipe and Fittings to 600 mm Nominal Diameter

.1 All steel pipe shall be ASTM A53, ERW, Grade B or steel pipe with equivalent or better mechanical, chemical properties with the following wall thickness:

.1 75 mm to 250 mm diameter inclusive: schedule 40.

.2 300 mm diameter: standard weight, 0.375 inch wall.

.3 350 – 600 mm diameter: 0.375 inch wall thickness.

.2 Steel butt weld fittings: Steel butt weld fittings shall be in accordance with ANSI B16.9 with wall thickness to match connecting pipe wall.

.1 Steel butt weld reducers as shown on the drawings.

.3 Steel Pipe Flanges: Steel pipe flanges for steel fittings shall be forged carbon steel to ASTM A181, Grade II, Class 150.

.4 Steel Pipe Flange faces: Flanges shall be flat face where connection is to flat face flanges and raised face where connection is to raised face flanges. Raised face flange facings shall be the same for connecting flanges.

.5 Steel Plate: to CAN3-G40.21-92, Grade 300W.

.6 Victaulic Couplings: Style 07 or as indicated on the drawings with gaskets rated for full vacuum.

.7 Reducers: Fabricated steel (eccentric or concentric) as indicated on the drawings;

.8 Bell Mouths for pump suctions: Fabricated concentric bell mouth as indicated on the drawings.

.9 Victaulic Fittings: As shown on the drawings.

Page 62: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 3

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

2.2 Sewage Pipe Linings and Coatings for Steel Pipe and Related Items

.1 Pipe linings and coatings for steel pipe shall be shop applied following fabrication and all welding.

.2 All steel pipe, fittings, flanges, couplings, fasteners and all attached accessories shall be coated and lined to pipe standards except where noted otherwise.

.3 Pipe linings and coatings shall conform in all respects with the following AWWA standard:

.1 AWWA C210 - 84: "Liquid epoxy coating systems for the interior and exterior of steel water pipelines."

.2 Colour: City of Vancouver Green (confirm with Owner).

.3 Top coat: two coats urethane to match colour specified by Owner.

.4 The supplier will be required to provide certification that the lining and coating material meets the required specification and that the application contractor is a qualified AWWA applicator and has proper facilities.

.5 Acceptable Products:

.1 Interior pipe linings: ICI Devoe - Bar Rust 236 or approved equal;

.2 Exterior pipe coatings: ICI Devoe - Bar Rust 236 or approved equal;

.3 Exterior pipe top coat: ICI Devoe - Devthane 369 or approved (Confirm colour with Owner).

.6 Fabricated metal items shall also be coated using same products (and colour) used for pipe coatings. See Division 5 and Division 9 for metal fabrications and painting.

.7 Contractor supplied pumps and motors shall be painted using same products (and colour) used for pipe coatings.

.8 All valves, fittings, couplings and all other metal components are to be coated to the pipe coating specification. If this equipment is supplied with a factory enamel finish it shall be top coated with the referenced top coat to match the required piping colour. Prior to top coating factory coatings the Contractor shall confirm the compatability of coatings systems and provide any barrier or primer coatings prior to top coating.

2.3 Small Bore Piping and Tubing

.1 Small bore piping and tubing shall be to the diameters and materials shown on the pump room drawings.

.2 Locations and lengths of small bore piping are shown in schematic form only and the Contractor shall be responsible for making all on site measurements required to confirm material quantities.

.3 Small bore piping for instruments shall be or 316 stainless steel pipe or tubing as shown on the drawings and shall include all necessary fittings, couplings, unions, ball valves,

Page 63: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 4

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

fasteners, straps, fasteners, instrument backboard and related accessories. All small bore pipe, tubing and accessories shall be rated for not less than 200 psi working pressure.

.4 Discharge piping for the sump pumps in the sewage pump room shall be type L copper pipe to ASTM B 88 with brazed joints and fittings. See section 15600 for sump pumps.

2.4 Flanged Adaptors and Restrained Flange Adaptpors

.1 Ebaa Iron Mega Flanges: See drawings.

.2 For nominal pipe sizes less than 350 mm (14 inch) diameter:

.1 Romac Style FCA 501 ductile iron body and end ring or approved equal;

.2 Epoxy coated;

.3 Gaskets to suit pipe outside diameters as confirmed by Contractor;

.4 Top coated by Contractor to match pipe coating colour.

.3 For nominal pipe size greater than 350 mm diameter:

.1 Romac Style FC 400 steel body and end ring or equal Robar;

.2 Epoxy Coated;

.3 Gaskets to suit pipe outside diameters as confirmed by Contractor;

.4 Top coated by Contractor to match pipe coating colour.

2.5 Straight and Transition Couplings

.1 Romac Style 400 with ductile iron body and end rings or equal Robar;

.2 Fusion bonded epoxy lined and coated to AWWA C213-01, 12 mils minimum thickness interior and exterior;

.3 Gaskets to suit pipe outside diameters as confirmed by Contractor;

.4 Top coated by Contractor to match pipe coating colour.

2.6 Resilient Eccentric Seated Plug Valves – Manually Operated

.1 Plug valves for use in the sewage pump room or wet area piping shall be ductile iron, lubricated, flanged with totally enclosed manual worm gear actuator operator (permanently lubricated) with bronze bushings- meeting following criteria:

.1 Round or rectangular ports with port equal to minimum 90% of pipe area;

.2 Welded nickel seating;

Page 64: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 5

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.3 One-piece valve plug covered with molded resilient facing of Buna N with 70 durometer rating;

.4 Grit seals;

.5 Thrust bearings, stainless steel shaft, bronze cartridge or self adjusting packing type shaft seal per AWWA C504 and C507.

.6 Confirm gear actuator mounting position with Engineer.

.7 Proof of design test, per AWWA C504 for leakage.

.8 Valve shall be rated for 175 psi working pressure with drop tight shot-off in both flow directions.

.9 Valve interior to be lined with 4-6 mils of a two part hi-build epoxy.

.10 Valve exterior to be prime coated by manufacturer and shop painted by the Contractor to same standards and colour as fabricated pipe.

.11 Acceptable plug valves:

.1 Dezurik;

.2 Valmatic;

.3 Pratt;

2.7 Resilient Eccentric Seated Plug Valves – Electrically Operated

.1 Plug valves for use in the sewage pump station or wet well area which are electrically operated shall be similar to manual plug valve but fitted with electric actuators.

.2 See section 15860 for quarter turn actuators and related items and requirements.

.3 Acceptable plug valves:

.1 Dezurik;

.2 Valmatic;

.3 Pratt;

2.8 All Stainless Steel Knife Gate Isolation Valves

.1 Knife gate valves to be bubble-tight at rated pressures for bi-directional flow conditions, and shall be satisfactory for applications involving shut-off service and valve operation after long periods of inactivity.

.2 Knife gate valves to be suitable for handling unscreened raw combined sewerage. Valves will normally operate in the fully open or fully closed positions.

Page 65: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 6

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.3 Pressure Rating: 1035 kPa (150 psi), pressure rating for valves to be CWP.

.4 Temperature Rating: Operating temperatures from 0°C to 35°C

.5 Stainless steel, solid one piece body, Type 316 or 317L.

.6 Replaceable resilient EDPM zero leakage valve seat.

.7 Gate shall be 316 or 317 L stainless steel of the same grade used in body

.8 Yoke shall be 316 or 317 Stainless steel.

.9 Yoke Fasteners shall be stainless steel.

.10 Stem shall be stainless steel.

.11 Packing to be PTFE (wedge shape).

.12 Followers - stainless steel.

.13 Flanges to be full lug, threaded ANSI B16.1 125/150

.14 Valve Actuator - Max. pull on handwheel 18 kg (40 lb)

.15 Packing Injectors - In-line replaceable packing complete with safety check valve to prevent back flow while replacing.

.16 Provide padlock lockout feature so that valves can be positively locked in the closed or

.17 Valves are to have resilient seats with no channels in the bottom of the valves.

.18 Acceptable valves:

.1 Fabri C37 S or approved equal.

2.9 Swing Check Valve – Anti Surge Type with Position Indicator

.1 Check valve shall be purpose designed to minimize surge by incorporating a quick closing spring assist design and reduced flapper angle.

.2 Ductile iron flanged body and cover with bronze flap ring and seat ring.

.3 Shaft shall be one piece stainless steel (type 304 or approved equal) with o-ring seals and shall be sufficiently extended from the body of the valve to allow the addition of external closing devices.

.4 The disk and arm shall be cast iron and the disk shall be fitted with a replaceable bronze seat.

.5 All internal components shall be replaceable in the field without removing the main valve from the pipeline.

.6 The valve shall be fitted with:

Page 66: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 7

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.1 Outside screw device under valve body to lift flapper for back flushing and:

.2 A flap position indicator on the top of the valve body to indicate any position of the valve from fully open to fully closed.

.7 The valve shall be flanged with a minimum pressure rating of 1035 kPa.

.8 Acceptable valves:

.1 Valmatic Surgebuster;

.9 Valve exterior to be prime coated by manufacturer and shop painted by the Contractor to same standards and colour as fabricated pipe.

2.10 Ball Valves (full bore)

.1 See drawings for requirements.

.2 All ball valves (unless specified otherwise) shall be 316 stainless steel Model G2 as supplied by M.A. Stewart or approved equal (500 psi working pressure).

2.11 Air Valves

.1 Air valves shall be as indicated on the drawings.

.2 Air valves shall be combination air/vacuum valves.

.3 Air valves shall have stainless steel bodies with stainless steel trim and floats.

.4 Air valves shall be rated for 150 psi working pressure.

.5 Air valves shall have 75 mm flanged inlet and outlet.

.6 Air valves inlets and outlets shall be connected to station piping using threaded brass piping. Outlet shall be piped to drain as indicated on the drawings.

.7 Air valves (unless stainless steel) shall be painted in accordance with pipe specifications.

.8 Acceptable products:

.1 A.R.I D-023 “Galil” as supplied by Martech Marketing, Surrey B.C.

2.12 Bolts & Nuts

.1 Where supplied as an integral part of manufactured products including: couplings, joint restraint assemblies and similar items:

.1 Bolts and nuts to be high strength low alloy steel to AWWA C111.

.2 All bolts and nuts shall have hexagonal heads and shall be zinc coated. Bolts shall not protrude more than 1/2 inch through nuts.

Page 67: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 8

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.2 Low Strength Bolts and Nuts for use in joining mechanical components including flanges and similar products not covered under manufactured products (to be used unless otherwise specified or noted on the drawings):

.1 Bolts to be carbon steel, Grade B to ASTM A307, heavy hex style, hot dip galvanized to ASTM A153, zinc plated to ASTM B633 or cadmium plated to ASTM B766. Bolt sizes to AWWA C110.

.2 Nuts and Washers: Nuts to be heavy hex carbon steel, to ASTM A563 Grade A, Washers to be flat hardened steel to ASTM F436. Nuts and washers to be zinc plated to ASTM B633 or cadmium plated to ASTM B766.

.3 Field paint all nuts and bolts after installation using same paint materials used for pipe coatings.

2.13 Flange Gaskets

.1 Flange gaskets for flat face flanges shall be full face type, manufactured from black natural rubber with a layer of cotton on both sides.

2.14 Pipe Supports and Brackets in the Sewage Pump Room

.1 Pipe supports and brackets shall be provided as shown on the drawings.

.2 All pipe supports and brackets shall be painted using same materials and requirements as pipe coatings.

.3 Pipe supports shall be installed using approved procedures for:

.1 grouting;

.2 leveling and setting of pipe supports;

.3 snugging up of pipe support to induce small amount of compression into support and then using wedges to maintain setting until anchor bolts and anchor bolt inserts are installed.

.4 installation of anchor bolts and inserts.

2.15 Pipe Supports and Brackets in the Wet Well Area

.1 Pipe supports and brackets shall be provided as shown on the drawings.

.2 All pipe supports and brackets shall be hot dip galvanized.

.3 Pipe supports shall be installed using approved procedures for:

.1 grouting;

.2 leveling and setting of pipe supports;

Page 68: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 9

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.3 snugging up of pipe support to induce small amount of compression into support and then using wedges to maintain setting until anchor bolts and anchor bolt inserts are installed.

.4 installation of anchor bolts and inserts.

2.16 Sump Pumps and Discharge

.1 Sump pumps, installation and discharge piping works shall be as shown on the drawings.

.2 Discharge piping includes removable hose section to match pump discharge (with stainless steel hose clamps), cam lock quick disconnect couplings and 75 mm diameter type L rigid copper or stainless steel pipe as shown on the drawings. Copper pipe shall be painted with same material as steel water pipe (confirm colour).

.3 Sump pump piping discharges to the wet well area as shown on the drawings.

3 EXECUTION

3.1 General

.1 Prior to all work in this section, the Contractor shall become thoroughly familiar with the site and all portions of the work within this section and other related sections, including electrical work.

3.2 Piping Layout and Installation

.1 Fabricate all pipe systems as detailed on the drawings.

.2 Welding shall be performed only by qualified companies and welders certified under CSA Specification W47.1 for the type of welding to be employed during the work.

.3 All piping shall be fabricated, welded, assembled, examined, inspected and tested in accordance with the requirements of ANSI/ASME code for pressure piping 31.3.

.4 The Contractor shall be responsible for taking accurate measurements in the pump station to ensure accurate fabrication and exact fit of all piping and closure pieces required for the pump station piping and pipe specials. Piping fabrication shall involve both shop and field work with pipe closure pieces field fit with final fabrication in the shop to ensure proper fit and alignment of all piping closures.

.5 Discharge piping for the station pumps shall not be finish bolted to the pump discharge head flange until discharge head and motor have been installed and the alignment and fit of pump components has been checked and approved by the pump supplier to ensure no residual stresses are induced in the pump or attached piping systems.

.6 Pump discharge and suction piping shall connect to pump suction and discharge nozzles or flanges with correct alignment without displacement or torque on piping or pump flanges and with no residual stresses induced in the pump or attached piping systems.

.7 All steel pipe welds are to be full penetration butt welds.

Page 69: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 10

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

3.3 Steel Pipe Welds

.1 Unless otherwise approved, all steel pipe welds shall be full penetration butt welds and shall be used for pipe to pipe joint welds, pipe to component welds.

.2 Unless otherwise approved all welds shall be shop welds.

.3 Steel pipe supplied by the contractor shall be provided with bevel ends suitable for butt welding.

.4 All steel pipe, fittings and other components shall have butt ends in conformance with the requirements of Section 7 of CSA Z662-94.

.5 Coatings and linings systems shall be installed on all welded joints in accordance with the requirements of the specifications.

3.4 Pipe Welding Procedures and Qualifications

.1 Prior to any shop production welding of steel pipe, the Contractor shall have all welding procedure specifications established, qualified and approved by the Engineer in accordance with the requirements of these specifications.

3.5 Pipe Shop Welding

.1 All welds shall be shop welds unless otherwise approved by the Engineer.

.2 All pipe welds shall be in full compliance with WCB health and safety regulations.

.3 Where steel pipe has been previously shop coated and is required to be field or shop cut and welded (if approved by the Engineer), existing pipe coatings and linings shall be removed from the interior and exterior of the pipe for the distance required for proper welding procedures and to eliminate damage to the existing coatings and linings systems.

.4 Coatings and linings systems shall be installed on all welded joints in accordance with the requirements of the specifications.

.5 All shop welds shall be non-destructively examined by the a qualified testing agency retained by the Contractor for imperfections and defects to determine their acceptability in accordance with these specifications. The Owner may retain a testing agency for independent testing.

.6 All welds which do not meet the acceptance criteria of these specifications shall be considered defective.

.7 Defective welds shall be repaired in accordance with AWWA C200 and AWWA C208 if such defective welds are considered repairable by the Engineer. Welds shall be repaired only after receiving approval from the Engineer.

3.6 Welding Inspection and Testing

.1 All welds including full and partial length pipe sections, specials, mitre bends, bends, fittings shall be examined by the Contractor's testing agency by radiographic or other approved methods to confirm the adequacy of the weld.

Page 70: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 11

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.2 The Owner may also retain an independent testing agency for welding inspections in which case the Contractor shall schedule and arrange for the Owners' testing agency to conduct all welding tests, inspections required under these specifications and as necessary for completion of the work.

3.7 Installation of Manual and Electric Actuated Valves

.1 The Contractor shall install all valve equipment as indicated on the drawings and in accordance with the recommendations of the valve manufacturer and supplier.

3.8 Application of Pipe Linings and Coatings (and for other specified metal items)

.1 Surface preparation shall be to SSPC SP 10 or as recommended by the lining manufacturer or required by AWWA standards or NSF requirements for potable water use.

.2 The lining and coating material shall be applied in strict accordance with the manufacturer's recommendations. Final DFT thickness of cured linings and coatings shall not be less than 18 mils as determined by shop inspection.

.3 Linings and coatings shall be heat cured.

.4 Linings and coatings shall be tested for imperfections as specified by the governing AWWA specifications. Any deficiencies found shall be repaired to specification requirements.

.5 Linings and coatings shall be applied after all shop welding for the pipe mitres has been completed. Top coat to be applied after coatings have cured and colour specified by the Owner.

.6 Field application of linings and coatings will not be permitted except for field touch-up of damaged surfaces or as directed by the Engineer.

.7 Hot dip galvanizing shall conform to Division 5 requirements.

3.9 Pressure Testing of Piping Systems

.1 All station piping and/or piping assemblies including pipe spools, valves, flanges, gaskets and related appurtenances shall be pressure tested to 150 psi water pressure.

.2 The pipe assembly will be deemed to have passed the pressure test when the pipe under test pressure maintains the 150 psi pressure without drop for a 1 hour period and does not require any make-up water to return the pressure to 150 psi.

.3 Should the piping assembly fail to meet the pressure test requirements, the pipe shall be repaired where leakage may be occurring and then retested. This procedure shall be repeated until the pressure test requirements are met.

.4 Co-ordinate pipe and valve equipment test with other Division 15 and Division 16.

3.10 Flushing Piping Systems

.1 Pump station piping and components shall be flushed to remove any accumulated debris in the pipelines, valve and appurtenances prior to testing.

Page 71: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15452 AND SEWAGE PUMP STATION PIPING, VALVES AND RELATED EQUIPMENT IN SEWAGE PUMP ROOM AND WET WELLS PAGE 12

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

END OF SECTION

Page 72: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 1

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1 GENERAL

1.1 Description

.1 The work of this section includes the supply, installation, testing, calibration and commissioning of installation of instruments in the sewage pump room a wet well area only including:

.1 Flow meters;

.2 Pressure transmitters;

.3 Pressure gauges;

.4 Level sensing equipment;

.5 Related items and accessories.

.2 Other instrumentation equipment may also be installed in the sewage pump room and wet well area and is not included in this specification. Refer to other sections for instrumentation not included in this specification but required for installation by the contract documents.

1.2 Work Included

.1 The work of this section includes but is not limited to the items generally described following:

.1 Supply, installation, testing, calibration and complete commissioning of the equipment specified in this section and to be installed in the sewage pump room and as noted on the drawings.

.2 Coordination with pumping equipment installations in the Pump Room and Wet Well Area. See Section 15600 “Pump Station Sewage Pumps”.

.3 Coordination with Division 16 work to ensure all equipment is wired, connected and tested.

.4 Supply and installation of all other mechanical items, equipment and components required or necessary to provide a complete working installation.

.5 Testing and commissioning to be in co-ordination with other related work including Division 15 mechanical work and Division 16 electrical work.

1.3 Shop Drawings

.1 Provide shop drawings for all equipment covered in this section.

.2 Submit detailed manufacturers technical literature and specifications for all equipment including installation and testing recommendations.

.3 Shop drawings to Division 1 Requirements.

Page 73: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 2

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1.4 Related Work

.1 Sewage Pumping Equipment Section 15600

.2 Slide Gates Section 15800

.3 Electric Multi Turn Actuators for Slide Gates Section 15800

.4 Electric 1/4 Turn Valve Actuators for Valves Section 15800

.5 Screens Section 15900

.6 Mechanical Equipment Division 15

.7 Electrical Equipment Division 16

2 PRODUCTS

2.1 Level Floats for Sump Pumps and High Level Alarms in Wet Wells

.1 Provide Flygt ENM-10 liquid level float switches, standard version complete with form-C contact, 20 m cable (minimum unless otherwise noted), strain relief connector and cable weight. Provide additional strain relief connector, Flygt Cat. No. 130598310 for each float switch.

.2 See drawings for location and installation details of floats.

2.2 Ultrasonic Level Sensing Equipment

.1 Ultrasonic level equipment shall be Miltronics MultiRanger 200 level controllers complete with XPS 15 transducer, submergence hood and extra cable. Available from Thos. W. MacKay & Sons Ltd or Siemens Canada as shown on the Contract Drawings.

.2 Transducers shall be XPS 15 c/w submergence shield and adequate cable to reach explosion proof junction box, shall be mounted to manufacturer’s specifications as shown on the drawings.

Page 74: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 3

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.3 Milltronics Level Equipment Table

Location of Transducer

Location of Controller

Controller CSA rating Transducer

Comments

Wet Well #1 as shown on drawings

Electrical Room

One common unit for wet well #1 & #2 transducers

Class 1 Zone 1 One level transducer & one common wet well controller #1/#2

Wet Well #2 as shown on drawings

Electrical Room

Same as above Class 1 Zone 2 Same as above

Upstream of Wet Screen #1 as shown on drawings

Electrical Room

One common unit for upstream and downstream screen transducers

Class 1 Zone 1 One level transducer & one common screen level controller #1/#2

Downstream of Screen #1 as shown on drawings

Electrical Room

Same as above Class 1 Zone 1 Same as above

Parshall Fume as shown on drawings

Electrical Room

One unit Class 1 Zone 1 One dedicated transducer and controller for level to flow conversion

2.3 Pipe Mounted Pressure Transmitters

.1 Pressure transmitters are required on the following applications:

.1 Suction header for each self priming sewage pump – four required;

.2 Discharge header for the self priming sewage pump – one required;

.3 Discharge header from the sewage transfer pump in the wet well area – one required;

.4 Nelson transfer piping in the sewage pump room – one required;

.2 Each location requires a specified pressure span;

.3 All locations in the pump room area require a CSA electrical rating of Class 1, Zone 2.

.4 All locations in the wet well are require a CSA electrical rating of Class 1 Zone 1.

.5 Pressure transmitter shall be industrial grade transmitter with 4-20 ma output, factory calibrated for a specified spans, rated for 600 psi working pressure and operated from a 24 VDC power supply.

.6 Zero, and span shall be field adjustable on-site using LCD display or Hart communicator. Hart communications unit to be supplied with pressure transmitters.

Page 75: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 4

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.7 Transmitters shall be flush thread mounted as detailed in the Contract Drawings.

.8 Transmitters shall have:

.1 0-100 psi range;

.2 0.2% accuracy of specified range;

.3 4-20ma output;

.4 316 stainless construction including process connections, ceramic diaphragm;

.5 Stainless steel brackets and stainless steel bolts for pipe mounting;

.6 LCD display meter, linear, 0-100 psi, user scalable integral with transmitter;

.7 Factory calibrated for spans shown in span table.

.9 Shop drawings and complete product data are required for all pressure transmitters.

.10 Unit assembly

.1 Transmitters shall be factory spanned and calibrated for the specified pressure spans within the specified pressure range of the transmitter and shall be factory certified and tagged to confirm the span and range of the transmitter.

.11 Span Table for Pressure Transmitters:

Location Install On Calibrated Span

CSA rating Nos of Units

Pump Room

Suction header On Sewage pumps

-15 psi to + 15 psi

Class 1 Zone 2 4

Pump Room

Station Discharge header

0 – 75 psi Class 1 Zone 2 1

Wet Well Discharge header Transfer Pump

0 – 75 psi Class 1 Zone 1 1

Pump Room

Nelson transfer piping 0 – 50 psi Class 1 Zone 2 1

.1 Confirm spans prior to ordering.

