Top Banner
A REPORT ON SUMMER TRAINING AT PRAGATI POWER CORPORATION LIMITED (A GOVERNMENT OF NCT DELHI UNDERTAKING) SUBMITTED TO TRAINING INCHARGE INDRAPRASTHA POWER GENERATION LIMITED & PRAGATI POWER CORPORATION LIMITED SUBMITTED BY AAKASH SINGH SENGAR (B.TECH PSE) ABHIJEET SHARMA (B.TECH PSE) AMAY JAIN (B.TECH PSE) GAURAV BALANI (B.TECH PSE) UJJWAL ANAND (B.TECH ENERGY TECHNOLOGY)
32
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SIP_Final_1

A REPORT ON

SUMMER TRAINING AT

PRAGATI POWER CORPORATION LIMITED

(A GOVERNMENT OF NCT DELHI UNDERTAKING)

SUBMITTED TO

TRAINING INCHARGE

INDRAPRASTHA POWER GENERATION LIMITED

&

PRAGATI POWER CORPORATION LIMITED

SUBMITTED BY

AAKASH SINGH SENGAR (B.TECH PSE)

ABHIJEET SHARMA (B.TECH PSE)

AMAY JAIN (B.TECH PSE)

GAURAV BALANI (B.TECH PSE)

UJJWAL ANAND (B.TECH ENERGY TECHNOLOGY)

Page 2: SIP_Final_1

A C K N O W L E D G E M E N T S

This project involved the collection and analysis of information from a wide variety of

sources and the efforts of many people beyond us. Thus it would not have been

possible to achieve the results reported in this document without their help, support

and encouragement. We would like to express our gratitude to the following people

for their help in the work leading to this report: Mr. K.S. Yadav (Deputy General Manager (Mechanical)) Mr. Sudhir Kumar (Manager – Technical (Electrical II)) Mr. Arvind Kumar Singh (Deputy Manager- Technical (Electrical

II)) Mr. Ashish (Deputy Manager- Technical (Electrical II) BOP

Unit) Mr. Vijay (Circuit Breaker Unit)

Page 3: SIP_Final_1

BRIEF PROFILE OF THE COMPANY: Pragati Power Corporation Limited is an undertaking of Government of NCT of Delhi. It was

incorporated on 9th January, 2001 to undertake power generation activities for supplying power to Delhi.

It is one of the leading Undertakings of GNCTD, generating profits since inception and paying dividends

regularly. It is presently having capital base of 2,019 crores and asset base of 3,319 crores. The

projected asset base and revenue income of Company in the near future are 6,000 crores and 5,000

crores respectively. The first project undertaken by the company was 330 MW gas based CCGT which

was fully commissioned in the year 2003-04. The station is presently operating at above 85% availability.

PPCL is presently setting up a 1500 MW Gas Based CCGT plant at Bawana in North-West Delhi to

augment the power generation at Load-Centre. Project is expected to fully commission by July 2011.

PPCL is also proposing to put up a 750 MW Gas Based CCGT at Bamnauli in South-West Delhi. The

project is expected to be commissioned in the year 2013-14. VISION:

To make Delhi-Power Surplus. MISSION:

To maximize generation from available capacity.

To plan & implement new generation capacity in Delhi.

Competitive pricing of our own generation.

To set ever-so high standards of environment Protection.

To develop competent human resources for managing the company, with good standards.

COMBINED CYCLE POWER PLANT:

Combined Cycle Power Plant (CCPP) or Combined Cycle Gas Turbine plant (CCGT)

A gas turbine generator generates electricity and heat in the exhaust is used to make steam, which

in turn drives a steam turbine to generate an additional electricity.

In CCPP, a successful common combination is the Brayton cycle (in the form of a turbine

burning natural gas) and the Rankine cycle (in the form of a steam power plant).

The gas turbine is comprised of three main components: a compressor, combustor and a turbine.

The air is, compressed in the compressor (adiabatic compression-no heat gain or loss), then mixed

with fuel and burnt by combustor under constant pressure conditions in the combustion chamber.

