SOLAR POWER A SUSTAINABLE ENERGY SOURCE DMRC’s INTITATIVES Delhi Metro Rail Corporation
Dec 16, 2015
SOLAR POWER A SUSTAINABLE ENERGY SOURCE
DMRC’s INTITATIVES
Delhi Metro Rail Corporation
Present Demand of around 150 MW.
Monthly Power Bill of approx Rs. 40 Cr.
Approx. 45% of Total expenditure.
Power Demand is more in Summers due to
increase in air conditioning load at stations
and trains.
DMRC’s POWER DEMAND
NEED FOR SOLAR POWER
Electricity is crucial to operate METRO,
Mostly Electricity is generated from fossil
fuels like coal, gas, which generate Carbon
dioxide adversely affecting the
environment.
To mitigate impact on environment, DMRC
has decided to use all possible areas for
installation of Solar Panels
• October 2012 – DMRC signed MoU with GIZ.
GIZ surveyed DMRC stations and Depots,
and prepared Detailed Project Reports for
Solar Power Plants at following three
locations :-
– Yamuna Bank Depot
– Yamuna Bank station
– Dwarka Sector – 21 Metro Station
THE BEGINNING
Shading across the day Shading area from on 21st December 4:00pm to 5:00 pm
Utilizable area was determined after Shading analysis.
Shading across the day on 21st December
Shading area from4.00PM to 5.00PM
DETAILED PROJECT REPORTS
Dwarka Sector – 21 Metro Station
Yamuna Bank Metro Station
Yamuna Bank Rail Depot
…….DETAILED PROJECT REPORTS
• GIZ introduced SECI (Solar Energy
Corporation of India), a GOI Company to
DMRC, and the MoU was signed in
September 2013.
• SECI floated tenders for roof top Solar
Plants and shortlisted M/s Sun Edison
(SEI Green) for Dwarka Sector – 21
Metro Station.
M.O.U. WITH SECI
• Various business models were explored
and financial calculations were done.
SECI suggested two models:-
CAPEX Model
RESCO Model
BUSINESS MODEL
Entire cost of Project to be borne by
DMRC (i.e. 70%) and
30% subsidy from SECI / MNRE.
CAPEX MODEL
• RESCO (Renewable Energy Service
Company) Model
• Project cost to be borne by the Developer
identified by SECI and the developer will
enter into a PPA (Power Purchase
Agreement) for 25 years with DMRC at a
mutually agreed tariff. 30% subsidy to the
Developer, will be provided by SECI.
• No Capital expenditure by DMRC.
RESCO MODEL
In order to mitigate the risk of extent of
power generated by Solar radiation,
DMRC preferred RESCO model.
MODEL SELECTED
In Feb 2014, Power Purchase Agreement
was signed with SEI Superior Pvt. Ltd.
(subsidiary of Sun Edison) for Dwarka
Sector – 21 Station.
Solar plant is operational from 27.06.2014
and has generated approx. 3.0 Lakh Units
in last Six Months.
AGREEMENT WITH SUN EDISON
THE TEAM WORK
Total Area:- approx 12,800 sq. mtr
Area used:- approx. 8000 sq mtr.
Installed Capacity:- 500 kWp
Solar Modules:- 1670 (300 W each)
Inverters :- 20Nos. of 20 kW (AC) each
Inverter Efficiency:- 98%
Nominal Generation:- 2200 units per day
Design Life of Plant:- 25 years.
SALIENT DETAILS OF PLANT
• From Roof top Solar Panels, AC power
has been transferred to Main Distribution
Board at Ground level in the Substation.
• Solar plant is synchronized with Grid.
• Inverter has a feature to ensure that first
the solar power is used, and additional
requirement is taken from grid.
• This ensures that all the solar power
generated is used.
GRID – CONNECTED PLANT
• Structures for solar modules placed without making a single hole on the roof.
• Structure designed to withstand a wind load of 200 kmph, which is rare in Delhi.
• Equipment to monitor sunlight, wind, temperature of site have been installed.
• Online monitoring of Power Generation (kW, kWh etc.) and weather parameters provided.
SOME IMPORTANT FEATURES
FIRST 500 KWp SOLAR POWER PLANT IN DWARKA SECTOR-21 METRO STATION
ONLINE MONITORING
• Structure Design was reviewed by DMRC
Civil Structure Design Cell.