.2 Transmitters shall be spanned for 4 - 20ma output over the specified span (or as instructed by the Engineer. Confirm all spans prior to ordering).

.12 Contractor to confirm model number with options & submit product data for review by Engineer prior to ordering.

.13 Acceptable models:

.1 Endress and Hauser - PMC 45 1 ½ inch MNPT flush thread mount with integral LCD;

Page 76: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 5

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.2 Approved equal.

2.4 Submersible Pressure Transmitters

.1 Description

.1 Pressure transmitters shall be submersible 2 wire DC excited (4-20ma output) units specifically designed for level measurements in groundwater wells and shall use piezoresistive machined silicon strain gauge with atmospheric vent to provide pressure compensation.

.2 Pressure transmitters shall be constructed of materials suitable for use in raw sewage and corrosive environments.

.3 Pressure transmitters shall be vented to atmosphere using a dedicated atmospheric vent tube connecting to a desiccant chamber.

.4 Transmitter and cable shall be waterproof and fitted with strain relieve.

.5 Transmitter cable shall terminate in a junction box fitted with dessicant.

.2 Materials of Construction

.1 Materials of construction of pressure transmitters shall be as follows:

.1 Body: titanium.

.2 Measurement diaphragm: flush coated elastomeric

.3 Cable: Polyurethane with integral strain relieve to prevent signal cable damage or elongation and rated for 100 lb load;

.4 Internally potted, with molded cable.

.3 Measuring Range and Output Accuracy

.1 Pressure transmitters shall be calibrated for a liquid water depth range of 0 to 10 meters.

.2 Combined non linearity, hysteresis, and repeatability shall be within +/- 0.25% of full scale.

.3 Long term stability: Less than +/- 0.1% full scale.

.4 Zero offset and span setting: +/- 0.25% of FS

.5 Temperature effects: +/- 0.3% full scale maximum. Temperature compensated.

.6 Overpresssure: not less than four times measuring range.

.7 Burst pressure: not less than six times measuring range.

Page 77: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 6

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.4 Electrical Requirements

.1 Power Supply: 9 – 32 VDC.

.5 Transmitter Output Requirements

.1 Output Signal:

.1 4-20 ma 2 – wire , loop powered;

.2 Output to be factory scaled such that 4 ma = lower range value and 20 ma = upper range value;

.3 Transmitter suitable for 300 meter distance from 24VDC power supply over twisted, shielded, armored 16 AWG cable.

.6 Dimensions

.1 Diameter not to exceed (½) one half the inside diameter of mounting dip tube as indicated.

.2 Fitted with 60 feet of cable.

.7 Accessories

.1 Sensor termination enclosure with desiccant or approved bellows.

.8 Approvals

.1 Assembly shall be CSA approved for use in Class 1 Zone 1 areas.

.2 CE marked.

.3 Waterproof to NEMA 6 (IP 68).

.9 Location

.1 Install one in each wet well as level backup to ultrasonic units.

.2 Units are 4-20ma transmitter which connect to the station PLC.

.10 Standard of Acceptance

.1 Druck PTX 1290;

2.5 Pressure Gauge Assemblies for Piping

.1 Pressure gauges shall be liquid filled, 64 mm diameter size, 0.5% accuracy to ANSI/ASME B40.1, grade 2A, with black phenolic case. Gauge calibration shall be 0-100 psi.

.2 MA Stewart G2 stainless steel ball valves shall be used for gauge isolation.

Page 78: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 7

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.3 All pipe and fittings in the gauge assemblies to be brass.

.4 Gauge spans shall be confirmed with the Engineer prior to ordering.

.5 Gauges to be Ashcroft Duragauge or approved equal.

.6 Pressure gauge assemblies are included with each sewage pump.

2.6 Magnetic Flow Meters and Local Converters

.1 Magnetic flow meter assemblies shall be to the dimensions indicated on the drawings. Three full pipe size flow meter assemblies are required in the sewage pump room and wet well areas:

.1 One on the 600 mm diameter forcemain discharge line in the pump room;

.2 One on the 250 mm diameter Nelson transfer piping system in the pump room area;

.3 One on the 300 mm diameter transfer pump discharge piping in the wet well area;

.2 The magnetic flow meter assemblies shall be pulsed DC unit as indicated on the drawings including:

.1 Flanged Flow tube: 304 stainless steel;

.2 150 carbon steel flanges with drilling and dimensions conforming to ANSI 16.5

.3 Polyurethane interior liner.

.4 Two completely insulated cylindrical and diametrically opposed ANSI 316 stainless steel, bullet nosed self cleaning electrodes fixed in place within the control portion of the meter tube.

.5 316ss grounding rings.

.6 Pressure ratings: Class 150 flanged unit shall have 200 psi working pressure rating with water temperature less than 20 degrees Celsius.

.7 Integral local converters/transmitters mounted on flowtubes for remote 4-20ma signal to electrical room.

.8 Flow meter sizes as indicated on the drawings.

.9 Flow meter assemblies are to be rated 0.2% accuracy instruments.

.10 Flow meter assemblies shall be complete with electrical and electronics connections to meet or exceed IEC 529 IP68 continuous submergence to 30 feet of water;

.11 Flowmeters approved for use in Class 1 Zone 1 areas.

.3 Approved Flow Meter Units (subject to meeting specification requirements):

Page 79: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 8

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.1 Standard of Acceptance: Endress and Hauser: Promag 53W;

.2 ABB: Magmaster MFE (0.2%);

.3 Rosemount: 8705 flowtube with 8712D transmitter (0.5% down to 1 ft/sec)

.4 Yokagawa Admag SE (0.2%)

2.7 Local Magnetic Flow Meter Transmitters

.1 Local magnetic flow transmitters shall be integral part of the flow meter and shall have the following minimum features:

.1 Two (2) line LCD touch display to simultaneously indicate rate of flow in engineering units and total flow.

.2 Bi-directional flow, indication and totalization in both forward and reverse direction.

.3 Isolated 4-20 ma DC output into 750 ohms

.4 Pulse output, integral alarms and discrete output

.5 Noise reduction algorithms

.6 Self diagnostics

.7 Program edit protection

.8 All memory data to be stored in non-volatile memory for 10 years without battery back-up.

.9 Automatic zero stability and a signal: media noise factor based on the square root of the multiplication of the magnetizing current (Amps peak to peak) and coil exiciter frequency (HZ) capability of nominally 4.0

.10 System accuracy at reference conditions of +/- 0.5% of reading for >.3 m/s or +/- 0.0015m/s for <0.3m/s.

.11 Digital full scale mean velocity adjustment from 0.25 m/s to 10m/s with media conductivities down to 1 micromho/cm

.12 Convertors shall be factory calibrated for following flow spans:

Location Install On Calibrated Span

CSA rating Nos of Units

Pump Room 600 mm Station forcemain header

0 – 800 litres/sec

Class 1 Zone 2 1

Pump Room Nelson 250 mm transfer piping

0 – 200 litres/sec

Class 1 Zone 2 1

Wet Well 300 mm transfer Pump Discharge

0 – 300 litres/sec

Class 1 Zone 1 1

Page 80: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 9

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

header

.13 Power supply: 120VAC.

.14 Flow meter transmitters shall provide a 4-20ma flow signal to the electrical room PLC.

2.8 Parshall Flume

.1 A Parshall flume shall be installed at the inlet to the station for measuring inflows to the station.

.2 The flume shall be fitted with a Milltronics MultiRanger 200 level controller and transducer as specified and calibrated to provide a direct reading in litres/second (or other flow rate required by the Owner).

.3 The Parshall flume shall be as manufactured by Plasti-Fab Incorporated and represented by Avensys Solutions located in Delta B.C. (phone - 403-266-1960).

.4 The Parshall flume shall be a heavy duty 12” x 24” nested flume with the nested insert easily removable when required.

.5 A copy of a typical 12” x 24” nested flume sketch is appended to this section. The sketch is not a shop drawing which the Contractor will be required to obtain from the manufacturer.

.6 Installation of the flume requires conformance with the installation requirements of the manufacturer and must be adhered to by the Contractor in all respects to ensure the accuracy of the installed flume.

.7 Failure of the Contractor to install the flume correctly and in accordance with the manufacturers instructions will require the Contractor to remove and replace the flume.

.8 Flume does not contain an FRP inlet adaptor. The inlet adaptor is to be constructed from cast in place concrete in accordance with the drawings. See drawings for details.

3 EXECUTION

3.1 General

.1 Prior to all work in this section, the Contractor shall become thoroughly familiar with the site and all portions of the work within this section and other related sections, including related civil, mechanical and electrical work.

.2 The Contractor shall ensure a qualified representative from each equipment supplier is onsite to confirm the correct installation, calibration and overall operation of the equipment supplied. The equipment representative shall inspect the installation, check the spans, operating parameters, wiring and all other related items and confirm in writing that all equipment supplied by the specific supplier has been installed and configured in accordance with the manufacturers recommendations and is operating correctly.

.3 Equipment suppliers shall also be onsite during start up and testing to confirm that all instruments are operating correctly and as required under operating condtions.

Page 81: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 10

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

3.2 Installation of Pressure Transmitters, switches and Gauges

.1 Install all pressure transmitters, switches and pressure gauges as indicated on the drawings.

.2 Prior to installation ensure all gauges are of proper range and transmitters are calibrated with 4-20ma output corresponding to specified spans.

.3 Ensure all pressure instruments are operating correctly by field testing. If any pressure instruments are found to be operating incorrectly as determined by testing, replace instruments with new units or repair if approved by the Engineer.

3.3 Floats

.1 Mount float switches for float actuation at levels indicated on the drawings.

.2 Ensure that floats are suspended clear from walls or other surfaces to prevent the floats from jamming against these as the floats tilt during operation. Low level floats shall be carefully secured and 2 cable weights installed to minimize movement of the floats.

3.4 Ultrasonic level Sensing Equipment

.1 Install ultrasonic level sensing equipment (controllers and transducers) in accordance with manufacturers instructions and recommendations.

.2 Wire and connect equipment in co-ordination with Division 16.

.3 Program level sensing equipment as instructed by the Engineer and provide services of equipment supplier for checking and commissioning.

.4 Carry out all adjustments, calibration and programming necessary for correct operation of equipment.

3.5 Parshall Flume

.1 Install Parshall Flume in strict accordance with manufacturers instructions and recommendations and as indicated on the drawings.

.2 Contractor is required to have the flume supplier inspect the flume installation prior to pouring concrete and supplier shall certify the installation is adequate level and ready for concrete surround.

.3 Following approval of flume supplier install concrete surround for flume and carry out other installation requirements.

.4 Install level sensing equipment on flume as indicated on the drawings. Program level sensing equipment as instructed by the Engineer and provide services of equipment supplier for checking and commissioning.

.5 Carry out all adjustments, calibration and programming necessary for correct operation of equipment.

Page 82: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15500 AND SEWAGE PUMP STATION PRESSURE, LEVEL, FLOW INSTRUMENTS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 11

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

3.6 Installation of Flow Meter Assemblies

.1 Install all flow meter assemblies as indicated on the drawings. Ensure manufacturer’s field representative is present to assist with this phase of the work.

.2 Prior to installation ensure all gauges are of proper range and transmitters are calibrated with 4-20ma output corresponding to specified spans.

.3 Ensure all flow meters are operating correctly by field testing. If any flow meters are found to be operating incorrectly as determined by testing, replace with new units or repair if approved by the Engineer.

END OF SECTION

Page 83: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 1

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1 GENERAL

1.1 Description

.1 Work under this section includes but is not limited to the supply, installation, testing and commissioning of pumps and related equipment in the sewage pump room and wet well area of the SEFC NEU. Pumps are located in other areas of the Energy Centre and are covered in other specification sections. Refer to other sections for pumps not included in this section. The pumps in the pump room and wet well area include:

.1 Four (4) self priming sewage pumping units located in the pump room. One spare pump bay will remain empty for a future pump.

.2 One (1) submersible sewage transfer pump located in the screen channel in the wet well area.

.3 One screen spray booster pump in the pump room.

.4 Two submersible drainage sump pumps in the pump room sump.

.5 Pumps operated on VFD’s will be operated as adjustable speed units in control loops. All pumping equipment and electric motors must be rated for use with variable frequency drives for variable speed operation under a motor frequency range from 20 to 60 Hertz.

.6 Pump motors must be specifically designed for VFD operation and be constructed with inverter (spike resistant) rated windings and insulation and also classified as premium efficient.

.7 All pump motors shall have CSA approval and CSA approval shall be submitted with shop drawings. Pumping equipment unless otherwise noted shall be approved by CSA for use if Class 1 Zone 2 hazardous areas.

.8 In the event of power failure, a standby diesel driven generator set will operate the pumping system.

.9 Detailed requirements for pumps and motors are provided in the specifications. Pump performance curve shape, efficiency, flow range (minimum to maximum), pump material components, critical speeds, manufacturing specifications and associated characteristics and features are criteria in pump selection.

Page 84: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 2

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.10 Pump Room and Wet Area Pump Lineup Summary Table:

Pump Type Nos of Units

Pump Capacity & TDH (m at l/s)

Flow Range (l/s)

Motor HP

Pump/Motor Electrical Classification

Sewage Pumps

Self Priming Belt Driven – VFD controlled

4 180 l/s at 24 meters

60 – 180

Class 1 Zone 2

Screened Sewage Transfer Pump

Submersible – VFD controlled

1 125 l/s at 25 meters (to be confirmed)

125 to 150 l/s

Class 1 Zone 2

Screen spray Booster Pump

Centrifugal Multistage Booster

1 3.8 l/s at 35 meters

3.8 l/s Class 1 Zone 2

Sump Pumps

Submersible 2 10 l/s 10 l/s Class 1 Zone 2

1.2 Basic Pump Selection Criteria

.1 Pumping Equipment will be required to meet the performance and other criteria specified in the Contract Documents. Pump performance criteria is based on the pumps operating over a specified flow range on variable frequency drives without exceeding the manufacturers recommended maximum or minimum continuous flow rate.

.2 Flow range is between the range shown which represents the minimum continuous flow rate with the pump operating at reduced speed and at the rated capacity of the pump with the pump motor operating at 60 Hz at the specified system head.

.3 See pump station drawings for general arrangement and layout of pumping equipment. The Contractor is responsible for ensuring all equipment is installed in accordance with the contract drawings.

1.3 Pump Motor Requirements (See also Division 16 Electrical Requirements)

.1 Pumps and pump motors must meet the following requirements:

.1 Pumps must not required more than 95% of nameplate horsepower over a pump operating range which extends from the minimum flow for the specified pump to 150% of the rated pump capacity with the pump running at full speed.

.2 Pumps requiring more than 95% of nameplate horsepower over the range for a given pump motor size must then use the next larger size motor.

1.4 Coordination of Pump Motor and Variable Frequency Drives

.1 The Contractor is advised that pumps and motors supplied must be co-ordinated with the selection and supply of the corresponding variable frequency drive to ensure that the continuous rated current output of each VFD in amps exceeds the maximum current in amps

Page 85: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 3

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

required by the pump motor when operating on VFD over the total specified pump flow range with the pump operating at full speed (not reduced speed). The maximum required pump motor current/power over the specified flow range shall be obtained from the pump manufacturer.

.2 The continuous rated current output in amps of each VFD must exceed the maximum required motor current (current required operating on PWM VFD) by at least 8 % when the pump motor is operating on a PWM type of VFD under the operating conditions specified. The Contractor is advised that pump motors require more current when operating on VFD’S than on utility sinewave power. The Contractor shall be responsible for obtaining the required motor current in amps from the motor manufacturer and co-ordinating the supply of VFD’S which meet the load requirements specified.

.3 The Contractor will be required to submit certified data with the tender that the pump motors and variable frequency drives meet the specifications and in particular that the continuous rated current output of the drives exceeds the required maximum motor by the specified amount. Drives and motors which do not meet the requirements of the specifications will not be acceptable for use on this project.

.4 See Division 16 and other specification sections for Variable Frequency Drives.

1.5 Work Included

.1 The work of this section includes but is not limited to the supply, installation and testing of all pumping equipment in the Pump Room and Wet Well Areas:

.2 Supply and Installation Services:

.1 Supply of station pumping equipment including:

.1 Specified pumps including motors and all accessories, mechanical seals, couplings, base plates, fasteners and all other related items;

.2 Provision of factory pump and motor performance data for all pumping equipment as specified in the contract documents. Pump data shall confirm pumps do not contain any reed frequencies within the specified operating pump speed range assuming a rigid foundation.

.2 Installation of approved pumping equipment in the station in accordance with the contract documents using qualified personnel and precision alignment techniques.

.3 Testing and commissioning of installed pumping equipment and related piping systems and related mechanical and electrical equipment and appurtenances in co-ordination with Division 15 and Division 16 specification requirements including co-ordination of equipment suppliers.

.4 Coordination with others in implementing a PLC control program for pump operation (Consultant to provide and load PLC program).

.5 Supply, installation, start-up, testing and commissioning of all other mechanical items, equipment and components required or necessary to provide a complete working pumping system.

Page 86: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 4

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.3 Field Services:

.1 The work also includes the following field services provided by both the contractor and the contractor’s equipment suppliers:

.1 Inspection of pump installations. The pump supplier shall inspect the installation of all pumps and all related items at appropriate times during installation (before and after pouring concrete support bases and confirm in writing that the assemblies have been installed in accordance with the pump supplier’s recommendations.

.2 Checking & confirming alignment of pump motors and belt drives at the site. If the motor and pump have been factory aligned and then disassembled for shipment, they shall be reassembled by the installation contractor acting under the strict supervision and direction of the pump supplier who, prior to start up of the pump, will carry out all tests required to confirm that the alignment between the pump and motor is within required tolerances and that motor to pump shafts, pulley belts and mechanical seals have been properly installed, aligned and connected and that the pump impeller settings are as required for correct operation of the pumping equipment.

.3 On site vibration tests on self priming variable speed sewage pumps will be carried out by an independent third party vibration specialist, (paid for by the Contractor, approved by the Engineer) during commissioning as outlined in these specifications to:

1. Confirm vibration, velocity and acceleration measurements are within the prescribed limits of these specifications (vibration tests to meet Hydraulic Institute requirements) over the specified operating range of the pump(s) operating on VFD’(S);

2. Confirm the pumping equipment does not contain a reed frequency and resulting vibration response within the specified operating range of the pump.

3. Vibration testing may be waived if the pump manufacturer provides written documentation confirming that the pumping unit will not contain reed frequencies within the specified operating range of the pumping unit and that no unusual vibration or noise is apparent during testing or commissioning. The Engineer shall be the sole judge in determining if vibration testing shall be waived.

.4 Certification that the pumps have been correctly installed by the Contractor and that all warranties are in effect prior to start-up.

.5 Start-up and commissioning services to confirm correct operation of the new pumps over the specified speed range when operating on VFD’S and specified.

.6 Submission of Operations and Maintenance manuals for the pumps including complete manufacturer’s drawings.

Page 87: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 5

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.4 Any deviations from the requirements of the specifications must be noted and fully described in the Form of Tender.

1.6 Shop Drawings

.1 Provide fully detailed and dimensioned shop drawings for approved pumping equipment including but not limited to:

.1 Pump, pump bearings, shaft bearings, materials of construction, coatings);

.2 Fabricated base plates, mechanical seals, couplings;

.2 Shop drawings to Division 1 requirements.

1.7 Standards

.1 The following pump standards shall apply to all pumping equipment unless noted otherwise:

.1 HI 9.6.4-2000 – Centrifugal and Vertical Pumps for Vibration Measurements and Allowable Values;

.2 HI 2.1-2.5-1994 – Vertical Pumps for Nomenclature, Definitions, Application and Operation;

.3 HI 2.6-1994 – Vertical Pump Tests;

.4 HI 9.6.1-1998 – Centrifugal and Vertical Pumps for NPSH Margin;

.5 HI 9.6.3-1997 – Centrifugal and Vertical Pumps for Allowable Operating Region.

.2 In the event of a conflict between the contract documents, and the standards noted above, the most stringent standard or specification requirement as determined by the Engineer shall apply.

1.8 Delivery Dates

.1 Pumps are to be ordered as soon as the Contractor receives a Notice to Proceed with delivery dates provided to the Engineer in writing.

.2 The Contractor shall be fully responsible for all pumping equipment during shipment and unloading, offloading and safe placement at the site and shall take all necessary precautions to ensure damage does not occur to the equipment. The Contractor shall ensure adequate equipment and labour is provided for unloading of the equipment.

.3 The Contractor shall repair or replace all components which as determined by the Engineer have been damaged during shipment, storage or offloading. All openings, flanges and machined surfaces shall be covered with 9 mm thick plywood cover plates for protection of exposed surfaces.

1.9 Pump Related Documentation to be Provided with Tender

.1 The Contractor shall provide detailed pump performance and other related information with the Form of Tender.

Page 88: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 6

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.2 Complete catalogue drawings showing arrangement, outline, dimensional details, weights and materials of construction of all principal components as well as all information necessary to show compliance with the specifications.

.3 Complete technical and specification information describing all mechanical and electrical components and complete warranty information for all equipment.

1.10 Pump Related Documentation to be Provided on Notice of Award

.1 The successful bidder shall submit the following information following notice of award of the contract:

.1 Two (2) copies of the following information for approval within the time period specified following the award of contract.

.1 Control schematic and wiring diagrams;

1. submit within two weeks of award.

.2 Shop drawings showing required dimensional information for pumping equipment including basic pump, shafts, bearings, mechanical seals, base plates, soles plates, as well as detailed pump hydraulic information and performance curves;

1. submit within one week of award.

.3 Shop drawings showing required dimensional information for electrical motors as well as detailed motor information and performance curves;

1. submit within one week of award.

.4 Complete operating instruction books including users manuals, installation procedures, spare parts lists.

1. submit prior to site installation.

.5 Operation and Maintenance manuals which include:

1. detailed parts lists;

2. component specifications;

3. operating instructions;

4. maintenance recommendations and schedules;

5. scaled dimensioned drawings for all pumps;

6. detailed mechanical, electrical and hydraulic information on pumps, components, motors and ratings.

Page 89: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 7

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

7. operating manuals, details of guarantees and recommended spare parts list.

8. Operations and Maintenance manuals shall be submitted on or before the date for delivery of the pumping equipment.

1.11 Related Work

.1 Electrical Division 16

.2 Mechanical Division 15

.3 Painting Division 9

.4 Piping Division 15

.5 Variable Frequency Drives Division 16

2 PRODUCTS

2.1 Self Priming Sewage Pumps (4 units)

.1 Self priming sewage pumps are to be Gorman Rupp Super T-10AS-B belt driven units as supplied by the John Brooks Company Ltd. in Coquitlam B.C. constructed with:

.1 Cast Iron casings;

.2 250 mm x 250 mm 125 lb ASA optional suction and discharge spool flanges;

.3 Continuous vane ductile iron impeller

.4 Metal bellows seal;

.5 Air Mate automatic glass filled polyester body air release valve;

.6 Seal plate and wear plate;

.7 High pump temperature shut down kit;

.8 Pump Drain Kit with stainless steel fittings:

.1 Supply one 30 foot long quick connect hose to be used for all four units.

.9 Cartridge type mechanical seal;

.10 Suction and Discharge Gauge Panel Kits with stainless steel pipe fittings:

.1 Discharge gauge range: 0 – 50 meters;

.2 Fitted to pump with pump with brackets and flexible hoses and stainless steel isolation ball valves on suction and discharge.

Page 90: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 8

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.2 Rated Pump Capacity: Each pump shall be rated at 180 l/s at a total dynamic head of 24 meters.

.3 Pumps are to be mounted on a continuous steel base rigidly supporting the pump, motor, motor stand and all other pump accessories.

.4 Pump motors are to be 1800 rpm units rated for use in Class 1 Zone 2 areas in accordance with the CEC.