The resulting hot gas expands through the turbine to perform work (adiabatic expansion).

FUEL: The primary fuel for gas turbine is natural gas being supplied by M/s GAIL through HBJ pipe line. The gas is

received at GAIL Terminal installed in the vicinity of the power station. M/s GAIL is committed to supply

1.75 MCMD of gas on daily basis at a pressure of 20 kg per sq. cm. The caloric value of natural gas being

received for power generation is in the band of 8200-8500 kilocalories. The secondary fuel for gas

Page 4: SIP_Final_1

turbine is HSD/Naptha, which is used in case no gas supply is available. Demineralized water is injected

to control NOx. While machine is operated on Liquid fuel i.e. HSD/Naptha.

A. MECHANICAL EQUIPMENTS:

1. HEAT RECOVERY STEAM GENERATOR (HRSG):

The Heat Recovery Steam Generator (HRSG) is a horizontal, natural circulation, single pressure,

water tube type steam generator with a single drum. It is unfired type and uses Gas turbine exhaust

gases as heat source. It has been designed to generate superheat steam at a pressure of 41.5

kg/cm2 and a temperature of 512 degree Celsius at a Main Stream Value (MSV).

It consists of following section:

a) Superheater section

b) Evaporator section

c) Economizer section

d) Condensate Pre heater (C.P.H) and components

e) Steel chimney

a) Superheater Section:

The Superheater Section of the HRSG is used to dry the saturated vapour being separated in the

steam drum. In some units it may only be heated little above the saturation point where in other

units it may be superheated to a significant temperature for additional energy storage. The

Superheater Section is normally located in the hotter gas stream, in front of the evaporator.

Page 5: SIP_Final_1

b) Evaporator Section: The most important component would, of course, be the Evaporator Section. So an evaporator

section may consist of one or more coils. In these coils, the effluent (water), passing through the

tubes is heated to the saturation point for the pressure it is flowing.

c) Economizer Section: The Economizer Section, sometimes called a preheater or preheat coil, is used to preheat the feedwater

being introduced to the system to replace the steam (vapour) being removed from the system via the

superheater or steam outlet and the water loss through blowdown. It is normally located in the colder

gas downstream of the evaporator. Since the evaporator inlet and outlet temperatures are both close to

the saturation temperature for the system pressure, the amount of heat that may be removed from the

flue gas is limited due to the approach to the evaporator, whereas the economizer inlet temperature is

low, allowing the flue gas temperature to be taken lower.

Page 6: SIP_Final_1

d) Condensate Pre- Heater (C.P.H) and Components: Low pressure feed water heaters also called condensate Pre heater sometimes used on combined

cycle units to heat the desecrator feed water thus the cycle required less desecration steam making

it more efficient. The purpose of condensate pre-heater is to increase the temperature of

demineralized water so that it requires lesser energy to be converted into steam which is pumped

into it by Condensate Extraction Pump after passing through the condenser. Now from CPH it is

pumped into de-aerator. The cycle for both LP and HP steam formation is same.CPH is

constructed of modules, consisting of spiral finned tubes welded to the top and bottom headers,

two rows (max.) per module. CPFI is designed for single pass flow on the gas side and multi-pass

flow on the tube side.

Page 7: SIP_Final_1

e) Steel Chimney: Steel Chimneys are used when the isolating dampers which allows the flue gases from the gas

turbine chamber to the boiler of the HRSG are closed then the flue gases are sent out into the

atmosphere through these chimneys.

Page 8: SIP_Final_1

2. CONDENSER:

The surface condenser is a shell and tube heat exchanger in which cooling water is circulated through

the tubes. The exhaust steam from the low pressure turbine enters the shell where it is cooled and

converted to condensate (water) by flowing over the tubes. Such condensers use steam ejectors or

rotary motor-driven exhausters for continuous removal of air and gases from the steam side to

maintain vacuum. For best efficiency, the temperature in the condenser must be kept as low as

practical in order to achieve the lowest possible pressure in the condensing steam. Since the

condenser temperature can almost always be kept significantly below 100oC where the vapour

pressure of water is much less than atmospheric pressure, the condenser generally works under

vacuum. Thus leaks of non-condensable air into the closed loop must be prevented. Plants

operating in hot climates may have to reduce output if their source of condenser cooling water

becomes warmer; unfortunately this usually coincides with periods of high electrical demand for

air conditioning. The condenser uses either circulating cooling water from a cooling tower to

reject waste heat to the atmosphere, or once-through water from a river.

