Top Banner
September 2017 E. Tröster, T. Ackermann, N. Martensen (Energynautics, Germany) Contact: [email protected] In Cooperation with Simulations and Tests of a Danish Smartgrid – The Cell Controller Pilot Project
26

Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

Aug 19, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

September 2017

E. Tröster, T. Ackermann, N. Martensen (Energynautics, Germany)

Contact: [email protected]

In Cooperation with

Simulations and Tests of a Danish Smartgrid – The Cell Controller Pilot Project

Page 2: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

DEVELOPMENT IN THE DANISH POWER SYSTEM

2

Source: Energinet.dk

Page 3: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

• Increased security of supply

• Sufficient domestic resources must be available to maintain a balance between demand and generation

• Improved operator knowledge of actual system conditions both locally and centrally

• Efficient system control particularly during emergencies

• Active usage of distributed generators

• Black starting capabilities using distributed generators

• Organising distributed generators into controllable Virtual Power Plants

IDENTIFIED TARGETS OF THE REDESIGN PROCESS

3

Page 4: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

150 kV 150 kV

60 kV 60 kV 60 kV

10 kV 10 kV 10 kV

60 kV 60 kV

60 kV

10 kV

10 kV 60 kV

10 kV

60 kV

Input

Cell controller

Output

4

Page 5: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

THE CELL CONTROLLER

5 5

Page 6: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

ÅRR

AGB

GLE

HEJ

VOB

BMØ

GØR HOS

FØV

BRØ

HOD

LIK

REV

VJV

BIS

MØR

BIO

BID

G

G

G

G

15,5 MW

G

8,8 MW

2 MW

3 MW 3,8 MW

Wind Wind

Wind

Wind

3,6 MW

7 MW

3,3 MW

2 MW

Wind

Wind 2 MW

2 MW

Wind

4 MW

Test Area 1

Installed CHP: 37 MW Installed Wind: 39 MW Max Load: 61 MW 150/60 kV Trafo: 100 MVA

PILOT CELL: HOLSTED 60 KV GRID AREA

6

Page 7: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

CELL CONTROLLER CONCEPT

• Each Cell can be regarded as a Virtual Generator with same or better controllability compared to a traditional power station unit of equal size

• Local distribution companies attain strongly increased possibilities of distribution network on-line monitoring and active control

• Automatic Cell transition to controlled island operation in case of imminent transmission system break-down

• Black-start of transmission system • Robust Cell Controller Concept designed to encompass all new types of DG units and

controller functionalities

Increase in security of supply Any new functionality as pure software development Re-design for the future Danish electric power system

7

Page 8: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

Monitoring total load and production within the Cell

Active power control of synchronous generators

Active power control of wind farms and large wind turbines

Reactive power control by utilising capacitor banks of wind turbines and grid

Voltage control by activating AVRs on synchronous generators

Frequency control by activating SGSs on synchronous generators

Capability of operating 60 kV breaker on 150/60 kV transformer

Capability of operating breakers of wind turbines and load feeders

Automatic fast islanding of entire 60 kV Cell in case of severe grid fault

Automatic fast generator- or load shedding in case of power imbalance

Voltage, frequency and power control of islanded Cell

Synchronising Cell back to parallel operation with the transmission grid

Black-starting support to transmission grid in case of black-out

LEVEL OF FUNCTIONALITY OF THE CELL CONTROLLER

8

Page 9: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

Hejnsvig: 2x 1.3 MVA

Billund: 3x 3.6 MVA

CHPS IN TEST AREA 1

9

Page 10: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

4x 1000 kW Windturbine NEG Micon NM60/1000

Monitoring

WINDTURBINES IN TEST AREA 1

10

Page 11: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

800 kVA synchronous condenser for voltage control

SYNCHRONOUS CONDENSER AND DUMP LOAD (SLC)

11

1000 kW dump load for frequency control

Page 12: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

500.0400.0300.0200.0100.000.000 [s]

1.005

1.002

0.999

0.996

0.993

0.990

Grid Breaker: Electrical Frequency/Terminal iGrid Breaker: Electrical Frequency/Terminal j

500.0400.0300.0200.0100.000.000 [s]

0.20

0.00

-0.20

-0.40

-0.60

-0.80

Grid Breaker: Active Power Import in MWGrid Breaker: Reactive Power Import in Mvar

DIg

SILE

NT

Resynchronisation Islanding

Frequency Dip

Frequency

Active Power

Reactive Power

SIMULATION: ISLANDOPERATION WITH WINDTURBINES

12

Page 13: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

500.0400.0300.0200.0100.000.000 [s]

1.00

0.75

0.50

0.25

0.00

-0.25

SLC Loadbank: Total Active Power in p.u.SLC BL Control: SetpointSLC BL Setpoint Calc: CtlSetpoint

500.0400.0300.0200.0100.000.000 [s]

1.04

1.02

1.00

0.98

0.96

0.94

0.92

SLC Loadbank: Electrical FrequencySLC Loadbank: Voltage, Magnitude in p.u.

