7/30/2019 Solley David 2000
1/86
THE WINSTON CHURCHILL MEMORIAL
TRUST OF AUSTRALIA
Report by: David Solley - 2000 Churchill Fellow
Project: To study the Upgrading of Large
Wastewater Treatment Plants for
Nutrient Removal
7/30/2019 Solley David 2000
2/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 2 of 39
CONTENTS
1 EXECUTIVE SUMMARY 4
2 INTRODUCTION 5
2.1 BACKGROUND 5
2.2 PURPOSE 5
2.3 ACKNOWLEDGEMENTS 5
3 PROGRAMME 6
4 UPGRADING OF LARGE WASTEWATER TREATMENT PLANTS 7
4.1 NUTRIENT REMOVAL 7
4.1.1 Biological Nutrient Removal 74.1.1.1 BARDENPHO AND UCT BNR PROCESSES 84.1.1.2 THREE STAGE VERSUS FIVE STAGE BNR PROCESS 114.1.1.3 SUBSTRATE UTILISATION 114.1.1.4 PREFERMENTATION OF PRIMARY SLUDGE 134.1.1.5 HYDRAULIC RETENTION TIME (HRT) 14
4.1.1.6 SOLIDS RETENTION TIME (SRT) 154.1.1.7 PLUG FLOW AND COMPLETE MIX REACTORS 154.1.1.8 CYCLIC/BATCH OPERATION 164.1.1.9 ATTACHED GROWTH PROCESSES 174.1.1.10 SECONDARY RELEASE OF PHOSPHORUS 184.1.2 Sludge Settleability, Scum and Foam 194.1.3 Control and Instrumentation 204.1.3.1 AERATION CONTROL 214.1.3.2 RECYCLE FLOWS CONTROL 224.1.3.3 SLUDGE SOLIDS CONTROL 234.1.3.4 EXTERNAL CARBON DOSE CONTROL 234.1.4 Separate Sidestream Treatment 24
4.1.4.1 SHARON PROCESS 254.1.4.2 PHOSPHORUS STRIPPER 264.1.5 Chemical Nutrient Removal 264.2 BIOSOLIDS HANDLING, TREATMENT AND DISPOSAL 27
4.2.1 Digestion 274.2.2 Sludge Hydrolysis 274.2.3 Dewatering and Thickening 284.2.4 Incineration, Agricultural Reuse and Final Disposal of Biosolids 294.3 EFFLUENT POLISHING, DISINFECTION AND REUSE 30
4.4 ODOURCONTROL 30
4.4.1 Chemical Scubbing 314.4.2 Biofilters 31
4.4.3 Disposing Odorous Air into Diffused Aeration Systems 324.5 PRIMARY TREATMENT AND PLANT BYPASS 32
7/30/2019 Solley David 2000
3/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 3 of 39
4.6 OPERATION 33
4.6.1 Operator Training 334.7 DESIGN DETAILS 34
5 CONCLUSIONS 35
6 RECOMMENDATIONS 37
7 REFERENCES 38
TABLES
TABLE 3.1 PROGRAMME HIGHLIGHTS 6
TABLE 4.1 COST COMPARISON OF SIDESTREAM N REMOVAL PROCESSES 24
LIST OF FIGURES
FIGURE 4.1 3 STAGE BARDENPHO BIOLOGICAL NUTRIENT REMOVAL PROCESS...........................8
FIGURE 4.2 UCT BIOLOGICAL NUTRIENT REMOVAL PROCESS............................................................9
FIGURE 4.3 OXIDATION DITCH PROCESS CONFIGURED FOR P REMOVAL......................................10
FIGURE 4.4 BCFS
PROCESS.........................................................................................................................10FIGURE 4.5 5 STAGE BARDENPHO BIOLOGICAL NUTRIENT REMOVAL PROCESS.........................11
FIGURE 4.6 BIO-DENIPHO PROCESS.........................................................................................................17
APPENDICES
APPENDIX A ITINERARY
APPENDIX B - CONTACTS
APPENDIX C TREATMENT PLANT DETAILS
APPENDIX D PHOTOGRAPHS
7/30/2019 Solley David 2000
4/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 4 of 39
1 EXECUTIVE SUMMARY
Name: David Solley
Address: 200 Kadumba St, Yeronga, Qld 4014
Position: Senior Process Engineer, Brisbane Water
Telephone: 07 3403 3325Email: [email protected]
Project Description: To study the upgrading of large wastewater treatment plants for
nutrient removal in Europe and North America, with particular
reference to overseas design and operations experience.
This fellowship involved an eight week programme including visits to 40 wastewatertreatment plants and two international water industry conferences in six countries (France,
the Netherlands, Denmark, Sweden, USA and Canada) and two continents.
In the Netherlands, the BCFS oxidation ditch plants and SHARON process wereinspected courtesy of Mr. Rob Vromans (BDG Engineers) and Mr. Jan Mulder (Hollande
Eilanden en Waarden) respectively.
In Denmark, Kruger A/S (Dr. Marinus Neilsen & Mrs. Tine Onnerth) introduced theiradvanced control technology, as well as inspecting the Cambi process.
Low effluent nitrogen BNR plants operating in similar climatic conditions to those inBrisbane were inspected in Hillsborough County (Tampa Florida, USA).
The pioneer for BNR technology in North America, Prof. Cliff Randall (Virginia Tech.)organised an itinerary including inspection of various BNR upgrades in the Chesapeake
Bay region (USA) and discussed his past and current BNR research.
Tours of BNR plants in Western Canada were organised by Dr A. Warren Wilson (ReidCrowther P/L). These plants included some of the earliest and recent North American
BNR upgrades, including those incorporating primary sludge fermentation.
Where very low effluent nitrogen concentrations (less than 5 mg/L) are required, a fivestage Bardenpho process (with primary settling) or oxidation ditch process (without
primary settling) is recommended. These processes are also suitable for achieving both
low phosphorus and nitrogen concentrations.
Advanced control and instrumentation offers great potential for achieving lower effluentnutrients and improved treatment efficiency. Key areas for improved control include
aeration control, recycle stream flow control and sludge solids/SRT control. This control
will be implemented at the Luggage Pt, Gibson Is and Oxley Ck WWTPs in Brisbane.
Effective utilisation of substrate is key to obtaining maximum nutrient removal in BNRprocesses. Reduction of aeration to that required for complete nitrification, maximising
EBPR, step feed of influent wastewater between anaerobic and anoxic zones and
prefermentation of primary sludge, will all contribute to achieving this objective. Side stream treatment of digestion dewatering liquors can be implemented for removal of
15 to 30% of the nitrogen load. The SHARON process is the most cost effective and
simple of the proven technologies. Research and pilot trials of alternative sidestream
treatment processes will be conducted over the next two years. Sidestream phosphorus
removal is likely to be unnecessary for most plants.
Multi-level training and qualifications for operators of advanced wastewater treatmentplants would be a positive development for the wastewater treatment industry. The Open
Learning Institute will be contacted to determine how their operations training
programme and qualifications could be further developed.
The information gathered from this fellowship will be disseminated through this report,presentations to colleagues and the wider water industry, working with colleagues toimplement the recommended improvements, and presentation of future case study results.
mailto:[email protected]:[email protected]7/30/2019 Solley David 2000
5/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 5 of 39
2 INTRODUCTION
2.1 Background
Wastewater treatment plants (WWTPs) in Australia are being required to remove
nutrients (nitrogen and/or phosphorus) from the wastewater to prevent degradation of
water bodies and the environment. Many new small to medium sized nutrient removalplants have been built in Australia in the last decade, but large WWTPs built in the
1970s for large cities are only now being upgraded for nutrient removal. Large
existing plants have typically been upgraded because of the value of the existing assets
and the high cost of new infrastructure.
This Fellowship provided the opportunity to visit upgraded large WWTPs in regions
where these plants have been operating for a number of years. No such plants and
first hand design or operations experience currently exists in Australia. The plants and
countries visited represent a selection of centres where significant developments have
taken place and an extensive operating history exists. The fellowship and this report
do not attempt to comprehensively cover all worldwide developments in wastewater
treatment plant upgrading and BNR technology.
2.2 Purpose
The purpose of this fellowship was to:-
Study the upgrading of WWTPs overseas; Investigate nutrient removal upgrades;
Focus on both design and operational aspects; Increase personal skills and knowledge; Benefit Australia; Pass on the skills and knowledge gained.
2.3 Acknowledgements
The support of the Winston Churchill Memorial Trust of Australia in making this
fellowship possible is gratefully acknowledged. Thank you also to my employer
Brisbane Water, for their assistance and providing time to undertake the fellowship.
