U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT MISSOURI AREA OFFICE OVERVIEW Society of American Society of American Military Engineers (SAME) Military Engineers (SAME) June 11, 2008 Military Construction Briefing & Military Construction Briefing & Site Tour Site Tour Hosted by: Fort Leonard Wood Resident Office, Kansas City District, USACE Fort Leonard Wood Chapter Fort Leonard Wood Chapter
Society of American Military Engineers (SAME). Fort Leonard Wood Chapter. June 11, 2008. Military Construction Briefing & Site Tour Hosted by: Fort Leonard Wood Resident Office, Kansas City District, USACE. MCA Tour Timeline. Permanent Party Barracks Phase I. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Society of American Military Society of American Military Engineers (SAME)Engineers (SAME)
June 11, 2008
Military Construction Briefing & Site TourMilitary Construction Briefing & Site Tour
Hosted by:Fort Leonard Wood Resident Office,
Kansas City District, USACE
Fort Leonard Wood ChapterFort Leonard Wood Chapter
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
MCA Tour TimelineTime: Event:
11:30 – 11:45 Gather at Tech Park
11:45 - 12:00 Welcome Guests; Pick-up Box Lunches
12:00 – 12:25 MILCON Briefing
12:25 – 12:30 Safety Briefing, Issue Hard Hats
12:30-12:35 Walk to Permanent Party Barracks Site
12:35-12:55 Walk through Permanent Party Barracks
12:55-13:00 Walk Back to Tech Park and Release
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Permanent Party Barracks Phase II
Permanent Party Barracks Phase I
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
AgendaAgenda• Overview of USACE
• Overview of Current Challenges
• What is Important at FLW
• Current Project Summary at FLW
• Questions
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of USACE
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Northwest Division
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of KC District
-2 Area Offices
-7 Resident Offices
-18 Lakes
-2 Hydro Power Dams
-350 Structures on Mo River (Revetments, Wing Dikes, Levees)
Kansas City DistrictKansas City District
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of FLW Resident Office
KC Resident Office (8 Personnel)
WAFB Resident Office (9 Personnel)
MO Area Office (5 Personnel)
-Area Engineer / ACO w/ $500K Warrant
-Mechanical Engineer
-Electrical Engineer
-Office Manager & Secretary
FLW Resident Office (22 Personnel)
-Resident Eng. / ACO w/ $500K Warrant
-Deputy Resident Engineer
-Submittals Technician
-3 Office Engineers
-4 –Quality Assurance Teams
-1 – QA Rep at GLWACH
Kansas Area Office
Kansas City District – COL Wilson
-Engineering & Construction Division (E&C)
-PM Division
Northwest Division – COL Miles
Engineering & Construction Division (E&C)
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Current ChallengesOverview of Current Challenges
• Army moving into the most comprehensive restructuring since WWII– USACE is planning to execute $40 Billion of MILCON Construction
from 2006 – 2011– At FLW alone, our construction placement will increase from about
$40 Million a year to over $200 Million a year through FY 08 and FY 09
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Current ChallengesOverview of Current Challenges• The army is transforming and has immediate needs that
must be met to support BRAC and the GTA Programs as well as re-stationing initiatives:– The recently released Army Stationing Plan, for example, will add
approximately 74K new Soldiers to the Army over the next 2-4 years– This plan will also add 6 new BCTs and 8 new MEBs which will be disbursed
at various posts across the country– This plan also re-stations units formerly stationed overseas to CONUS
military bases– FLW for example is receiving approximately 3,000 plus additional trainees
this summer through the TRAPS program and is also receiving a FORSCOM MEB in October
• Creates Need for additional Barracks Bed Space, family housing, dining facilities, etc…)
• Creates Need for additional infrastructure (sewage, water, phone lines, roads, training ranges, parking, etc… to support influx of personnel)
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Current ChallengesOverview of Current Challenges
• The GWOT has created several unique demands:– USACE oversees massive construction programs supporting OIF and
OEF through the GRD and AED– On the home front, the army is also involved in improving living
conditions and programs for soldiers and families to take care of them and improve retention rates (Examples: improving housing, post facilities, Warrior in Transition Units, etc…)
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Current ChallengesOverview of Current Challenges
• To support these and many other programs, the army has a need for USACE to deliver projects faster and cheaper with more sustainable designs and without diminishing quality
• In order to stay relevant in meeting the Army’s needs, USACE is itself transforming and thinking outside of the box and changing its systems and ways of doing business– MILCON Transformation– At the local level, we are also doing a lot to stay relevant and
meet our immediate customer’s needs and expectations
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
What is Important at FLW?