Page 9: SIP_Final_1

3. DEAERATOR: A steam generating boiler requires that the boiler feed water should be devoid of air and other

dissolved gases, particularly corrosive ones, in order to avoid corrosion of the metal. Generally, power

stations use a deaerator to provide for the removal of air and other dissolved gases from the boiler

feedwater. A deaerator typically includes a vertical, domed deaeration section mounted on top of a

horizontal cylindrical vessel which serves as the deaerated boiler feedwater storage tank. Practical considerations demand that in a steam boiler/ steam turbine/generator unit the circulating steam, condensate, and feed water should be devoid of dissolved gases, particularly corrosive ones, and dissolved or suspended solids. The gases will give rise to corrosion of the metal in contact thereby thinning them and causing rupture. The solids will deposit on the heating surfaces giving rise to localized heating and tube ruptures due to overheating. Under some conditions it may give rise to stress corrosion cracking.

Page 10: SIP_Final_1

4. COOLING TOWERS: Cooling towers are heat removal devices used to transfer process waste heat to the atmosphere.

Cooling towers may either use the evaporation of water to remove process heat and cool the

working fluid to near the wet-bulb air temperature or rely solely on air to cool the working fluid

to near the dry-bulb air temperature. Common applications include cooling the circulating water

used in oil refineries, chemical plants, power stations and building cooling. The towers vary in

size from small roof-top units to very large hyperboloid structures (as in Image 1) that can be up

to 200 meters tall and 100 meters in diameter, or rectangular structures (as in Image 2) that can be

over 40 meters tall and 80 meters long. Smaller towers are normally factory-built, while larger

ones are constructed on site. At PPCL, ID Cooling Towers are used and arranged in the form of a

row of 8 cells separated by block partition walls from basin sills to the fan deck.

Fan Specifications: 8 bladed, axial flow and each blade have a diameter of 9144 mm.

Page 11: SIP_Final_1

5. GAS TURBINE:

The Gas Turbine are steady flow power machines in which a gas (usually air) is compressed,

heated, and expanded for the purpose of generating power. Gas turbines may deliver their power

in the form of torque or one of several manifestations of pneumatic power, such as the thrust

produced by the high-velocity jet of an aircraft propulsion gas turbine engine. Gas turbine

machines vary in size from large, 250,000-hp utility machines, to small automobile, truck, and

motorcycle turbochargers producing as little as 5 hp. Gas turbines are used in electric power

generation, propulsion, and compressor and pump drives. The most efficient power generation

systems in commercial service are gas turbine combined cycle plants with power-to-fuel energy

efficiencies of more than 50% (higher heating value basis) or 55% (lower heating value basis).

Page 12: SIP_Final_1

Constructional Features:

Compressor Stages 17.0 Turbine Stages 3.0 Number of Combustors 14.0 Pressure Ratio 12.6 Firing Temperature (in o C) 1124 GT Speed (rpm) 3000 Capacity (in MW) 104 Number of units 2 Gas Pressure (in kg/sq. cm) 20

GAS TURBINE SYSTEM AIR FILTRATION SYSTEM: We need Filtration of inlet air to prevent ingestion of contaminants to avoid Erosion, Fouling, Corrosion, Hot gas path corrosion etc. Filtration can remove some, but not all substances like oil vapour, smoke which cause fouling of compressor blades. These are needed to be removed by online or offline cleaning washing of compressor using ash free detergents.

Air consumed by 1 GT (Frame 9 E) from atmosphere is 435 Kg/s approx.