The hospitality and freely given time and knowledge of each person who hosted me
overseas is greatly appreciated. Prof. Cliff Randall (Virginia Tech.), Dr A. Warren
Wilson (Reid Crowther P/L) and Mr. Rob Vromans (BDG Engineers) were
exceptionally generous.
Special thanks to Dr Peter Dold, Dr A. Warren Wilson and Mr. Nick Reid for planting
the seed and strongly encouraging me to travel overseas to see how things are done
elsewhere.
7/30/2019 Solley David 2000
6/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 6 of 39
3 PROGRAMME
The fellowship involved an eight week programme and included visits to:-
40 wastewater treatment plants; 2 international water industry conferences; 6 countries in two continents.
The two conferences attended were:-
The First World Water Congress of the International Water Association, heldin Paris, France;
The Second International Symposium on Sequencing Batch ReactorTechnology, held in Narbonne, France.
Countries visited included:-
France; The Netherlands; Denmark; Sweden; USA (Florida, Atlanta, Chesapeake Bay region); Canada (Calgary, Okanagan Valley, Vancouver).
Table 3.1 below, lists the highlights of the fellowship programme.
TABLE 3.1 PROGRAMME HIGHLIGHTSLocation Activity Organisation/Contact
France 1st World Water Congress
2nd Int. Symposium on SBR Technology
3 WWTPs
IWA
IWA
Vivendi Water/OTV
The
Netherlands4 BCFS
oxidation ditch WWTPs
2 SHARON sidestream processes
BdG Engineers
Jan Mulder & Grontmij
Denmark 4 BioDenipho plants & Cambi process Kruger A/S
Sweden Trickling filter WWTP
ANOX AB (research activities)
Gryaab/Peter Balmer
Asa Malmqvist
Florida, USA 3 WWTPs
4 WWTPs
Hillsborough County
Orange County
Atlanta, USA 3 WWTPs City of Atlanta/Joe Porter
ChesapeakeBay, USA
6 WWTPsVirginia Polytechnic (research activities)
Prof. C. RandallProf. C. Randall
Canada 7 WWTPs Reid Crowther Ltd
Appendices A to D contain greater detail on the itinerary, personal contacts and
wastewater treatment plants visited for this fellowship.
7/30/2019 Solley David 2000
7/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 7 of 39
4 UPGRADING OF LARGE WASTEWATER TREATMENT PLANTS
Prior to the last decade, wastewater treatment plants were constructed primarily for
organic carbon removal. During the last decade, the process of upgrading wastewater
treatment plants to meet more stringent environmental requirements has tended to be
almost continuous. The main driver for these upgrades has been increased
eutrophication and pollution of receiving water bodies, though water reuse
requirements are beginning to have an impact on treated wastewater quality. The
process of upgrading is likely to continue as effluent requirements become more
stringent and treatment technology develops, driven by increasing urbanisation and
increased understanding of the detrimental environmental effects of wastewater
discharges.
4.1 Nutrient Removal
The primary objective of any nutrient removal upgrade is that the nutrient removal
requirements be met, usually for nitrogen and/or phosphorus. Elements to be
considered in achieving this objective include the process configuration, design, andthe control and operation of the process.
Secondary considerations for an upgrade include the capital and operating costs, the
degree of flexibility incorporated for unexpected conditions, the reliability and
robustness of the process and the ease of operation. Capital cost is largely influence
by the size of the tankage required for the process. Operating costs are mainly
influenced by personnel, energy and chemical usage. For activated sludge processes,
the settling characteristics of the sludge will have the greatest influence on reliability
and operability.
4.1.1 Biological Nutrient Removal
Almost all wastewater nutrient removal processes developed in the last decade have
been based on biological nutrient removal (BNR) principles. This is largely due to the
overall cost advantages of BNR in most cases. Chemical treatment to further remove
phosphorus is sometimes applied, when the nutrient removal achieved by BNR is
insufficient to meet effluent requirements. Non-biological removal of nitrogen from
municipal wastewater is difficult to achieve (in comparison to BNR). Therefore, the
usual strategy is to remove all the required nitrogen and as much phosphorus as
possible with BNR, then remove the remaining phosphorus requirement with chemical
precipitation of phosphorus (refer Section 4.1.5).
Biological nitrogen removal is achieved by the nitrification/denitrification process,
where the influent ammonium is oxidised to nitrite/nitrate, which in turn is reduced to
nitrogen gas. Two different groups of bacteria carry out the two step process. The
ammonium oxidising bacteria operate in an aerobic environment and the nitrate/nitrite
reducing bacteria operate in the absence of dissolved oxygen. The denitrifying
bacteria also require substrate/carbon for the reduction reaction. The processes can be
achieved in a number of formats, including attached growth/fixed film systems and
suspended culture/activated sludge systems.
Enhanced biological phosphorus removal (EBPR) is achieved by bacteria capable ofstoring substrate/carbon and releasing phosphorus in an anaerobic zone (that is, in the
absence of dissolved oxygen and nitrate/nitrite). These bacteria are then able to utilise
7/30/2019 Solley David 2000
8/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 8 of 39
the stored substrate to store excess amounts of phosphorus in an aerobic environment.
By wasting excess biosolids from the aerobic zone of the process, excess phosphorus
is removed from the wastewater by these phosphate accumulating bacteria. Recent
research also shows that excess phosphorus uptake can occur in the presence of
nitrate/nitrite and absence of dissolved oxygen (anoxic conditions) (refer Section
4.1.1.3). EBPR is conventionally achieved in suspended culture/activated sludge
processes, but recent research has successfully demonstrated EBPR with attached
growth processes (albeit with some difficulty).
For biological removal of both nitrogen and phosphorus, nitrification/denitrification
and EBPR are combined in the one process, usually using a single sludge system. For
low effluent concentrations of both nitrogen and phosphorus, a conflict usually exists
in municipal wastewater, where the amount of substrate available for EBPR and
denitrification is limiting on one or both of the processes (refer Section 4.1.1.3).
Additional substrate can be added to the process to make up the substrate deficit, for
either the denitrification or EBPR processes. Alternatively, chemical precipitation of
the required phosphorus deficit can be applied.
A large variety of process alternatives have been developed on the above principles,
each with a particular advantage or designed to overcome the limitations of another.
The choice of process type is largely dependent on the nutrient removal requirements,
site constraints and the influent wastewater characteristics amongst other factors.
Some of the significant process alternatives examined as part of the fellowship are
presented below.
4.1.1.1Bardenpho and UCT BNR ProcessesOf the processes investigated, most fall into two main groups; the Bardenpho processand the University of Cape Town (UCT) Process. In the three stage Bardenpho
process (refer Figure 4.1), influent wastewater combines with return sludge from the
clarifier in an unaerated reactor (anaerobic zone). In this zone, phosphorus is released
and substrate stored by the phosphorus accumulating bacteria, in the absence of
nitrate. The process flow then enters an anoxic zone, where it combines with a nitrate
recycle from the end of the aerobic zone. In this unaerated zone, the returned nitrate is
reduced to nitrogen gas. The flow then enters an aerobic zone, where ammonia is
oxidised to nitrate. Phosphorus is removed from the process with the excess biosolids,
which are wasted either from the clarifier underflow or the aerobic zone. Nitrogen is
removed as nitrogen gas bubbling from the anoxic zone.
Figure 4.1 3 Stage Bardenpho Biological Nutrient Removal Process
Return Sludge
Mixed Liquor Recycle
Anaerobic Anoxic Aerobic
7/30/2019 Solley David 2000
9/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 9 of 39
One limitation of the Bardenpho process, is that nitrate returned to the anaerobic zone
with the return sludge from the clarifier can reduce the effectiveness of the phosphorus
release/substrate storage mechanism. The magnitude of this effect is directly related
to the levels of nitrate in the return sludge stream. In a process designed for low
nitrogen, low nitrate levels are likely achieved, minimising the mass of nitrate returned
with the sludge to the anaerobic zone. Endogenous denitrification of the return sludge
in the clarifier sludge blanket, return channels or pipe work can also reduce the mass
of nitrate returned. In Johannesburg/Westbank type modifications, a specific
predenitrification zone can be included for nitrate removal from the RAS. In some
plants, a proportion of the influent wastewater (say 10%) can be fed to the
predenitrification zone, to increase the denitrification rate that would be achieved by
reliance on endogenous respiration (Bonnybrook and Summerland WWTPs, Canada).