• IET Soldier Bed Space (TRAPS Relocatables, TBUP, and Starship Barracks)
• Facilities for Future Combat Support Brigade
• Upgrading Post Infrastructure to support the large increase in facility demands (ie…sewer, roads, phones, etc…)
• Upgrading Ranges to support training for TRADOC and FORSCOM Units
• Supporting the installation’s Master Plan development and implementation
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
BT / OSUT & AIT Long Term Transition Plans
TRAPS Relocatables Rolling Pin Barracks – (Built 1950s to 1960s)
Specker Barracks (Built in 1970s)
Starship Barracks Complex
• Provide immediate bed space for BT and AIT Soldiers to meet Summer Surge / TRAPS Requirements
• Over the next 10-25 years, the installation wants to replace rolling pin barracks and Specker barracks with over 15 phases of Starship Complexes
Renovating through TBUP Program over next 4-8 years
Recently Renovated by CENWK-EC-MD
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Long Term Master Plan for
FLWN
• Segregate BCT, AIT, Permanent Party, and FORSCOM Zones of FLW
• ADPs are being developed in these areas by KC District
• Phases of implementation:
• Move non-applicable facilities out of zoned areas
• Renovate existing facilities while implementing long term plans to build new facilities
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
MILCON Projects: ($101.2M)
Project Name: Contract Completion Date:
Permanent Party Barracks - Phase I (The First of Five Phases Awarded) 21-Dec-07
Permanent Party Barracks - Phase II 25 Sep-08
Basic Combat Training Barracks Complex 31 Jan 10
Child Development Center 30 Jun 10
Current Project Summary - FLW
Photos of Permanent Party Barracks Phases I & II to Follow
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – Permanent Party Barracks Phase I
Permanent Part Barracks
– Phase I Completed
Photographs
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – Permanent Party Barracks Phase II
• 19 Additional Buildings currently under construction
• A third GTF Phase is to be awarded this spring to construct 27 additional barracks
• Phases IV and V are also being considered as potential supplementals in the Murtha Bill for FY 08
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
O&M Projects: ($95.1M)
Project Name: Contract Completion Date:
Specker Barracks Renovation - Phase II 30-Mar-08
Training Barracks Upgrade Program 828 & 829 due 6 Jun 08
TRAPS Relocatables 07 07 Apr 08
TRAPS Relocatables 08 15 Jun 08
Current Project Summary - FLW
Photos of Specker Barracks, TBUP, and TRAPS 07 Sites to Follow
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – Specker Barracks Renovation
Specker Complex
Interior Work Improved Appearance & Provided Adequate Airflow
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – TBUP Phase I
BKJ adding Bump out portion of Bldg 829
Bldgs 828 & 829 Must be turned back to FLW by 6 Jun 08
QA, George Edgington, conducts Initial Inspection of Block Shear Wall Construction
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – TBUP Phase I (Continued)
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – TRAPS 07
Major Setbacks in a 120 Day Contract include 1) Design Development & Review, 2) Permits, 3) Ordering and Delivering Trailer Units, 4) Obtaining Transformers
Interior Finishes of TRAPS 07 Barracks
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Projected FY08 Projects
Project Name:Acquisition Strategy:
FundingType:
New Double Dining Facility – GTF D-B MCA
Range 7 & 8 D-B-B MMCA
Combat Pistol Range D-B GTF
Multiple Purp. Machine Gun RNG D-B GTF
TBUP Renovation – Phase II D-B O&M
Permanent Party Barracks - GTF D-B GTF
Sewage Treatment Plant D-B
Unit Operations Facility D-B MCA
Chapel D-B MCA
Sapper Leader Course Design Directive D-B MCA
Upcoming Projects - FLW
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Projected FY08 Projects
Project Name:Acquisition Strategy:
FundingType:
Permanent Party Barracks – Ph. I D-B MCA
Permanent Party Barracks – Ph. IV D-B MCA
Consolidated TMC D-B MCA
94th EN BN HQ Complex D-B MCA
Company HQ Bldgs (times 2) D-B MCA
Vehicle Maintenance Shop D-B MCA
Upcoming Projects - FLW
* Note: There are about $87M in potential supplemental contracts. It is not looking at this point as though the Murtha Bill will include these supplementals, but this office is preparing to staff them in the event they are awarded.