.5 Pump speed reduction from nominal 1800 rpm motor speed to specified speed at rated capacity shall be obtained by shives and belt assembly. Estimated pump speed for rated capacity is 1300 rpm.

.6 Pump motors are to be purpose designed to operate on VFD’s and incorporate spike resistant windings.

.7 Pump base plate and motor support stand:

.1 See attached shop drawing appended to this specification;

.8 Pump Coatings: Pump, motor and pump base are to be coated with manufacturer’s enamel finish and shall be suitable for top coating to match pump station piping colour if required.

.9 Spare Parts: Spare parts to be provided with the self priming pumps include the following items:

Pumps Spare Parts to be Supplied Nos. Required Self Priming Sewage Pumps

One complete rotating assembly One only

Check valve Four (one for each pump) Pivot cap Four (one for each pump) Cleanout Cover Gasket Four (one for each pump) Shim set Four (one for each pump) Bearing HSG O-Ring Four (one for each pump) Seal end Plate O-Ring Four (one for each pump) Front wear plate Four (one for each pump) Suction Hd Gasket Four (one for each pump)

2.2 Submersible Screened Sewage Transfer Pump (One unit)

.1 Screened sewage transfer pump shall be a non clog Flygt CP 3231 unit complete with (pump size and motor hp to be confirmed):

.1 Pump discharge base elbow;

.2 316 stainless steel guide rails;

.3 Top rail bracket and intermediate bracket rail support , galvanized steel;

.4 Thermal and leakage monitors,

Page 91: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 9

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.5 Minicas 11 monitoring unit installed in accordance with the electrical drawings;

.6 25 meter length of power cable.;

.7 Galvanized steel lifting chain with galvanized steel shackle to connect chain to the pump;

.8 Galvanized lifting bracket fixed to the pump for the purpose or providing an alternate means of removing the pump in addition

.2 Pump Accessories

.1 Confirm the length of guide rails, lifting chain, and power cable piror to ordering pump all of the following lengths prior to shipping:

2.3 Submersible Sump Pumps (Two Units)

.1 Sump pumps for the drainage sump in the pump room shall be non clog portable Flygt CS 3085 MT (curve 63-436-00-5330 with 151 mm diameter impeller), and 3 hp 600 VAC, three phase motors complete with:

.1 Cast Iron volutes and impellers with 304 stainless steel exposed nuts, bolts and fasteners;

.2 Pump pump stand;

.3 Hose connection on pump for use as shown on the drawings

.4 Thermal and leakage monitors,

.5 Minicas 11 monitoring unit installed in accordance with the electrical drawings;

.6 25 meter length of power cable;

.7 Galvanized steel lifting chain with galvanized steel shackle to connect chain to the pump;

.8 Galvanized lifting bracket fixed to the pump for the purpose or providing an alternate means of removing the pump in addition

.2 Pump Accessories

.1 Confirm the length of lifting chain, and power cable prior to ordering pump all of the following lengths prior to shipping:

.2 Discharge piping includes 55 mm diameter hose to match pump discharge (with stainless steel hose clamps), cam lock quick disconnect couplings and field run 75 mm diameter rigid copper piping as shown on the drawings. Copper pipe from sump to wet well shall be in conformance with Section 15452 and painted with same material as pump suction and discharge piping (confirm colour).

.3 Float Switches for Sump Pumps: See Section 15500 Pump Related Instrumentation.

Page 92: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 10

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

2.4 Screen Spray Booster Pump (One Unit)

.1 Screen spray booster pump shall be a Grundfos CR 10 - 4 with rated capacity of 60 usgpm at 50 psi (3.8 l/s @ 35 meters TDH) and non overloading motor.

2.5 Electric Motors Self Priming Pumps

.1 Ratings

.1 Motors for self priming sewage pumps shall be 575 VAC, three phase, 60 Hz, solid shaft, premium efficient, inverter duty motors, with nominal synchronous rpm rotational speeds specified.

.2 Motors shall be NEMA B designed squirrel cage rotor induction motors with 1.15 service factor, NEMA frame CSA approved for use in Class 1 Zone 1 area.

.3 Motors shall be designed, rated and specifically labelled for use with inverters meeting all requirements of NEMA MG-1, Part 31, latest edition.

.4 Motors shall have class F insulation and class B temperature rise at a 1.15 service factor when operating on sine wave power.

.5 Motor manufacturer shall provide temperature rise and service factor information when operating on PWM vector type inverter.

.6 Motors shall be balanced to refined standards, as per Nema MG1, part 7 and shall have a peak velocity (free/rigid) not greater than 0.06 inches/second and peak velocity (resilient) not greater than 0.08 inches/second.

.2 Dual Nameplates

.1 Dual motor nameplates shall provide all NEMA design information under sine wave power as well as under VFD use.

.3 Frequency Range

.1 Pump motors shall be operable over a frequency range of 20 Hz to 60 Hz using 600 VAC, Vector Type Variable Frequency Drives sized for the motor loads associated with standard torque characteristics of a centrifugal pump.

2.6 Inverter Rated Motors

.1 Motors shall be of special design and rated for use with PWM VFD’S. Specific design features for inverter use shall include but not be limited to the following:

.1 Inverter Grade Class F insulation.

.2 Two cycles of vacuum pressure impregnation with 100% solid epoxy resins providing 7 mils insulation build.

.3 Refined balance.

Page 93: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 11

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.4 Insulated thrust bearings.

.5 High efficiency.

.6 Special dual use nameplate if applicable.

2.7 Factory Testing of Self Priming Sewage Pumps

.1 Each self priming pump shall be factory tested in accordance with the latest standards of the Hydraulic Institute using calibrated shop drivers and instrumentation from shut off head to 150% of design capacity for head, capacity, brake horsepower and efficiency at the rated speed.

.2 Certified copies of non witnessed test results shall be provided to the Engineer for approval prior to shipment.

3 EXECUTION

3.1 General

.1 Prior to all work in this section, the Contractor shall become thoroughly familiar with the site and all portions of the work within this section and other related sections, including electrical work.

3.2 Concrete Pump Bases

.1 Concrete pump bases shall be constructed as an integral unit and installed as shown on the drawings including the fabrication and setting of anchor bolts prior to installation of fabricated pump and motor base.

.2 Pump base shall be sized in accordance with the contract drawings, pump shop drawings and in accordance with the pump manufacturers recommendations.

.3 Pump bases shall include reinforcing dowels and concrete encasement as shown on the drawings.

3.3 Grout Fabricated Pump and Motor Base Plate

.1 Grout between fabricated pump base and concrete foundation pad shall be a high strength non shrink grout as detailed on the drawings. All grout shall be Masterflow 928.

.2 Grouting shall be in strict accordance with the contract documents and with the recommendations of the pump supplier and the grout supplier.

.3 All personnel employed by the Contractor for installing pumps, motors, piping and pump foundations shall be experienced and qualified in the installation of rotating equipment foundations.

3.4 Installation, Assembly and Fitting of Pumping Equipment:

.1 Protect all pumping equipment during installation.

.2 Any damage to the pumping equipment shall be corrected by repair or replacement as directed by the Engineer.

Page 94: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 12

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.3 Install the pumping equipment in accordance with the manufacturers recommendations, data sheets, drawings or applicable shop drawings.

.4 Support, anchor and brace all pumping, piping and assemblies adequately and securely as shown on the drawings and/or directed by the Engineer.

.5 Clean all flanges, gaskets and other connection fittings.

.6 Do not fix piping assembly in place until all components are properly aligned and installed.

.7 Piping assemblies shall permit normal pipe contraction and expansion without undue strain on any portion.

.8 Ensure no foreign material is left in piping runs.

.9 Use approved methods for grouting between pump and motor fabricated base plate and the concrete foundation to ensure pump is level and free of distortion or unbalanced forces prior to grouting. Grout shall be uniformly installed under base plates to provide uniformly distributed support. Grout forms shall be used for grouting.

.10 Install, fit and grout all pipe supports to same standards and procedures as pumps.

.11 Touch up shop or field applied paint any surfaces damaged during installation or other work activities.

3.5 Installing Pumps & Related Components

.1 The pumps and motors shall be assembled and installed as indicated on the drawings and the Contractor shall be responsible for ensuring the centerline elevations of all suction and discharge piping are correct before pouring concrete foundations, grouting or installing pump related components.

.2 The Contractor shall adhere to the basic procedures described herein for setting and installing the pumps and related equipment and in all cases shall be responsible for implementing suitable procedures and techniques and employing qualified personnel to ensure all equipment is installed correctly and in conformance with the recommendations of equipment suppliers and established industry procedures for specified pumping equipment.

.3 The Contractor shall arrange to have the pump supplier onsite to check the alignment between the pump and motor (as well as the overall installation) and shall abide by any instructions provided by the pump supplier to correct any installation deficiencies or related problems.

.4 Final alignment of couplings shall be witnessed by the Engineer, Contractor and pump supplier and the pump supplier shall submit a written certification that the Contractor has installed the pumping equipment in accordance with the manufacturers and suppliers recommendations. No pumping equipment shall be operated or energized unless the pump supplier certifies that the pumps have been installed in accordance with the recommendations and instructions of the pump manufacturer and that all pump and motor warranties are in effect.

.5 The Contractor shall employ and used qualified personnel only for the installation, alignment and fitting of all pumps, motors and connecting piping. Qualified personnel shall include qualified machinists and/or millwrights experienced in pumping equipment installations.

Page 95: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 13

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.6 The Contractor shall submit detailed information on proposed procedures to be used for the installation of the pumping equipment to the Engineer not less than two weeks in advance of the start of pump installation work and shall adjust and modify proposed procedures if requested by the Engineer. In all cases, the Contractor is responsible for the correct installation of all equipment installed under this contract.

3.6 Inspections, Testing and Commissioning on Site - Acceptance Tests

.1 The Contractor shall have the pump supplier provide qualified technicians to inspect the installed pumps and motors and all equipment prior to start-up and shall confirm by inspection or other means that the pumping equipment (including motor rotation) have been installed, connected, aligned and fitted correctly and in strict accordance with the manufacturers recommendations and applicable specifications and that all warranties are in effect. Written confirmation that the installation has been inspected and reviewed by the pump supplier and that warranties are in effect shall be provided to the Engineer within two days of inspection. The Contractor and pump supplier shall check the alignment between the motor and pump shafts to confirm they are within specification tolerances for eccentricity and parallelism.

.2 Should the Contractor/pump supplier determine that the pumping equipment or components have not been installed correctly and that the installation is deficient, the Contractor shall immediately provide written notification to the Engineer complete with written instructions detailing the applicable deficiencies and the procedures required to correct such deficiencies. The Engineer shall be the sole judge in determining which party (the installation contractor or the pump supplier) shall bear the cost for correcting deficiencies. Following correction of deficiency work the supplier shall re-inspect the installation and advise the Engineer in writing that all deficiencies have been corrected and that the equipment is ready for start-up.

.3 Following the Contractor’s/pump suppliers final inspection and approval, the pumping equipment shall then be tested and commissioned by the pump suppliers technicians along with the installation Contractor and the VFD supplier and in the presence of the Engineer to confirm by operation and test procedures, the correct operation of pumping equipment, pump controls and related equipment. During the test work the pump supplier shall be responsible for co-ordinating all parties to ensure testing is done to specified and approved procedures.

.4 Acceptance Testing:

.1 Acceptance testing terminology, definitions and procedures for testing shall be based on ANSI Hydraulic Institute standards where applicable and as supplemented or modified by these specifications to confirm correct operation under VFD operation.

.2 Acceptance testing shall include testing under the following categories:

.1 Installation inspection and testing: As specified in this section.

.2 Hydraulic testing: Hydraulic testing shall consist of running the pump at full speed and at reduced speed to determine that the pump discharge and pump head conform to the certified pumps performance curves provided by the pump manufacturer. Hydraulic testing shall include:

1. Operation of each pump over a range of motor frequencies (30Hz - 60Hz), and a range of flow rates (shut off head to 120% or rated pump

Page 96: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 14

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

capacity) using the station flow meter to record discharge and pressure gauges to record suction head and discharge head.

2. Measurement and recording of current, voltage, power factor and other electrical and/or mechanical data to confirm shaft horsepower and total motor energy consumption.

.3 Vibration testing for Compliance with Hydraulic Institute (only if required):

1. The pump supplier shall utilize the specialist services of the qualified third party firm specified in the Form of Tender for all vibration monitoring and testing.

2. Vibration testing of the pump train shall involve the use of accurate vibration sensors, recording and other equipment as required, to measure and monitor equipment vibration and to ensure the pump/motor assembly is operating within specified vibration limits (displacement, velocity and acceleration) over the specified speed/frequency range of the pump and to confirm that the pump train does not generate or display a critical speed or resonant frequency response within the speed range of 900 - 1800 rpm.

3. The vibration specialist shall provide a written report to the Engineer outlining the results of the vibration acceptance tests, clearly stating if the pump meets or exceeds the specified vibration limits (displacement, velocity and acceleration) for all speed conditions tested.

4. Maximum allowable vibration levels for displacements, velocities, acceleration and test locations shall be as specified in the Hydraulic Institute ANSI/HI 2.4 Standards for Centrifugal Pumps latest edition.

.3 The Engineer shall be the sole judge in interpreting and evaluating all vibration tests and in determining if a device or piece of equipment is operating correctly and as specified. The pump supplier shall abide by all decisions or instructions issued by the Engineer concerning the correct operation of devices or equipment.

.4 The cost of any changes, modifications, adjustments or replacements which in the opinion of the Engineer are due to errors or omissions by the pump supplier shall be charged to the pump supplier.

.5 Should the pumping equipment not meet the requirements of the acceptance tests over the specified speed range, the pump supplier shall take immediate action to correct or replace the equipment or carry out such remedial measures are required and shall carry out additional tests until the pumping equipment meets the requirements of the acceptance tests.

3.7 Testing and Commissioning of Pumping Systems

.1 Following all mechanical and electrical work the Contractor shall carry out adequate testing and commissioning of all installed components to adequately confirm satisfactory and correct operation of all components over a range of operating conditions. The Engineer will assist the

Page 97: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 15

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

Contractor in setting up the testing and commissioning activities but the Contractor will be responsible for carrying out all activities.

.2 The Contractor shall be responsible and bear the costs associated with co-ordinating and providing the on site technical services from suppliers of the following equipment for programming, setting-up and commissioning activities:

.1 Pumps and motors and related items;

.2 Variable Frequency Drives;

.3 Digital and analog instruments;

.4 Pressure transmitters.

.5 Flow meters;

.6 All other equipment or components related to pump operation;

.3 Testing of pumping systems shall be done jointly with the testing of electrical power and control systems.

.4 Mechanical and Electrical Components to be tested include:

.1 Piping systems including valves, couplings and spool pieces.

.2 Valves and electric actuators,

.3 Pressure transmitters, gauges, electric valves.

.4 All electrical power and control systems installed under Division 16 relating to pumping equipment.

.5 All instrumentation systems installed under Division 16 relating to pumping equipment.

.5 Testing of pumping systems shall include:

.1 Running each VFD in automatic mode to test proportional band operating speed of the pumping equipment under variable flow rate conditions to confirm the correct operation and control of the system based on the wet well level, pressure and flow meter sensing and other related control items.

.2 Running pumps individually and in parallel to confirm pump station flow sequences.

.3 Running each pump in manual mode under the strict supervision of the Engineer and under specified and controlled conditions.

.4 Priming and re-priming pump to determine priming and re-priming times are as required.

.6 Testing of pump start/stop and all alarm points to confirm the correct operation and sequence of operations of the pumping system under normal and alarm conditions including:

Page 98: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15600 AND SEWAGE PUMP STATION SEWAGE PUMPS AND RELATED EQUIPMENT IN PUMP ROOM AND WET WELLS PAGE 16

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.1 Start pressures:

.2 Stop pressures

.3 High pressure alarms.

.4 Low pressure and suction alarms.

.5 Flow rate readings for pump sequencing and out of bounds alarm.

.7 Any test items which overlap with Division 16 electrical work, shall be tested jointly with both trades present.

.8 Any overlap between Division 15 and Division 16 work shall be co-ordinated by the Contractor.

.9 It shall be the Contractor's responsibility in all cases and without limitation to provide all items required for the work and to co-ordinate between all particular trades involved, particularly the work of Division 15 and Division 16.

.10 Other items will be tested under Division 16 electrical work including power supply, wiring, breakers, conduit, connections, terminations, lighting and heating and instrumentation.

3.8 Test Reports

.1 The Contractor shall prepare a test report based on the testing and commissioning work at the site and shall include all calibration calculations, all set points and observed readings.

.2 The test reports shall include confirmation of manufacturers and suppliers recommended procedures for installation, testing and calibration. The following data shall also be provided:

.1 Pump flows;

.2 Suction and discharge pressures;

.3 Pump speeds (rpm and Hz);

.4 Other information requested by the Engineer.

.3 Test report data shall be included in the Operations and Maintenance Manuals. See applicable section.

.4 Pump commissioning shall be done in co-ordination with testing and commissioning requirements as required in the Contract Documents.

END OF SECTION

Page 99: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15700 AND SEWAGE PUMP STATION HVAC EQUIPMENT PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Scope of Work

.1 Execute all work and furnish all products as specified herein and in accordance with the contract documents.

1.2 1.2 Work Included

.1 Unit Heater HVAC UH-1

.2 Fans

.3 Pumps

2 PRODUCTS

2.1 Unit Heater HVAC UH-1

.1 Unit Heater Schedule:

.1 UH-1: Trane UHS 42-S, horizontal, 280 l/s [590 cfm], 4.4 kW [15 MBH], 0.10 l/s [1.5 gpm] of 82ºC [180ºF] heating water, 110 volts, 1/20.

2.2 Fans

.1 Provide fans as scheduled herein.

.2 Install fans in accordance with manufacturer's instructions.

.3 Use neoprene vibration isolators when supporting fan from structure.

.4 Provide flexible duct connections.

.5 Fan schedule:

.1 HVAC 101 (Wet Well Supply Fan):

.1 Woods 19J, 1700 l/s @ 150 Pa, 1700 rpm, 1 hp motor, 575/3/60.

.2 HVAC 107 (Odour Control Room Supply Fan):

.1 2 speed, 1320 l/s high speed @ 150 Pa, 750 l/s low speed, Loren Cook 150 SQN-B, 1 hp 2 speed, 2 winding motor, 575/3/60.

.3 HVAC EF-1 (Wet Well Booster Exhaust Fan):

.1 Woods 19J, 1700 l/s @ 125 Pa, 1700 rpm, 1 hp motor, 575/3/60, epoxy coated inside and out.

.4 HVAC EF-2 (Dry Well Exhaust Fan):

Page 100: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15700 AND SEWAGE PUMP STATION HVAC EQUIPMENT PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.1 Woods 24J, 2400 l/s @ 150 Pa, 2 hp motor, 575/3/60.

.5 HVAC EF-3 (Heat Pump Area Exhaust Fan)

.1 Woods 30 GJ, 4,700 l/s @ 250 Pa, 1140 rpm, 5 hp motor, 575/3/60.

.6 HVAC EF-4 (Generator Area Exhaust):

.1 8000 l/s @ 125 Pa, Woods 30J, 1760 rpm complete with 1.5-metre silencer, 10 hp, 575/3/60.

.7 HVAC EF-5 (Office Washroom Exhaust Fan):

.1 Loren Cook GC-180 ceiling cabinet blower, 60 l/s @ 63 Pa, 97 watt motor, 110/1/60, maximum sones 2.4. Accessories: Variable speed controller, wall cap.

.8 HVAC EF-7 (Odour Control Room Exhaust Fan):

.1 Woods 15J, 570 l/s @ 150 Pa, 1700 rpm, 0.5 hp motor, 575/3/60, epoxy coated inside and out.

.9 HVAC EF-8 (Boiler Area Exhaust Fan):

.1 Loren Cook 42XLWH propeller fan, 9,500 l/s @ 40 Pa, 3 hp motor, 575/3/60, complete with motorized backdraft damper.

2.3 Chilled Water System Accessories

.1 Furnish in the locations shown on the drawings the following equipment to be used in conjunction with the heating system:

.1 Expansion Tank ET-1:

.1 Amtrol AX40, tank volume shall be 82 litres, acceptance volume 19 litres, ASME Section VIII, Division 1.

.2 Water Makeup Stations:

.1 20 mm (3/4") make-up assembly consisting of strainer, backflow preventer, and pressure reducing valve bypass, pressure gauges and pressure relief valve piped to the nearest drain.

.3 Relief Valves:

.1 Supply ASME approved relief valve side outlet type, furnished in sufficient number and size to provide ample relieving capacity in accordance with ASME Boiler Code. Pipe all relief valves directly to drains.

2.4 Pump HVAC P-1

.1 Pumps are Armstrong Series 4300 split-coupled vertical in-line type. The pumps shall be radially split, single stage centrifugal type with bronze fitted casing with equal size suction and

Page 101: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15700 AND SEWAGE PUMP STATION HVAC EQUIPMENT PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

discharge flanges, with separate tapped flush line and pressure gauge connections. The pump shall have a cast bronze dynamically balanced impeller, stainless steel shaft, lower carbon throttle bushing, inside unbalanced type mechanical seal with carbon rotating face, ceramic stationary seat and EPDM secondary seal.

The pump shall be complete with a factory furnished flush and vent line. The driving motor shall be premium efficiency, inverter rated vertical solid shaft, squirrel cage induction type, built to NEMA standards. The motor shall have drip proof enclosure and be suitable for a 575/3/60 power supply. Provide in the flush line to the mechanical seal a 50-micron cartridge filter, or alternatively a cyclone separator when the pump pressure differential exceeds 30 psig, and floating ball type sight flow indicator suitable for the working pressure encountered. The motor shall be connected to the pump through a high tensile aluminum, split type spacer coupling to permit servicing of the mechanical seal without disturbing the pump, motor, or electrical wiring. The coupling shall be protected by a guard.

.2 The pumps shall be UL listed and CSA approved.

.3 Pumps are Armstrong, Grundfos, or other approved circulators with capacity, model, horsepower, pressure rating, rpm and efficiency as specified herein.

.4 Pump Schedule:

.1 HVAC P-1:

.1 11.0 l/s (175 gpm) @ 165 kPa (55 feet), motor 5 hp, 575/3/60, Armstrong Series 4300, 3x3x8, 1800 rpm, with Flo-trex valve and suction guide.

2.5 Pumps - Circulators

.1 Inline circulators are maintenance free, in-line, single stage, and wet rotor type with the motor mounted directly to the volute. The pump volute shall be constructed of cast iron and rated at 1000 kPa (145 psi) working pressure. The impeller, impeller inlet cone, rotor can, and rotor cladding shall be constructed of stainless steel. The impeller shall be secured directly to the motor shaft by means of a stainless steel split cone. The motor shaft shall be constructed of aluminum oxide ceramic and shall be supported by two radial bearings mounted in a stainless steel bearing plate and rotor can. The pump shall not have a coupling or mechanical seal.

.2 Pump motors shall be selected so as to be non-overloading at any point on the pump operating curve. The motor shall be cooled and lubricated by the pumped fluid and shall require no scheduled maintenance.

.3 The pumps shall be UL listed and CSA approved.

.4 Pumps are Armstrong, or other approved circulators with capacity, model, horsepower, pressure rating, rpm and efficiency as specified herein.

.5 Provide a blanking plate for all dual head pumps so that one pump can be operated while the other is removed.

.6 Pump Schedule:

.1 HVAC P-2:

Page 102: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15700 AND SEWAGE PUMP STATION HVAC EQUIPMENT PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.1 4.54 l/s (72 gpm) @ 45 kPa, (15 feet) ½ hp motor, 575/3/60, Armstrong Series S55, 1800 rpm.

.2 HVAC P-3:

.1 2.00 l/s (32 gpm) @ 45 kPa, (15 feet) ½ hp motor, 575/3/60, Armstrong Series S55, 1800 rpm.

.3 HVAC P-4:

.1 0.08 l/s (1.3 gpm) @ 30 kPa, (10 feet) 1/25 hp motor, 110/1/60, Armstrong Astro 25.