Airborne dust contains sodium & Potassium twice as in soil, arises from fine particles of soil, leads to hot corrosion.

Also contains hydrocarbon from vehicular pollution and nearby power plants.

Contains other solid, liquid and gaseous contaminations

Page 13: SIP_Final_1

AIR FILTER HOUSE:

AIR FILTER:

AIR FILTRATION AT PPCL:

1160 filters are fitted in filter house of the plant.

For changing of filter set, a skid with four platforms are fabricated and fixed with the

existing tiers for quick changing of filters which saved downtime of GT from 24 hrs to 6

hrs.

Initially 100% synthetic, washable type filters were used, had only internal cage and did not have pleat locking.

New filters of 20% synthetic media with internal and external cage along with pleat lock

and dimple.

Page 14: SIP_Final_1

STEAM TURBINE: A steam turbine is a mechanical device that extracts thermal energy from pressurized steam, and converts it

into useful mechanical work. It has almost completely replaced the reciprocating piston steam engine

primarily because of its greater thermal efficiency and higher power-to-weight ratio. Also, because the

turbine generates rotary motion, rather than requiring a linkage mechanism to convert reciprocating to

rotary motion, it is particularly suited for use driving an electrical generator — about 86% of all electric

generation in the world is by use of steam turbines. The steam turbine is a form of heat engine that derives

much of its improvement in thermodynamic efficiency from the use of multiple stages in the expansion of the

steam, as opposed to the one stage in the Watt engine, which results in a closer approach to the ideal

reversible process. It converts the energy stored in steam into rotational mechanical energy.

Page 15: SIP_Final_1

SPECIFICATIONS OF STEAM TURBINE:

H.P Turbine Single flow with 28 reaction stages L.P. Turbine Double flow with 8 reaction stages H.P. Stop and Control Valves 2 L.P. Stop and Control Valves 2 Rated Speed 50/s Max. Speed (No Time Limitation) 51.5/s Min. Speed (No Time Limitation) 47.5/s Critical Speed (in r.p.m) 1292/2492 H.P. Steam Flow (in T/hr) 390 L.P. Steam Flow (in T/hr) 80

AUXILARIES AND AUXILARY SYSTEM:

1. BOILER FEED PUMP:-

Boiler feed pump is used to feed water to steam generator boiler drum at desired pressure and temperature. As the water is fed to the steam generator it has to be at the temperature & pressure that of the steam generator. Two types of BFP’s are used in the plant: a) HPBFP:

Motor Specifications: Power Rating (in kW) 1500 Stator Amps (in A) 157 Stator Volts (in V) 6600 Speed (in r.p.m) 1487 Insulation Class F

Pump Specifications:

Type of Pump Centrifugal Discharge (in m3 per hr) 240 Head (in m) 1407 Speed (in r.p.m) 4240 Temperature (in oC) 1516

b) LPBFP:

Specifications:

Power Rating (in kW) 45 Voltage Rating (in V) 415 Speed (in r.p.m) 2955 Current (in A) 72 Efficiency 92%

Page 16: SIP_Final_1

2. OIL COOLER:-

It is a Shell-Tube type Heat Exchanger which are used to cool the lubricating oil system of the generator and the turbine in order to control viscosity and reject heat. Specifications: Shell Side Tube Side

Operating Fluid Oil Water Flow Rate (in LPM) 165 650 Operating Pressure (in kg/cm2) 3 4 Test Pressure (in kg/cm2) 15 15 Inlet Temperature (in oC) 70 38 Outlet Temperature(in oC) 45 40.76 Heat Transfer Capacity (in 125.18 125.18 kW)

3. FILTRATION PUMP (STRAINER):

Specifications: Design Pressure (in kg/cm2) 10 Design Temperature (in oC ) 160 Operating Fluid Feed Water

4. AUXILARY OIL PUMP (AOP):

An auxiliary oil system pump is used to supply oil at the start-up of the steam turbine generator. It

supplies the hydraulic oil system required for steam turbine's main inlet steam stop valve, the

governing control valves, the bearing and seal oil systems, the relevant hydraulic relays and other

mechanisms. At a preset speed of the turbine during start-ups, a pump driven by the turbine main

shaft takes over the functions of the auxiliary system. Specifications:

