Site Prepared under for plantation under Preparation 1 st Site Developed for Plantation near PEPSI 1
3

Site Prepared under for plantation under Preparation

Jan 17, 2016

Download

Documents

malise

1 st Site Developed for Plantation near PEPSI. Site Prepared under for plantation under Preparation. Before After. (Compound wall made by NIA protect sapling). Schematic plan for Plantation at Naroda GIDC Plot next to PEPSI. Entry. 25 mtrs. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Site Prepared under for plantation under Preparation

Site Prepared under for plantation under

Preparation

1st Site Developed for Plantation near PEPSI

1

Page 2: Site Prepared under for plantation under Preparation

Before After(Compound wall made by NIA protect sapling)

2

Page 3: Site Prepared under for plantation under Preparation

25 mtrs

600

mtr

s

Plantation to be done at 4 x4 mt spacing, in four rows. With every 4th to be a Neem tree

We shall try get below from Director of Garden & Timber Merchant Association

Qty of Plantation that can be done– ( 1450-sapling, 700 creeper)

•125# Pinkeshia•125# Peltoforum•125# Gulmohar•125# Raintree•125# Neem•700# Bogun creeper•700# Karen

We shall also try to get •Ficus religiosa (Pipul)•Timber plant

Schematic plan for Plantation at Naroda GIDC Plot next to PEPSI

Entry

Entry

Sapling

Creeper

3