Assignment 2:

Site report

Submission date:

6th December 2013

Place:

Symphony Hill, Cyberjaya

Group Member:

Ng Wei Lin 0316302

Page 2: site report.docx

8/13/2019 site report.docx

http://slidepdf.com/reader/full/site-reportdocx 2/10

Objectives

1)  To know the type of the building that demanded in current market

2)  To know the construction flow of a project

3)  To experience the life of being a future quantity surveyor

4)  To deepened the knowledge of building material used  in current construction

 practice

5)  To learn the innovation and creativity of material used in the project

6)  To understand the design idea of the project

7)  To understand the application of calculation in measurement

8)  To observe the behavior of the work being done

9)  To apply the knowledge that we learned from the book10) To learn the application of different structural used in the project in current

construction practice.

Page 3: site report.docx

8/13/2019 site report.docx

http://slidepdf.com/reader/full/site-reportdocx 3/10

Introduction

On 0835h, the bus start to travel to a site located in Cyberjaya. As the traffic was in good

condition, the bus driver took around 30 minutes to travel to a site named Symphony Hill,

Cyberjaya.

On 0920h, when the bus reached the entrance of guard house of Symphony Hill, we were

surprised that we were going to visit such large project. After some sort of arrangement,

we walked to the main office to understand the project briefly. The office is exhibiting

the 3D model of the house that they offered and the master plan of this area.

On 1000h, the project manager, En Md Umar Sabtu and the core engineer, En Zu of this

 project introduced their experiences and emphasized the safety precaution. He explained

that we were going to visited Mozart and had completed about 90 %. After 10 minutes,we started our journey to the site with the white color heavy safety helmet.

Symphony Hill is built with the concept of club house which is facilitated with various

facilities such as swimming pool, gymnasium room, tennis room and concierge service.

Mozart is one type of residence area with the theme of garden link terrace house. It is

categorized to Type A with 34units, Type B with 84 units and Type C with 4 units which

are in different sizes.

After 60 minutes of visit, we took our way back to Taylor. Before we left, we said thank

you to two core person of the project by spending their time brought to explain the site

condition to us.

Page 4: site report.docx

8/13/2019 site report.docx

http://slidepdf.com/reader/full/site-reportdocx 4/10

Content 

On 0900h, we reached the entrance of the project thathad to visit. They used temporary fencing covered with

yellow color sheet to separate the main road and the

construction place to prevent the unauthorized access

to the site. En Md Umar Sabtu, the project manager

and En Zu, the engineer was introducing the project to

us briefly. He said that the project had completed

around 90% and 10% more to work on and estimated

to complete on 2014.

After knowing the main focus of us were in

foundation, formwork, reinforcement bar, and

column, En Umar, brought us to a place that

surrounded by houses. He explained that the type of

foundation used is pad footing. It is the only place

that using pad footing as foundation. Beside of the

 pad footing, raft foundation was constructed on most

of the area. Due to the consideration of the cost as

well as the soil condition, they decided to build the

combination of pad and raft foundation as the

foundation to solve the different settlement of the

soil. Moreover, he told us the way of waste water

 process to the drainage system.

Page 5: site report.docx

8/13/2019 site report.docx

http://slidepdf.com/reader/full/site-reportdocx 5/10

 Then, the engineer lead us to another place take took 5 minutes distance. The place is the

temporary storage of the different diameter of the reinforcement bar and the bricks. There

is also a place that the workers accommodate and the shelter for the workers. After all of

us gathered in the this place, the workers started to move the engine of the external

genarator to show us the reinforcement bar bending process. The engineers also showed

us the freshly bent stirrup and told us to used 5D formula to calculate the bent for the

stirrup.

On the way to the 3rd

  place, we passed by the putlog scaffold and the independent

scaffold. Our sight were attracted by the workers which were tiring and placing the H

shaped reinforcement bar to form a cage. While the truck crane was lifting up the

insulation to a upper level. The cement tanker truck was mixing the cement.

Page 6: site report.docx

8/13/2019 site report.docx

http://slidepdf.com/reader/full/site-reportdocx 6/10

 

After that, we proceeded to a fully furnished garden link terrace house, we entered into a

upper floors balcany with the concept private. We saw lines tiring with a tiny strings and

the bricks were arranged tidying beside the beams. According to Ms Ang, the lines are

used to form the straight line when constructing the wall while the gray brcks were the

 preparation work for the workers to construct the wall.

Page 7: site report.docx

8/13/2019 site report.docx

http://slidepdf.com/reader/full/site-reportdocx 7/10

My observation/photo

They used the combination of clay brick and red brick because clay bricks are much more

cheaper than red bricks but are not suitable for load bearing wall while red bricks are

used to construct the load bearing wall.

They are using silt fence that is reusable as the temporary

fencing for the construction site to prevent unauthorized

access to the site.

According to Ms Ang, 2T16 diameter reinforcement bar is beingfixed at each edges of the formwork.

Page 8: site report.docx

8/13/2019 site report.docx

http://slidepdf.com/reader/full/site-reportdocx 8/10

 Picture below is showing the formwork for the wall.

The only precast part in this project is the drainage

according to the engineer.

This is the dogleg staircase with a wood handrail and supports by

steel. The material using for this staircase is glass baluster as it

created the feeling of modernity.

Unglazed mosaic tile is being applied in building for

the swimming pool and stain steel handrail with

 building a glass baluster are used to prevent rusting

when contact with water.

Page 9: site report.docx

8/13/2019 site report.docx

http://slidepdf.com/reader/full/site-reportdocx 9/10

 

The type of roof using is the shed roofing.

Reinforced concrete wall was constructed on site.

Temporary material storage in the house. The wall

is constructed by tiles.

Page 10: site report.docx

8/13/2019 site report.docx

http://slidepdf.com/reader/full/site-reportdocx 10/10

Conclusion

We really feel lucky and excited have the opportunity to visit a real site in this semester.

We appreciate the time on site that helped me on imagination during the learning process

in the future. It also helped me to deepen the knowledge in construction area and the

 behavior of doing things.

As time is essence, the works were done part by part by the worker. The workers are

skilled and could bend different diameter of bents without using ruler. For us, the

construction site is considered a dangerous and muddy place, as we have observed every

step before I walked to avoid unnecessary injured.

Lastly, thank you to Ms Ang’s arrangement to a s ite visit and we have gained a lot of

knowledge with the explanation of the Ms Ang, En Umar and En Zu. We hope to visit

more sites in the coming semester.