In order to better protect the anaerobic zone from nitrate, the UCT (University of
Cape Town) configuration returns sludge from the end of the anoxic zone to the
anaerobic zone, which can be controlled to have low or zero nitrate (refer Figure 4.2).Disadvantages cited for this configuration include the need for an additional recycle
stream (and associated pumps, pipes etc), and diluted mixed liquor solids in the
anaerobic zone resulting in larger anaerobic volume. Some proponents of the UCT
configuration argue that a larger anaerobic zone is not required, as the process favours
a greater mass proportion of phosphorus accumulating bacteria.
Figure 4.2 UCT Biological Nutrient Removal Process
Two VIP (Virginia Initiative Project) plants were inspected near Chesapeake Bay in
the USA. These plants are essentially high rate UCT processes that achieve excellent
phosphorus removal and good nitrogen removal with a low hydraulic retention time(HRT).
The oxidation ditch process for biological phosphorus and nitrogen removal is
essentially a three stage Bardenpho process with a very high mixed liquor recycle rate
(refer Figure 4.3). Typically these plants are configured without primary settling, with
the process usually operated at long sludge retention time (SRT) and long HRT (so
called extended aeration). The advantage of this process is that effluent total
nitrogen of less than 3 mg/L is possible for almost any wastewater (Randall et.al.,1992). With very low nitrate levels in the return sludge, good phosphorus removal is
Return Sludge
Mixed Liquor Recycle
Anaerobic Anoxic Aerobic
Anoxic Recycle
7/30/2019 Solley David 2000
10/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 10 of 39
also possible. The disadvantages include large tankage requirements and the
disadvantages associated with not including primary settling (such as higher aeration
demand, and no primary sludge available for anaerobic digestion and subsequent gas
utilisation; refer Section 4.1.1.3).
Figure 4.3 Oxidation Ditch Process Configured for P Removal
The BCFS oxidation ditch plants (Netherlands) included a UCT type configuration
with an oxidation ditch (refer Figure 4.5). This may be unnecessary from a
phosphorus removal viewpoint, because with an oxidation ditch it should be possible
to operate the process with low nitrate in the sludge return stream. However, the
proponents of this system cite the advantages of better settling sludge and better
utilisation of substrate (by denitrifying dephosphating bacteria) for this system (refer
Sections 4.1.2 and 4.1.1.3 respectively for discussion of these aspects).
Figure 4.4 BCFS Process
The Bonnybrook plant (Calgary, Canada) has the capability of operating in either a
Bardenpho or UCT configuration. Experience at this plant was that the UCT
configuration gave greater variation in the phosphorus removal performance comparedto the Bardenpho configuration (the current operating configuration).
Mixed Liquor Recycle
Anaerobic Anoxic Aerobic
Anoxic Recycle
Return Sludge
AnoxicSelector
Anaerobic
Anoxic
Return Sludge
Influent
EffluentAerobic
7/30/2019 Solley David 2000
11/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 11 of 39
4.1.1.2Three Stage Versus Five Stage BNR ProcessFor greater removal of nitrogen, five stage processes are proposed to give greater
nitrate removal. Typically, a secondary anoxic zone is included after the primary
aeration zone, where endogenous denitrification occurs. Alternatively, additional
external substrate can be dosed into this zone for higher denitrification rates.
Following this zone, a secondary aeration zone is usually included to reaerate thewastewater and nitrify any ammonia produced as a result of the endogenous activity in
the secondary anoxic zone. Figure 4.4 shows the five stage Bardenpho process
configuration.
Randall (1997) concluded from his investigations, that an effluent TN limit of 3 mg/L
cannot be achieved with a three stage BNR process. Accounting for the
unbiodegradeable TKN in the effluent (usually greater than 1 mg/L) would require
effluent ammonia and nitrate levels totalling 2 mg/L. This is not typically achievable
with a three-stage process. Process options for low nitrogen then include a five stage
BNR process, or post-denitrification in a denitrification filter for example. As
discussed in Section 4.1.1.1, Oxidation ditches without primary settling (essentially a
three stage process), have demonstrated in South East Queensland and overseas that
they are another alternative for effluent TN less than 3 mg/L.
Figure 4.5 5 Stage Bardenpho Biological Nutrient Removal Process
4.1.1.3Substrate UtilisationTo achieve low effluent concentrations of both nitrogen and phosphorus, a conflict can
exist between the amount of substrate available and required. This is often the case
with municipal wastewater. It follows then, that the appropriate utilisation of
available substrate for the various biological processes is a critical success factor for
BNR.
As discussed in Section 4.1.1, for low concentrations of both nutrients, the focus is
usually to first achieve the nitrogen removal requirement. Therefore, the required
amount of substrate available for denitrification should be ensured. As demonstrated
by the BCFS plants (Netherlands), this can be achieved in a couple of ways (van
Loosdrecht, 1998).
The use ofdenitrifying phosphorus removing bacteria (DPB) can maximise the useof substrate. These bacteria remove 1 mg/L of P for every 4-5 mg/L of nitrate
removed, essentially utilising the same substrate for both objectives (about 20
Return Sludge
Mixed Liquor Recycle
Anaerobic Anoxic Aerobic Anoxic Aerobic
7/30/2019 Solley David 2000
12/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 12 of 39
mgCOD/L). Kuba et. al. (1996 & 1997) report that these bacteria require recycling of
activated sludge through anaerobic and anoxic conditions for a good accumulation,
and are found in abundance in many UCT-type processes. A maximum reduction of
50% of the COD required, compared to conventional aerobic phosphorus
uptake/nitrogen removal processes is reported. DPB observations are widely supported
(Randall, 1997).
At the Genemuiden WWTP (Netherlands), the DPB activity was found to be not as
high as at other BCFS
plants. This was possibly due to low VFA in the wastewater,
nitrate or oxygen recycle to the anaerobic zone and less recycle of nitrate to the anoxic
zone. That is, the BNR process was not operating as well.
It is not known whether other process configurations with suitable anoxic and
anaerobic fractions and recycles can achieve enhanced phosphorus uptake under
anoxic conditions. Results from the Westbank plant (Kelowna, Canada), suggest that
significant phosphate uptake is taking place in the anoxic zones of this three stage
Bardenpho process; the DPB mechanism a likely cause. Randall suggests that theUCT process favours DPB because the UCT process provides the most reliable EBPR.
Because the UCT process best protects the anaerobic zone from nitrite/nitrate, the
VFA present in the wastewater is all used for EBPR, thus maximising DPB. It also
follows then that the VFA/PO4 ratio is also an important factor in determining the
degree of DPB possible.
Step feed of influent was applied at a number of plants inspected. One variation
found at the Bowie plant (Maryland, USA) and the Kelowna, Lake Country, Westbank
and Summerland plants (British Columbia, Canada), was to step feed influent
wastewater, part to the anaerobic zone and the remainder to the anoxic zone. This
ensured that the required proportion of the substrate required for EBPR anddenitrification was applied to the respective zones. An added benefit is that the solids
concentration in the anaerobic zone is kept higher, and its size could therefore be
reduced. Although this process would result in readily biodegradable substrate being
fed directly to the anoxic zone (with its low F/M ratio), there was no evidence of a
significant deterioration in sludge quality or rise in SVI (refer Section 4.1.2). The
percentage of wastewater fed direct to the anoxic zone was 50 to 60% in the Bowie
plant and up to 30% for the Canadian plants. In New York City, 13 of the 14
wastewater treatment plants are to be converted from plug flow aeration processes to
step feed anoxic/aerobic processes for nitrogen removal.
At the Bjergmarken WWTP (Roskilde, Denmark), a proportion of the raw wastewatercould be bypassed around the presettling and sent direct to the bioreactors. The
proportion of wastewater fed direct to the bioreactor was controlled to ensure
sufficient substrate for denitrification.
Endogenous substrates are a significant contributor to the requirements for
denitrification. These are produced and utilised throughout the BNR process.
Therefore, it follows that the denitrification process benefits if the aerobic retention
time and oxygen provided are minimised, providing the maximum endogenous
substrate for the anoxic process. Usually, the objective of the aeration zone is
complete nitrification, so excess aeration provided above that required for complete
nitrification is wasted. This additional aeration also consumes endogenous substrate
that should be saved for the anoxic zone and denitrification, and also causes
7/30/2019 Solley David 2000
13/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 13 of 39
unnecessary release of nutrients through the cell destruction of the aerobic endogenous
activity. These minimum aeration objectives were the focus of many processes
inspected (Netherlands, Denmark, Chesapeake Bay/USA and Canada). The objectives
were often achieved through control of the aerobic fraction and oxygen supplied.
Further detail of this control is given in Section 4.1.3.1.
Van Loosdrecht et.al. (1997) supported maximising the fraction of nitrifying bacteria
in the BNR process to minimise aerobic endogenous activity, through:-
Operating at long SRT Primary settling to minimise the accumulation of inerts and heterotrophic
bacteria
Not combining chemical phosphorus removal with the activated sludgeprocess, to prevent accumulation of chemical precipitates in activated sludge.
