Top Banner
Site Practice Concrete Construction Alistair Russell
74

Site Practice

Jan 01, 2017

Download

Documents

vophuc
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Site Practice

Site Practice

Concrete Construction

Alistair Russell

Page 2: Site Practice

• Site practice affects finished product

• Handling & placing• Compaction & finishing• Curing• Cracking & expectations• Joints & tolerances

26 March 2015 Concrete Construction - Site Practice 2

Site Practice

Context: Concrete slabs

Page 3: Site Practice

• We have 4 courses on offer including a 2-day course devoted to just this topic – we can’t do that in 1 hour!

• Guide to Concrete Construction book –free

• Best practice video on YouTube – free

26 March 2015 Concrete Construction - Site Practice 3

CCANZ Courses

Page 4: Site Practice

• Starts as soon as concrete discharged from truck – 1st step in concrete’s life

• Move as quickly & efficiently as possible• Workable, without segregation – balance

26 March 2015 Concrete Construction - Site Practice 4

Handling & Placing

Page 5: Site Practice

• Get this right and the life of the structure will go well

• Get this wrong, and your life will not go well –compaction etc &remediation, cost…

26 March 2015 Concrete Construction - Site Practice 5

Handling & Placing

Page 6: Site Practice

26 March 2015 Concrete Construction - Site Practice 6

Primary Considerations

• Workability basically means how easy concrete is to use – and place

• More water = more workable

• Generally “runnier” concrete is easy to useTOO RUNNY = SEGREGATION

• Long term performance

Page 7: Site Practice

• Workability related to nature of job– Thin forms – more

workable concrete– Mass sections – less

workability required– Concrete pumps –

require a plastic and cohesive mix

26 March 2015 Concrete Construction - Site Practice 7

Workability (slump)

Page 8: Site Practice

• Avoiding Segregation• Aiding Compaction

• Correct term is “placing” not “pouring”– Implies some control over process

26 March 2015 Concrete Construction - Site Practice 8

Placing

Page 9: Site Practice

26 March 2015 Concrete Construction - Site Practice 9

Avoiding Segregation

Flatwork

General Principles• Whatever method,

place without delay• Deposit in face

already poured• Slopes-start at

bottom

Page 10: Site Practice

• Chutes• Barrows• Crane & skip or Bucket/skip• Pumps and Pipelines

• Concrete must be uniform and delivered at appropriate rate – x m3/hour

26 March 2015 Concrete Construction - Site Practice 10

Distribution Methods

Page 11: Site Practice

26 March 2015 Concrete Construction - Site Practice 11

Pumps and Pipelines

Page 12: Site Practice

• Specialised pumping operations• Notify concrete supplier of method of

placement – NZS 3109, 6.2• Pump mixes

– High slump– High(er) shrinkage– Not great off-form finish

26 March 2015 Concrete Construction - Site Practice 12

Pumps and Pipelines

Page 13: Site Practice

• Often compaction and finishing are part of the same operation– Often for flat work – flat horizontal surfaces

• Remember a smooth surface is not necessarily evidence of good compaction

26 March 2015 Concrete Construction - Site Practice 13

Compaction & Finishing

Page 14: Site Practice

26 March 2015 Concrete Construction - Site Practice 14

Compaction

Page 15: Site Practice

• Compaction enables concrete to reach:– Design strength– Density– Low permeability– Specified surface finish

• Compaction sometimes merges into finishing

26 March 2015 Concrete Construction - Site Practice 15

Compaction

Page 16: Site Practice

• Expel entrapped air• Pack aggregate particles• Increase

– Reinforcement bond– Ultimate strength– Abrasion resistance– Durability

• Minimise shrinkage and cracking

26 March 2015 Concrete Construction - Site Practice 16

Purpose of Compaction

Increases density

Page 17: Site Practice

• 2 stage process– Liquefaction occurs quickly– Expelling entrapped air more slow