DIg

SILE

NT

Active Power Frequency

Voltage

SIMULATION: DUMP LOAD (SLC)

13

Page 14: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

500.0400.0300.0200.0100.000.000 [s]

0.80

0.60

0.40

0.20

0.00

-0.20

Trf 50366: Psum WT1Trf 50366: Qsum WT1

Switching of capacitor bank

Active Power

Reactive Power

SIMULATION: WINDTURBINE

14

Page 15: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

500.0400.0300.0200.0100.000.000 [s]

0.250

0.125

0.000

-0.125

-0.250

-0.375

Synchronous Condenser: Total Reactive Power in p.u.Qctrl: Ref

500.0400.0300.0200.0100.000.000 [s]

0.050

0.025

0.000

-0.025

-0.050

-0.075

-0.100

Synchronous Condenser: Total Active Power in p.u.

500.0400.0300.0200.0100.000.000 [s]

1.0250

1.0125

1.0000

0.9875

0.9750

0.9625

0.9500

Synchronous Condenser: Electrical FrequencySynchronous Condenser: Voltage, Magnitude in p.u.

500.0400.0300.0200.0100.000.000 [s]

2.50

2.00

1.50

1.00

0.50

0.00

-0.50

Selector: icSynchronous Condenser: Current, Magnitude in p.u.

DIg

SIL

EN

T

Active Power

Reactive Power

Frequency

Voltage

Switching of capacitor bank

SIMULATION: SYNCHRONOUS CONDENSER

15

Page 16: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

60 kV 10 kV 0,4 kV

Billund Hejnsvig

VOB AGB

BID HEJ

STI BIS

KLN GLB FUG CHP TRØ GRØ MØL

KT22 KT21

HEJ GEN1

HEJ GEN2

HEJ SC

HEJ SLC

HEJ WT1

HEJ WT2

HEJ WT3

HEJ WT4

BID GEN1

BID GEN2

BID GEN3

CEN SØK

KT21

KVV

Cell Controller

Mini Island

MEASUREMENT RESULTS

16

Page 17: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

MEASUREMENT TEST 1: „MINI ISLAND“ FREQUENCY

17

Page 18: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

MEASUREMENT TEST 1: „MINI ISLAND“ VOLTAGE

18

Page 19: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

60 kV 10 kV 0,4 kV

Billund Hejnsvig

VOB AGB

BID HEJ

STI BIS

KLN GLB FUG CHP TRØ GRØ MØL

KT22 KT21

HEJ GEN1

HEJ SC

HEJ SLC

HEJ WT1

HEJ WT2

HEJ WT3

BID GEN1

CEN SØK

KT21

KVV

Cell Controller

MEASUREMENT TEST 2: ISLAND OPERATION

19

Page 20: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

MEASUREMENT TEST 2: ISLAND OPERATION FREQUENCY

At time of island, cell generation (which includes over 1 MW of wind power) exceeds load by 470 kW.

Frequency increases immediately, but SLC and CHP governors react to compensate.

During island, cell frequency fluctuates as wind generation varies from 800 to 1350 kW. Cell Controller reacts and maintains cell within all grid code given boundaries.

Cell reconnected to grid.

20

Page 21: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

MEASUREMENT TEST 2: ISLAND OPERATION SYNCHRONIZATION

Once a reconnection to the grid is requested, the Cell Controller brings cell frequency and voltage phase within range of grid values. The Master Synchronizer reconnects only when cell frequency and voltage phase are sufficiently close to the grid values.

21

Page 22: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

60 kV 10 kV 0,4 kV

Billund Hejnsvig

VOB AGB

BID HEJ

STI BIS

KLN GLB FUG CHP TRØ GRØ MØL

KT22 KT21

HEJ GEN1

HEJ WT1

HEJ WT2

HEJ WT3

BID GEN1

CEN SØK

KT21

KVV

Cell Controller

MEASUREMENT TEST 3: IMPORT/EXPORT CONTROL

22

Page 23: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

Billund CHP

Hejnsvig CHP

Setpoint

Actual value

MEASUREMENT TEST 3: IMPORT/EXPORT CONTROL

23 1 hour

Page 24: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

Grid connected import/export control (virtual generator operation)

Emergency transfer to sustained hybrid island operation

Islanded wind only operation with SC and SLC

ACHIEVED TEST RESULTS

24

Page 25: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

CONCLUSIONS

A utility scale smart grid concept has been successfully demonstrated. Lessons learned from the project: • By adding ICT to the system a higher security of supply can be achieved, however it also

adds new sources of failure.

• Modelling and simulations are powerful tools to test new control strategies before going into the field. In case of island operation dynamic simulations are necessary!

25

Page 26: Simulations and Tests of a Danish Smartgrid – The Cell ... · 0.000 100.00 200.0 300.0 400.0 [s] 500.0 1.005 1.002 0.999 0.996 0.993 0.990 Grid Breaker: Electrical Frequency/Terminal

26

THANK YOU FOR YOUR ATTENTION!