Power Rating (in kW) 11 Voltage Rating (in V) 415 Current Rating (in A) 163 Speed (in r.p.m) 2975

Page 17: SIP_Final_1

5. JACKING OIL PUMP (JOP): JOP is used so as to ensure that there is no metal contact between a journal and the bearing. These are

positive displacement pumps that provide high pressure supply of oil under strategic journals of the

turbo generators and oil lifts the shaft slightly. Two types of JOP’s are used in the plant based on the supply of power namely:

a. JOP DC

This JOP runs on the DC supply from the Battery Bank and is used when the AC supply is not used i.e. in case of emergency situation so as to prevent friction between turbine blades and the

ground.

Specifications:

Power Rating (in kW) 11 Voltage Rating (in V) 125 Current Rating (in A) 112 Speed (in r.p.m) 1500

b. JOP AC

This JOP runs on three phase AC power supply.

Specifications:

Power Rating (in kW) 11 Voltage Rating (in V) 415 Current Rating (in A) 20.5

6. INSTRUMENT AIR COMPRESSOR (IAC):

An instrument air compressor controls the application of air for operating valves in pneumatic

instruments. Valves are process control equipment for industrial instruments and instrument air

compressors ensure that the air passing through to power these process control equipment is of

the correct pressure and temperature. Specifications:

Compressor Outlet Pressure (in bar) 5.9 Outlet AC Voltage (in kV) 235.1 Outlet AC Current (in A) 136.5

Efficiency of the plant: 47% to 51% Compressed Air: 10-12 kg/cm2

B. WATER TREATMENT PLANT

Boiler makeup water to the extent of 1.5-2% of the total flow is required to replenish the loss of

water through leakage from fittings and bearings, boiler blow-down escape with non condensable

gases in the Deaerator, turbine glands, and other causes. This makeup water needs to be treated

prior to feeding it to the boiler for-

Prevention of hard scale formation on the heating surfaces,

Elimination of corrosion,

Control of carry-over to eliminate the deposition on super heater tubes,

Prevention of silica deposition and corrosion damage to turbine blades. The cooling water makeup also demands significant amount of water at a prescribed parameters of PH turbidity, conductivity etc. Also, water is needed for various other plant activities at various

Page 18: SIP_Final_1

levels of cleanliness such as firefighting, service water etc. This entire water requirement is met

by the water treatment plant of the power plant. Thus, the water treatment plant treats the water

according to the requirements to which it needs to be put at various sections in the power plant.

This whole process largely comes under water treatment, which starts at the point, raw water

enters the plant boundaries and continues till the water id dispatched after treatment to its desired

destination.

a. RAW WATER:

The power plant receives its raw water from two sewage treatment plants namely, Delhi Gate Sewage Treatment Plant and Sen Nursing Home Sewage Treatment Plant. This water is not suitable for use in the power plant and has to be treated. Raw water contains a variety of impurities such as –

suspended solids and turbidity, Organics, Hardness(salts of calcium and magnesium), alkalinity(bicarbonates, carbonates, hydrates), Silica, and

Dissolved gases(O2 and CO2) Firstly the raw water is aerated i.e. oxygen is added to it by letting it to pass through stepped

platform into a storage tanks which is divided into two parts. After the water is aerated it is

pumped to Lime Softening Plant (also known as Stilling Chamber) where the turbidity and

hardness of the water are reduced. Here, lime, chlorine, poly electrolyte and ferric alum are dosed

in the stilling chamber. Ferric alum reduces the turbidity of the water and poly electrolyte

enhances sludge formation. Lime is added to the raw water to remove the hardness while chlorine

neutralizes the biological matter.