• Compaction is complete when no more air bubbles rise to surface

26 March 2015 Concrete Construction - Site Practice 17

Process of Compaction

PROCESS: Liquefaction of the concrete which allows it to slump and fill the form

TIME: 3 to 5 seconds

PROCESS: The expulsion of air

TIME: 7 to 15 seconds

. Total time: 10-20 seconds

Page 18: Site Practice

26 March 2015 Concrete Construction - Site Practice 18

Effect on Hard Concrete

Page 19: Site Practice

26 March 2015 Concrete Construction - Site Practice 19

Finishing

Page 20: Site Practice

• While concrete is still plastic:– Levelling– Floating– Trowelling– Other treatments

• Purpose of finishing is to achieve:– Level or specified profile– Flatness– Surface density and texture

26 March 2015 Concrete Construction - Site Practice 20

Flatwork Finishing

Page 21: Site Practice

1. Screeding – hand/timber/mechanical screed

2. Floating– To level surface– Compact surface layers

3. Trowelling– To produce smooth, hard and durable

surface & densify surface

26 March 2015 Concrete Construction - Site Practice 21

Flatwork Finishing

Page 22: Site Practice

26 March 2015 Concrete Construction - Site Practice 22

Screeding

Page 23: Site Practice

• Even but open surface texture– Embed large particles– Remove imperfections– Compact and consolidate fines at surface– Close minor cracks

• When bleed water stops• Must be able to stand on concrete – minor

indentations

26 March 2015 Concrete Construction - Site Practice 23

Floating

Page 24: Site Practice

• Bull floating• Hand floating• Machine floating

26 March 2015 Concrete Construction - Site Practice 24

Floating

Page 25: Site Practice

• Final surface treatment– Working the surface– Compact top surface

• Delay between floating and trowelling– Stiffening of concrete

• Smoothness, density & wear resistance

26 March 2015 Concrete Construction - Site Practice 25

Trowelling

Page 26: Site Practice

• Flat blade – don’t create ripples• Subsequent trowels tilt the blade

– Once concrete is firm enough

• Blisters mean blade is too pitched• Blisters reduce durability + ugly

26 March 2015 Concrete Construction - Site Practice 26

Trowelling

Page 27: Site Practice

26 March 2015 Concrete Construction - Site Practice 27

Trowelling

Hand trowellingShould give a ringing sound

Machine trowellingRegular pattern

Hand trowel in corners

Page 28: Site Practice

26 March 2015 Concrete Construction - Site Practice 28

Trowelling

Page 29: Site Practice

26 March 2015 Concrete Construction - Site Practice 29

Trowelling

Page 30: Site Practice

• Footpaths, patios, paths & steps• Not in industrial floors – need crisp edge

26 March 2015 Concrete Construction - Site Practice 30

Edging

Page 31: Site Practice

26 March 2015 Concrete Construction - Site Practice 31

Curing

Page 32: Site Practice

• Cement hydration – chemical reaction– Requires water– Takes days, weeks– Starts fast, gets slower, will continue (forever)

• Curing – process of controlling loss of moisture– Allows time for hydration to occur

26 March 2015 Concrete Construction - Site Practice 32

Curing

Page 33: Site Practice

• Prevent loss of moisture– Leave formwork in place– Cover with impermeable membrane

• Continuously wetting surface– Ponding– Spraying

26 March 2015 Concrete Construction - Site Practice 33

Curing

Page 34: Site Practice

• Impermeable Membrane– Formwork– Plastic sheeting

• Water– Ponding– Sprinkling*

– Wet coverings• Accelerated curing

26 March 2015 Concrete Construction - Site Practice 34

Methods of Curing

*Water blaster spraying upwards into wind

Page 35: Site Practice

• Comprehensive physical barriers not always practical/economical

• Curing Compounds achieve same resultsSika Antisol®

• Apply after bleed water stops

• Be aware of coatings– Wax based – no painting– Resin based – ok to paint (acrylic)

26 March 2015 Concrete Construction - Site Practice 35

Curing Compounds

Page 36: Site Practice

• For appearance or function• Surface treatments depends on:

– Traffic & frequency– Chemicals– Impact loads

• Warehouse floors with steel wheel loads (forklifts) – high strength concrete– Specified by designer– Proper compaction, finishing and curing