• Quality Control of Material and at Site
Installation work.
• As per DMRC practice all protections for
Overload, Lightening surges and Earthing
have been provided.
• Plant Operation after EIG Clearance.
CHECKS BY DMRC
PLANT DEDICATED TO NATION on 11.08.14
By Hon’ble Minister for Urban Development
To formalize and channelize efforts,
Solar Policy was issued on 16.07.14.
Target of 20 MWp in 3 years.
DMRC SOLAR POLICY
Continuing with implementation of Solar
Policy following installations have been
recently completed:-
(a)Anand Vihar Metro Station:- 115 kWp
(b)Pragati Maidan Station:- 85 kWp
(c)Metro Enclave:- 50
kWp
TOTAL :- 250 kWp
SOLAR POWER PROJECTS IN DMRC
SOLAR PLANT AT ANAND VIHAR STATION
SOLAR PLANT AT PRAGATI MAIDAN STATION
SOLAR PLANT AT METRO ENCLAVE
• DMRC has been entitled as implementing
agency for National Solar Mission.
• Granted Central Financial Assistance of
Rs. 25.50 Crores (15% of Benchmark
Cost) for installing 20 MW.
APPROVALS FROM M.N.R.E.
DMRC has awarded work for Solar Plant of
1.5 MWp capacity at Yamuna Bank Depot.
Tenders for 7.0 MWp have been invited and
are due for submission next week.
For Balance Capacity, Tenders are likely to
be invited in March 2015.
WORK IN PROCESS
Bidders to Quote :-
1. Capital Cost,
2. Year – wise Tariff for 25 years.
Lowest Offer identified based on Levellised
Tariff with discounting rate of 11% per
annum (based on SECI’s Formula).
TENDER EVALUATION CRITERIA
TARIFF SHEET FOR DWARKA – 21
Year 1 2 3 4 5 6 7 8 9 10Tariff 6.0 6.0 6.0 6.2 6.3 6.5 6.7 6.9 7.1 7.3
Annuity Factor 1.00 0.91 0.83 0.75 0.68 0.62 0.56 0.51 0.47 0.42
Year 11 12 13 14 15 16 17 18 19 20
Tariff offered 7.5 7.7 7.9 8.1 8.4 8.4 8.4 8.4 8.4 8.4 Annuity Factor 0.39 0.35 0.32 0.29 0.26 0.24 0.22 0.20 0.18 0.16
Year 21 22 23 24 25
Tariff offered 8.4 8.4 8.4 8.4 8.4
Annuity Factor 0.15 0.14 0.12 0.11 0.10
Levellised Tariff 6.94
TARIFF COMPARISON
0
5
10
15
20
25
6 6 6.17 6.52 6.89 7.28 7.69 8.138.360000000000018.360000000000018.360000000000018.360000000000018.36000000000001 6.48 7.14 7.88 8.68 9.57 10.56
11.64 12.83
14.15 15.59
17.19 18.96
20.90
Tariff of Solar Power Grid Tariff #
YEAR
TARIFFS IN DIFFERENT PPAs
CAPACITY Subsidy Levelised Tariff
(Rs./ kWhr)
Tender By
500 kWp 30% 6.94 SECI
250 kWp 30% 6.0 SECI
1,500 kWp 15% 6.73 DMRC
250 kWp 30% 5.845 SECI
Salient Features of PPA
• Owner and Operator – Developer.
• Operation, Maintenance, Repairs,
Spares for 25 years by developer
• User has option to Purchase the plant.
• During system disruptions due to roof
repairs etc. interests of Developer
safeguarded by deemed generation
clause.
• Penalties for Delay in payment.
• Arbitration clauses.
• Present taxes to be borne by developer.
• Any new taxes by user.
• Default Clause of Power Producer
• Default Clause of Purchaser
• Force Majeure conditions.
Salient Features of PPA (Contd.)
Use Curved Roofs of Stations,
Strength of existing Structures,
Orientation not suited for Solar Power,
Power Block in Operational areas,
Developers lack experience with Metro,
Assimilation of Technology Upgrades in
PPA.
Reduction in CFA from 30 % to 15%.
CHALLENGES
This is just a beginning !!!
DMRC Ltd.Metro Bhawan,Fire Brigade LaneBarakhamba Road, New Delhi-110001
Thank You !!