7/29/2019 Site Observation Report Sample
1/6
Date: 26/02/2013
Observation of Status of Escalator and Lift Works:
12 nos escalator not yet commence installation at sector 2 4 nos lift not yet commence work at sector 2
Item Location Observation Note
1.
S2 L3 GL: 23/G2
Glass Lifts S2-PL4 & S2-PL5
Assembly of lifts yet to commence awaiting erection of steel structure.
Civil WorksConstruction of Level 3bfloor which is above the lift locations is
yet to complete i.e. installation of lifts isnot possible.
Escalator S2-ESC6
Escalator assembled and ready forinstallation. The possibility of the
intermediate beam obstructing the erection
of the escalator is yet to be confirmed.
2.
S2 L3 GL: 21-22/F
Service Lift S2-SL-5
Assembly of lifts yet to commence. Civil WorksConstruction of the lift core
is yet to commence.
3.
S2 L3 GL: 19a/F-G1
Escalator S2-ESC1
Escalator length is about 800mm longerthan the length between the landings.
JV yet to resolve the discrepancy.
7/29/2019 Site Observation Report Sample
2/6
Item Location Observation Note
4.
S2 L3 GL: 22-23/F
Escalator S2-ESC8
Escalatorassembled and ready forinstallation.
Civil Work- Insufficient width at upperlanding. No action yet to rectify the
problem.
5.
S2 L3 GL: 23-24/F
Escalator S2-ESC9
Escalatorassembled and ready forinstallation.
Civil WorkInsufficient width at lowerpit and insufficient width at upper landing.
No action yet to rectify the problem.
6.
S2 L2 GL: 21-22/B
Escalator S2-ESC3 & S2-ESC4
Escalatorassembled and ready forinstallation.
Civil WorkSize of pits are not adequate.No action yet to rectify the problem.
7/29/2019 Site Observation Report Sample
3/6
Item Location Observation Note
7.
S2 L3 GL: 24-25/B-C
Vehicle Lift S2-VL1
No access from Level 3 to Lift MotorRoom.
8.
S2 L3 GL: 25/F
Passenger Lift S2-PL6
Assembly of lifts yet to commence. Civil WorksConstruction of the lift core
is to be expedited.
9.
S2 L2 GL: 26-27/G2-H
Escalators S2-ESC10, S2-ESC11, S2-
ESC13 & S2-ESC14
Escalatorassembled and ready forinstallation.
Civil WorkMismatched of lengthsbetween landings and lengths of
escalators.
7/29/2019 Site Observation Report Sample
4/6
Item Location Observation Note
10.
S2 L2 GL: 25-26/G-G1
Escalators S2-ESC12
Escalatorassembled and ready forinstallation.
Civil WorkCorridor wall obstructing theinstallation of the escalator. Pit yet to be
constructed. No action yet to rectify theproblem.
11.
S2 L3 GL: 25-26/G1-G2
Escalators S2-ESC7
Escalatorassembled and ready forinstallation.
Civil WorkIntermediate beamobstructing the erection of the escalator.
No action yet to rectify the problem.
12.
Passenger Lift S2-PL7 & S2-PL7
Water tightness problem interruptinstallation of lift equipments inside the
lift cores.
7/29/2019 Site Observation Report Sample
5/6
Item Location Observation Note
13.
S2 L2 G/L: 27a/G-F
Escalators S2-ESC7
Installation work commence today.
7/29/2019 Site Observation Report Sample
6/6
Date: 26/02/2013
Observation of Status of Escalator and Lift Works:
4 nos escalator installation is in progress at sector 6 2 nos glass lift steel structure works are in progress at sector 6
Item Location Observation Note
1.
S6 L2 G/L: 22a/J1a
Escalators S6-ESC1 (cover with plastic
sheet)
Installation - work in progress Power Supplyoutstanding cabling work
Glass Lift S6-PL1
Steel Structure work in progress Installation of lift in progress
2.
S6 L2 G/L: 22a/J1a
Escalators S6-ESC2 (cover with plastic
sheet)
Steel Structure work in progress Power Supplyoutstanding cabling work
Glass Lift S6-PL2
Steel Structure work in progress Installation of lift in progress
3.
S6 L2 G/L: 22b-23b/H4-H6
Escalators S6-ESC3 & S6-ESC4
Work in progress