26 March 2015 Concrete Construction - Site Practice 36

Surface Treatments

Page 37: Site Practice

• Densifiers – for polishing floors

26 March 2015 Concrete Construction - Site Practice 37

Polished Floors

Page 38: Site Practice

• Slip – for pedestrians• Skid – for wheels

• NZS 3114 defines surface finishes• F – Formed finish (from formwork)• U – Unformed finish (exposed to air)

26 March 2015 Concrete Construction - Site Practice 38

Slip & Skid

Page 39: Site Practice

• Slip – for pedestrians• Skid – for wheels

• NZS 3114 defines surface finishes

26 March 2015 Concrete Construction - Site Practice 39

Slip & Skid

F1 F6

Page 40: Site Practice

• Slip – for pedestrians• Skid – for wheels

• NZS 3114 defines surface finishes

26 March 2015 Concrete Construction - Site Practice 40

Slip & Skid

U2 U5

Page 41: Site Practice

• Examples U3 Trowelled Finish– Gradual variations limited to a maximum of 5

mm.– Abrupt variations limited to a maximum of 3

mm.

26 March 2015 Concrete Construction - Site Practice 41

Floor Tolerances

Page 42: Site Practice

Formed Finish Classification Hot Conditions

> 20°

AverageConditions≤ 20° > 12°

Cold Conditions≤ 12° > 5°

Beam and slab soffits

Forms 4 days 6 days 8 days

Supporting members (shores or backprops)

12 days 18 days 24 days

Vertical faces Finishes F6, F5, F4

1 day 2 days 3 days

Finishes F3, F2, F1

9 hours 12 hours 18 hours

A minimum of 2 days applied to the stripping of vertical faces where frost damage is likely.

26 March 2015 Concrete Construction - Site Practice 42

Formwork Removal

Table 5.3 NZS 3109 – minimum formwork stripping times for in situ concrete

Page 43: Site Practice

26 March 2015 Concrete Construction - Site Practice 43

Other Finishes

Exposed Aggregate

Brushed

Sand Blasted

Polished

Page 44: Site Practice

Exposed Aggregate

• Natural rounded coarse aggregate– Not quarried rock (too

jagged)• Chemical retarder on

surface– Apply after bleed stops– Before setting

• 20MPa (not 17.5MPa)– Reduces stone loss

26 March 2015 Concrete Construction - Site Practice 44

Page 45: Site Practice

Exposed Aggregate

• Surface retarder – e.g. Sika Rugasol®

• Delays hydration of cement for 3-6mm depth

• Garden sprayer• Uniform coverage is

essential• Retardation period ≤ 24h

– Wash off prior to set– Wash low pressure

26 March 2015 Concrete Construction - Site Practice 45

Page 46: Site Practice

Cracks in Concrete• Concrete has low tensile strength

0 – 24 hours - plastic shrinkage cracksprevent rapid moisture loss- plastic settlement cracksrevibrate concrete- thermal movement cracksuse low heat mix (eg flyash)

7 days – 2 years - restrained shrinkage crackingadequate reinforcingdetailing of movement joints

26 March 2015 Concrete Construction - Site Practice 46

Page 47: Site Practice

• Fill – well compacted and even• Control joints

– Saw cuts initiate cracking– 12–18 hours after finishing– Insert crack inducer

• Joint layout – 5m between (6m in NZS3604)

– Align with walls where possible– Square bays are best

26 March 2015 Concrete Construction - Site Practice 47

Crack Avoidance

Page 48: Site Practice

26 March 2015 Concrete Construction - Site Practice 48

Page 49: Site Practice

• Contraction Joints

• Expansion Joints

26 March 2015 Concrete Construction - Site Practice 49

Joints

Concrete shrinks 6 – 10mm per 10m length

Page 50: Site Practice

26 March 2015 Concrete Construction - Site Practice 50

Contraction Joints

Page 51: Site Practice

• Oxides – most coloured concrete– Mixing is important

• Spray on coloured compounds– Can fix as you go– Less durable

• Coloured concrete usually doesn’t affect the strength

26 March 2015 Concrete Construction - Site Practice 51

Coloured Concrete

Page 52: Site Practice

26 March 2015 Concrete Construction - Site Practice 52

Colouring Oxides

Page 53: Site Practice

• Powdered or liquids– Penetrate all through the concrete– Add to mixing concrete