Primary settling of wastewater is often incorporated in treatment plants to minimise
energy requirements and operating costs. The primary sludge removed is usuallystabilised in an anaerobic digester in combination with waste activated sludge (WAS)
(refer Section 4.2). Methane gas produced in the digestion process can be used for
various energy needs at the plant. Energy is also saved in reduced aeration and costs
are saved with lower excess biosolids production in the BNR process. However,
plants lacking sufficient substrate or with a poor TKN/COD ratio may require the
substrate available from primary sludge for the BNR process (primary sludge usually
contains a more favourable TKN/COD ratio than that for settled wastewater).
Oxidation ditches without primary settling usually produce very low effluent nitrogen
levels through utilisation of all the available substrate and a favourable TKN/COD
ratio. Prefermentation of the primary sludge to obtain VFA and readily available
substrate for the BNR process is discussed in Section 4.1.1.4.
Of course, there is always the option to meet substrate needs from an external source;
whether it is commercial grade methanol, acetate or a waste product from another
industry. Of the plants inspected that dosed an external carbon source, methanol was
most commonly utilised for denitrification. One disadvantage is that the activated
sludge culture needs to adapt to utilising methanol, whereas dosing with acetate
requires no acclimatisation. This is most likely due to the natural occurrence of
acetate substrates in most municipal wastewaters.
4.1.1.4Prefermentation of Primary SludgePrefermentation of primary sludge is another method for gaining readily
biodegradable substrate for the BNR process. The substrate gained is in the form of
volatile fatty acids (VFA), which is the required substrate for EBPR. For this reason
prefermentation is most often applied to EBPR, where the prefermenter substrate is
dosed to the anaerobic zone. The critical ratio in assessing the VFA requirements for
EBPR is TP/VFA, and prefermenters are usually sized/designed on this basis.
Prefermenter generated substrate could be dosed to anoxic zones to assist with
denitrification, but this wasnt found at the plants visited. Fermentation of primary
sludge will lead to the release of nitrogen and phosphorus, which had previously been
removed from the effluent with the primary sludge. For this reason, careful
consideration must be given to this additional nutrient load when assessing thebenefits of prefermentation (important for nitrogen, more so than for phosphorus).
7/30/2019 Solley David 2000
14/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 14 of 39
There are various types of prefermenter configurations available, but complete mix
and static fermenters were the types incorporated at the plants inspected (Canada). In
the static fermenter, primary sludge is discharged to a reactor/tank, which is similar in
configuration to a gravity thickener (sludge loading approximately 30 kg/m2/d). A
thick sludge blanket is maintained in the reactor, corresponding to the required sludge
age. The fermentation products are elutriated from the sludge blanket into the
supernatant by the thickening action and stirring of the scraper/picket fence rake.
These systems are favoured for their simplicity and easy control (i.e. maintenance of a
sludge blanket level). Static prefermenters can be controlled to various sludge blanket
levels, corresponding to the required sludge age for a particular temperature/season
(Kelowna plant, Canada). Complete mix fermenters incorporate a complete mix
reactor ahead of a separation process, which is usually a gravity settler.
At the Bonnybrook plant (Calgary, Canada), the formation of methogenous bacteria is
controlled by periodically aerating the fermenter reactor for short periods, using a
course bubble diffuser system installed in the reactor. At Penticton WWTP, the staticfermenters are fully mixed for an hour a day (and at times, on a couple of other
occasions throughout the day also), using vertical shaft mixers. This is also to control
the formation of methogenous bacteria and elutriate the VFA. Odour control is
necessary for prefermenters and those inspected were fully covered, with odorous gas
removed to odour treatment systems (refer Section 4.4 and Appendix C).
The Nansemond (Virginia, USA) and Summerland (Kelowna, Canada) plants operate
their primary clarifiers to maintain deep sludge blankets, in order to ferment the settled
solids. The VFA formed is elutriated from the sludge blanket to the primary effluent
in much the same way as a static fermenter; by action of the sludge thickening and
stirring of the sludge blanket by the scraper mechanism. In doing so, the Nansemondplant is able to consistently reduce the effluent total phosphorus from about 1.1 mg/L
to less than 1 mg/L. Reid Crowther P/L recommended reducing the primary settling
tank (PST) peak overflow rate from the normal 4.5-5.5 m/hr to less than 3.5 m/hr in
this mode of operation, to allow thickening of the primary sludge in the PST. (This is
similar to the approach that has been adopted at Luggage Pt WWTP in Brisbane).
4.1.1.5Hydraulic Retention Time (HRT)Hydraulic retention time has perhaps the greatest influence on the capital cost of a
treatment plant. The greater the HRT, the larger the tankage required. The HRTs of
the plants inspected varied from 6 hours to greater than 24 hours. Generally, theplants achieving greater nitrogen removal operated at a higher HRT (apart from
exceptions such as Largo WWTP, which incorporates post-denitrifying filters). There
is often a link between HRT, SRT and MLSS concentration in the bioreactor (refer
Section 4.1.1.6). For example, oxidation ditches without primary settling and long
SRT often require a high HRT to maintain MLSS in a workable range (say 4000 to
5000 mg/L). Phosphorus removal does not appear to be influenced significantly by
HRT in the normally applied range.
The VIP plants (Virginia, USA), based on the UCT configuration, were designed and
are operated with very low HRT (about 6 hours). These plants achieved low
phosphorus levels (less than 1 mg/L) and moderately low nitrogen levels (8 mg/L). Itshould be noted that even lower nitrogen results (say 6 mg/L) could probably have be
7/30/2019 Solley David 2000
15/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 15 of 39
obtained by increasing the nitrate recycle (to 2 times the inlet flow rate), but this
performance was not required to meet licence at these plants. The wastewater treated
at these plants is quite dilute compared to Australian conditions. So when comparing
performance, the effluent concentrations should not be considered in isolation to
percentage removal and the effluent nutrient mass figures, which are not quite as
impressive.
4.1.1.6Solids Retention Time (SRT)The solids retention time is one of the key parameters in designing and operating a
BNR plant. The SRT defines the average time which bacteria are retained in the
process, and with the wastewater loading, effectively determines the mixed liquor
solids level in the process. The maximum SRT value (and hence solids level) possible
for the process, is defined by the capacity of the final clarification step. That is, the
limit for solids in the bioreactor corresponds to the maximum allowable flux loading
on the clarifiers. Put another way, the SRT determines the size of the clarifiers for the
process and has a large influence on capital cost of a plant. It follows then, that an
improvement in solids settleability can lead to greater flexibility and possible increase
in the SRT of the process or lower capital cost (refer Section 4.1.2).
Wastewater temperature also has an influence on the required SRT for a process, with
lower temperatures requiring higher SRTs. This is most important with respect to
nitrification. Many plants in cold temperature have difficulty fully nitrifying during
winter months, and this is often reflected in their nitrogen licence (Canada and
Denmark).
The generally held view is that for nitrogen removal, the longer the SRT, the better the
performance; and for phosphorus, the shorter the SRT, the better the P removalperformance. So to achieve both N and P removal, a compromise is often required.
The approach is usually to ensure the required biological N removal and supplement
the biological P removal with chemical precipitation. For complete nitrification, a
minimum SRT is required, dependent on the aerated fraction in the bioreactor and the
wastewater loading and temperature. The SRT then required to achieve the desired
nitrate level is dependant on the substrate available. If there is adequate readily
available substrate in the raw wastewater, then the reliance on endogenous
denitrification is diminished and the SRT could be quite low. If the TKN/COD ratio is
unfavourable, then the plants reliance on endogenous denitrification increases and
generally the SRT is increased. Of the plants inspected, many are achieving very low
effluent phosphorus and low nitrogen with quite a low SRT (e.g. the Canadian plantssuch as Kelowna and Summerland and the VIP processes in Virginia, USA). On the
other hand, many long SRT plants achieved very low nitrogen and phosphorus, albeit
often with the addition of precipitant chemicals.
Control of SRT is fundamental to the performance of most BNR process. It provides a
stable control parameter, which allows adjustments in mixed liquor solids to meet
varying wastewater loadings. Many plants have different SRT set points for different
seasons of the year; or may more directly control SRT to wastewater temperature
(Summerland WWTP, Canada). Further details on SRT and solids control are given
in Section 4.1.3.3.