Page 19: SIP_Final_1

b. CLARIFICATION:

From the stilling chamber (located prior to the clarification tank) water is allowed to stand for

sometime in a big tank or reservoir, most of the suspended material settles down. The decanted

water is quiet clear and is taken out from outlet located at convenient points. This process of

clarification can be accelerated by adding coagulants such as ALUM (aluminum sulphate) or

ferrous sulphate or sodium aluminate. These result in the formation of a FLOC or precipitate of

aluminum hydroxide which tends to amalgamate colloidal, organic and suspended impurities that

settle down. The tank in which the whole process takes place is called clarification tank.

c. FILTRATION:

Water filtration is the process of separating suspended and colloidal impurities from the water by

passing it through a porous medium. A bed of granular filter material or media is used in most

power plant applications. A filter may be defined simply as a device consisting of a tank, a means

of supporting a working filter bed within the tank, suitable filter media, and necessary piping,

valving and controls. There are four types of filters that are used in the plant- Gravity Filter:

There are three Gravity Filters in the plant. These filters consists layers of sand, gravels and stones through water is filtered and sent to the Twin Bed Gravity Filters.

Twin Bed Gravity Filters (TBGF):

There are two such type of filters that are installed in the plant. These filters consist of a layer of Anthracite (best quality coal) in the bottom and above this layer is the layer of sand. Turbidity of water becomes 1-2 NTU

Activated Carbon Filter (ACF):

These filters consists of Activated Carbon which removes Cl2, odour, color, etc. from the water. These filters are two in number

Cartridge Filter:

These filters consists of cartridges which further filters the water coming

from the ACF and sends it to the RO Plant for further treatment. Impurities

of order of 5 microns are reduced and the turbidity is 0.11 NTU but the

conductivity is 1508 .7 S/cm

d. REVERSE OSMOSIS DEMINERALISATION (RODM):

It is a type of Membrane Desalination for desalination of brackish water to produce de-mineralized water fit for steam turbine cycle and auxiliary equipment’s cooling.

Reverse Osmosis:

This is a process in which osmosis takes place when pressure is applied. In this process the tank is divided into two chambers separated by a semi-permeable membrane made up of

Page 20: SIP_Final_1

Polyamide. When pressure is applied on water in one chamber then the water moves into the second chamber through the semi permeable membrane due to difference in pressure.

The water obtained from the RO system is called Permeate Water (Water from which most of the dissolved solids have been removed by the process of reverse osmosis) which is stored in the Permeate tank.

Mixed Bed:

From the Permeate tank the water is sent to the Mixed Bed which consists of cationic and anionic

resins which can be recharged using HCl and NaOH. In the Mixed Bed the conductivity of the

permeate water is reduced to less than 0.1% and the water from the mixed bed is called De-

Mineralized Water or DM Water which is used in the HRSG system for the generation of the

steam. From the Mixed Bed the DM water is pumped into the DM Water Tank.

C. ELECTRICAL EQUIPMENTS:

1. GENERATOR:

Generator is a device which converts mechanical energy into electrical energy. The plant have

total three generators out of which two generators are run by Gas Turbine (2*GTG) and the

remaining by Steam Turbine (1*ST). Rotating field type generators are employed which are

ventilated by the fans of rotor shaft or separately driven fans. The Generators used have 2 poles,

generates a frequency of 50 Hz and speed of the generators are 3000 r.p.m (Speed= 120*f/P)

The Power output of the two GTG’s is 2*104= 208 MW and the power output of the ST is 122 MW. Total power generated is 330 MW and the voltage is 10.5 kV.

Auxiliary Systems used for Generators are: a. Lubricating Oil System b. Hydrogen Cooling System c. Seal Oil System d. Stator Cooling Water System e. Excitation System

Tests are conducted on the generator for checking the insulation of the stator and rotor windings. The tests are-

Tan Delta Insulation Capacitance test:

Tan Delta is a diagnostic test conducted on the insulation of cables and

windings. It is used to measure the deterioration in the cable. It also gives an

idea of the aging process in the cable and enables us to predict the remaining

life of the cable. It is alternatively known as the loss angle test or the

dissipation factor test. The Tan Delta test works on the principle that any

insulation in its pure state acts as a capacitor. The test involves applying a

very low frequency AC voltage. The voltage is generally double the rated

voltage of the cable or winding. Insulation Resistance test:

The insulation resistance test (meggering) is of value for future comparison and also for determining if the transformer is to be subjected to the applied

Page 21: SIP_Final_1

voltage test. The winding insulation resistance test is a DC high voltage test

used to determine the dryness of winding insulation system. The test

measures the insulation resistance from individual windings to ground and/or

between individual windings.