• Peter Fell• Permacolour NZ• Rockwood – Elements and Atmospheric range

• Part of the specification• Seek expert advice• Beware multi-batch variations

26 March 2015 Concrete Construction - Site Practice 53

Colouring Oxides

Page 54: Site Practice

[email protected]

• IB 18: Architectural Surface Finishes• IB 33: Specification and Production of Concrete

Surface Finishes• IB 86: Self-Compacting Concrete

• CCANZ Concrete Construction Course 8-9 September, Auckland

www.ccanz.org.nz

26 March 2015 Concrete Construction - Site Practice 54

Further Reading

Page 55: Site Practice

Site Practice

Concrete Construction

Alistair Russell

Page 56: Site Practice

Baldev Kesha

Concrete Mix designs and Applications

Page 57: Site Practice

Concrete Standards

• NZS 3101 Concrete Structures- A Standard for designers

• NZS 3109 Concrete Construction- Should be on every job site outlines good construction practice.

• NZS 3104 Specification for Concrete Production-Outlines the quality controls rules for producing concrete.

• NZS 3121, NZS 3122, AS1478, Quality of materials which are use to make concrete

• NZS3111, NZS3112 Method of conducting tests to prove properties

57

Page 58: Site Practice

Basic concrete materials

• Portland – cement reacts with water to provide strength

• Sand (fine agg) – provides cohesion & workability

• Stone (coarse agg) – provides stiffness and limits movement

• Mixing water – provides lubrication and hydrates cement

58

Page 59: Site Practice

Chemical Admixtures

• Water reducers – improve dispersion and cut water content

• Air-entrainers – create micro-bubbles that improve

workability

• Accelerators – increase chemical reaction & reduce setting

time

• Retarders – decease chemical reaction & increase setting

time

• Pump aids – stabilisers that increase viscosity of concrete

• Shrinkage – reduce drying shrinkage of concrete

• Others – corrosion inhibitors, expansive agents, foamers59

Page 60: Site Practice

Supplementary Cementitious Materials (SCM’s)

• Flyash, fine ash from burning coal, supplied by GBC from Huntly.

• GGBS, Ground Granulated Blast Furnace Slag. Waste product from iron manufacture. Sold as Duracem as a Slag/GP blend 65/35.

• Microsilica- very fine natural silica sold by GBC.

All improve the durability of concrete but have differing characteristics.

60

Page 61: Site Practice

Other Materials

• Recycled slurry water: – Increasing plants are reusing washing water in concrete rather than disposing

• Steel and synthetic fibres:– Increasing demand for fibre reinforcedconcrete in floor slabs, tunneling & mining

• Surface treatments, pigments – Aesthetics of concrete is critical for somearchitectural projects

61

Page 62: Site Practice

Components of Concrete

62

Page 63: Site Practice

Concrete performance

63

Fresh propertiesFirst 6-10 hours

Hardened propertiesNext 50-100 years

WorkabilityBleedingPumpabilityFinishabilitySetting time

StrengthDurabilityStabilityAesthetics

Performance

Page 64: Site Practice

Components of Concrete

64

Page 65: Site Practice

Concrete performance

65

Fresh propertiesFirst 6-10 hours

Hardened propertiesNext 50-100 years

WorkabilityBleedingPumpabilityFinishabilitySetting time

StrengthDurabilityStabilityAesthetics

Performance

Page 66: Site Practice

Displays

66

Page 67: Site Practice

Making Samples

67

Kerikeri Stone Store – Historicalsite

Fontera – ColaberationInternal and External finishesClient, Architect, Interior Designer, Landscape Architect,Main contractor, Placer

We will endeavour to find a suitable site to view

Page 68: Site Practice

Muriwai Atmospheric Black

68

Page 69: Site Practice

Silverdale Shopping Centre –Concrete tells a History story

69

Page 70: Site Practice

Waikato University

70

Page 71: Site Practice

Speights Ale House - Nelson

71

Page 72: Site Practice

ASB Black Polished Floor

72

Page 73: Site Practice

Tait - Christchurch

73

Page 74: Site Practice

Thank you

74