3 EXECUTION

3.1 General

.1 Install all equipment in accordance with the manufacturer's recommendations.

.2 Ensure that installed equipment is not subject to any undue stress or strain.

.3 Check that all equipment is vibration free, and where necessary adjust equipment or supports to ensure that equipment is quiet in operation and / or provide external vibration isolators, if necessary, so that no vibration is transmitted to the building structure.

.4 Adequately protect all finished work, and make good, without cost any damage caused during the execution of the works prior to acceptance.

3.2 Miscellaneous Metal

.1 Provide and install all miscellaneous metalwork associated with this section of the works. This includes steel and angle iron supports required for air handling equipment.

.2 Prime coat all steelwork and leave ready for finish by others.

END OF SECTION

Page 103: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15720 AND SEWAGE PUMP STATION AIR HANDLING UNITS PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Work Included

.1 Supply of a complete packaged indoor air-handling units including:

.1 Casing

.2 Outdoor air and return air dampers

.3 Heating coil or chilled water cooling coil with drain pan

.4 Supply fan

.5 Motor and drive for each fan

.6 Filter section

.7 Duct connections

.2 . Supply of filters for the air-handling units.

1.2 Quality Assurance

.1 Fans to conform to AMCA and shall bear AMCA certified rating seal.

.2 Coil capacities, pressure drops and selection procedures shall be certified in accordance with ARI Standard 410.

.3 Filter media shall be ULC listed, Class I or Class II, as approved by local authorities.

.4 The factory-installed wiring shall be factory CSA approved.

1.3 Submittals

.1 Submit the following as part of the shop drawings:

.1 Dimensions and weights (total and sectional)

.2 Capacities

.3 Certifications

.4 Component performance

.5 Electrical characteristics

.6 Casing construction details

.7 Wiring interconnections

.8 Gauges and finish of materials

Page 104: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15720 AND SEWAGE PUMP STATION AIR HANDLING UNITS PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.9 Fan curves with marked operating point

.10 Fan acceleration times and critical speeds

.11 Sound power levels spectrum at the inlet, outlet, and exterior of the unit at the unit's operating point

.12 Coil selection worksheets

.13 Air filter information

.14 Electrical requirements including wiring diagrams for interlocks and controls, indicating factory-installed and field-installed wiring.

.15 Installation instructions

2 PRODUCTS

2.1 Air Handling Units - General

.1 Air-handling units are Trane indoor M-Series Modular Climate Changers complete with fan section, heating coil section and/or cooling coil section, filter section, centrifugal fan, motor, heating coil and/or cooling coil, filter section with 300 mm deep Merv 13 cartridge filters in slide-in frames, intake section, and mixing box section for units HVAC-104 and HVAC-106.

.2 Casings shall be double wall with perforated liner and 25 mm thick 1.5 lb insulation.

.3 Repair all defective factory applied insulation and paint after installation of units.

.4 Fan Section

.1 Centrifugal fan as specified with forward curved blades. Fan wheel to be mounted on one-piece shaft.

.2 Fan statically and dynamically balanced, final test with fan and motor in place.

.3 Fan and motor integrally mounted on welded steel channel base.

.4 Units shall have internal isolators for the fan with minimum 25 mm static deflection. Isolate the fan casing and other components in accordance with Section 15070, "Noise, Vibration, and Seismic Control".

.5 Casing shall be double wall with perforated inner liner. Cabinet casing shall be galvanized steel or factory baked semi-gloss primer. Casing sufficiently braced and reinforced to prevent distortion during transportation hoisting and erection. Provide access door or panel, heavy gauge galvanized steel double panel insulated between panels, flush mounted on casing, one piece continuous gasketting for positive seal and complete with hinges for access door and quick-opening handle with locking latch or latches. Extend grease fittings as required for external lubrication. Provide a base rail under the entire cabinet assembly.

.6 Factory insulate casing walls and roof internally with 3.0 lb/ft3 density 25 mm coated glass fibre acoustic insulation.

Page 105: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15720 AND SEWAGE PUMP STATION AIR HANDLING UNITS PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.7 Provide IAQ drain pan.

.8 Submit the following with shop drawings:

.1 Fan curves indicating operating point

.2 Spectrum of sound power level at operating point

.5 Motor and Drive:

.1 Motors mounted on slide rails. Motors are to be 1800 rpm, 575 volt, 3 phase, inverter duty, high efficiency type.

.2 Adjustable V-belt drive assembly for motors up to and including 7.5 hp, fixed V-belt drive assembly for motors over 7.5 hp.

.3 Drives with minimum service factor of 1.5 based on motor horsepower.

.4 Belt guard, open expanded metal with galvanized steel sides, expanded metal face with opening for tachometer.

.6 Coil Section

.1 Casings to be double wall galvanized steel, formed to prevent air bypassing the heating surface, and flanged for ductwork connections with IAQ drain pan.

.2 Provide coil arranged as shown on the drawings.

.3 Coils shall be suitable for operation under the conditions specified.

.4 Coils to have end connections as shown on the drawings.

.5 Factory insulate casing walls and roof internally with 3.0 lb/ft3 density 25 mm coated glass fibre acoustic insulation.

.7 Filter Section

.1 Provide 300 mm deep Merv 13 cartridge filters.

.2 Install 1 complete set filter cartridge element in each and every bank of filters. Provide a spare set of filter media.

.3 All filter sections designed for slide-in application with gasketed access door on side.

.4 Casing shall be double wall with perforated inner liner. Factory insulate casing walls and roof internally with 3.0 lb/ft3 density 25 mm coated glass fibre acoustic insulation.

.8 Access Sections

.1 Provide access sections with hinged access doors between the section upstream of the coil to provide full maintenance access.

Page 106: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15720 AND SEWAGE PUMP STATION AIR HANDLING UNITS PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Casing shall be double wall with perforated inner liner. Factory insulate casing walls and roof internally with 3.0 lb/ft3 density 25 mm coated glass fibre acoustic insulation.

2.2 Air Handling Unit HVAC-102 (Dry Well)

.1 Size: 12

.2 Air flow capacity: 2360 l/s (5,000 cfm) @ 370 Pa external static pressure.

.3 Fan: 12B – 15” FC

.4 Motor: 7.5 hp

.5 Heating Coil:

.1 Coil and Fin Type: Trane type UW, Delta-Flo H

.2 Coil Size: 1 @ 813 mm high

.3 Face Area: 1.14 m2

.4 Rows: 2

.5 Fin Spacing: 367 per metre

.6 Entering Air: -9.44ºC

.7 Leaving Air: 15.56ºC

.8 Fluid: Water

.9 Entering Fluid: 50ºC

.10 Fluid Temperature Drop: 11.11ºC

.11 Fluid Flow Rate: 1.98 L/s

.12 Total Capacity: 91.51 kW

.13 Air Pressure Drop: 30.89 Pa

.14 Fluid Pressure Drop: 4.1 kPa

.6 Cooling Coil: None

.7 Filter Section: Included

.8 Mixing Box: None

2.3 Air Handling Unit HVAC-103 (Heat Pump Area)

.1 Size 21

Page 107: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15720 AND SEWAGE PUMP STATION AIR HANDLING UNITS PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Airflow capacity: 4,720 l/s (10,000 cfm) @ 370 Pa external static pressure.

.3 Fan: 21B – 20” FC

.4 Fan speed: 1062 rpm

.5 Motor: 15 hp

.6 Heating Coil: None

.7 Cooling Coil:

.1 Coil and Fin Type: Trane type UW, Delta-Flo H

.2 Coil Size: 1 @ 1143 mm high

.3 Face Area: 1.93 m2

.4 Rows: 6

.5 Fin Spacing: 489 per metre

.6 Entering Air: 30ºC DB, 20.6ºC WB

.7 Leaving Air: 19.0ºC DB, 17.0ºC WB

.8 Fluid: 30% ethylene glycol

.9 Entering Fluid: 16.1ºC

.10 Fluid Temperature Rise: 6.7ºC

.11 Fluid Flow Rate: 2.61 L/s

.12 Capacity: 64.46 kW sensible, 64.46 kW total

.13 Air Pressure Drop: 154 Pa

.14 Fluid Pressure Drop: 21 kPa

.8 Filter Section: Included

.9 Mixing Box: Included

2.4 Air Handling Unit HVAC-104 (Electrical Room)

.1 Size 35

.2 Airflow capacity: 11,800 l/s (25,000 cfm) @ 310 Pa external static pressure.

.3 Fan: 50A – 33” FC

.4 Fan speed: 521 rpm

Page 108: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15720 AND SEWAGE PUMP STATION AIR HANDLING UNITS PAGE 6

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.5 Motor: 20 hp

.6 Heating Coil: None

.7 Cooling Coil:

.1 Coil and Fin Type: Trane type W, Prima-Flo E

.2 Coil Size: 1 @ 762 mm high, 1 @ 838 mm high

.3 Face Area: 4.43 m2

.4 Rows: 8

.5 Fin Spacing: 334 per metre

.6 Entering Air: 27.8ºC DB, 18.3ºC WB

.7 Leaving Air: 14.0ºC DB, 13.4ºC WB

.8 Fluid: 30% ethylene glycol

.9 Entering Fluid: 10ºC

.10 Fluid Temperature Rise: 6.7ºC

.11 Fluid Flow Rate: 8.15 L/s

.12 Capacity: 200.1 kW sensible, 200.1kW total

.13 Air Pressure Drop: 152 Pa

.14 Fluid Pressure Drop: 31.3 kPa

.8 Filter Section: Included

.9 Mixing Box: None (Site fabricated)

2.5 Air Handling Unit HVAC-105 (Boiler Area)

.1 Size 35

.2 Airflow capacity: 7550 l/s (16,000 cfm) @ 370 Pa external static pressure.

.3 Fan: 35B – 25” FC

.4 Fan speed: 786 rpm

.5 Motor: 20 hp

.6 Heating Coil:

.1 Coil and Fin Type: Trane type UW, Delta-Flo H

Page 109: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15720 AND SEWAGE PUMP STATION AIR HANDLING UNITS PAGE 7

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Coil Size: 1 @ 1448 mm high

.3 Face Area: 3.17 m2

.4 Rows: 2

.5 Fin Spacing: 279 per metre

.6 Entering Air: -8.0ºC

.7 Leaving Air: 15ºC

.8 Fluid: Water

.9 Entering Fluid: 50ºC

.10 Fluid Temperature Drop: 11.11ºC

.11 Fluid Flow Rate: 4.54 L/s

.12 Total Capacity: 210.5 kW

.13 Air Pressure Drop: 34 Pa

.14 Fluid Pressure Drop: 8.6 kPa

.7 Cooling Coil: None

.8 Filter Section: Included

.9 Mixing Box: None

2.6 Air Handling Unit HVAC-106 (Office)

.1 Size 03

.2 Air flow capacity: 560 l/s (1,200 cfm) @ 125 Pa external static pressure.

.3 Fan: 3A – 9.5” FC

.4 Fan speed: 1741 rpm

.5 Motor: 1 hp

.6 Heating Coil:

.1 Coil and Fin Type: Trane type TT, Prima-Flo E

.2 Coil Size: 1 @ 457 mm high

.3 Face Area: 0.26 m2

.4 Rows: 2

Page 110: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15720 AND SEWAGE PUMP STATION AIR HANDLING UNITS PAGE 8

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.5 Fin Spacing: 269 per metre

.6 Entering Air: 20.0ºC

.7 Leaving Air: 25.6ºC

.8 Fluid: Water

.9 Entering Fluid: 50ºC

.10 Fluid Temperature Drop: 11.11ºC

.11 Fluid Flow Rate: 0.08 L/s

.12 Total Capacity: 3.8 kW

.13 Air Pressure Drop: 14 Pa

.14 Fluid Pressure Drop: 2.4 kPa

.7 Cooling Coil:

.1 Coil and Fin Type: Trane type P2, Prima-Flo H

.2 Coil Size: 1 @ 1448 mm high

.3 Face Area: 0.26 m2

.4 Rows: 6

.5 Fin Spacing: 524 per metre

.6 Entering Air: 23.4ºC DB, 16.6ºC WB

.7 Leaving Air: 14.6ºC DB, 13.3ºC WB

.8 Fluid: 30% ethylene glycol

.9 Entering Fluid: 12.2ºC

.10 Fluid Temperature Rise: 6.7ºC

.11 Fluid Flow Rate: 0.30 L/s

.12 Capacity: 7.28 kW sensible, 7.28kW total

.13 Air Pressure Drop: 165 Pa

.14 Fluid Pressure Drop: 53 kPa

.8 Filter Section: Included

.9 Mixing Box: Included

Page 111: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15720 AND SEWAGE PUMP STATION AIR HANDLING UNITS PAGE 9

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

3 EXECUTION

3.1 General

.1 Install all equipment in accordance with the Manufacturer's recommendations.

.2 Align all drives, check and adjust equipment for free rotation.

.3 Ensure that installed equipment is not subject to any undue stress or strain.

.4 Check that all equipment is vibration free, and where necessary adjust equipment or supports to ensure that equipment is quiet in operation and that no vibration is transmitted to the building structure.

.5 Adequately protect all finished work, and make good, without cost any damage caused during the execution of the works prior to acceptance.

3.2 Air Handling Units

.1 Install the air-handling units in accordance with manufacturer's recommendations.

3.3 Miscellaneous Metal

.1 Provide and install all miscellaneous metalwork associated with this section of the works. This includes steel and angle iron supports required for air handling equipment.

.2 Prime coat all steelwork and leave ready for finish by others.

END OF SECTION

Page 112: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15800 AND SEWAGE PUMP STATION AIR DISTRIBUTION PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 General

.1 Execute all work and furnish all products as specified herein and in accordance with the contract documents.

.2 The general intent is to furnish ductwork in accordance with the recommendations of the current ASHRAE guide unless otherwise noted herein.

1.2 Work Included

.1 Ductwork and all accessories.

.2 Air outlets.

.3 Duct cleaning

.4 Silencers

1.3 Quality Assurance

.1 Ductwork shall be in accordance with the requirements of NFPA 90A.

.2 Fabricate ductwork in accordance with SMACNA standards and ASHRAE handbooks.

2 PRODUCTS

2.1 Ductwork

.1 Rectangular and round low velocity, low pressure ductwork, unless specifically noted otherwise, is made from ASTM designation A527-67 steel with 1-1/4 oz. zinc coating. Galvanizing quality must allow the sheets to be bent flat upon themselves with no fracture to the coating or base metal.

.2 Provide round ductwork in 3.5-metre lengths to minimize joints.

.3 Fabricate all ductwork in accordance with SMACNA Duct Construction Standards to suit the application and pressure developed.

.4 All ductwork within the Wet Well area and within the Odour Control Room shall be aluminum.

.5 All Wet Well area exhaust ductwork that is located outside the wet well area shall be all welded 18 gauge stainless steel.

2.2 Access Doors

.1 Furnish access doors or removable duct access sections as required for inspection, maintenance and cleaning and as shown on the drawings and as specified herein.

Page 113: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15800 AND SEWAGE PUMP STATION AIR DISTRIBUTION PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Rectangular ductwork access doors to be Nailor Hart Series 0800 low leakage die formed doors with 25 mm insulation and backing plate, camlock closure, and positive seal gasketting. Doors to be galvanized steel for galvanized steel ductwork, aluminum for aluminum ductwork.

.3 Round ductwork access doors to be Nailor Hart Model 0890.

.4 Access doors to be minimum 300 mm x 150 mm for ducts of maximum dimension of 350 mm, 450 mm x 250 mm for all other ducts, or as required for service access.

.5 Ductwork Access Door Locations

.1 Either side of all equipment and restrictions in air handling system (i.e., turning vanes, coils, axial fans, fire dampers, etc.).

.2 The base of every riser.

.3 In duct runs as required to allow access to every 15 metre section.

2.3 Volume Dampers

.1 Provide volume dampers in the specified locations and where required to facilitate air system balance.

.2 Volume Dampers Description for Ducts Over 200 mm

.1 . Opposed multi-blade design, for squeeze action unless noted otherwise.

.2 Mechanism with friction lock wide pitched screw.

.3 Hardware to be as follows riveted to the duct and dampers:

Duct Type Dial Regulator

.1 Uninsulated Ventlock #635

.2 Insulated Ventlock #637

.3 Volume Damper Description for Ducts Under 200 mm

.1 Single blade butterfly design.

.2 Centreline fastened to 9 mm square bar.

.3 9 mm quadrant control.

.4 Hardware to be as follows riveted to the duct and damper.

Duct Type Dial Regulator

.1 Uninsulated Ventlock #635

.2 Insulated Ventlock #637

Page 114: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15800 AND SEWAGE PUMP STATION AIR DISTRIBUTION PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.4 Mark all damper rods with end slots to indicate damper position.

2.4 Fire Dampers

.1 Fire dampers shall be UL listed and carry the label of the Underwriters Laboratory of Canada.

.2 Fire dampers are interlocking blade design. Blades attached in the air stream for velocities 7.5 m/s and lower where aspect ratio is 2:1 or less, use low resistance type fire damper with blades out of the air stream for velocities above 7.5 m/s and aspect ratios greater than 2:1.

.3 Set fusible links at 71ºC on exhaust and recirculation ducts 104ºC on supply ducts unless otherwise noted.

2.5 Grilles, Registers and Diffusers

.1 Furnish grilles, registers and diffusers as shown on the drawings and with frames suitable for the application. All equipment with a baked enamel finish in finished areas or anodized aluminum in other areas.

2.6 Silencers

.1 Provide silencers as specified herein and shown on the drawings.

2.7 Intake and Exhaust Louvres

.1 Provide extruded aluminum louvres as shown and specified on the drawings.

.2 Louvres shall be fabricated from extruded aluminum and painted with a baked enamel finish with colour as selected by the architect.

.3 Provide 12 mm mesh birdscreen behind the louvre.

.4 Louvres to be Airolite K6776.

2.8 Control Dampers

.1 Provide opposed blade control dampers where shown on the drawings (designated MD-). Only use parallel blade dampers where indicated.

.2 Damper blades to be of galvanized steel or extruded aluminum, adequately stiffened and provided with stainless steel shafts with oil impregnated sintered bronze bearings. Outdoor air and exhaust air dampers to be low leakage type with continuous neoprene edge stops and seals on all sides. Dampers to be Ruskin CD60 or other approved.

.3 Damper Schedule

.1 MD-1:Boiler Room relief 8000 l/s 6 @ 1800 x 400

.2 MD-2: Generator Room intake 8000 l/s 6000 x 825

.3 MD-3: Electrical Room outdoor air intake 12000 l/s 3000 x 2000

Page 115: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15800 AND SEWAGE PUMP STATION AIR DISTRIBUTION PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.4 MD-4: Electrical Room return 12000 l/s 3000 x 750

.5 MD-5: Electrical Room relief 12000 l/s 4800 x 1500

.6 MD-6: HVAC EF-1 Discharge 2500 l/s 750 x 750

.7 MD-7: HVAC EF-7 Discharge 2100 l/s 750 x 750

.8 MD-8: Generator Room return 6000 l/s 1200 x 900

3 EXECUTION

3.1 Ductwork

.1 Route and run ducts approximately as diagrammatically shown. Report all deviations to the Engineer for approval before proceeding. Carefully co-ordinate installation of exposed ductwork with other services.

.2 Insofar as possible, construct the ducts in accordance with the dimensions shown on the drawings. Where necessitated by building construction, alter the dimensions maintaining the same equivalent size. Size ducts from ASHRAE table of equivalent rectangular and round ducts, latest edition.

.3 Use a centreline radius not less than 1-1/2 times the width of the duct in the plane of rotation of the radius for all bends, tees and elbows unless dimensioned otherwise. Where this radius is not possible, fit formed airfoil blade duct-turns of approved design in low velocity ductwork. Obtain approval from the Consultant before using splitters or radii larger than 1-1/2 duct width.

.4 Construct transitions with maximum expansion angles of 30 degrees and maximum contraction angles of 45 degrees.

.5 Construct collars between ducts and diffusers with length equal to or greater than the diffuser neck diameter. All grilles, dampers and diffuser accessories are the same manufacturer as the diffusers.

.6 Make straight collars between the supply ducts and grilles not less than 300 mm in length and provide individual adjustable blade type distribution grids at the connection. Provide suitable cushion heads at the end of the low-pressure ducts.

.7 Duct dimensions shown are required clear inside dimensions. Where internal insulation is used, increase sheet metal dimensions by the thickness of the insulation maintaining the net dimensions shown.

.8 Support vertical ducts where they pass through the floor using angles, riveted and/or bolted to the duct, bearing on the structure with rubber pads. In addition, where required seal all openings around ducts and pipes with sheet metal of sufficiently heavy gauge to constitute a fire, noise and smoke separation. The separation must have a rating to match the rating of the barrier through which the ducts and pipes are passing. Use galvanized clamps drawn tight to support round ductwork at the floors, bearing on the structure with rubber pads. On exposed ductwork, provide galvanized angle collars to conceal the above construction both above and below the floor.

Page 116: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15800 AND SEWAGE PUMP STATION AIR DISTRIBUTION PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.9 Leave a smooth interior surface on all seams and joints. Break the corners and groove the longitudinal seams using Pittsburgh lock, button or lock slide or double seam corners. Bolt all bracing with backing plates. Do not use aluminum pop rivets.

.10 Construct ductwork in accordance with SMACNA standards.

.11 Fittings are of the slip joint type with all 90 degree elbows of the fabricated 5 piece type or miter elbows where shown on drawings. No crimping of the fittings is allowed. Lap all joints in the direction of airflow wherever possible and make them smooth on the inside. Stagger lockseam joints at least 90 degrees. Seal all joints with solder or a woven fabric material coated with a water-based sealant, which shall be non-toxic, non-combustible and non-flammable in a wet or dry state tested in accordance with ULC S-102. Flame spread not to exceed 25, and smoke developed not to exceed 50. Apply sealer to inside of joints on ducts and plenums under positive pressure where accessible and to outside of joints on ducts and plenums under negative pressure.

.12 Provide and mount flexible connections in ductwork connecting to fans and equipment. Construct coupling with Duro-Dyne grip-loc 6" wide flame resistant, neoprene coated heavy glass fabric, having a weight of 0.27 lb/ft2, in accordance with the requirements of NFPA bulletins #90A (1978).

.13 Do not leave pockets, ledges or projections inside the ducts. Remove all dirt, rubbish, duct accumulation of any description from the ductwork during erection. Block all duct openings immediately to prevent the entrance of construction dirt and materials.

.14 Seal all low velocity ductwork with Duro-Dyne S-3 standard grade fire resistant low velocity duct sealer. Sealer shall be in accordance with the requirements of NFPA 90A, 1978.

.15 Construct the ductwork to the following pressure classifications:

.1 Supply ductwork: +500 Pa [+2" wg]

.2 Exhaust ductwork: -500 Pa [-2" wg]

3.2 Interior Duct Insulation

.1 Insulate the ductwork on the interior where shown on the drawings, using material characteristics and methods as specified in Section 15080.

3.3 Fire Dampers

.1 Install fire dampers in accordance with NFPA Bulletin #90A and 90B-1999 and/or the requirements of authorities having jurisdiction.

.2 Extend the steel sleeve maximum 750 mm clear of the fire-separation, and use a breakaway connection to the ductwork. Retain fire-damper by means of steel angles. Fire damper must stay in place at the protected opening in case of fire.

.3 Provide access door for servicing fire dampers as specified.

.4 Size dampers so that clear duct interior dimensions are maintained (i.e. damper frames, blade housing) and mechanism are external to the ducts. Where openings are either too small or too

Page 117: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15800 AND SEWAGE PUMP STATION AIR DISTRIBUTION PAGE 6

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

large to accommodate the fire damper, provide a sleeve or extra flashing to seal the opening. For sleeve or flashing, use sufficient metal gauge thickness to maintain the fire rating.

