SLC PHASE 2 ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING respect integrity innovation collaboration excellence 1 ALISDAIR ELLIOT – CONSTRUCTION MANAGER
Dec 18, 2015
SLC PHASE 2 ST KENNETHS PRIMARY SCHOOLPARENT COUNCIL MEETING
respect
integrity
innovation
collaboration
excellence
1ALISDAIR ELLIOT – CONSTRUCTION MANAGER
ST KENNETHS PRIMARY SCHOOL PARENT COUNCIL MEETING
SECT
ION
1
2.0 Project Overview & Images3.0 BLL Project Team & Logistics4.0 Current Progress & Phase 2 / 3 Transition5.0 Q & AClose
1.0 Introduction and Agenda
2
ST KENNETHS PRIMARY SCHOOL 2.1 Project Overview
Building: GIFA
ST KENNETHSPRIMARYSCHOOL
3569 m²
The project: This project is our fourth new-build primary school building to be constructed within Phase 2 Tranche 1 of the South Lanarkshire Primary Schools Modernisation Programme.
The Client: South Lanarkshire Council
The Contract: PPC 2000 (Partnering framework contract agreement)
Overview: The project comprises the tandem build construction of a new two-storey 16 classroom primary school. In addition to the classrooms, the building comprises private and main stream nurseries, a double gym hall, general purpose room, library and IT Suite. The new building is located within the existing school campus, formerly the location of the existing sport pitch and car park. The works are being carried out in two phases to allow the existing school to operate whilst the new building is under construction. On completion of the new school building the users will decant from existing to new allowing progression into phase 2 where the scope is to remove asbestos from the existing school, demolish the building, complete the sports pitch and finish the hard and soft landscaping.
Construction: The construction of the primary school is a steel frame structure with holorib decking topped with a concrete floor slab on pads/strip foundations. The building will have predominantly a facing brick outer leaf with areas of metal cladding and curtain walling on the elevations. The roof will be an aluminium standing seam roof throughout.
Internally, underfloor heating has been incorporated throughout the building with fit out specification aligning with other projects in the programme.
Externally, the scheme includes external hard and soft landscaping and lighting design scheme complete with a standard 60 x 40 metre sports pitch, car parking / pupil drop off with playground & soft play areas around the school/nursery. 4
ST KENNETHS PRIMARY SCHOOL 3.0 PROJECT TEAM / SITE LOGISTICS
SECT
ION
3 3.0 Project Team & Site Logistics
3.1 BLL Design Team3.2 BLL Construction Team3.3 Site Logistics
6
ST KENNETHS PRIMARY SCHOOL 3.1 BLL Design Team
Structural EngineerCost Consultant Services EngineerArchitect
This is the design team engaged upon the St Kenneth’s Primary School Project
7
ST KENNETHS PRIMARY SCHOOL3.2 BLL Construction Team
TRACEY-LEIGH FINDLAYFramework Commercial Manager
ANDY STRONACHFramework Manager
TOM CAIRNEYFramework
Safety Manager
BARRY O’HAGANFramework Delivery Manager
OMAR AHMED WAZIRPlanning Manager
Alisdair ElliotConstructionSite Manager
CO
RE
TEA
MD
ELIV
ERY
TEA
M
GORDON ANDERSONRegional Director
DES
IGN
TEA
M
ED PARRYCommercial Director
EMMA ROBBCommercial Manager
Michael McMullanConstruction
Manager (Part)
TBCFinishes Construction
Manager (Part) 8
ST KENNETHS PRIMARY SCHOOL 3.0 PROJECT TEAM / SITE LOGISTICS
SECT
ION
4 4.0 Programme
4.1 Current Progress4.2 Phase 2 / 3 Transition
13
ST KENNETHS PRIMARY SCHOOL 4.1 Current Progress
Works on site at present comprise the following:
External Works
•External Brickwork
•Curtain Walling Windows and Doors
•External Cladding
14
PROGRESS
Bovis Lend Lease are currently reporting works on programme with all works due for completion 23/07/10
ST KENNETHS PRIMARY SCHOOL 4.1 Current Progress
Internal Works
•Interior Fit Out (Joinerwork, floor finishes, suspended ceilings)• •Mechanical & Electrical Installation
•Architectural Metalwork
•Decoration
•Gym Fit Out
15
ST KENNETHS PRIMARY SCHOOL 4.2 Phase 2 / 3 Transition
Demolition of the existing school is scheduled to be completed during November 2010. Following which BLL will install synthetic sports pitch and carry out further hard and soft landscaping works
BLL are scheduled to complete all Phase 3 works during January 2011
BLL are intending to use the existing delivery entrance of East Mains Road to service the Phase 3 works
16
Bovis Lend Lease are scheduled to take possession of the Phase 3 site on the 30 July 2010 and commence preparation works for demolition of the existing school.