Winding Resistance test:

Measurement is made to check transformer windings and terminal

connections and also both to use as reference for future measurements and to

calculate the load loss values at reference (e.g. 75ºC) temperature. Measuring

the winding resistance is done by using DC current and is very much

dependent on temperature. Generator cooling is done using CO2 which is cooled by water through fin fan system which uses ID Fans.

Page 22: SIP_Final_1

2. TRANSFORMER:

Transformer is a device that transforms electrical energy form from one alternating voltage to

another alternating voltage without change in frequency. IEEE defines transformer as a static

electrical device, involving no continuously moving parts, used in electric power system to

transfer power between circuits through the use of electromagnetic induction. Types of Transformers in the power plant are:

Power Transformer:

Transformers that are installed at the ending or receiving end of long high voltage transmission lines are called Power Transformers.

Instrument Transformer:

Instrument transformers are high accuracy class electrical devices used to

isolate or transform voltage or current levels. The most common usage of

instrument transformers is to operate instruments or metering from high

voltage or high current circuits, safely isolating secondary control circuitry

from the high voltages or currents. The primary winding of the transformer is

connected to the high voltage or high current circuit, and the meter or relay is

connected to the secondary circuit. These are of two types:

a. Potential Transformer:- Potential transformers (PT) (also called voltage

transformers (VT)) are a parallel connected type of instrument

transformer. They are designed to present negligible load to the supply

being measured and have an accurate voltage ratio and phase relationship

to enable accurate secondary connected metering.

b. Current Transformer:- Current transformers (CT) are a series connected

type of instrument transformer. They are designed to present negligible

load to the supply being measured and have an accurate current ratio and

phase relationship to enable accurate secondary connected metering. Auto Transformer

Page 23: SIP_Final_1

An autotransformer (sometimes called auto step down transformer) is an

electrical transformer with only one winding. The "auto" (Greek for "self")

prefix refers to the single coil acting on itself and not to any kind of

automatic mechanism. In an autotransformer, portions of the same winding

act as both the primary and secondary sides of the transformer. The winding

has at least three taps where electrical connections are made. Transformer on the basis of working i.e.

a. Step Up Transformer: - Transformer that steps up the voltage and have

primary winding as the LV side and secondary winding as HV side.

b. Step Down Transformer: - Transformer that steps down the voltage and have Primary winding as HV side and Secondary winding as LV side.

Specifications of Generating Transformer:

Type of Cooling OFAF ONAF ONAN Rating HV (MVA) 114 79.8 57 Rating LV (MVA) 114 79.8 57 No load Voltage (HV in 230 230 230 kV)

No load Voltage (LV in 10.5 10.5 10.5 kV)

Line Current HV 28.16 200.32 143.08 (Amps)

Line Current LV 6268.37 4387.86 3134.19 (Amps)

% Impedance at Normal 12.5(+ or -) 7.5% TOL

Tap (HV-LV)

Class of Insulation A

Temp. rise oil (in o C) 35

Temp. rise winding (in o 40 C)

HV 950 kVp, 395 kVrms

LV 75 kVp , 28 kVrms

HVN 95 kVp , 38 kVrms

Page 24: SIP_Final_1

Conservator Air Cell Type

Connection Symbol YNd11

Specifications of Unit Auxiliary Transformer:

Type of Cooling ONAN/ ONAF

Rating HV (MVA) 16/20

Rating LV (MVA) 16/20

No Load Voltage HV (kV) 10.5

No Load Voltage LV (kV) 6.9

Line Current HV (Amps) 879.77/1099.71

Line Current LV (Amps) 1338.78/1673.48

Temp rise Oil (in o C) 50

Temp rise Winding (in o C) 55

HV 75 kVp , 28 kVrms

LV 60 kVp , 20 kVrms

Connection Symbol Dyn1

3. SWITCHYARD:

For any power station, switchyard is an important part which bridges the generating station and

the distribution system i.e. via switchyard the generated electricity is fed to the sub-stations. It

connects the GTPS to the northern grid. The switchyard of Gas Turbine Power Plant is of 220

KV. The voltage generated is 10.5 KV, which is then step up to 220 KV by generator transformer.