.5 Allow for providing attendance on completion of the works to demonstrate the correct operation of all fire, smoke and combination dampers.

3.4 Grilles, Registers and Diffusers

.1 Provide and install all grilles, registers and diffusers as shown on drawings and specified in Equipment Schedule.

3.5 Cleaning of Air Distribution Systems

.1 The ductwork shall be cleaned using a standard hand vacuum cleaner unit prior to balancing.

3.6 Miscellaneous Metal

.1 Provide and install all miscellaneous metalwork associated with this section of the work. This includes but is not limited to all steel and angle iron supports for air handling equipment specified in Section 15800 and all steel and angle iron supports for ductwork.

.2 Prime coat all steelwork and leave ready for finish by others.

END OF SECTION

Page 118: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15840 AND SEWAGE PUMP STATION SLUICE GATES AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 1

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1 GENERAL

1.1 Scope

.1 Description of Work

.1 Provide all labor, material and equipment necessary to furnish and install stainless steel flow control sluice gates and operators/actuators as specified herein and as shown on the contract documents.

.2 Sluice gates and actuators are to be installed in a hazardous area and will be required to meet the requirements of the CEC (Canadian Electrical Code) for wet wells.

.3 Sluice gates are to be fitted with electric actuators or manual actuators as indicated on the drawings.

.4 The equipment provided under this section shall be fabricated, assembled, erected, and placed in proper operating condition in full conformity with the drawings, specifications, engineering data, instructions and recommendations of the equipment manufacturer unless exceptions are noted by the engineer.

.5 Gates and operators shall be supplied with all the necessary parts and accessories indicated on the drawings, specified or otherwise required for a complete, properly operating installation, and shall be the latest standard product of a manufacturer regularly engaged in the production of fabricated gates.

.2 Gates supplied under this section shall be Fabrcated AWWA C561 Stainless Steel Flow Control Sluice/Slide Gates as manufactured by:

.1 H. Fontaine Ltd (Smith Cameron, Surrey, B.C. Ltd 604-596-5522 ) . Slide Gate Model 20 or;

.2 Golden Harvest (Golden Harvest Burlington Washingtion, USA 360-757-4334). Slide Gate Model UH-46.

1.2 Governing Standards

.1 Except as modified or supplemented herein, all gates and operators shall conform to the applicable requirements of AWWA C561, latest edition.

1.3 Quality Assurance

.1 The manufacturer shall have experience in the production of substantially similar equipment, and shall show evidence of satisfactory operation in at least 50 installations. The manufacturer’s shop welds, welding procedures and welders shall be qualified and certified in accordance with the requirement of the latest edition of ASME, Section IX.

.2 Gates shall be shop inspected for proper operation before shipping.

.3 The manufacturer shall be ISO 9001: 2000 certified.

Page 119: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15840 AND SEWAGE PUMP STATION SLUICE GATES AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 2

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1.4 Submittals

.1 The manufacturer shall submit shop drawings showing the detailed dimensions, gate and seal construction details and materials used in the gate and lift mechanism. Submittals shall also be coordinated with and include shop drawings for gate actuators. Submittals shall be in accordance with Division 1 requirements.

2 PERFORMANCE

2.1 Leakage

.1 Sluice gates shall be watertight under the design head conditions, subject to the following leakage allowances. Under the design seating and unseating head, the leakage shall not exceed 0.05 U.S. gallon per minute per foot (0.60 l/min per meter) of seating perimeter (one half of AWWA C561 requirements).

2.2 Design Head

.1 The sluice gates shall be designed to withstand the design head shown in the sluice gate schedule.

2.3 Seal Performance Test

.1 The gate’s sealing system shall have been proof tested through a cycle test in an abrasive environment and should show that the leakage requirements are still obtained after 25,000 cycles with a minimum deterioration.

3 PRODUCT

3.1 Sluice Gates

.1 General Design Gates shall be self-contained of the rising stem, configuration as indicated on the drawings and the gate schedule.

.2 Wall Thimble: Not applicable. Gates shall be wall mounted using grout pad as indicated.

.3 Frame: The gate frame shall be constructed of structural members or formed plate welded to form a rigid one-piece frame. The frame shall be of the flange back design suitable for mounting on a concrete wall (CS), concrete wall with extra-wide flange (CWX) as indicated. The guide slot shall be made of UHMWPE (ultra high molecular weight polyethylene).

.1 The frame and configuration shall be of the flush-bottom type and shall allow the replacement of the top and side seals without removing the gate frame from the concrete or wall thimble.

.4 Slide: The slide shall consist of a flat plate reinforced with formed plates or structural members to limit its deflection to 1/720 of the gate’s span under the design head.

.5 Guides and Seals: The guides shall be made of HUMWPE (ultra high molecular weight polyethylene) and shall be of such length as to retain and support at least two thirds (2/3) of the vertical height of the slide in the fully open position.

Page 120: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15840 AND SEWAGE PUMP STATION SLUICE GATES AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 3

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.1 Side and top seals shall be made of UHMWPE (ultra high molecular weight polyethylene) of the self adjusting type. A continuous compression cord shall ensure contact between the UHMWPE guide and the gate in all positions. The sealing system shall maintain efficient sealing in any position of the slide and allow the water of flow only in the opened part of the gate.

.2 The bottom seal shall be made of resilient neoprene set into the bottom member of the frame and shall form a flush-bottom.

3.2 Operators and Stem

.1 Electric Actuators are to be used on all gates except one manually operated gated as indicated on the drawings and in the gate schedule.

.2 Stem and Couplings: The operating tem shall be of stainless steel designed to transmit in compression at least 2 times the rated output of the operating manual mechanism with a 40 lbs (178 N) effort on the crank or handwheel.

.1 The stem shall have a slenderness ration (L/r) less than 200. The threaded portion of the stem shall have machined cut threads of the ACME type.

.2 Where electric operators are used, the stem design force shall not be less than 1.25 times the output thrust of the electric motor and attached gearing in the stalled condition.

.1 For stems in more than one piece and with a diameter of 1 ¾ inches (45 mm) and larger, the different sections shall be joined together by solid bronze couplings. Stems with a diameter smaller than 1 ¾ inches (45mm) shall be pinned to an extension tube.

.3 The couplings shall be grooved and keyed and shall be of greater strength than the stem.

.3 Gates having a width greater than two times their height shall be provided with two lifting mechanisms connected by a tandem shaft.

.4 Stem Guides: Stem guides shall be fabricated from type 304L stainless steel. The guide shall be equipped with an UHMWPE bushing. Guides shall be adjustable and spaced in accordance with the manufacturer’s recommendation. The L/ratio shall not be greater than 200.

.5 Stem Cover: Rising stem gates shall be provided with a clear polycarbonate stem cover. The stem cover shall have a cap and condensation vents and a clear mylar position indicating tape. The tape shall be field applied to the stem cover after the gate has been installed and positioned.

.6 Lifting Mechanism: Manual operators of the types listed in the schedule shall be provided by the gate manufacturer.

.1 All bearings and gears shall be totally enclosed in a weather tight housing. The pinion shaft of crank-operated mechanisms shall be constructed of stainless steel and supported by roller or needle bearings.

Page 121: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15840 AND SEWAGE PUMP STATION SLUICE GATES AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 4

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.2 Each manual operator shall be designed to operate the gate under the maximum specified seating and unseating heads by using a maximum effort of 40 lbs (178 N) on the crank or handwheel, and shall be able to withstand, without damage, an effort of 80 lbs (356 N).

.3 The crank shall be removable and fitted with a corrosion-resistant rotating handle. The maximum crank radius shall be 15 inches (381 mm) and the maximum handwheel diameter shall be 24 inches (610 mm).

.7 Yoke: Self-contained gates shall be provided with a yoke made of structural members or formed plates. The maximum deflection of the yoke shall be 1/360 of the gate’s span.

4 MATERIALS

Part Material

Frame, yoke, stem guides, slide, stem extension

Stainless Steel ASTM A-240 Type 304L

Side seals, stem guide liner

Ultra high molecular weight polyethylene (UHMWPE) ASTM D-4020

Compression cord Nitrile ASTM D-2000 M6BG 708, A14, B14, E014, E034

Bottom Seal Neoprene ASTM D-2000 Grade 2 BC 510

Threaded Stem Stainless Steel ASTM A-276 Type 303 MX

Fasteners ASTM F593 and F594 GR1 for Type 304

Pedestal, Handwheel, Crank Tenzaloy aluminum

Gasket (between frame and wall) EPDM STM 1056

Stem Cover

Polycarbonate STM D-3935

Lift Nut, Couplings Manganese Bronze ASTM B584 UNS-C86500

5 SCHEDULE

Gate Identification

GA -1 GA -2 GA -3 GA -4 GA -5 GA- 6

Gate Type SC SC SC SC SC SC Size - Width x Height 750 x

1700 1100 x 1400

750 x 1700

1000 x 1300

1000 x1300

1000 X 1200

Page 122: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15840 AND SEWAGE PUMP STATION SLUICE GATES AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 5

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

Operating Floor Elevation

-0.6 meters

-0.6 -0.6 meters

+0.2 +0.2 meters

-0.6 meters

Top of Frame Elevation

+0.194 +0.794 +0.194 +0.80 +0.80 +1.05

Invert Elevation

-3.965 -2.39 -3.965 -2.46 -2.46 -1.78

Head (Seating / Unseating)

6 meters 6 meters

6 meters 6 meters 6 meters 6 meters

Mounting

CW CW CW CW CW CWX

.1 NOTE: Dimensions and elevations are approximate only and to be confirmed by the Contractor and shown on submittal drawings for review by the Engineer.

.2 Gate Type Self-contained

.3 Mounting:

.1 CW Mounted on a concrete wall

.2 CWX Mounted on a concrete wall in front of a pipe (specify type of pipe)

6 EXECUTION

.1 Installation: Gates and appurtenances shall be handled and installed in accordance with the contract drawings and manufacturer’s recommendations.

6.2 Field Tests

.1 Following the completion of each gate installation the gates shall be operated through at least two complete open/close cycles. For electrically operated gates, limit switches shall be adjusted following the manufacturer’s instructions.

.2 Gates should be checked for leakage by the contractor (refer to the “Performance” section for approval criteria).

END OF SECTION

Page 123: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15850 AND SEWAGE PUMP STATION MULTI TURN ELECTRIC ACTUATORS AND RELATED EQUIPMENT FOR SLIDE GATES PAGE 1

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1 GENERAL

1.1 Scope

.1 Description of Work

.1 Provide electric multi turn actuators fitted to five (5) separate slide gates as specified herein and as shown on the contract documents. See Section 15800 for slide gates. See section 15452 for plug valves and section 15860 for corresponding quarter turn actuators. Slide gate manufactures shall obtain actuator from actuator supplier for fitting to gates for factory testing.

.2 Slide gates fitted with multi turn electric actuators are to be installed in a hazardous area and will be required to meet the requirements of the CEC (Canadian Electrical Code) for wet wells and shall be rated for use in hazardous areas rated Class 1 Zone 1.

.3 The equipment provided under this section shall be fabricated, assembled, erected, and placed in proper operating condition in full conformity with the drawings, specifications, engineering data, instructions and recommendations of the equipment manufacturer unless exceptions are noted by the engineer.

.4 Slide gates and operators shall be supplied with all the necessary parts and accessories indicated on the drawings, specified or otherwise required for a complete, properly operating installation, and shall be the latest standard product of a manufacturer regularly engaged in the production of fabricated gates and actuators.

.2 Basic Requirements

.1 The actuators shall be suitable for use on a nominal 575 volt three-phase 60 Hertz power supply and are to incorporate motor, integral reversing starter, local control facilities, and terminals for remote control and indication connections.

.2 The actuator shall include a device to ensure that the motor runs with the correct rotation for the required direction of valve travel with either phase sequence of the three-phase power supply connected to the actuator.

.3 It shall be possible to carry out the setting of the torque, turns, and configuration of the indication contacts without the necessity to remove any electrical compartment covers.

.3 Special Requirements

.1 Wet well actuators are also to be fitted with positioners such that the position of the two (2) gates at the entrance to the wet wells can be controlled remotely from the station PLC using a 4 – 20 ma signal.

2 ACTUATOR SIZING:

.1 The actuator shall be sized to guarantee gate closure at a specified differential head of 6 meters of water (tbc). The safety margin of motor power available for seating and unseating the gate shall be sufficient to ensure torque switch trip at maximum valve torque with the supply

Page 124: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15850 AND SEWAGE PUMP STATION MULTI TURN ELECTRIC ACTUATORS AND RELATED EQUIPMENT FOR SLIDE GATES PAGE 2

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

voltage 10% below nominal. The operating speed shall be such as to give gate closing and opening at approximately 10-12 inches per minute unless otherwise stated in the job specification.

3 AMBIENT TEMPERATURE:

.1 The actuator shall be capable of functioning in an ambient temperature ranging from minus - 30 °C to +70 °C.

4 MOTOR:

.1 The electric motor shall be Class F insulated with a time rating of at least 15 minutes at 104°F (40°C) or twice the gate operating time, whichever is the longer, at an average load of at least 33% of maximum gate torque.

.2 Electrical and mechanical disconnection of the motor should be possible without draining the lubricant from the actuator gearcase. Plugs and sockets are not acceptable as a means of electrical connection for the motor.

5 MOTOR PROTECTION:

.1 Protection shall be provided for the motor as follows:

.1 The motor shall be de-energized in the event of stall when attempting to unseat a jammed gate.

.2 Motor temperature shall be sensed by a thermostat to protect against overheating.

.3 Single phasing protection.

6 GEARING:

.1 The actuator gearing shall be totally enclosed in an oil- filled gearcase suitable for operation at any angle. All main drive gearing must be of metal construction. The drive shall incorporate a lost-motion hammerblow feature. For rising spindle gatess, the output shaft shall be hollow to accept a rising stem and incorporate thrust bearings of the ball or roller type at the base of the actuator, and the design should be such as to permit the gearcase to be opened for inspection or disassembled without releasing the stem thrust or taking the gate out of service.

.2 Standard SAE80EP gear oil shall be used to lubricate the gearcase. Special or exotic lubricants shall not be used as they may be difficult to source in remote locations.

.3 Rotork IB Bevel Gear Operator required for installation on IQ Actuator.

.1 Due to head wall clearance at the influent screen channel gates, the three (3) IQ Actuators at these locations shall be mounted to IB Bevel Geared Lifts to provide clearance between the actuator and concrete wall. Direct drive units will not be considered for these three (3) gates.

Page 125: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15850 AND SEWAGE PUMP STATION MULTI TURN ELECTRIC ACTUATORS AND RELATED EQUIPMENT FOR SLIDE GATES PAGE 3

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

7 HAND OPERATION:

.1 A handwheel shall be provided for emergency operation engaged when the motor is declutched by a lever or similar means; the drive being restored to power automatically by starting the motor. The hand/auto selection lever should be padlockable in both "Hand" and "Auto" positions. It should be possible to select hand operation while the actuator is running or start the actuator motor while the hand/auto selection lever is locked in "Hand" without damage to the drive train.

.2 The handwheel drive must be mechanically independent of the motor drive, and any gearing should be such as to permit emergency manual operation in a reasonable time. Clockwise operation of the handwheel shall give closing movement of the valve unless otherwise stated in the job specification. The handwheel shall be operable with maximum rim pull of 60 lbs at maximum unseating/seating head.

8 DRIVE BUSHING:

.1 The actuator shall be furnished with a drive bushing easily detachable for machining to suit the gate stem or gearbox input shaft. Normally the drive bush shall be positioned in a detachable base of the actuator. Thrust bearings, when housed in a separate thrust base, should be of the sealed-for-life type.

9 TORQUE AND TURNS LIMITATIONS:

.1 Torque and turns limitation to be adjustable as follows:

.1 Position setting range: 2.5 to 100,000 turns, with resolution to 7.5° of actuator output.

.2 Torque setting: 40% to 100% rated torque.

.3 Torque sensing must be affected directly electrically or electronically. Extrapolating torque from mechanically measured motor speed is not acceptable due to response time. Torque measurement shall be independent of variations in frequency, voltage or temperature.

.1 “Latching" to be provided for the torque sensing system to inhibit torque off during unseating or during starting in mid-travel against high inertia loads.

.2 The electric circuit diagram of the actuator should not vary with gate type remaining identical regardless of whether the valve is to open or close on torque or position limit. An inexpensive setting tool is required for non-intrusive calibration and interrogation of the actuator. This setting tool will provide speedy interrogation capabilities as well as security in a non-intrusive intrinsically safe watertight casing.

10 REMOTE VALVE POSITION/ACTUATOR STATUS INDICATION:

.1 In the event of a (main) power (supply) loss or failure, the position contacts must continue to be able to supply remote position feedback and maintain interlock capabilities.

.2 A backup power source must be provided in the actuator to ensure correct remote indication should the actuator be moved manually when the power supply is interrupted.

Page 126: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15850 AND SEWAGE PUMP STATION MULTI TURN ELECTRIC ACTUATORS AND RELATED EQUIPMENT FOR SLIDE GATES PAGE 4

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.3 The position of the actuator and gate must be updated contemporaneously, even when the power supply is not present.

.4 Four contacts shall be provided which can be selected to indicate any position of the gate with each contact externally selectable as normally open or normally closed. The contacts shall be rated at 5A, 250V AC, 30V DC.

.5 As an alternative to providing gate position, any of the four above contacts shall be selectable to signal one of the following:

.1 Gate Opening or Closing

.2 Gate Moving (Continuous or Pulsing)

.3 Local Stop Selected

.4 Local Selected

.5 Remote Selected

.6 Open or Close Interlock Active

.7 ESD Active

.8 Motor Tripped on Torque in Mid-Travel

.9 Motor Tripped on Torque Going Open

.10 Motor Tripped on Torque Going Closed

.11 Pre-Set Torque Exceeded

.12 Valve Jammed

.13 Actuator Being Operated by Handwheel

.14 Lost Main Power Phase

.15 Customer 24V DC or 120V AC Supply Lost

.16 Battery Low

.17 Internal Failure Detected

.18 Thermostat Tripped

.6 Provision shall be made in the design for the addition of a contact less transmitter to give a 4-20mA analog signal corresponding to gate travel for remote indication.

Page 127: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15850 AND SEWAGE PUMP STATION MULTI TURN ELECTRIC ACTUATORS AND RELATED EQUIPMENT FOR SLIDE GATES PAGE 5

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

11 LOCAL POSITION INDICATION:

.1 The actuator must provide a local display of the position of the valve, even when the power supply is not present. The display shall be able to be rotated in 90 degree increments so as to provide easy viewing regardless of mounting position.

.2 The actuator shall include a digital position indicator with a display from fully open to fully closed in 1% increments. Red, green, and yellow lights corresponding to Open, Closed, and Intermediate positions shall be included on the actuator. The digital display shall be maintained even when the power to the actuator is isolated.

.3 The local display should be large enough to be viewed from a distance of six feet (6’) when the actuator is powered up.

12 INTEGRAL STARTER AND TRANSFORMER:

.1 The reversing starter, control transformer, and local controls shall be integral with the valve actuator, suitably housed to prevent breathing and condensation buildup. For ON/OFF service, this starter shall be an electromechanical type suitable for 60 starts per hour and of rating appropriate to motor size. For modulating duty, the starter shall be suitable for up to a maximum of 1,200 starts per hour. The controls supply transformer shall be fed from two of the incoming three phases. It shall have the necessary tapings and be adequately rated to provide power for the following functions:

.1 120V AC energization of the contactor coils

.2 24V DC output where required for remote controls

.3 Supply for all the internal electrical circuits

.2 The primary and secondary windings shall be protected by easily replaceable fuses.

13 INTEGRAL PUSH BUTTONS AND SELECTOR:

.1 Integral to the actuator shall be local controls for Open, Close, and Stop, and a local/remote selector switch, padlockable in any one of the following three positions:

.1 Local Control Only

.2 Off (No Electrical Operation)

.3 Remote Control plus Local Stop Only.

.2 It shall be possible to select maintained or non-maintained local control.

.3 The local controls shall be arranged so that the direction of gate travel can be reversed without the necessity of stopping the actuator.

14 CONTROL FACILITIES:

.1 The necessary wiring and terminals shall be provided in the actuator for the following control functions:

Page 128: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15850 AND SEWAGE PUMP STATION MULTI TURN ELECTRIC ACTUATORS AND RELATED EQUIPMENT FOR SLIDE GATES PAGE 6

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.2 Removable links for substitution by external interlocks to inhibit valve opening and/or closing.

.3 Connections for external remote controls fed from an internal 24V DC supply and/or from an external supply of (min. 12V, max. 120V) to be suitable for any one or more of the following methods of control:

.1 Open, Close, and Stop

.2 Open and Close

.3 Overriding Emergency, Shutdown to Close (or Open) Valve from a "Make" Contact.

.4 Two-Wire Control, Energize to Close (or Open), De-Energize to Open (or Close)

.4 Selection of maintained or push-to-run control for modes (A) and (B) above shall be provided and it shall be possible to reverse valve travel without the necessity of stopping the actuator. The starter contactors shall be protected from excessive current surges during travel reversal by an automatic time delay on energization of approximately 300 ms.

.5 Provision shall be made for connectivity with field bus control systems via a plug-in card. The following interfaces shall be available:

.1 Pakscan

.2 Modbus

.3 Profibus

.4 Foundation Fieldbus

.6 The internal circuits associated with the remote control and monitoring functions are to be designed to withstand simulated lightning impulses of up to 2.0 kV.

.7 MONITORING & DIAGNOSTICS FACILITIES:

.8 Facilities shall be provided for monitoring actuator operation and availability as follows:

.9 Monitor (availability) relay, having one change-over contact, the relay being energized from the control transformer only when the Local/Off/Remote selector is in the "Remote" position to indicate that the actuator is available for remote (control room) operation.

.10 Where required, it shall be possible to provide indication of thermostat trip and "Remote" selected as discreet signals.

.11 A non-intrusive hand-held computer must be available, capable of duplex communication for uploading and downloading all variables for the actuator as well as performing detailed diagnostics.

.12 Actuators shall include a diagnostic module, which will store and enable download of historical actuator data to permit analysis of changes in actuator or gate performance. A software tool shall be provided to allow configuration and diagnostic information to be reviewed and analyzed and reconfigured. Additionally, diagnostic data shall be available over an IrDA™ port, which

Page 129: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15850 AND SEWAGE PUMP STATION MULTI TURN ELECTRIC ACTUATORS AND RELATED EQUIPMENT FOR SLIDE GATES PAGE 7

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

can be relayed to a remote facility by an IrDA™ compatible cellular telephone. After remote analysis, changes to the actuator configuration can be relayed back to the actuator via cellular telephone.

.13 Diagnostic status screens must be provided to show multiple functions simultaneously so troubleshooting can be affected rapidly and efficiently. All diagnostic information should be contained on no more than eight (8) screens so multiple functions can be checked simultaneously.

.14 Provision shall be made to display gate torque demand as a percent of rated actuator torque and position simultaneously, so as to facilitate valve troubleshooting and diagnostics.

14.2 WIRING AND TERMINALS:

.1 Internal wiring shall be of tropical grade PVC insulated stranded cable of appropriate size for the control and three- phase power. Each wire shall be clearly identified at each end.

.2 The terminals shall be embedded in a terminal block of high tracking resistance compound.

.3 The terminal compartment shall be separated from the inner electrical components of the actuator by means of a watertight seal.

.4 The terminal compartment of the actuator shall be provided with a minimum of three threaded cable entries. When required, a forth cable entry shall be provided.

.5 All wiring supplied as part of the actuator to be contained within the main enclosure for physical and environmental protection. External conduit connections between components is not acceptable.

.6 Control logic circuit boards and relay boards must be mounted on plastic mounts to comply with double insulated standards. No more than a single primary size fuse shall be provided to minimize the need to remove single covers for replacement.

.7 A durable terminal identification card showing plan of terminals shall be provided attached to the inside of the terminal box cover indicating:

.1 Serial Number

.2 External Voltage Values

.3 Wiring Diagram Number

.4 Terminal Layout

.8 This must be suitable for the contractor to inscribe cable core identification beside terminal numbers.

15 ENCLOSURE:

.1 Actuators shall be 'O' ring sealed, watertight to IP 68, and shall at the same time have an inner watertight and dustproof 'O' ring seal between the terminal compartment and the internal electrical elements of the actuator fully protecting the motor and all other internal electrical

Page 130: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15850 AND SEWAGE PUMP STATION MULTI TURN ELECTRIC ACTUATORS AND RELATED EQUIPMENT FOR SLIDE GATES PAGE 8

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

elements of the actuator from ingress of moisture and dust when the terminal cover is removed on site for cabling.

.2 Enclosure must allow for temporary site storage without the need for electrical supply connection.

.3 All external fasteners should be of stainless steel.

.4 Actuators for explosion/hazardous applications shall in addition be certified flameproof for Class 1 Zone 1 for use in wet wells as required by the Canadian electrical code.

16 STARTUP KIT:

.1 Each actuator shall be supplied with a startup kit comprising installation instruction, electrical wiring diagram, and sufficient spare cover screws and seals to make good any site losses during the commissioning period.

17 PERFORMANCE TEST CERTIFICATE:

.1 Each actuator must be performance tested and individual test certificates shall be supplied free-of-charge. The test equipment should simulate a typical valve load and the following parameters should be recorded:

.1 Current at maximum torque setting

.2 Torque at maximum torque setting

.3 Flash Test Voltage

.4 Actuator Output Speed or Operating Time. In addition, the test certificate should record details of specification, such as gear ratios for both manual and automatic drive, closing direction, and wiring diagram code number.

18 WARRANTY:

.1 Each actuator shall be warranted for a minimum of 12 months of operation up to a maximum of 18 months from shipment.

19 EXPERIENCE:

.1 All technologies and devices used in the actuator must have a minimum of four years’ of commercial operating experience for that specific manufacturer, including torque and position sensing, lubrication, and electrical compartment design.

20 STARTUP AND COMMISSIONING

.1 The manufacturer or qualified representative of the manufacturer shall provide on site field services for the testing and commissioning of the installed actuators and gate assemblies including checking wiring, installation, calibration of operating parameters, testing and commissioning to ensure the actuator/gate assembly operates as intended.

Page 131: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15850 AND SEWAGE PUMP STATION MULTI TURN ELECTRIC ACTUATORS AND RELATED EQUIPMENT FOR SLIDE GATES PAGE 9

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

21 TRAINING OF CITY PERSONNEL

.1 The manufacturer or qualified representative of the manufacturer shall provide training for City of Vancouver personnel in the use, operation, calibration and basic troubleshooting of the actuators. Training may be carried out on site or at a City designated location and shall include four hours onsite training and an additional 3 hours class room training if so required. Class room training may be converted to additional onsite training as determined by City of Vancouver personnel.

22 OPERATIONS AND MAINTENANCE MANUALS

.1 Fully detailed operations and maintenance manuals shall be provided by supplier including drawings, parts lists, wiring diagrams specific to the installation, specifications, troubleshooting recommendations, operating procedures and other information necessary for operating and maintaining the actuators.

23 ACCEPTABLE MANUFACTURERS AND ACTUATOR:

.1 Rotork Controls (Canada) Ltd.

.2 Rotork Actuator Model: IQ Pro for all gates

.3 Two wet well gate actuators to be fitted with positioner units (Folomatic)

END OF SECTION

Page 132: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15860 AND SEWAGE PUMP STATION QUARTER TURN ELECTRIC ACTUATORS FOR PLUG VALVES ON/OFF AND MODULATING PAGE 1

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1 GENERAL

1.1 Scope

.1 Description of Work

.1 Provide quarter turn electric actuators fitted to three (3) separate plug valves as specified herein and as shown on the contract documents.

.2 See Section 15850 for multi turn actuators for slide gates.

.3 See section 15452 for plug valves.

.4 Plug valves fitted with electric actuators are to be installed in a hazardous area and will be required to meet the requirements of the CEC (Canadian Electrical Code) for wet wells or dry wells as specified herein.

.5 The equipment provided under this section shall be fabricated, assembled, erected, and placed in proper operating condition in full conformity with the drawings, specifications, engineering data, instructions and recommendations of the equipment manufacturer unless exceptions are noted by the engineer.

.6 Quarter turn valves and operators shall be supplied with all the necessary parts and accessories indicated on the drawings, specified or otherwise required for a complete, properly operating installation, and shall be the latest standard product of a manufacturer regularly engaged in the production of quarter turn plug valves.

.2 Basic Requirements

.1 Actuators shall be suitable for use on a nominal 575 volt, three-phase, 60 Hertz power supply and are to incorporate motor, integral reversing starter, local control facilities, and terminals for remote control and indication connections.

.2 The actuator shall include a device to ensure that the motor runs with the correct rotation for the required direction of valve travel with either phase sequence of the three-phase power supply connected to the actuator.

.3 It shall be possible to carry out the setting of the torque, turns, and configuration of the indication contacts without the necessity to remove any electrical compartment covers.

.3 Special Requirements

.1 Two actuators shall be purpose designed for modulating duty and by means of an integral self contained controller which can accept a 4 – 20 ma signal and provide a 4 – 20 ma output signal indicating the valve position. Comparison of the signals shall cause the controller to provide an error signal which will drive the valve to the correct position. The input signal to the actuator shall be from a PLC or similar device.

Page 133: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15860 AND SEWAGE PUMP STATION QUARTER TURN ELECTRIC ACTUATORS FOR PLUG VALVES ON/OFF AND MODULATING PAGE 2

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

2 ACTUATOR SIZING:

.1 The actuator shall be sized to guarantee valve closure at the specified differential pressure of 25 meters (to be confirmed). The safety margin of motor power available for seating and unseating the valve shall be sufficient to ensure torque switch trip at maximum valve torque with the supply voltage 10% below nominal. The operating speed shall be such as to give valve closing and opening time of approximately 30 seconds unless otherwise stated in the job specification.

3 AMBIENT TEMPERATURE:

.1 The actuator shall be capable of functioning in an ambient temperature ranging from minus - 30 °C to +70 °C.

4 MOTOR:

.1 The electric motor shall be a 24 VDC permanent magnet, low inertia, Class F insulated, with thermostat protection. A transformer is provided to allow three phase, single phase or DC power supplies to be connected.

.2 Electrical and mechanical disconnection of the motor should be possible without draining the lubricant from the actuator gearcase. Plugs and sockets are not acceptable as a means of electrical connection for the motor.

5 MOTOR PROTECTION:

.1 Protection shall be provided for the motor as follows:

.1 The motor shall be de-energized in the event of stall when attempting to unseat a jammed valve.

.2 Motor temperature shall be sensed by a thermostat to protect against overheating.

.3 Single phasing protection.

6 GEARING:

.1 The actuator gearing shall be totally enclosed in an oil- filled gearcase suitable for operation at any angle. All main drive gearing must be of metal construction. The drive shall incorporate a lost-motion hammerblow feature. (For rising spindle valves, the output shaft shall be hollow to accept a rising stem and incorporate thrust bearings of the ball or roller type at the base of the actuator, and the design should be such as to permit the gearcase to be opened for inspection or disassembled without releasing the stem thrust or taking the valve out of service).

.2 Standard SAE80EP gear oil shall be used to lubricate the gearcase. Special or exotic lubricants shall not be used as they may be difficult to source in remote locations.

7 HAND OPERATION:

.1 A handwheel shall be provided for emergency operation engaged when the motor is declutched by a lever or similar means; the drive being restored to power automatically by starting the motor. The hand/auto selection lever should be padlockable in both "Hand" and "Auto"

Page 134: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15860 AND SEWAGE PUMP STATION QUARTER TURN ELECTRIC ACTUATORS FOR PLUG VALVES ON/OFF AND MODULATING PAGE 3

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

positions. It should be possible to select hand operation while the actuator is running or start the actuator motor while the hand/auto selection lever is locked in "Hand" without damage to the drive train.

.2 The handwheel drive must be mechanically independent of the motor drive, and any gearing should be such as to permit emergency manual operation in a reasonable time. Clockwise operation of the handwheel shall give closing movement of the valve unless otherwise stated in the job specification.

.3 Handwheel shall be operable with maximum 60 lbs rim pull.

8 DRIVE BUSHING:

.1 The actuator shall be furnished with a drive bushing easily detachable for machining to suit the valve stem or gearbox input shaft. Normally the drive bush shall be positioned in a detachable base of the actuator. Thrust bearings, when housed in a separate thrust base, should be of the sealed-for-life type.

9 TORQUE AND TURNS LIMITATIONS:

.1 Torque and turns limitation to be adjustable as follows:

.1 Torque setting: 40% to 100% rated torque.

.2 Torque sensing must be affected purely electrically or electronically. Extrapolating torque from mechanically measured motor speed is not acceptable due to response time. Torque measurement shall be independent of variations in frequency, voltage or temperature.

.3 “Latching" to be provided for the torque sensing system to inhibit torque off during unseating or during starting in mid-travel against high inertia loads.

.2 The electric circuit diagram of the actuator should not vary with valve type remaining identical regardless of whether the valve is to open or close on torque or position limit. An inexpensive setting tool is required for non-intrusive calibration and interrogation of the actuator. This setting tool will provide speedy interrogation capabilities as well as security in a non-intrusive intrinsically safe watertight casing.

10 ACTUATORS FOR MODULATING DUTY

.1 The plug valves for the Nelson transfer piping system shall be fitted with actuators specifically designed for modulation duty.

.2 Nelson Transfer modulating valves shall include a controller that will accept a 4-20mA analog signal and provide a 4-20mA output signal for flow control. The starter shall be suitable for 1200 starts per hour. The controller shall compare the input signal with the feedback signal to produce an error signal. The controller shall cause the motor to move the valve or gate in a direction so as to reduce the magnitude of the error signal. The controller positioning accuracy shall be plus or minus 1.0 percent of travel or better. Operating speeds, unless otherwise stated, shall be 90 degrees per minute for rotary operators. It shall be possible to adjust Dead Band (0-9.9% of travel) and a Motion Inhibit Timer (2-99 secs), and select action upon loss of signal.

Page 135: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15860 AND SEWAGE PUMP STATION QUARTER TURN ELECTRIC ACTUATORS FOR PLUG VALVES ON/OFF AND MODULATING PAGE 4

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

11 ACTUATORS FOR NON MODULATING DUTY (ON/OFF DUTY)

.1 The plug valves for the heat pump return piping in the wet well shall be fitted with non modulating actuators and shall be suitable for 60 starts/hour. Actuators for non modulating service shall be the same as modulating actuators except as noted in ITEM 10.

.2 Technologies and devices used in the actuator must have a minimum of five (5) years of commercial operating experience for that specific manufacturer. This to include position sensing, lubrication, and electrical compartment design.

12 REMOTE VALVE POSITION/ACTUATOR STATUS INDICATION:

.1 In the event of a (main) power (supply) loss or failure, the position contacts must continue to be able to supply remote position feedback and maintain interlock capabilities.

.2 A backup power source must be provided in the actuator to ensure correct remote indication should the actuator be moved manually when the power supply is interrupted.

.3 The position of the actuator and valve must be updated contemporaneously, even when the power supply is not present.

.4 Four contacts shall be provided which can be selected to indicate any position of the valve with each contact externally selectable as normally open or normally closed. The contacts shall be rated at 5A, 250V AC, 30V DC.

.5 As an alternative to providing valve position, any of the four above contacts shall be selectable to signal one of the following:

.1 Valve Opening or Closing

.2 Valve Moving (Continuous or Pulsing)

.3 Local Stop Selected

.4 Local Selected

.5 Remote Selected

.6 Open or Close Interlock Active

.7 ESD Active

.8 Motor Tripped on Torque in Mid-Travel

.9 Motor Tripped on Torque Going Open

.10 Motor Tripped on Torque Going Closed

.11 Pre-Set Torque Exceeded

.12 Valve Jammed

Page 136: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15860 AND SEWAGE PUMP STATION QUARTER TURN ELECTRIC ACTUATORS FOR PLUG VALVES ON/OFF AND MODULATING PAGE 5

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.13 Actuator Being Operated by Handwheel

.14 Lost Main Power Phase

.15 Customer 24V DC or 120V AC Supply Lost

.16 Battery Low

.17 Internal Failure Detected

.18 Thermostat Tripped

.6 Provision shall be made in the design for the addition of a contact less transmitter to give a 4-20mA analog signal corresponding to valve travel for remote indication when required.

13 LOCAL POSITION INDICATION:

.1 The actuator must provide a local display of the position of the valve, even when the power supply is not present. The display shall be able to be rotated in 90 degree increments so as to provide easy viewing regardless of mounting position.

.2 The actuator shall include a digital position indicator with a display from fully open to fully closed in 1% increments. Red, green, and yellow lights corresponding to Open, Closed, and Intermediate positions shall be included on the actuator. The digital display shall be maintained even when the power to the actuator is isolated.

.3 The local display should be large enough to be viewed from a distance of six feet (6’) when the actuator is powered up.

14 INTEGRAL STARTER AND TRANSFORMER:

.1 The reversing starter, control transformer, and local controls shall be integral with the valve actuator, suitably housed to prevent breathing and condensation buildup. For ON/OFF service, this starter shall be an electromechanical type suitable for 60 starts per hour and of rating appropriate to motor size. For modulating duty, the starter shall be suitable for up to a maximum of 1,200 starts per hour (as noted in items 10 and 11). The controls supply transformer shall be fed from two of the incoming three phases. It shall have the necessary tapings and be adequately rated to provide power for the following functions:

.1 120V AC energization of the contactor coils

.2 24V DC output where required for remote controls

.3 Supply for all the internal electrical circuits

.2 The primary and secondary windings shall be protected by easily replaceable fuses.

15 INTEGRAL PUSH BUTTONS AND SELECTOR:

.1 Integral to the actuator shall be local controls for Open, Close, and Stop, and a local/remote selector switch, padlockable in any one of the following three positions:

Page 137: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15860 AND SEWAGE PUMP STATION QUARTER TURN ELECTRIC ACTUATORS FOR PLUG VALVES ON/OFF AND MODULATING PAGE 6

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.1 Local Control Only

.2 Off (No Electrical Operation)

.3 Remote Control plus Local Stop Only.

.2 It shall be possible to select maintained or non-maintained local control.

.3 The local controls shall be arranged so that the direction of valve travel can be reversed without the necessity of stopping the actuator.

16 CONTROL FACILITIES:

.1 The necessary wiring and terminals shall be provided in the actuator for the following control functions:

.2 Removable links for substitution by external interlocks to inhibit valve opening and/or closing.

.3 Connections for external remote controls fed from an internal 24V DC supply and/or from an external supply of (min. 12V, max. 120V) to be suitable for any one or more of the following methods of control:

.1 Open, Close, and Stop

.2 Open and Close

.3 Overriding Emergency, Shutdown to Close (or Open) Valve from a "Make" Contact.

.4 Two-Wire Control, Energize to Close (or Open), De-Energize to Open (or Close)

.4 Selection of maintained or push-to-run control for modes (A) and (B) above shall be provided and it shall be possible to reverse valve travel without the necessity of stopping the actuator. The starter contactors shall be protected from excessive current surges during travel reversal by an automatic time delay on energization of approximately 300 ms.

.5 Provision shall be made for connectivity with field bus control systems via a plug-in card. The following interfaces shall be available:

.1 Pakscan

.2 Modbus

.3 Profibus

.4 Foundation Fieldbus

.6 The internal circuits associated with the remote control and monitoring functions are to be designed to withstand simulated lightning impulses of up to 2.0 kV.

17 MONITORING & DIAGNOSTICS FACILITIES:

.1 Facilities shall be provided for monitoring actuator operation and availability as follows:

Page 138: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15860 AND SEWAGE PUMP STATION QUARTER TURN ELECTRIC ACTUATORS FOR PLUG VALVES ON/OFF AND MODULATING PAGE 7

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.2 Monitor (availability) relay, having one change-over contact, the relay being energized from the control transformer only when the Local/Off/Remote selector is in the "Remote" position to indicate that the actuator is available for remote (control room) operation.

.3 Where required, it shall be possible to provide indication of thermostat trip and "Remote" selected as discreet signals.

.4 A non-intrusive hand-held computer must be available, capable of duplex communication for uploading and downloading all variables for the actuator as well as performing detailed diagnostics.

.5 Actuators shall include a diagnostic module, which will store and enable download of historical actuator data to permit analysis of changes in actuator or valve performance. A software tool shall be provided to allow configuration and diagnostic information to be reviewed and analyzed and reconfigured. Additionally, diagnostic data shall be available over an IrDA™ port, which can be relayed to a remote facility by an IrDA™ compatible cellular telephone. After remote analysis, changes to the actuator configuration can be relayed back to the actuator via cellular telephone.

.6 Diagnostic status screens must be provided to show multiple functions simultaneously so troubleshooting can be affected rapidly and efficiently. All diagnostic information should be contained on no more than eight (8) screens so multiple functions can be checked simultaneously.

.7 Provision shall be made to display valve torque demand as a percent of rated actuator torque and position simultaneously, so as to facilitate valve troubleshooting and diagnostics.

18 WIRING AND TERMINALS:

.1 Internal wiring shall be of tropical grade PVC insulated stranded cable of appropriate size for the control and three- phase power. Each wire shall be clearly identified at each end.

.2 The terminals shall be embedded in a terminal block of high tracking resistance compound.

.3 The terminal compartment shall be separated from the inner electrical components of the actuator by means of a watertight seal.

.4 The terminal compartment of the actuator shall be provided with a minimum of three threaded cable entries. When required, a forth cable entry shall be provided.

.5 All wiring supplied as part of the actuator to be contained within the main enclosure for physical and environmental protection. External conduit connections between components is not acceptable.

.6 Control logic circuit boards and relay boards must be mounted on plastic mounts to comply with double insulated standards. No more than a single primary size fuse shall be provided to minimize the need to remove single covers for replacement.

.7 A durable terminal identification card showing plan of terminals shall be provided attached to the inside of the terminal box cover indicating:

.1 Serial Number

Page 139: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15860 AND SEWAGE PUMP STATION QUARTER TURN ELECTRIC ACTUATORS FOR PLUG VALVES ON/OFF AND MODULATING PAGE 8

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.2 External Voltage Values

.3 Wiring Diagram Number

.4 Terminal Layout

.8 This must be suitable for the contractor to inscribe cable core identification beside terminal numbers.

19 ENCLOSURE:

.1 Actuators shall be 'O' ring sealed, watertight to IP 68, and shall at the same time have an inner watertight and dustproof 'O' ring seal between the terminal compartment and the internal electrical elements of the actuator fully protecting the motor and all other internal electrical elements of the actuator from ingress of moisture and dust when the terminal cover is removed on site for cabling.

.2 Enclosure must allow for temporary site storage without the need for electrical supply connection.

.3 All external fasteners should be of stainless steel.

.4 Actuators for explosion/hazardous applications shall in addition be certified flameproof for Class 1 Zone 1, Actuators shall be adequate for Class 1 Zone 1 use in a wet well as required by the Canadian electrical code.

20 STARTUP KIT:

.1 Each actuator shall be supplied with a startup kit comprising installation instruction, electrical wiring diagram, and sufficient spare cover screws and seals to make good any site losses during the commissioning period.

21 PERFORMANCE TEST CERTIFICATE:

.1 Each actuator must be performance tested and individual test certificates shall be supplied free-of-charge. The test equipment should simulate a typical valve load and the following parameters should be recorded:

.1 Current at maximum torque setting

.2 Torque at maximum torque setting

.3 Flash Test Voltage

.4 Actuator Output Speed or Operating Time. In addition, the test certificate should record details of specification, such as gear ratios for both manual and automatic drive, closing direction, and wiring diagram code number.

22 WARRANTY:

.1 Each actuator shall be warranted for a minimum of 12 months of operation up to a maximum of 18 months from shipment.

Page 140: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15860 AND SEWAGE PUMP STATION QUARTER TURN ELECTRIC ACTUATORS FOR PLUG VALVES ON/OFF AND MODULATING PAGE 9

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

23 EXPERIENCE:

.1 All technologies and devices used in the actuator must have a minimum of four years’ of commercial operating experience for that specific manufacturer, including torque and position sensing, lubrication, and electrical compartment design.

24 TRAINING OF CITY PERSONNEL

.1 The manufacturer or qualified representative of the manufacturer shall provide training for City of Vancouver personnel in the use, operation, calibration and basic troubleshooting of the actuators. Training may be carried out on site or at a City designated location and shall include four hours onsite training and an additional 3 hours class room training if so required. Class room training may be converted to additional onsite training as determined by City of Vancouver personnel.

25 OPERATIONS AND MAINTENANCE MANUALS

.1 Fully detailed operations and maintenance manuals shall be provided by supplier including drawings, parts lists, wiring diagrams specific to the installation, specifications, troubleshooting recommendations, operating procedures and other information necessary for operating and maintaining the actuators.

26 ACCEPTABLE MANUFACTURERS

.1 Rotork Controls, Inc.

.2 Rotork Controls (Canada) Ltd.

.3 Acceptable quarter turn valves:

.4 IQT for open/close duty. - Heat Pump Return (on/off) Valve

.5 IQTM for modulating duty. - Nelson Transfer Modulating Valves

END OF SECTION

Page 141: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Work Included

.1 Complete system of electric, electronic, and DDC automatic controls for the air-handling units, supply and exhaust fans, and unit heaters.

.2 Computer software.

.3 Remote panels, sensors, control devices, and control circuit transformers.

.4 Wiring, piping, raceways pneumatic tubing, and conduit.

.5 Instrumentation.

.6 Calibrations, adjustments and checkouts.

.7 Instructions for Owners.

1.2 Quality Assurance

.1 Guarantee the complete automatic control systems for a period of one (1) year from the date of final acceptance by the Consultant.

.2 Provide for complete service of controls including call backs for one year from date of final acceptance by Consultant. In addition to required service calls, submit written report to Consultant after each inspection.

1.3 Submittals

.1 Provide shop drawings complete with system schematics, mixing diagrams, operating data and detailed description of operational sequences of controls.

.2 At completion of installation including calibration of controls and start up, make detailed check of all control systems and submit written report to the Consultant.

1.4 Control System Contractor

.1 Complete set of automatic controls for the mechanical systems shall be supplied and installed by a firm specializing in this type of work. Acceptable control system contractors and system type are:

.1 Trane British Columbia

.2 Olympic Controls

.3 Control Solutions Ltd.

.4 Johnson Controls Ltd.

.5 Honeywell Limited

Page 142: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.6 Energrated Systems Ltd.

.7 Modern Systems Management Ltd.

.2 Any other Control System Contractor wishing to bid on this work shall submit a request in writing a minimum of fourteen days prior to bid closing. If approved for bidding, an addendum will be issued adding the Contractor to the above list.

1.5 Sensors and Associated Equipment

.1 The DDC Control System shall be supplied with all sensors, relays and associated equipment to fully connect the required points. Field point installation shall be performed in a neat and orderly fashion with all components marked or labeled to correspond with the marking or labeling in the Project Record drawings. Use baggage style plastic pockets and cards for mounting labels.

1.6 Graphics

.1 Provide graphical symbolic illustrations of the connected systems and spaces, along with the required point identification. The graphics shall be developed using the system manufacturer’s Windows based Graphics software package.

.2 The graphic screens shall have visible icons and “live” objects which are used to facilitate point and click movement between different system graphics, as well as to and from real-time displays of associated time schedules, trend logs, PID controllers, programmed sequences of operation, etc. Pop-up windows are activated when real-time objects are clicked, providing the option to manually override the associated equipment, or to display, edit, print, or graph additional data associated with it. The setpoints shall be adjustable by changing the setpoint indication on the graphic (with proper password level authority).

.3 The following graphics screens shall be provided:

.1 Floor plan of building showing equipment and room temperature sensor locations. The actual and setpoint temperatures shall be shown on the plan.

.2 Schematics of each air handling system and supply and exhaust fan system with sensor setpoint and actual reading, damper position, and fan status shown.

2 PRODUCTS

2.1 Damper Operators

.1 Provide damper operators to suit the air handling unit control dampers, operators to be adequately sized to provide smooth and full travel in both directions.

.2 Generally operators to be maintenance free 24-volt direct coupled actuators with 95 degree rotation, maximum noise level of 45 dBA, position indicator, non-overloading, and shall be UL listed. Direction of rotation shall be reversible without wiring change.

.3 Separate damper operators to be provided where individual dampers are installed. On multi-section dampers, install separate damper operators for each section except where a jack shaft drive arrangement is indicated.

Page 143: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.4 Provide damper linkages where direct coupling of motor to damper shaft is not possible.

.5 Mount damper operators on mounting brackets adequately stiffened.

.6 Actuators for modulating dampers with edge seals shall be as follows, or other approved:

Damper Area Actuator Torque

.1 Up to 5 sq. ft. Belimo LM24-SR 35 in-lb.

.2 5 sq. ft. to 20 sq. ft. Belimo SM24 -SR 133 in-lb.

.3 21 sq. ft. to 40 sq. ft. Belimo GM24-SR 266 in-lb.

Actuators for on-off control of dampers under 2 ft2 to be Belimo KM24 or other approved.

.4 Honeywell Models ML7275 for 25 in-lb, ML7285 for 50 in-lbs, and ML9295 for 142 in-lbs are approved equals.

2.2 Room Temperature Sensors

.1 Provide all room temperature sensors as shown on the drawings and as specified.

.2 All sensors to be capable of responding to a temperature change of 0.1°C. Sensors to have adjustable sensitivity and set point.

.3 Thermostats are to be key adjustable, wall-mounted type and are to have window with set point in degrees C visible. Do not provide temperature-indicating thermometer.

.4 Co-ordinate location of instruments with light switches and to Consultant's approval, mounting height 1500 mm above finished floor level unless otherwise stated. Mount electrical instruments on standard electrical rough-in boxes.

2.3 Conduit, Wiring and Cabling

.1 All work shall be installed to the Canadian Electrical Code and local building codes.

.2 Where there is not an alternative to supplying equipment, which is not CSA certified, submit such equipment to the Inspection Authorities for special inspection and obtain approval before delivery of equipment to site. Such equipment must be individually identified in the bid.

.3 The Contractor is responsible for all control wiring and connections (120 Volt and less) including those between line voltage temperature controls, safety, limiting and other devices directly related to starters, holding coils, auxiliary contactors, interlocks, relays, etc., as required for the performance of control system and sequence of operation as specified.

.4 All wiring is to be run in conduit. Do not use exposed conduit or wiring in public areas of the building. Any conduit installed exposed in service areas shall be painted to match the surroundings.

.5 Use coded conductors throughout with different coloured conductors for each phase and white wire for neutral. For DC systems and circuits, use red (positive) and black (negative).

Page 144: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.6 Identify each wire and cable at every termination point. The Contractor shall be responsible for replacing any marker that may have fallen off before the warranty period is over.

.7 Size of conduit and size/type of wire shall be the design responsibility of this Contractor, except as noted.

.8 110V circuits shall be, at a minimum of #12 AWG RW-90 copper. For runs over 35 metres in length, use #10 AWG RW-90 copper.

2.4 Control Hardware

.1 Provide enameled steel enclosures for mounting motor control relays and components, which require additional protection. Enclosures are to meet NEMA specifications where required by the Canadian Electrical Code.

.2 All components shall be positioned to provide easy access for maintenance or replacement.

2.5 Control Microprocessors

.1 The installation of microprocessors to control the new dual duct mixing boxes is not included and will be done during the next phase.

.2 Provide conduit between the dual duct box microprocessor location and the dual duct box and between the microprocessor and the DDC system connection point.

2.6 Control Valves

.1 Provide for installation by the Mechanical Contractor the control valves required for the systems, as shown on the drawings.

.2 All control valves to have ANSI Class 150 bronze bodies up to NPS 2", ANSI Class 125 flanged cast iron bodies for NPS 2-1/2" and larger.

.3 Ensure that valves have a tight shut off against the full differential pressure imposed by the system.

.4 Actuator to be self-contained, self-adjusting linear actuators with linkages that mount directly on the control valve and valve position indicator, 0-10 volt input. Provide smooth operation through entire range of control valves. Valves to be Honeywell V5011 or V5013 with ML784/ML984 actuators, Powers VE698, Belimo models B209 – B250, or approved equal.

.5 Unless specified otherwise, control valves for proportional operation to have characterized seats or characterizing disks, and sized according to the required flow rates and a 3-psi pressure drop.

.6 Control Valve Schedule:

Valve No. Equipment Size (mm) Cv L/s Valve Type Control

CV-1 HC-102 32 16 1.98 3 way Modulating

CV-2 CC-103 40 25 2.61 3 way Modulating

Page 145: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

CV-3 HC-105 50 40 4.54 3 way Modulating

CV-4 CC-104 75 100 8.15 3 way Modulating

CV-5 CC-106 12 4 0.30 3 way Modulating

CV-6 HC-106 12 2.5 0.08 3 way Modulating

CV-7 HWT PLG-2 50 40 4.92 2 way Modulating

CV-8 HVAC UH-1 12 4 40.13 2 way On-off

3 EXECUTION

3.1 General

.1 The installation shall conform both to manufacturer's recommended procedures and to all applicable codes and regulations and to the approval of the authorities having jurisdiction.

.2 Provide all control components, wiring, devices, and labour to accomplish the control sequences as described herein.

3.2 Calibration

.1 Set up and calibrate controls during initial start-up of the systems and check, recalibrate and readjust as necessary during the Commissioning Period.

3.3 Installation of Sensors/Switches

.1 Sensors provided under this contract shall be installed in accordance with the manufacturer's prescribed procedure.

3.4 Heat Pump Area Air Handling System HVAC-103, Exhaust Fan HVAC EF-3

.1 Provide a control valve complete with modulating operator for the chilled water coil and connect the valve to the DDC system analog output.

.2 Provide modulating actuators for the outdoor air, return air dampers, and connect actuators to the DDC system analog output.

.3 Provide a supply duct temperature sensor and connect the sensor to the DDC system analog input.

.4 Provide two room temperature sensors and connect the sensors to the DDC system analog inputs.

.5 Connect the DDC panel outputs to the HVAC-103 supply fan and the HVAC EF-3 motor magnetic starters.

.6 Provide pressure sensors in the supply duct and the exhaust duct to provide proofing of the supply fan and exhaust fan operation.

.7 Provide an outdoor air sensor and connect to the DDC system analog input.

Page 146: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 6

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.8 Provide DDC system programming to perform the following sequence of operation:

.1 The supply fan and exhaust fan is started and stopped by the DDC system program control.

.2 Open the outdoor air damper, relief air damper, and return air dampers to minimum positions upon system activation. Modulate the flow of outdoor air between 33% and 100% and position the cooling coil valve in sequence so as to maintain the supply air temperature just cool enough to satisfy the setpoint of the room temperature sensors using the average of the two room temperature sensors.

.9 Provide an alarm signal input to the system if any of air filter Magnehelic gauge is out of range. The Magnehelic gauges with high limit switches are specified in Section 15851.

.10 Upon signal from the refrigerant sensor system specified in Section 15910, fully open the outdoor air damper and close the return air damper to provide full exhaust air ventilation to the area.

.11 Provide an alarm signal if the room temperature rises above 30°C.

3.5 Electrical Room – Air Handling System HVAC-104

.1 Provide a control valve complete with modulating operator for the chilled water coil and connect the valve to the DDC system analog output.

.2 Provide modulating actuators for the outdoor air, return air, and relief air dampers and connect actuators to the DDC system analog output.

.3 Provide a supply duct temperature sensor and connect the sensor to the DDC system analog input.

.4 Provide four room temperature sensors and connect the sensors to the DDC system analog inputs.

.5 Connect the DDC panel outputs to the HVAC-104 supply motor magnetic starters.

.6 Provide pressure sensors in the supply duct to provide proofing of the supply fan operation.

.7 Provide DDC system programming to perform the following sequence of operation:

.1 The supply fan is started and stopped by the DDC system program control.

.2 Open the outdoor air damper, relief air damper, and return air dampers to minimum positions upon system activation. Modulate the flow of outdoor air between 5% and 100% and position the cooling coil valve in sequence so as to maintain the supply air temperature just cool enough to satisfy the setpoint of the room temperature sensors using the average of the four room temperature sensors.

.8 Provide an alarm signal input to the system if any of air filter Magnehelic gauge is out of range. The Magnehelic gauges with high limit switches are specified in Section 15720.

.9 Provide an alarm signal if the room temperature rises above 30°C.

Page 147: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 7

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

3.6 Boiler Area Air Handling System HVAC-105, Pump HVAC P-2

.1 Provide a control valve complete with modulating operator for the heating water coil and connect the valve to the DDC system analog output.

.2 Provide a 6 m capillary tube freeze-stat and connect the valve to the DDC system analog input.

.3 Provide a supply duct temperature sensor and connect the sensor to the DDC system analog input. Deactivate the fan, open the heating valve fully, and signal an alarm upon activation.

.4 Provide four room temperature sensors and connect the sensors to the DDC system analog

.5 Connect the DDC panel outputs to the HVAC-105 supply fan motor magnetic starters.

.6 Connect the DDC panel outputs to the pump HVAC-P-2 motor magnetic starters.

.7 Provide pressure sensors in the supply duct to provide proofing of the supply fan operation.

.8 Provide two-position actuators for the relief air dampers and connect actuators to the DDC system analog output.

.9 Provide DDC system programming to perform the following sequence of operation:

.1 The supply fan is started and stopped by the DDC system program control.

.2 Open the relief dampers upon activation of the system.

.3 The system operates at 100% outdoor air. On call for heating, activate pump P-2 and position the heating coil valve so as to maintain the supply air temperature just warm enough to satisfy the setpoint of the room temperature sensors using the average of the four room temperature sensors.

.10 Provide an alarm signal input to the system if any of air filter Magnehelic gauge is out of range. The Magnehelic gauges with high limit switches are specified in Section 15851.

.11 Provide an alarm signal if the room temperature rises above 30°C.

3.7 Dry Well Area Air Handling System HVAC-102, Pump HVAC P-3

.1 Provide a control valve complete with modulating operator for the heating water coil and connect the valve to the DDC system analog output.

.2 Provide a 6 m capillary tube freeze-stat and connect the valve to the DDC system analog input. Deactivate the fan, open the heating valve fully, and signal an alarm upon activation.

.3 Provide a supply duct temperature sensor and connect the sensor to the DDC system analog input.

.4 Provide two room temperature sensors and connect the sensors to the DDC system analog inputs.

.5 Connect the DDC panel outputs to the HVAC-102 supply fan motor magnetic starters.

Page 148: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 8

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.6 Connect the DDC panel outputs to the pump HVAC-P-3 motor magnetic starters.

.7 Provide pressure sensors in the supply duct to provide proofing of the supply fan operation.

.8 Provide an outdoor air sensor and connect to the DDC system analog input.

.9 Provide DDC system programming to perform the following sequence of operation:

.1 The supply fan is started and stopped by the DDC system program control.

.2 The system operates at 100% outdoor air. On call for heating, activate pump P-3 and position the heating coil valve so as to maintain the supply air temperature just warm enough to satisfy the setpoint of the room temperature sensors using the average of the four room temperature sensors.

.10 Provide an alarm signal input to the system if any of air filter Magnehelic gauge is out of range. The Magnehelic gauges with high limit switches are specified in Section 15851.

.11 Provide an alarm signal if the room temperature rises above 30°C.

3.8 Office Air Handling System HVAC-106, Pump HVAC P-4

.1 Provide a control valve complete with modulating operator for the chilled water coil and connect the valve to the DDC system analog output.

.2 Provide a control valve complete with modulating operator for the heating water coil and connect the valve to the DDC system analog output.

.3 Provide modulating actuators for the outdoor air, return air dampers, and connect actuators to the DDC system analog output.

.4 Provide a 6 m capillary tube freeze-stat and connect the valve to the DDC system analog input.

.5 Provide a supply duct temperature sensor and connect the sensor to the DDC system analog input.

.6 Provide a room temperature sensor and connect the sensors to the DDC system analog inputs.

.7 Connect the DDC panel outputs to the HVAC-106 supply motor magnetic starters.

.8 Connect the DDC panel outputs to the pump HVAC-P-4 motor magnetic starters.

.9 Provide pressure sensors in the supply duct to provide proofing of the supply fan operation.

.10 Provide DDC system programming to perform the following sequence of operation:

.1 The supply fan is started and stopped by the DDC system program control.

.2 Open the outdoor air damper and return air dampers to minimum positions upon system activation. Modulate the flow of outdoor air between 20% and 100% and position the cooling coil valve, or activate pump P-4 and position the heating coil valve in sequence so as to maintain the supply air temperature just cool or warm enough to satisfy the setpoint of the room temperature sensor.

Page 149: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 9

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.11 Provide an alarm signal input to the system if any of air filter Magnehelic gauge is out of range. The Magnehelic gauges with high limit switches are specified in Section 15720.

.12 Provide an alarm signal if the room temperature rises above 30°C.

3.9 Wet Well Supply – Fan HVAC -101, Exhaust Fan HVAC-EF-1 Control

.1 Connect the DDC panel outputs to the supply fan HVAC-101 and the exhaust fan HVAC-EF-1 motor magnetic starters.

.2 Provide a two-position actuator for the EF-1exhaust air damper and connect actuator to the DDC system output.

.3 Provide a manual hand-off-auto switch just inside the north entrance door to the Wet Well to control the two fans.

.4 Open the exhaust damper upon activation of the exhaust fan.

.5 Provide a DDC system start-stop for the supply fan and for the exhaust fan.

3.10 Odour Control Room Supply – Fan HVAC -107, Exhaust Fan HVAC-EF-7 Control

.1 Connect the DDC panel outputs to the supply fan HVAC-107 and the exhaust fan HVAC-EF-7 motor magnetic starters.

.2 Provide a manual hand-off-auto switch just outside the north entrance door to the Odour Control room from the Dry Well.

.3 Provide a two-position actuator for the EF-7 exhaust air damper and connect actuator to the DDC system output.

.4 Open the exhaust damper upon activation of the exhaust fan.

.5 Provide a DDC system start-stop for the supply fan and for the exhaust fan.

3.11 Generator Room Exhaust – Fan HVAC-EF-4 Control

.1 Connect the DDC panel output to the exhaust fan HVAC-EF-4 motor magnetic starter.

.2 Provide motorized damper actuators for the air intake damper and the bypass damper.

.3 Provide a room temperature sensor and connect to the DDC system analog input.

.4 Provide a DDC system start-stop for the exhaust fan.

.5 Upon activation of the generator, open the outdoor air damper and activate the exhaust fan.

.6 Open the bypass damper to maintain the room air temperature above 10°C.

3.12 Boiler Room Exhaust – Fan HVAC-EF-8 Control

.1 Connect the DDC panel output to the exhaust fan HVAC-EF-4 motor magnetic starter.

Page 150: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15900 AND SEWAGE PUMP STATION CONTROLS PAGE 10

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 Provide a hand-off-auto switch for the fan located on the wall below the fan.

.3 Provide a DDC system start-stop for the exhaust fan.

.4 Activate the exhaust fan upon a signal from the gas detector specified in Division 16.

3.13 Unit Heaters HVAC UH-1

.1 Provide electric control valve to start the flow of water through the unit heater on call for heat.

.2 Provide an aquastat to prove the flow of hot water before allowing the fan to start.

.3 Provide a wall mounted electric thermostat with fan switch to control the operation of the unit heater and the control valve.

3.14 Alarm Signal Reporting

.1 Send an alarm message if any mechanical equipment alarms are activated. This includes:

.1 Heat pump room temperature high.

.2 Electrical Room temperature high.

.3 Room pressure differential out of range.

.4 Air filter fault

.5 Refrigerant or gas alarm activation

.6 Air supply low temperature.

.7 Air supply high temperature.

.8 Room air temperature out of range.

.9 Coil low temperature protection (freezestat) activation.

END OF SECTION

Page 151: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15910 AND SEWAGE PUMP STATION REFRIGERANT ALARM SYSTEM PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Work Included

.1 Provide all labor, materials, products, equipment and service to supply and install a refrigerant, toxic and combustible gas detection and control system for the heat pump units and chiller as indicated on the drawing and specified in this section.

.2 Commission the refrigerant alarm system.

1.2 Reference Standards

.1 Unit shall be certified to ULC and CSA requirements.

2 PRODUCTS

2.1 Equipment

.1 Provide a complete Honeywell Analytics refrigerant gas detection and alarm system including a control panel, power transformers, relay modules, remote alarm panel, refrigerant gas detectors, and strobes and horns.

2.2 Transmitters

.1 Provide four Honeywell Analytics model VA-201T-Q1-R134A Infrared R134A transmitters. Mount the units where shown on the drawings.

3 EXECUTION

3.1 General

.1 The installation shall conform both to manufacturer's recommended procedures and to all applicable codes and regulations and to the approval of the authorities having jurisdiction.

.2 Provide all control components, wiring, devices, labour, and programming to accomplish the control sequences as described herein.

.3 Provide an audible and visual alarm within the Mechanical Room and outside the entrance doors at the level 1.5 m adjacent the boiler and the entrance door from the fan room. Provide a keyed silencing switch outside the two entrance doors that would silence the audible alarm but allow the visual alarm to continue to operate.

.4 Provide switches outside the Level 1.5 m entrance door adjacent the boiler and the entrance door from the fan room to manually activate exhaust fan HVAC EF-3, air handling unit HVAC 103, and close the recirculation damper of HVAC 103 upon an emergency incident.

.5 Activate exhaust fan HVAC EF-3, air handling unit HVAC 103, and close the recirculation damper of HVAC 103 when concentration reaches TLV-TWA/Alarm Level A

.6 Activate audible and visual alarms (located on the controller and the external strobe horn) when concentration reaches TLV-STEL/Alarm Level B.

Page 152: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15910 AND SEWAGE PUMP STATION REFRIGERANT ALARM SYSTEM PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.7 Provide remote readouts of the refrigerant alarms at both access doors.

3.2 Equipment Installation

.1 The installation of the components and wiring shall be by the equipment supplier.

.2 Install and connect equipment in accordance with the manufacturer's instructions.

3.3 Commissioning

.1 Fully commission the modified refrigerant gas detection system.

END OF SECTION

Page 153: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 1

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

1 GENERAL

1.1 Description

.1 The work of this section includes the supply, installation, testing and commissioning of wastewater screening equipment and related equipment to be installed in one inlet channel in the pump station wet well.

.2 Screens supplied under this section shall be Waste-Tech, Inc. FSM influent self-cleaning filter screen Model FRS 1300 or equal.

1.2 Scope

.1 Description of Work

.1 Provide all labor, material and equipment necessary to furnish and install One (1) mechanically self-cleaned filter screen, designed to treat 400 l/s (9.13 mgd) maximum flow rate at a water depth of 4.50 ft in a 5.00 ft wide x 11.04 ft deep channel as specified herein.

.2 This specification covers the general requirements for the design, fabrication, and testing of a mechanically cleaned filter screen system including a screenings discharge flume and its appurtenances.

.2 Work and Components Included

.1 The screen shall be inclined approximately 75 degrees from the horizontal and shall be held firmly in the channel by a support frame attached to the top of the channel. The design shall be of the type with identical one piece perforated curved filter elements mounted horizontally on parallel screen drive links to form an endless moving belt which collects, conveys, and discharges all solids greater than the selected screen opening size. As each filter element transverses the periphery of the drive sprocket, the curved portion of the element moves beneath the revolving cleaner brush, which ejects all debris off the screen face and efficiently cleans the element. The clean element descends on the downstream side of the screen to the bottom of the channel before ascending on the upstream side of the screen to the screenings drop off into the screenings flume which discharges the screenings into the adjacent channel.

.2 The contractor shall furnish and install the items listed below ready to run:

.1 Filter screen and perforated filter screen elements with positive lifting devices designed to remove spherical solids from the bottom of the channel floor. Screen panels with ledges on the top which do not lift solids from the bottom of the channel will not be approved.

.2 Frame and covers

.3 Screen drive shafts and sprockets with geared drive unit

.4 Cleaner brush and drive shaft with geared drive unit

Page 154: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 2

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.5 Screenings discharge flume

.6 Anchor bolts

.7 Electrical controls

.8 Spare parts

.3 Related Work Specified Elsewhere

.1 Division 15 and Division 16.

.2 Requirements for the following items are specified under Division 16, Electrical of the specifications.

.1 Motors, motor starters, breakers, switch gear, wiring, conduit, alarm light and howler.

1.3 Qualifications

.1 Manufacturer

.1 It is the intention of the specifications to cover minimum acceptable quality equipment for a complete installation.

.2 Part numbers or trade names are used in this specification only to facilitate the description of the equipment and in no way implies that equal equipment of other manufacturers cannot be used.

.2 Manufacturer’s Experience

.1 The Equipment Manufacturer shall have not less than five (5) successful years experience in the design, construction, and operation of equipment of the design specified at hundred (100) plants in the USA.

.2 The Engineer will require evidence in the form of operating records from these plants to substantiate any claims concerning the ability of the equipment to perform as required.

1.4 Submittals

.1 Operating instructions, manuals and shop drawings shall be submitted in accordance with Division 1.

.2 Submittals shall include the following:

.1 Sufficient product data including shop drawings to verify compliance with the specifications and to illustrate the construction or assembly of the products.

.2 Manufacturer, model and type.

.3 Shop drawings with key installation and overall dimensions and total weights of the product.

Page 155: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 3

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.4 Detailed specifications and data describing the materials used.

.5 Electrical wiring diagram.

1.5 Equipment Manufacturer’s Service Representative

.1 General

.1 The manufacturer shall be able to provide local service and spare parts for the screen.

.2 Installation assistance

.1 Provide on site installation assistance for the equipment supplied in the form of a qualified operating and service engineer employed by the manufacturer.

.3 Equipment Startup and Operator Training.

.1 Provide startup for the equipment supplied.

.4 Operating Instructions and/or Operator Training

.1 The filter screen manufacturer shall provide a qualified service engineer to inspect the completed installations for lubrication, alignment, free operation and proper control, and to instruct operations personnel in the proper operation and maintenance of the units. At least two (2) days of field service shall be provided. At least one (1) day shall be devoted exclusively to training, which shall include both classroom and field training.

.2 A day trip is defined as eight (8) on-site working hours.

.3 The location of the installation is Vancouver, British Columbia, Canada.

1.6 Guarantees

.1 The filter screens shall be unconditionally guaranteed to meet or exceed design criteria detailed in Part 2 of this specification.

2 PRODUCTS

2.1 Design Criteria

.1 General

.1 The filter screen system shall be a Waste-Tech, Inc. FSM influent self-cleaning filter screen Model FRS 1300 or equal.

.2 Materials

.1 All moving wetted parts, all wetted parts on which moving parts ride, all filter belt components under guiding, bearing, or driving loads shall be 304 stainless steel, wear resistant heat treated, high tensile, wear resistant steel, or DELRIN polyacetal as noted below:

Page 156: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 4

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.1 The frame shall be minimum 3/16" thick 304 stainless steel.

.2 The discharge chute, and all nuts and bolts shall be 304 stainless steel.

.3 The drive shafts and sprockets shall be 304 stainless steel specially hardened for the intended purpose.

.4 The screening elements shall be one piece curved 304 stainless steel and will not require upstream protection using coarse bar screens.

.5 The special designed heavy duty drive links will be 304 stainless steel specially hardened for the intended duty.

.6 The side and bottom seals shall be replaceable contoured DELRIN polyacetal with 304 stainless steel fasteners.

.7 The screening element support rails shall be DELRIN polyacetal or equivalent. Wood support rails will not be accepted.

.8 All other appurtenances shall be of manufacturer’s standard coated material.

.2 All fasteners shall be 304 stainless steel.

.3 Description

.1 Normal daily flow: 3.00 mgd

.2 Peak flow: 9.13 mgd

.3 Channel width: 5.00 ft

.4 Channel depth: 11.04 ft

.5 Channel bottom to operating floor: 11.04 ft

.6 Screenings discharge height above operating floor level: 4.5 ft

.7 Maximum water level: 8 ft (tbc)

.8 Filter element clear opening: 2 mm

.9 Angle of screen: 750

.10 Maximum differential head the screen shall withstand: 11.04 ft (differential height between the upstream and downstream water levels)

2.2 Mechanically Cleaned Screen

.1 General

.1 The screen shall be designed to provide maximum solids filtration and thus maximize capture of debris and minimize rate of head loss increase through the screen. This

Page 157: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 5

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

shall be achieved by means of one piece perforated curved filter elements. The maximum openings shall be 2 mm. The screen will be operated intermittently by means of differential head measurement.

.2 The screen shall be securely anchored to the top of the channel and designed to resist all forces generated in the event of a full channel depth of 11.04 ft on the upstream side and no water on the downstream. Routine service, repair or replacement of damaged parts, shall be possible with the screen in the channel.

.3 The use of roller chain, filter shafts and rollers and/or two or more motors for screen rotation is not acceptable. Screens which run the chain rollers on metal supports will not be acceptable.

.4 Unit shall be designed so that maintenance of the drive mechanism can be accomplished at operating floor level. Screen elements shall be capable of removal at the operating level without taking the screens out of the channel or effecting the continuous or intermittent rotation of the screen.

.5 The screen shall be factory assembled and tested for a minimum of 8 hours prior to delivery and shall be delivered to the site fully assembled (other than the motor/reducer unit, discharge chute, and support legs). It shall be capable of being set in place and field erected by the contractor with minimal field assembly.

.2 Filter Screen

.1 The one piece curved screening elements shall be minimum 1/8" thick and fixed by four fasteners to the heavy duty 304 stainless steel drive links having 7.87" pitch x 1.38" x 0.2" thick section which shall ride on 2" x 1.5" thick DELRIN acetal supports located on the upstream and downstream sides of the screen. On every fifth screen panel a set of static, non engaging 'finger' type lifters shall be attached to the lower edge of the panel, designed specifically to lift spherical and large size solids (stones, cans, bottles, rag clumps etc) from the bottom of the channel. A submerged curved 1/2" thick stainless steel plate shall be provided at the foot of the screen to prevent ingress of stones and grit creating wear on the elements. A revolving lower guide arrangement consisting of two life sealed bushings, two 3.15" diameter stub shafts and two bolts on 7.87" pitch x 3/4" thick discs shall maintain accurate alignment of the screen elements. To prevent metal to metal wear and bearing damage no submerged roller bearing wheels and spindles will be allowed. Screens which do not support the drive chains on the downstream side will not be approved. Screens that use lifting ledge on top of the panel thereby preventing the removal of solids from the bottom of the channel floor will not be permitted.

.2 To prevent deflection, the one-piece filter elements shall have a minimum thickness of 1/8" and shall be made of curved 304 stainless steel. This is required to insure structural integrity and smooth operation. Engaging tines, fingers or engaging elements, which can bind or jam, will not be acceptable.

.3 The screen shall be automatically self-cleaning through the interaction of the one piece filter elements with the cleaner brush. The drive mechanism shall be designed to insure that the screen runs smoothly without jamming. A series of stationary 304 stainless steel lifters shall be fixed at intervals on the screen elements. They will be designed to remove spherical solids from the bottom of the channel, which may otherwise roll back

Page 158: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 6

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

off the screen face and accumulate thus creating a wear problem as the screen elements are moving thru the solids as they ascend on the upstream side of the screen. The screen panels will be driven at a speed of 15 fpm during normal operation and 30 fpm during high flow or high water levels. The screen must be able to operate at a speed that keeps pace or exceeds the accumulation rate of the screenings during a storm event. Single speed motors driving the screen band at 10 fpm will not be approved.

.4 A rotating deflector consisting of a 304 stainless steel tube roller wiper fabricated from 3.5 inches O.D. complete with 1.75 inches diameter stainless drive steel shafts at each end supported by pillow block bearings and driven by a max ½ hp TEFC geared drive unit. The roller wiper shall turn at max 20 rpm and function to direct all solids removed from the screen by the revolving brush cleaner and direct them to the screenings discharge flume attached to the screen discharge. conveyor. The rotating deflector prevents bypassing of solids into the downstream channel. The controls for operating the roller wiper shall be provided with the FSM screen control panel, and the wiper shall operate whenever the screen is turning.

.3 Filter Screen Belt

.1 The screen filtration belt shall be provided with one piece perforated curved elements, which limits the maximum opening to 2 mm in any direction. This restricted opening profile prevents long thin materials from passing through the openings. The screen shall have a maximum 0.80 square feet of contact surface per square foot of wetted filtration surface area.

.2 No cleaning devices which cause trash to be pushed or dropped into the interior of the filtration belt will be allowed.

.3 Due to the risk of high differential levels on the screen, in the event of a power failure, excess solids load condition, mechanical breakdown etc. the screen shall be designed to withstand a maximum differential head of 11.04 ft measured from the upstream water level to the downstream water level. The manufacturer shall provide calculations showing that it will meet this requirement. A test will be conducted at site, before the screen or screens are accepted, during which time the screen will be tested for a minimum period of two hours at the specified maximum differential head condition.

.4 Should the screen fail this test, for example there is bending, bowing, buckling or other significant signs of mechanical damage then the screen shall be removed at the manufacturers cost.

.5 The horizontal space between adjoining screen panels will not exceed the specified screen opening at any point between any adjacent panels. The screen manufacturer shall make a witnessed measurement of the screen panel adjoining spaces before acceptance at site and if more than 10% are greater than the dimension of the specified screen perforation the screen will not be accepted until the manufacturer has corrected the problem and a re-measurement as above confirms the specification has been met.

.6 To control the build up of biological slimes behind the screen panels, a 2 inch diameter internal spray water wash spray bar will be provided, manufactured from 304 stainless steel. The spray bar will be attached in the internal space between the rotating screen panels and the spray water will be directed to wash each screen panel as the panel

Page 159: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 7

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

moves past the spray nozzles. The spray bar will supply approximately 7 gpm at a pressure of 25 psi. The spray orifices will be non-plugging and suitable for use with treated effluent water. A minimum 1" NPT connection will be located on one side of the screen frame above the operating floor level and the water supply connection will include an inline strainer, manual operated gate valve, and solenoid valve suitable for attaching to the 1" NPT connection. The screen internal spray washer shall be operated manually at the discretion of the plant personnel based on a visual inspection of the screen panel internal surfaces.

.4 Screen Drive Unit

.1 The two speed drive unit shall be a hollow shaft type reducer with a 225:1 reduction equipped with anti-friction bearings and designed in accordance with AGMA recommendations for 24 hours, Class II service. The motor shall be no larger than 1.5/3.0 hp, 1760 rpm, TEFC, 230/600VAC/3/60 current and rated for use in a Class 1 Zone 1 hazardous area. Overload protection shall be provided by an electrical overload device (Tsubaki Shock Relay Model TSB50 or equal) that senses motor current draw.

.5 Screen Cleaner Brush Drive Unit

.1 The screen cleaner brush drive unit shall be a hollow shaft type reducer with a 13:1 reduction equipped with anti-friction bearings and designed in accordance with AGMA recommendations for 24 hours, Class II service. The motor shall be no larger than 2 hp, 1760 rpm, TEFC, 600VAC/3/60 and rated for use in a Class 1 Zone 1 hazardous area. Overload protection shall be provided by an electrical overload device (Tsubaki Shock Relay Model TSB50 or equal) that senses motor current draw.

.6 Screenings Rotating Deflector Drive Unit

.1 The screenings rotating deflector drive unit shall be a hollow shaft type reducer with a 750:1 reduction equipped with anti-friction bearings and designed in accordance with AGMA recommendations for 24 hours, Class II service. The motor shall be no larger than 1/2 hp, 1760 rpm, TEFC, 600VAC/3/60 and rated for use in a Class 1 Zone 1 hazardous area. Overload protection shall be provided by an electrical overload device (Tsubaki Shock Relay Model TSB50 or equal) that senses motor current draw.

.7 Hydraulic Screenings Flushing Flume

.1 The connecting chute from the filter screen to the screenings flushing flume shall be manufactured of 14 gauge 304 stainless steel. The flume shall be provided to carry the screenings to the adjacent channel.

.2 An inlet connection to the flume can be used to periodically flush the screenings into the adjacent channel by means of 3/8” spray nozzle using a total of 5 gpm treated effluent at 40 psi. located at the high end of the flume. 304 stainless steel piping, solenoid valve, flow and pressure control valve will be provided by the Contractor.

.8 Painting

.1 All non-machined surfaces other than galvanized or stainless steel shall be shop painted.

Page 160: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 8

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.1 Sandblast per SSPC-SP6

.2 One (1) coat Tnemec 90-93, or equal, 2.5 mils DFT.

.3 Colour to be confirmed.

.9 Limit Switches for Screen

.1 Torque overload limit switch.

.2 All switches shall be SPCT and rated not less than 10 amp at 120 volts AC.

.10 Controls and Control Panel

.1 One (1) Primary Control Panel, rated Class 1 Zone 1 for use in hazardous areas and waterproof, with separate Off-On power selector switch and controls for the filter screen shall be provided, and shall contain the following logic devices for proper screen operation:

.1 Relays, timers and alternator as required to monitor the screen mounted limit switches and level switch and perform necessary logic functions.

.2 Control power “Off-On” selector switch.

.3 “Torque Overload” alarm light (amber) to indicate failure due to a torque overload condition.

.4 “Screen Forward” run indicating light (green).

.5 “Reset” pushbutton.

.2 Two solid-state timers shall be provided to automatically initiate operation of each filter screen. One (1) frequency of run timer adjustable from 10 to 10230 seconds (in 10 second increments), one duration timer adjustable from 1 to 1,023 seconds (in 1 second increments).

.3 Main circuit breakers and a reversing magnetic starter, with a control transformer rated 150VA extra capacity, shall be supplied by others, and located in the customers motor control center.

.4 Signal inputs from screen control panel to plant central computer system for operation and alarm status as follows:

.1 One (1) each screen fail signal, indicating a problem requiring attention.

.2 One (1) each screen high level signal from filter screen sensor.

.3 Three (3) each screen run status signal from the screen drive, screen cleaner brush and screenings deflector drive motors.

.11 Spare Parts per Unit

Page 161: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 9

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

.1 Manufacturer’s recommended spare parts to be included with screen.

3 EXECUTION

3.1 Installation

.1 Equipment shall be installed in accordance with the manufacturer’s recommendations to provide a complete installation.

3.2 Electrical Connections and Controls

.1 Wiring and conduits for electrical power, control and instrumentation will be provided by the electrical Contractor under Division 16 – ELECTRICAL.

Page 162: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 10

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

APPENDIX A

General Arrangement of Waste-Tech FSM FRS 1300x75/2 Filter Screen

Page 163: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 11

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

Page 164: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 12

1 MODEL FSM 1600 X 75/6 FILTERSCREEN

2 FILTERSCREEN INSTALLATION INSTRUCTIONS

1. The base frame anchor bolts should be installed in the correct location on the concrete base 2. The base frame (item 2) should be bolted to the screen. 3. With the screen in a horizontal position, attach lifting straps to the lifting lugs (item 3). Begin to raise the

screen into a vertical position. (Two cranes or lifting sources will be required to place the screen in the channel)

FIGURE 1 FIGURE 2

4. The complete unit can now be lowered into the channel and the base frame located on the anchor bolts.

5. Using a precision level the unit should be checked for level, and shims should be used under the base frame to correct any irregularities in the concrete. Only then can the base frame anchor bolts be secured.

6. With the screen in place, attach the channel screen supports (item 5) to the channel walls on the downstream side of screen.

7. The base frame should now be grouted in. 8. Grout fill channel floor recess to form transition slope to & from Screen housing.

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

Page 165: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15940 AND SEWAGE PUMP STATION WASTEWATER SCREENS AND RELATED EQUIPMENT IN SEWAGE WET WELLS PAGE 13

ITT PS08037 Omni Engineering Inc. / 162178 June 2008

9. The bottom front and rear rubber seals (item 9) should be adjusted to form a seal between the screen and the channel floor.

10. The motors can now be wired. 11. The wash water system can now be installed.

END OF SECTION

Page 166: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15950 AND SEWAGE PUMP STATION TESTING, ADJUSTING AND BALANCING PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Scope of Work

.1 The supply and exhaust air systems shall be balanced.

.2 The heating water system and chilled water system shall be balanced.

1.2 Requirements

.1 Balancing of air handling systems shall be carried out by an accredited Balancing Sub-Trade with technicians specifically trained in the field of balancing. Technicians should have a minimum of four years experience.

.2 This work shall not replace normal factory start-up service for equipment.

.3 The Contractor will supervise the Balancing Sub-Trade and:

.1 Provide sufficient time for balancing prior to substantial completion.

.2 Make corrections to facilitate the balancing work.

.3 Adjust fan drives as requested by the Balancing Sub-Trade.

.4 Maintain all systems in full operation during the balancing period.

.5 Add balancing dampers where insufficient.

.6 Provide access to balancing devices.

1.3 Balancing Contractors

.1 Acceptable Balancing Contractors are:

.1 Western Mechanical Services (1977) Ltd; and

.2 K.D. Engineering Co.

.2 Any other Balancing Contractor wishing to bid on this work shall submit a request in writing a minimum of seven days prior to tender closing and submit a list of reference projects of similar magnitude with Owner's name and telephone number, and the Mechanical Contractor's name and telephone number. If approved for bidding, an addendum will be issued adding the Contractor to the above list.

2 PRODUCTS

2.1 Dampers, Belts and Pulleys

.1 Provide required balancing dampers, balance valves, belts and pulley changes found necessary to properly balance the air system.

Page 167: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15950 AND SEWAGE PUMP STATION TESTING, ADJUSTING AND BALANCING PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

3 EXECUTION

3.1 General

.1 Balance according to the full intent and requirement of the ASHRAE handbook - HVAC Systems and Application (latest edition) - Testing, Adjusting and Balancing Chapter.

.2 The Contractor shall inform the Consultant at least 48 hours prior to the commencing of testing. The Consultant (or his representative) may, at his discretion, witness all or some of the test readings and procedures.

.3 The Balancing Sub-Trade shall agree to perform spot checks where requested by the Consultant.

.4 The Balancing Sub-Trade shall advise the Contractor in writing, of any defects encountered during the testing operation. A copy of this advice shall be forwarded to the Consultant.

3.2 Balancing Air Systems

.1 Adjust duct and terminal balance dampers and adjustable turning devices to obtain design quantities with +/- 10% at each outlet and inlet on supply, return and exhaust systems. Maintain the design relationship between the supply and exhaust air system quantities.

.2 Fan volumes to be set to give 100 - 110% of design specified volumes to allow for some duct leakage.

.3 Permanently mark with paint or label the final position of all balancing dampers and air turning devices.

.4 Adjust the registers and diffusers to obtain the optimum draft-free air distribution pattern at occupant level.

.5 Check and field set controllers on mixing boxes.

.6 Verify and design air volumes of all boxes (maximum and minimum). Adjust setpoints as required.

.7 Verify the operation of all:

.1 Thermostats operating valves or boxes.

.2 On/Off switches on equipment.

.3 Interlocks between exhaust fans, dampers and boxes.

.8 Seal all holes used for flow and pressure measurements with metal plugs.

3.3 Balancing Water Systems

.1 After hydrostatic testing and cleaning of all water systems, each piping system shall be balanced.

Page 168: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15950 AND SEWAGE PUMP STATION TESTING, ADJUSTING AND BALANCING PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 A portable differential pressure meter, suitable for use with the flow measuring balance valves, shall be used for determination of flow to each of the major systems.

.3 Set balance valves and balance fittings to obtain uniform pressure and/or temperature differences across terminal heating/cooling elements and coils, acknowledging the different design pressure and/or temperature drop/rises.

.4 Mark the final balance position on all balance valves and balance fittings.

4 REPORTS

4.1 General

.1 The report shall include the following requirements and information:

.1 Submit a Statutory Declaration certifying that the testing and balancing procedures have been completed, that complete factual reports have been distributed and that directions have been given to the Contractor to correct faults and omissions and finally, that follow-up testing, after correction of faults and omissions has been completed and recorded.

.2 The Balancing Sub-Trade shall provide the most recent date of recalibration of all instruments used. Instruments must have been recalibrated within 6 months prior to use on this contract.

.3 The Balancing Reports shall be forwarded to the Consultant for approval and certification. They will form part of the Operating and Maintenance Manuals.

.4 The drawings and schedules shall have a maximum size of 11" x 17" with 1/2" margin on the left for binding.

.5 Each major system component and measurement point shall be referenced to the applicable room number.

.6 Include the date of test, or retest, system designation numbers and the area served by each system.

4.2 Air Handling Systems

.1 Fan I.D. Number

.1 CFM Capacity specified, actual, % variation

.2 CFM Outlets/Inlets specified, actual

.3 Leakage actual

.4 Fan

.1 RPM specified, actual

.2 Make specified, actual

Page 169: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15950 AND SEWAGE PUMP STATION TESTING, ADJUSTING AND BALANCING PAGE 4

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.3 Size specified, actual

.4 Model specified, actual

.5 Outside Air %

.6 Return Air %

.7 Rotation

.2 Motor

.1 Size specified, actual

.2 Phase/Volts/RPM specified, actual

.3 Current Draw rating, actual

.4 Starting Rating

.5 Pulley Position

.3 Static Pressures

.1 Supply Fan

.1 Suction specified, actual

.2 Discharge specified, actual

.2 Return Fan

.1 Suction specified, actual

.2 Discharge specified, actual

.3 Across each coil at full air flow

.4 Across each filter bank at full air flow

.4 Duct Traverses

.1 Main Ducts

.2 All Filter Banks

.3 All Coils

.5 Temperatures

.1 Outside Air Temperature - measure maximum and minimum zone supply temperatures at time of test. Measure air entering and leaving temperatures (D.B. and W.B.) for all coils.

Page 170: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15950 AND SEWAGE PUMP STATION TESTING, ADJUSTING AND BALANCING PAGE 5

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.6 Volume

.1 Measure cfm of VAV boxes.

4.3 Exhaust Air Systems

.1 Exhaust Fan I.D. Number

.1 CFM Capacity specified, actual, % variation

.2 CFM Inlets specified, actual

.3 Fan RPM specified, actual

.1 Make specified, actual

.2 Size specified, actual

.3 Model specified, actual

.4 Rotation

.2 Motor

.1 Size specified, actual

.2 Phase/Volts/RPM specified, actual

.3 Current Draw rating, actual

.4 Pulley Position

.3 Static Pressures

.1 Suction specified, actual

.2 Discharge specified, actual

.3 Total specified, actual

4.4 Water System

.1 Temperatures

.1 Entering and leaving water temperature at each terminal heating/cooling element, coil and heat exchanger.

.2 Flow Rates

.1 Readings at each measuring station

END OF SECTION

Page 171: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15995 AND SEWAGE PUMP STATION COMMISSIONING PAGE 1

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

1 GENERAL

1.1 Scope of Work

.1 Commissioning applies to all project service systems, all components with functioning or moving parts, and any project component whose specified performance is appropriately subject to field-testing and verification. Some life safety systems have acceptance procedures and verification tests mandated by the required Codes or Standards governing their design and installation. It is intended that such acceptance procedures and verification tests be an integral part of the commissioning process for those systems. For this project, commissioning will apply to equipment, components and systems comprising the following:

.1 Heating, ventilating and air-conditioning systems, including controls

.2 Exhaust systems

.3 All “automatic action” interfaces between systems.

1.2 Requirements

.1 Furnish labour and material to accomplish complete commissioning of the project systems as outlined above and as specified herein.

.2 Commissioning responsibilities, in general terms, are to be those contained in The Code of Practice for Commissioning Mechanical Systems in Buildings issued by the Standing Committee of Consulting Mechanical Engineers and Mechanical Contractors in British Columbia. The Code of Practice was written specifically for mechanical systems, however similar responsibilities and scope of work are to apply, as appropriate, to all systems and components to which commissioning applies.

.3 Copies of the Code of Practice can be obtained from:

.1 Mechanical Contractors Association of BC 3210 Lake City Way Burnaby, BC V5A 3A4

.4 Meticulous attention to detail and to documentation of results is required for the functional performance verification phase of commissioning. This is to ensure that the contractor has complied in every respect with the Contract Documents and to provide assurance of the same to the Owner. In this regard, Section 8, ACCEPTANCE PROCEDURES, of ASHRAE Guideline 14989, Guideline for Commissioning of HVAC Systems, provides relevant information for all systems, even though it was written specifically for HVAC systems.

1.3 Commissioning Contractor

.1 Commissioning work and reporting shall be carried out by an independent commissioning agent experienced in the commissioning of mechanical systems.

.2 Acceptable Commissioning Contractors are:

.1 Western Mechanical Services (1977) Ltd; and

Page 172: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15995 AND SEWAGE PUMP STATION COMMISSIONING PAGE 2

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

.2 K.D. Engineering Co.

.3 Any other Commissioning Contractor wishing to bid on this work shall submit a request in writing a minimum of seven days prior to tender closing and submit a list of reference projects of similar magnitude with Owner's name and telephone number, and the Mechanical Contractor's name and telephone number. If approved for bidding, an addendum will be issued adding the Commissioning Contractor to the above list.

2 PRODUCTS

Not Applicable

3 EXECUTION

3.1 Mechanical Systems

.1 Verify calibration of thermostats, temperature sensors and related controls, such as damper settings and valve positions.

.2 Verify readings of the control system, such as:

.1 Temperature

.2 Air Flow

.3 Damper positions

.4 Water pressure

.5 Water temperature

.6 Fire damper operation

.3 Verify operation of system modes, such as economy cycle, smoke removal, and in specific:

.1 Damper and fan operation

.2 Smoke detector response

.3 Zone response

.4 Verify that the total HVAC system is performing to provide conditions as outlined in the Design Intent.

3.2 Fire Dampers

.1 After the completion of the sheet metal work and any associated fire-stopping, verify that each fire damper will fully close without assistance when the link is disconnected. Reset the fire dampers following testing.

.2 Confirm that adequate access is provided to service each fire damper.

Page 173: southeast false creek energy center section 15010

SOUTHEAST FALSE CREEK ENERGY CENTER SECTION 15995 AND SEWAGE PUMP STATION COMMISSIONING PAGE 3

ITT PS08037 Versacon Consultants Inc. / 162178 June 2008

3.3 Check Lists

.1 Prepare a checklist for all items to be verified. The checklist shall itemize each point to be checked with a space for sign-off by the commissioning person.

.2 Submit checklist for approval by the Consultant prior to commencement of the verification procedure.

.3 The original signed-off checklists shall be submitted to the Consultant for review prior to the Substantial Performance inspection visit by the Consultant.

.4 A copy of the signed-off checklists shall be included in the Operation and Maintenance Manuals.

3.4 Meetings

.1 The commissioning agent will be required to arrange regular weekly meetings of the contractors involved the equipment to be commissioned, the relevant consultants, and the owner’s representative.

.2 Written minutes of the meetings shall be prepared and distributed to all involved.

3.5 Scheduling Work

.1 The commissioning agent shall prepare and distribute a schedule for the activities identifying what equipment is being acted upon and the personnel involved. The schedule shall be reviewed and updated at the regular weekly meetings.

END OF SECTION