4.1.1.7Plug Flow and Complete Mix Reactors
7/30/2019 Solley David 2000
16/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 16 of 39
Each zone in a BNR process can be designed either as a plug flow reactor, complete
mix reactor, or some variation between the two extremes. A plug flow reactor
provides the most efficient arrangement, where all the flow remains in the reactor for
essentially the same duration; that is, a uniform residence time. Plug flow reactors can
generally be sized smaller than complete mix reactors. Plug flow reactors also allow
for better control. For example, when recycling from a plug flow anoxic zone to the
anaerobic zone in the UCT process, there is a much better chance that the recycle
stream has low nitrate in the plug flow reactor than in a complete mix reactor.
Selectors in particular are reported to give much better performance in the plug flow
configuration (refer Section 4.1.2).
However, maintaining mixed liquor solids in suspension in a plug flow reactor can be
difficult to achieve and can promote short-circuiting when mechanically mixed.
Unless the reactor is configured such that the forward velocity of the mixed liquor
through the reactor is greater than about 0.27 m/s (as in an oxidation ditch), then the
best that can be achieved will be a number of complete mix reactors in series. The
greater the number of complete mixed reactors, the closer the approximation to plugflow. The efficiency and power requirements of the mechanical mixing system also
needs to be balanced against the desire for plug flow. Each complete mix zone will
require at least one mechanical mixer. Very efficient mixing can be provided for large
complete mix reactors, using large diameter impeller, slow speed mixers (Kelowna
WWTP, Canada).
4.1.1.8Cyclic/Batch OperationVarious alternatives exist for cyclic/batch operation BNR processes. In these
processes, the aeration and wastewater feed applied are cycled to produce varying
conditions in the reactor. The Danish developed Bio-Denipho
process has beenadopted throughout Denmark and applied in various parts of the world (Florida, USA
and Australia). Figure 4.6 shows the various phases of the process, as usually applied
(alternatives exist with phases where both reactors operate in an anoxic mode). Mixed
liquor is fed alternatively to the two main bioreactors, which are sequentially operated
in anoxic and aerobic modes.
The process is reported to give increased flexibility over continuous processes, in that
the HRT and mass fraction of the anoxic and aerobic zones can be adjusted by
variation of the various phase lengths. A greater degree of on-line instrumentation is
usually applied to these types of processes, aimed at optimising this available
flexibility. The process also eliminates the requirement for a nitrate recycle, leadingto some potential energy savings.
Of the plants inspected, the performance of the cyclic processes did not exceed the
performance of many continuous processes, despite this increased flexibility. This is
likely either because there has been an increasing focus on providing flexibility in
continuous processes, or the degree of flexibility is not required due to the continuous
processes being quite well matched to their loading conditions. The SRT and HRT
adopted were at the long end of the range for the examined plants, indicating that the
increased flexibility had not lead to great capital cost savings. At the South County
plant (Tampa, USA), the process has not been operating in the cyclic BioDenipho
mode for over six months. The operators have preferred operating the plant in acontinuous mode, with the two oxidation ditches operating continuously in series. A
7/30/2019 Solley David 2000
17/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 17 of 39
low DO concentration is maintained at this plant, which would be promoting
substantial SND (simultaneous nitrification/denitrification).
Figure 4.6 Bio-Denipho Process
4.1.1.9Attached Growth ProcessesAs an alternative to suspended growth processes (e.g. activated sludge BNR), attached
growth BNR processes are being investigated and adopted for a number of plants.
These process types include:-
trickling filters, suspended and fixed carrier processes, biological filters.
Suspended and fixed carrier processes are usually combined with activated sludge inthe same process stream. Biomass grows on the carriers, as well as forming activated
sludge flocs. The carrier media are retained in the bioreactor and the activated sludge
flows through to the clarifier for separation. For many attached growth projects, the
aim of installing the media in the aerobic zone is to improve the plants nitrification
capacity. The biomass growth for nitrification is usually more difficult to establish in
an activated sludge process, and also forms only a thin biomass film on the carriers,
avoiding the bulky heterotrophic growth that often leads to clogging of the carrier
media. The effectiveness of clogged media is severely reduced due to limited contact
between the wastewater and the biomass, plus the media can sink to the bottom of the
reactor floor.
Anoxic
Aerobic
Return Sludge
Anaerobic
PHASE A
Aerobic
Return Sludge
Anaerobic
PHASE B
Anoxic
Aerobic
Return Sludge
Anaerobic
PHASE C
Aerobic
Return Sludge
Anaerobic
PHASE D
Aerobic
Aerobic
7/30/2019 Solley David 2000
18/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 18 of 39
Trials using LinPor
sponges overcame clogging problems by utilising airlift pumps
to squeeze out inert material (Chesapeake Bay, USA). At the Annapolis plant
(Maryland, USA), ring-lace attached growth media are installed in the last two thirds
of the aerobic zone of the bioreactor. Most of the nitrification at the Annapolis plant
was complete in the first third of the aeration zone, so it was difficult to gauge the
success of the trial. From this and similar trials carried out in Canada and Australia, itseem appropriate to install media throughout the whole aeration zone in processes
with up-front anaerobic/anoxic zones (e.g. MLE, Bardenpho or UCT processes). Most
of the readily available substrate has been absorbed onto the activated sludge flocs in
the unaerated zones and nitrifier growth on the carriers should predominate for the
whole aerated zone.
Worm growth on ring lace or carrier media is also a common problem with attached
growth processes. This has been successfully controlled in aeration zones by turning
the air off each day for a period, and also by chlorinating the RAS (Annapolis, USA).
Carrier media have also been successfully used for separate denitrification reactors orwithin unaerated zones with an activated sludge process. Mechanical mixing is then
required to keep the media mobile and any activated sludge in suspension. Estimated
of the mixing power require for carriers in unaerated reactors is estimated between 10
to 13 W/m3 (Maurer, 2000). This was confirmed by Anox AS (Sweden), as between
10 to 20 W/m3.
Trickling filters were included in a couple of plants inspected (Goteburg, Sweden and
Vancouver, Canada). The reported advantages of trickling filters, which lead to their
inclusion in these plants, included their robust performance, low operating cost,
simplicity and higher nitrification rates (for Goteburg). None of the trickling filter
plants examined achieved low effluent nitrogen.
Post-denitrification filters, with the addition of substrate for denitrification, have been
included at several plants throughout Europe and the USA. Two French water
companies (OTV/Vivendi and Degremont/Lyonnaise) have implemented biological
filter processes as the main biological treatment process in the Paris region (France).
The biological filter processes adopted there are the companies proprietary products
(such as BIOSTYR
and BIOFOR
) which are filters configured for nitrogen
removal. Methanol addition to the unaerated section of the filter provides suitable
conditions for denitrification. These processes are compact and achieve substantial
nitrogen reduction, though not matching that of BNR processes elsewhere and at
higher capital and operating cost. The BAF process (biologically aerated filter) at the
Roanoke plant (Virginia, USA), has experienced media retention and inlet screening
problems. The second stage filters also clog with algae regularly. The BAF is taken
off-line twice a day for cleaning.
4.1.1.10 Secondary Release of PhosphorusSecondary phosphorus release occurs under anaerobic conditions, when phosphorus is
released by the EBPR bacteria without substrate storage. This is believed to have a
detrimental effect on EBPR, as excess phosphorus uptake by these bacteria cannot
then occur in the aerobic zone. Low effluent nitrate can cause secondary release of
phosphorus in the final settling tanks (FSTs) and RAS return stream. To overcomethis effect, the preference is often to operate with some effluent nitrate, when low
7/30/2019 Solley David 2000
19/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 19 of 39
concentrations of phosphorus are required. Secondary release can also occur if
anaerobic or secondary anoxic zones are too large, such that for a significant part of
the zone, the nitrate and VFA are zero. These effects may be controlled by providing
flexibility in the sizing of these zones and through control of nitrate levels (i.e. recycle
rates, DO and carbon dosing control; refer Section 4.1.3).
An alternative view is that secondary release in an anoxic environment may not
necessarily be a disadvantage, as substrate storage has still been measured with this
release (Randall, Virginia Tech.). The mechanism could be associated with glycogen
storage, as the glycogen may be converted to PHA at the end of the anoxic zone.
4.1.2 Sludge Settleability, Scum and Foam
Activated sludge settleability and the degree of scum formation and foaming can be
the most influencing factors in determining the ease of operating a BNR plant. Sludge
settleability governs the final clarification or separation step in the activated sludge
process. A sludge that has poor settleability results in difficulty with separating the
biological solids from the treated effluent. In the worst case, process failure occurs
when the sludge solids are lost with the effluent. Poor sludge settleability usually also
indicates that the activated sludge will have poor thickening and dewatering
characteristics (that is, low thickened sludge and cake solids content from thickening
and dewatering processes such as gravity thickeners, belt presses and centrifuges
refer Section 4.2).
The most widely adopted measure of sludge settleability is the sludge volume index
(SVI). BNR plants are notorious for sludges that have poor settling characteristics and
high SVI values, usually greater than 150 mL/g and often in the 200 to 300 mL/g
range. The result of this is that the final clarifiers in a BNR plant are usually sizedconservatively, to avoid process failure when the sludge is settling poorly. If plants
can be designed to reliably produce a good settling sludge, then the reliability of the
process is increased and/or the size of clarifiers can confidently be reduced, resulting
in capital and operational savings.
Of the plants inspected, the BCFS processes (Netherlands) and VIP processes
(Virginia, USA) consistently produced the lowest SVI sludges. The features of these
processes proposed to lead to this excellent sludge settleability include a UCT
configuration and plug flow or compartmentalised anaerobic selectors. The BCFS
processes use a carousel type selector configuration and the VIP processes, two to
three complete mix reactors in series. Some complete mix anaerobic selectors alsoproduced good settleability, so this is obviously not the only influencing factor.
Selectors are designed so that a sufficiently high F/M (food/micro-organism) ratio
exists for the floc forming bacteria to out-compete filamentous bacteria. In theory,
anaerobic selectors are sized such that all the readily available substrate is adsorbed
into the activated sludge flocs in this high F/M environment. This substrate is then not
available in a low F/M environment where filamentous bacteria have a competitive
advantage. Good settling sludges were produced at the plants where the anaerobic
zones were greater than 10% of the bioreactor volume.
The benefits of the UCT process in producing good settling sludge is attributed to that
processs complete elimination of nitrite from the anaerobic selector. The presence ofnitrites in the aerobic zone is reported to favour filamentous bacteria (Randall,
7/30/2019 Solley David 2000
20/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 20 of 39
Virginia Tech.). Nitrite is a powerful oxidiser and is thought to inhibit floc-forming
bacteria. In the UCT process it is possible and best to control the nitrate recycle to
have little or no nitrate at the end of the anoxic zone, as the presence of nitrate usually
indicates the present of some nitrite. Oxidation ditches (without upfront anaerobic
selectors) could have nitrite contact conditions quite easily with their high
recirculation rates, and this may be the cause of their notoriously poor settlebility.
Low selector nitrate/nitrite is also possible with other process configurations (e.g.
Bardenpho and BioDenipho processes), by maintaining low effluent nitrate and/or by
completely denitrifying the return sludge.
In the BCFS
processes, the first part of the anoxic reactor is also compartmentalised
to provide an anoxic selector (refer Figure 4.4). This selector is provided for
absorption of the soluble hydrolysis products that remain after the anaerobic zone.
Introduction of this anoxic selector reportedly lead to reductions in SVI from around
150 mL/g to between 80 and 100 mL/g at one of the BCFS
plants, which is typical
for the process type (van Loosdrecht, 1998).
Many plants reported severe scum problems, particularly when mixed liquor
concentrations were high (generally during winter). One successful control method
was to remove the scum from the bioreactor (Canada and Atlanta, USA). The
approach is to remove the scum forming organisms from the surface of the bioreactor
where they are growing. Several of the Canadian plants selectively wasted sludge and
scum together from the end of the bioreactor.
Foam control using poly-aluminium chloride dosing (e.g. PAX-14 by Kemwater) has
been successful practised in the Netherlands and in Denmark (Naestved WWTP)
against microthrix filamentous bacteria. The chemical is dosed at 70 to 80
mgPAX/kgVSS. The theory is that the alum coats the filaments and decreases theircompetitiveness. Improvements are reported to occur in 2 to 3 days from
commencement of dosing.
4.1.3 Control and Instrumentation
The degree of control applied to the plants inspected varied from manual adjustment
of equipment without the aid of on-line instrumentation (e.g. no on-line DO meters at
Falkenburg WWTP, Florida), to state of the art control systems with automatic set-
point adjustment (Denmark). More advanced control systems generally allowed
plants to achieve improved performance, rather than lower staffing levels. In essence,
the more advanced control systems have allowed monitoring and tuning of thetreatment process to a degree that would never have been considered manually. It is in
this area of advanced control and instrumentation that the greatest improvements
could be made in achieving low effluent nutrients in Australia.
Improved instrumentation is partly responsible for the improvements in control.
Reliable nutrient meters are becoming available, and advances are focused on reduced
maintenance, low running costs (e.g. less reagents) and higher sample frequency. For
example, the Dr Lange Nitrax probe is used extensively in Europe for online nitrate,
utilising the UV measurement principle. This meter is capable of giving true on-line
readings, rather than the reactor chemistry meters, which have a sample frequency
of about fifteen minutes or so.
7/30/2019 Solley David 2000
21/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 21 of 39
All plants with on-line nutrient analysers, incorporated sample filtering (using simple
cross-flow membrane systems).
4.1.3.1Aeration ControlControl of aeration in BNR plants has been achieved in many ways, the usual
objective being to control to a DO set-point in the aerated zones, sufficient to removeammonia-nitrogen. By controlling the aeration to the minimum required to achieve
complete nitrification (say ammonia less than 1 mg/L), the following objectives can be
achieved:-
The substrate utilised aerobically is minimised, providing the maximum fraction ofsubstrate for denitrification,
Aeration energy is minimised, Aerobic degradation of the biomass is minimised.
Essentially, aerating the process after all ammonia is removed is wasted effort and islikely to be detrimental to the process.
At the Genemuiden WWTP (Netherlands), the aeration in the main aerobic reactor is
controlled to a DO set point at the reactor outlet. In the anoxic/aerobic swing reactor,
the surface aerator is controlled by turning the aeration on when the ORP value at the
outlet of the reactor is less than a set point (say < -100 mV); and off when the DO at
the outlet of the main aeration reactor reaches above a high set point. Controlling the
ORP in the swing zone between zero and 150 mV can ensure that suitable conditions
for simultaneous nitrification/denitrification (SND) occur. In this way, the aeration
mass fraction is optimised at this plant.
Sen and Randall (1990) successfully controlled aeration at the Bowie WWTP using
feedback from an on-line effluent alkalinity meter. The effluent alkalinity was used to
control the oxygen supplied by increasing when alkalinity rose above a set range and
vice versa. The control method is appropriate for systems with long HRT, low F/M
and high recycle rates (e.g. oxidation ditches). Low DO levels were also maintained
(0.5 mg/L), to reduce the oxygen applied and maximise SND. Sen and Randall also
showed that effluent phosphorus levels rose along with turbidity, when the amount of
oxygen supplied was insufficient for substrate stabilisation and nitrification. In this
way, turbidity has been used to control aeration in the Schreiber Corporation plants
(Maryland, USA).
In Denmark, the aeration system DO set points were controlled to ammonia and OUR
(as determined by the on-line DO and air flow rate measurements). Similar automatic
DO set point adjustment to on-line ammonia values has been implemented at the
Beckton WWTP (U.K.). The operational mode of aerobic/anoxic swing zones can
also be controlled to effluent ammonia values.
The Summerland plant (Kelowna, Canada) automatically changes the aeration system
DO set point through 12 different set point values during each day. The set-point
values are manually entered by the operator, with the objective of maintaining
ammonia between 0.6 and 0.8. Grab samples are taken from time to time, to monitor
the effluent ammonia achieved. The samples are analysed using the commonlyavailable test kits that utilise pre-packaged reagent vials (Merck, Dr.Lange and Hach).
7/30/2019 Solley David 2000
22/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 22 of 39
Set point adjustments are manually made on the basis of these results and wastewater
temperature.
At the end of an aerobic zone, over-aeration is often caused by low oxygen demands
mismatched with the inability of the aeration system to sufficiently reduce the airflow.
Also, the requirement for mixing in this zone (i.e. to keep the mixed liquor in
suspension) often requires the airflow to be higher than that required by the biological
process. This can lead to carryover of oxygen into the anoxic zone and reduced
efficiency of the denitrification process. Solutions to the problem include:-
Installing supplemental mechanical mixing in these aeration zones (Utoy CkWWTP, Atlanta USA).
Installing coarse bubble diffusers for the low aeration demand sections of theaeration zone (Westbank WWTP, Kelowna Canada).
Pulsing the aeration system on and off in these sections, to provide minimumaeration but sufficient mixing.
4.1.3.2Recycle Flows ControlThe mixed liquor recycle flows in a BNR process have also been successfully
controlled for improved nutrient removal at many plants. Control of the nitrate (or
A) recycle, aims to return the optimum mass of nitrate to the anoxic zone to
maximise removal. In the UCT type processes, this is particularly critical, in that the
nitrate at the end of the anoxic zone (where the mixed liquor is recycled to the
anaerobic zone) should be minimised preferably to zero.
Most plants keep the mixed liquor recycles at a constant rate, while the most basic
control paces the mixed liquor recycles to the plant inflow (Florida, USA). TheBCFS plants controlled the nitrate and anaerobic mixed liquor recycles to ORP
values from meters located at the ends of the anoxic and anaerobic zones respectively.
When the redox value becomes greater than a set-point value (-100 mV at the end of
the anoxic and 300 mV at the end of the anaerobic), the respective pump rate is
reduced linearly with increasing redox value. In Denmark, Kruger AS control the
nitrate recycle rate to the nitrate level at the end of the anoxic zone. In their
experience, they found ORP to be too sensitive a control parameter.
Control of the return sludge flow from the FSTs has also been optimised at some
plants. Kruger A/S (Denmark) control the return sludge flow to a constant suspended
solids level in the return stream. Two different set point flow rates are adopted for dayand night (for sludge dewatering reasons). Control of the sludge return flow rate to
maintain a constant sludge blanket level in the FSTs, has also been successfully
adopted at some plants in Denmark and Florida. Dr Lange Sonatax ultra sonic
sludge blanket detectors are used in Netherlands successfully. As an indicator of the
efforts being made to reduce maintenance, the instrument has a wiper to automatically
clean biofilm growth off the element, with an alarm indicated when the wiper needs
replacing.
At the South County plant (Florida, USA), the return sludge flow is paced to the main
stream effluent flow rate. This gives a much better response to the flow being applied
to the FSTs than using plant inflow. However, pacing of the return sludge flow to
plant flow should be applied cautiously, as this may have disastrous results during
7/30/2019 Solley David 2000
23/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 23 of 39
peak flow conditions. Although the objective of returning solids to the bioreactor
during the peak load is desirable (from a F/M ratio perspective), the solids flux
loading on the FSTs is greatly exacerbated by higher sludge recycle flows at the time
when the loading is critical.
4.1.3.3Sludge Solids ControlThe two usual choices for solids control in the activated sludge process are either to
maintain a mixed liquor suspended solids (MLSS) level, or to control to a solids
retention time (SRT). Control to a set point MLSS range is often favoured, due to its
simplicity. The operators of a treatment plant often become comfortable with a solids
level that is suitable for the BNR process. This may work very well, especially for
plants where the loading does not vary significantly. Different MLSS levels may be
adopted for different mixed liquor temperatures or seasons of the year. Some of the
BCFS
plants (the Netherlands) control to solids and are greatly aided in this by the
use of on-line suspended solids meters.
Control to a set point SRT provides control of the MLSS appropriate to the process
requirements and independent of plant loading. While arguably a technically superior
control method, in practice the control can be erratic when wasting solids from the
FST underflow, due to variations in RAS solids concentration. When mixed liquor
wasting from the bioreactor is practised, control to an SRT set point becomes simple
and easy to control (the volume of sludge wasted per day is equivalent to the
bioreactor volume divided by the SRT in days). Mixed liquor sludge wasting from the
end of the BNR bioreactor also has the advantage of:-
Wasting sludge with the highest phosphorus content.
Providing the opportunity to selectively waste collected scum with the mixedliquor (Canada).
As with MLSS control, different SRT set points are often adopted for different mixed
liquor temperatures or seasons of the year.
On-line solids meters were widely used throughout Europe and America for control,
with reported success. Most instruments used an infrared measurement principle.
This is different to the experience in Brisbane, where the accuracy of readings was
poor unless the meters were frequently calibrated (at least weekly). This may be due
the highly varying sludge quality at the plants where these meters were installed (these
meters are optical instruments and varying floc/filament sizes and proportions arelikely to require very frequent calibration).
4.1.3.4External Carbon Dose ControlControl of external carbon dosing to an on-line effluent nitrate value is often applied
to post-denitrification processes (France, Netherlands & USA). Kruger A/S
(Denmark) control external carbon dosing to the main BNR process through
monitoring of nitrate levels and the calculated OUR (from DO and air flow meters).
The capacity for denitrification is calculated (as the OUR/4), and the denitrification
need is calculated (as the measured nitrate in the effluent or recirculation point).
When the need exceeds the capacity, then carbon dosing is implemented.
7/30/2019 Solley David 2000
24/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 24 of 39
4.1.4 Separate Sidestream Treatment
Significant quantities and concentrations of nutrients can be found in the sidestreams
of most wastewater treatment processes. The most common of these is the dewatering
liquid from digested sludge, which is very high in ammonium and phosphorus. This
sidestream includes centrate/filtrate from the cake dewatering process and any digester
supernatant removed. Other high nutrient sources may include tankered industrial orseptic wastes. Most of these sidestreams are conventionally returned to the head of
the main process, where they are combined with the raw wastewater. Estimates of the
nitrogen load from this sidestream return are between 15 and 30% of the total nitrogen
load on the process. The phosphorus load is largely dependent on the degree of EBPR
and the degree to which struvite and similar compounds form in the sludge digesters
and surrounding pipe work.
A promising recent development is the separate treatment of these high nutrient
sidestreams, which is reported to be more efficient and lower cost (Vandaele et al.,
2000). The effect of sidestream treatment is to unload the main nutrient removal
process, resulting in lower effluent nutrient concentrations.
Sidestream treatment methods for nitrogen removal include:-
Air stripping, Steam stripping, MAP (magnesium ammonium phosphate or struvite) process, Ion exchange processes, Conventional biological nitrification/denitrification processes, Nitrification/denitrification variations involving sequencing batch reactors (SBR),
membrane bioreactors and attached growth systems.
Mulder (2000) gives cost estimate for the various different techniques available for
nitrogen removal from sidestreams, shown in Table 4.1 below.
TABLE 4.1 COST COMPARISON OF SIDESTREAM N REMOVAL PROCESSES
Process Cost estimate (Euro/kg N)
Air stripping
Steam stripping
MAP/CAFR process
Membrane bioreactorBiofilm airlift reactor
SHARON process
6.0
8.0
6.0
2.85.7
1.5
Sidestream treatment processes for phosphorus removal include MAP and chemical
precipitation processes. Very few plants incorporating anaerobic digesters were found
to carry out sidestream phosphorus removal, and yet many achieved excellent effluent
phosphorus results. This is due to the formation of struvite, calcium phosphate and
vivianite in the digester, which usually removes the necessity for P removal from
sidestream flows. Studies show that greater quantities of magnesium are also taken up
by the EBPR bacteria, which then becomes available in anaerobic digesters forstruvite formation (Pattarkine and Randall, 1999). Typically, up to two thirds of the
released phosphorus remains in the digested sludge in these various crystaline forms.
7/30/2019 Solley David 2000
25/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 25 of 39
To maximise the effect, it is recommended that removal of supernatant from anaerobic
digesters is not practised. The Danish experience is also that phosphorus release from
anaerobic digesters is generally not a problem.
4.1.4.1SHARON ProcessThe SHARON (Single reactor for High activity Ammonia Removal Over Nitrite)
process has been developed in the Netherlands for the treatment of high strength
ammonium wastewater from the dewatering of digested sludge (Mulderet. al., 2000).
Two plants utilising the SHARON process were inspected in the Netherlands; the
Dokhaven plant in Rotterdam and the Utrecht WWTP. In this process, the ammonium
is nitrified to nitrite as the intermediate, followed by denitrification of nitrite to
nitrogen gas. This has the following advantages over conventional
nitrification/denitrification (via nitrate):-
75% of the aeration energy is required to oxidise ammonium to nitrite, and 60% of the carbon addition is required for denitrification starting with nitrite.
The ammonium oxidation is simply controlled to nitrite by operating at elevated
temperature (30 to 40 C) and low solids retention time (SRT). The process is
essentially achieved without sludge retention, such that biomass growth and washout
are in equilibrium. That is, the SRT is equal to the hydraulic retention time (HRT), at
about 1 to 2 days. The process generates excess heat, usually requiring a heat
exchanger for cooling. A heat exchanger may also be required for heating during
startup. pH control is very important and can be achieved with the addition of alkali.
However, experience has shown this is unnecessary and that addition of methanol with
the resulting recovery of alkalinity through denitrification is sufficient to maintain a
stable pH. The Dokhaven plant operates with a simple single reactor system operatingin a aerobic/anoxic cycle, which is superior to the two reactor continuous system at
Utrecht WWTP. The process is very stable and simple to operate.
Greater than 90% removal of ammonium is achieved with the SHARON process,
which is fairly independent of the initial ammonium concentration. Therefore, a
greater mass of nitrogen is removed with higher initial nitrogen concentrations,
favouring the process for high concentration applications (around 1 g.NH4/L or higher
at the Dokhaven plant).
The SHARON process has been evaluated in a number of studies as being the most
cost effective (Mulder et al.,2000) and most robust (Vandaele et al.,2000) sidestreamtreatment for nitrogen removal. Evidence from the two sites inspected indicated that
the SHARON process was highly effective.
The new ANAMMOX (aerobic ammonium oxidation) process is currently being
developed as a variation on the SHARON process, in which the ammonium is
oxidised by serving as the electron donor in a denitrification reaction. In effect, the
ammonium meets the energy requirements of the denitrification process, removing the
need for substrate addition. By combining the process with a process in which nitrite
is produced (e.g. SHARON), a nitrogen removal process is possible which requires
much less oxygen (half that required for the SHARON process), no additional
substrate and very low sludge production (Van Loosdrecht and Jetten, 1998). This,and similar processes are being developed by a number of different research groups
7/30/2019 Solley David 2000
26/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 26 of 39
and shows promise for lower cost and more effective nitrogen removal from
sidestreams. (Brisbane Water in co-operation with the University of Queenslands
Advanced Wastewater Management Centre, Redland Shire Council and the
Queensland Governments Advanced Wastewater Treatment Technology Scheme will
be researching and pilot-trialing ANAMMOX type processes over the next two years).
4.1.4.2Phosphorus StripperOne innovative alternative developed for the BCFS process (Netherlands), puts a
twist on sidestream treatment by specifically creating a high strength phosphorus
stream from the main BNR process. Where chemical phosphorus removal is required,
they have implemented a system that withdraws pre-settled phosphorus rich liquor
from the end of the anaerobic zone (that is, following EBPR phosphorus release). The
phosphorus is then chemically precipitated from this high strength stream. Greater
efficiency is achieved by chemically dosing in the sidestream rather than the main
process stream, due to the high phosphorus concentrations. An in-tank settler has
been developed for decanting the phosphate rich liquor from the anaerobic zone (van
Loosdrecht et.al., 1998).
4.1.5 Chemical Nutrient Removal
BNR has been chosen for most nutrient removal upgrades in order to minimise
chemical usage and costs. Where chemicals are added, they are often in the form of
substrate for the BNR process. The most common substrate chemicals added are
methanol, ethanol or acetate. Acetate is usually more expensive, but has the
advantage of being suitable substrate (VFA) for EBPR and not requiring biomass
acclimatisation for nitrogen removal. Acclimatisation is likely not required for acetate
because it occurs natural in most domestic wastewaters, whereas methanol or ethanol
does not.
As discussed in Section 4.1.1, chemical phosphorus removal is often applied to BNR
plants to remove additional phosphorus that is not removed in the biological process.
This is usually achieved by dosing precipitant chemicals either into the mixed liquor
entering the bioreactor, or the mixed liquor stream feeding the FSTs. This was
widely practiced at the treatment plants inspected. The FSTs need to be adequately
sized for the additional chemical sludge load, which can be significant.
Alternatives precipitant chemical dosing points include:-
dosing to the PST feed (which places an additional chemical sludge load on thePSTs) (France),
dosing the effluent from the FSTs (which would require a downstream separationprocess such as settling or filtration),
dosing into the sewers, which is often practised for odour control, dosing to a separated sidestream (refer Section 4.1.4.2).
The two main precipitant chemicals used for phosphorus removal are alum and ferric
salts. There is some concern that ferric salts can have a detrimental effect on EBPR
processes, due to some inhibition of the phosphorus accumulating bacteria. This has
recently been summarised and studied in a series of papers by de Haas et.al. (2001).At the Bonnybrook plant (Calgary, Canada), it was also reported that iron salts caused
7/30/2019 Solley David 2000
27/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 27 of 39
the UV disinfection to become ineffective, due to increased fouling of the UV lamps
and reduced efficiency from adsorption. It is also important not to remove too much
phosphorus (through overdosing of chemical precipitants), as this has lead to nutrient
deficiency in BNR processes (Virginia, USA).
4.2 Biosolids Handling, Treatment and Disposal
The management of biosolids is a major challenge for modern wastewater treatment
plants. A variety of techniques are used for the handling, treatment and disposal of
biosolids. Mainstream BNR processes place greater demands on the sludge stream of
nutrient removal plants.
New biosolids stabilisation and treatment processes have been introduced to increase
the destruction of volatile solids and pathogens (refer Section 4.2.1 and 4.2.2). In
doing so, biosolids disposal options are improved. With greater volatile solids
destruction comes greater release of bound nutrients, often requiring separate
treatment of sludge return liquors for nutrient removal (refer Section 4.1.4).
4.2.1 Digestion
Many plants include digestion processes for sludge stabilisation. Aerobic digestion is
not common, but anaerobic digestion is widely used. In Denmark, the numbers of
plants incorporating anaerobic digestion is still increasing, with those using aerobic
digestion remaining unchanged over the past few years. This seems fairly typical of
Europe and America. Aerobic digestion is often chosen with the objective of retaining
excess phosphorus bound with the EBPR bacteria. However, many plants have
demonstrated this in unnecessary, due to formation of struvite and similar compounds
from the released phosphorus in the anaerobic digester (refer Section 4.1.4).
As an alternative to conventional mesophilic anaerobic digestion, thermophilic
anaerobic digestion is being adopted at many plants. The defining difference between
the two processes is the operating temperature; about 37 C for mesophilic and 55 C
for thermophilic. Different anaerobic bacterial groups dominate at either operating
temperature. Reported characteristics of thermophilic digestion include:-
HRT lowered to 12 days or less (mesophilic time almost halved), Disinfects/pasteurises the sludge, increasing disposal options, Suitable for 100% WAS,
Struvite precipitation increased at higher temperature, Volatile solids destruction not greatly increased over mesophilic digestion, May need steam to heat sludge effectively (scaling of heat exchangers reported
otherwise, though a few plants still used heat exchangers).
4.2.2 Sludge Hydrolysis
Sludge hydrolysis processes cause the rupture of biosolids cell structures, releasing
the water tied up in the cells and dissolving organic cell matter. Essentially, the
sludge is cooked prior to digestion. This released substrate results in greater overall
volatile solids destruction when applied prior to anaerobic digestion. Various
hydrolysis processes have been developed including Cambi, Krepro, Porteus, Krampol(Alfa Laval) and Zimpro.
7/30/2019 Solley David 2000
28/86
Churchill Fellowship 2000 Report David Solley
Upgrading of Large Wastewater Treatment Plants for Nutrient Removal Final Report 20/03/02
C:\WINNT\Profiles\so7sbw.000\Desktop\working\Churchill Report.doc Page 28 of 39
In the Cambi process, steam is used to directly heat sludge under pressure prior to
digestion. At the Naestved WWTP (Denmark), the Cambi process heats dewatered
waste activated sludge (at about 14 to 16% DS) to a temperature of between 160 to
180 C and pressure of between 8 to 10 bar. The sludge is subject to these conditions
for between 30 and 60 minutes. Following cooling, the sludge is pumped to the
anaerobic digesters for stabilisation (a mesophilic process). The Cambi processappears much simpler than many of the alternatives.
The Cambi thermal hydrolysis process is reported to give the following advantages
over conventional anaerobic digestion:-
Increased biogas production (by approximately 60%); Increased volatile solids destruction; Improved dewaterability of digested biosolids (from say 18% to greater than 35%
using a belt filter press, though very dependent on the dewatering equipment);
Less polymer usage for sludge dewatering;
Increase in the digester reaction rates and hence digester capacity; Improved stability of the digested sludge cake; Pasteurisation of the waste biosolids (suitable to meet the USEPA standards).
Thermal hydrolysis may also be applied to primary sludge, but the improvements in
biogas production and solids destruction during digestion are not nearly as significant
as those for waste activated sludge. However, thermal hydrolysis is often applied to
primary sludge for the pasteurisation benefits.
The Cambi process is reported to usually give an energy benefit. That is, the energy
available from the increased biogas produced exceeds the energy requirements for the
Cambi process. This would be dependent on the nature of the biosolids raw product
and the thickening/dewatering equipment used. No figures were provided for the
Naestved plant (as the plant had only recently been commissioned - March 2000).
Other plants report significant savings in energy and biosolids disposal costs, leading
to payback periods as short as four years for some case study plants.
Sludge hydrolysis processes create a higher nutrient mass in the sludge dewatering
filtrate return stream, caused by the increased biosolids destruction. This higher
nutrient return to the main process increases the requirement or possibility for
sidestream treatment (refer Section 4.1.4), and options are