This 220 KV is fed to the 220 KV switchyard. The switchyard has the double bus bar system i.e.

one is main bus and the other one is secondary bus. Some of the functions are:

Change voltage from one level to another Switch transmission and distribution circuits into and out of the grid system. Measure electric power quantities flowing in the circuits. Eliminate lightning and other surges from the system.

The Switchyard in the PPCL plant is maintained by Delhi Transco Limited (DTL).

Page 25: SIP_Final_1
Page 26: SIP_Final_1

Components used in the Switchyard are:

a. Isolators:

They are designed to open a ckt under no load. Its main purpose is to isolate portion of the circuit from the other & is not intended to be opened while current is flowing in the line.

b. Circuit Breakers:

It is a piece of equipment which can break the circuit automatically under faulty conditions and make the circuit either manually or by remote control under faulty conditions. They can be classified as:

Oil Circuit Breaker Air Blast Circuit Breaker Vacuum Circuit Breaker Gas (SF6) Circuit Breaker

In PPCL switchyard maintained by DTL, Gas (SF6) Circuit Breaker or Sulphur Hexafluoride Circuit Breaker is used.

Page 27: SIP_Final_1

Ratings of Gas Circuit Breaker in the Switchyard:

Also Vacuum Circuit Breaker is also used in plant and is maintained by PPCL and its ratings

are shown in the figure

Page 28: SIP_Final_1

c. Relays:

A relay is an electrically operated switch. Many relays use an electromagnet to

mechanically operate a switch, but other operating principles are also used, such as solid-

state relays. Relays are used where it is necessary to control a circuit by a low-power

signal (with complete electrical isolation between control and controlled circuits), or

where several circuits must be controlled by one signal.

In the switchyard maintained by DTL, there are a number of relays including electromagnet relays, numerical relays etc.

Also there is a master relay called 186,186 which detects even a small fault in the circuit and trips the circuit breaker.

Page 29: SIP_Final_1

d. Insulators:

Insulators are used in electrical equipment to support and separate electrical

conductors without allowing current through themselves. An insulating material used

in bulk to wrap electrical cables or other equipment is called insulation. The term

insulator is also used more specifically to refer to insulating supports used to attach

electric power distribution or transmission lines to utility poles and transmission

towers. They support the weight of the suspended wires without allowing the current

to flow through the tower to ground. e. Bus Couplers:

Bus coupler is a device which is used to couple one bus to the other without any interruption in power supply and without creating hazardous arcs. It is achieved with the help of circuit breaker and isolators.

Page 30: SIP_Final_1

f. Current Transformer:

C.T is an instrument transformer used for protection & metering of high values of currents. C.T is used for reducing AC from higher to lower value of measurement/protection/control.

g. Potential Transformer:

They are used to increase the range of voltmeters in electrical substations and generating stations. They are also called voltage transformer.

Page 31: SIP_Final_1

h. Lightning Arrester:

A lightning arrester is a device used on electrical power systems and

telecommunications systems to protect the insulation and conductors of the system

from the damaging effects of lightning. The typical lightning arrester has a high-

voltage terminal and a ground terminal. When a lightning surge (or switching surge,

which is very similar) travels along the power line to the arrester, the current from the

surge is diverted through the arrestor, in most cases to earth. i. Earthing Links:

Switchyard Earthing is provided to protect personally from shocks and hazards from electrical equipments.

Page 32: SIP_Final_1

Single line diagram of DTL Substation in PPCL: