SICK WELL ANALYSIS ANALYSIS OF SICK WELLS - A SYSTEM
APPROACH
Oil and gas production, in broad sense of word, can be
subdivided into three or more separate fields of science and
technology.
Production process in the reservoir:
Geosciences and Reservoir Engineering
Production of oil and gas from the well:
Reservoir and Production Engineering
Surface gathering and transportation:
Production Engineering
Therefore it is quite evident that in the context of well or
reservoir analysis, knowledge of geosciences, production as well as
reservoir engineering is equally important
TYPE OF WELLS
1) Oil wells: Exploratory / Development.
- Self flow.
- Having influx, but no flow to the surface.
2) Gas wells: Exploratory / Development.
- Low pressure
- High pressure
3) Injection wells: Gas / water
SYSTEM APPROACH
- WHAT IS A SICK WELL?
A well is termed as sick when it is proved or indicative of
hydrocarbon bearing but having little productivity or producing
with excessive quantity of unwanted fluids.
Similarly, an injection well (either drilled as an injector or
converted) is considered to be sick when its intake is low.
Based on the performance, it is an accepted practice to keep
such wells under sick category.
This approach provides first guidelines towards further
action.
However, the above concept does not speak anything about the
real potential of the well. Hence, a better yardstick would be to
compare the present performance of a well with its best known
producing /intake capacity.
- THEREFORE
In the truest sense, a well can be considered as sick when its
performance is appreciably different from its best-known
capacity.
Once, this definition is agreed to, it may delete or add a few
more wells,as sick, based on the present performance only.
But a closure look into this definition will reveal that it has
got its own limitation regarding data gap. To adopt such practice,
it is essential to have a reference parameter.
The parameter, which is widely used to rate a well, is known as
Productivity Index for producing well and Injectivity Index for an
injector.
Throughout the producing history of a well, Productivity Index
measurement can be used in determining, if the well is producing
without any damage. In case of abnormal deviation remedial measure
can be taken.
But in real field situation this parameter is often missing,
especially for the wells, which have never flowed.
Sick well analysis is a continuous process, which updates the
present scenario. Regular studies are carried out as a routine
within a organization from time to time at different levels. An
example may give some idea about the kind of study which can be
taken up.
Salient features of one such study are discussed in brief.
ON SHORE VI PLAN VIIPLAN VIIIPLAN
Total number of
Wells at the
Beginning 6 325 464
No. of wells fallen
Sick during the period933 2485 3822
No of wells available
For liquidation 1379 2810 4286
No of wells liquidated
During the period 1054 2346 3224
Findings of another study carried out in one of the Operating
Regions revealed that nearly 2500 tons per day of oil production is
feasible if all the wells are worked over successfully.
Both studies together have come with interesting
observations.
There is increasing trend of sick wells with time.
At a given time, percentage of sick wells can be as high as
20 to 30 % of total operating wells
Appreciable quantity of oil is blocked behind idle wells
Planning,
Execution
Monitoring
PLANNING
Step 1: Identify the wells on the basis of present
performance
Step 2: Data collection
Nature of data Source
-Geological/Reservoir
Model/map Seismic ,Log, drilling
Formation Type Core, Log, Well cutting.
Pay thickness (Iso- pay Map) Log
Porosity (Iso-porosity map) Core, Logs.
Permeability (Iso-permeability map) Core, Well tests.
Pressure (Iso-bar map) Well tests, DST.
Temperature Well tests, Logs
Formation Volume factor PVT,Correlation
Viscosity/Sp.Gravity Lab.Sample analysis.
Compressibility Core,Correlation
- Well Details
Well completion: Drilling Records.
Well Construction: Well data sheet
Casing /Tubing
Packer
Lift system
Wellheads
Productivity Index (Iso P.I map) Well Tests, DST.
Skin (Damage / Improvement) Well Tests, DST.
Flow Efficiency: Well Tests, DST.
-Production
Rate of Production Well Tests, Separator.
Gas oil ratio Well tests,
Water cut Sample analysis
- Environmental
Logistic Local Administration
Society
Safety
- Financial
Financing Cost.
Operational cost Local Finance
Statutory obligations
Price of produced fluids
Step III: Carry out technical analysis.
Probable causes of sickness
Diagnostic tools.
Remedial measures
The most frequent problems in a producing field in respect
of well performance are
Poor production
High water or gas production
Probable reason(s) for poor production
Low reservoir energy.
Low reservoir permeability.
High viscosity of the fluid.
Damage to well bore.
Inadequate lift mechanism
Mechanical trouble.
Unknown problems
Wells with high water or gas production
The common reason for excess water or gas production is
Rise of oil- water contact or expansion of gas oil contact.
Coning of water or gas.
Preferential movement of water or gas through high permeable
streaks or fractures.
Leakage behind or through casing.
Rise of oil water contact:
This phenomenon is observed for a water drive reservoir.
Water drive term is used in designating a mechanism which
involves movement of water into the reservoir as oil and
gas are produced. Water influx into a reservoir may be edge
water or bottom water, the latter indicating that a water zone
of
underlies the oil sufficient thickness so that water movement
is
essentially vertical The natural source of water drive is
the
result of expansion of water and rock in the aquifer. However
it
may result from artesian flow also.
As the water encroaches either for bottom or edge water
drive,
there will be increasing volume of water produced and
eventually water will be produced in all the wells.
Expansion of gas-water contact
Where there is an initial gas cap, oil is saturated and there is
no
liquid expansion Energy. In this situation the energy stored
in
the dissolved gas is supplemented by the gas cap. In case of
gas cap drive, as production proceeds and reservoir pressure
declines , the expansion of gas cap displaces the oil down
wards. This results increase of gas oil ratio (GOR) in
successively lower wells.
Coning of water /gas
Water cone forms where oil is underlain by water and the
well
completed in oil zone only. When well starts flowing, it
creates
a lower pressure zone near the well bore due to draw-down.
The water underlain tries to flow upward. The movement of
water is controlled by the vertical permeability of the
producing
strata.
Similarly, gas coning occurs when gas oil contact is within
well
and the well is completed in the oil zone .Similar mechanism
as
that of water coning work for movement of gas in downward
direction.
Height of the cone will increase with the magnitude of
pressure
drawdown
Preferential movement of gas /water.
This is observed when the reservoir is heterogeneous in
respect
of permeability and the oil is considerably more viscous
than
water. Many producing zones are having different
permeability
in horizontal and vertical direction. Zones of lower or
higher
permeability are often found to exhibit continuity through out
a
reservoir or portion there of. Where such stratification exists,
the
displacing water (either injected or natural influx) sweeps
faster
through more permeable zones so that much of oil in the
lower
permeable zones must be produced over a longer period of
time
at high water cut.
Water cut in the producing well, at any time, depends on the
capacity i.e. kh of the producing well formation and the
capacity (kh ) of the of the zone which has broken through
water production.
Given a series of beds with thickness h1, h2 ......hn and the
permeability k1, k2 . ......kn the surface water cut can be
expressed as
fw = Qw/ Qw + Qo =
( 1.127 W(h(kw (hw / uwL
----------------------------------------------------------
-------------------
( 1.127 W (p( k w (hw) / uw L + (1.127 W (p (k o ( h) / uo Bo
L
However, it is not easy to calculate water cut theoretically
as most of the time, required data will not be available.
The diagnostic tool, which have been proved to be quite
successful in the field is Production Logging
Step IV: Conclude studies. Suggest further action plan. The
conclusions can be listed as follow
Group of wells A: Problems identified.
- Natural
Live with the situation
Delete from the list
Group of wells B: Problems and remedial measures are
identified
Resources are available.
Techno-economically viable.
High priority
Group of wells C: Problems and remedial measures
are identified.
Resources are not available within
organization. Need to purchase
or hire technology from out side.
Techno economically viable.
Low priority.
Group of well D: Problems and likely solutions
are identified.
Resources are not available within organization.
Remedial measures have got limited success as per available case
history.
Recommended to refer Central committee for Expert advice.
Group of wells E: Problems identified.
Wells are beyond repair.
Recommended to be deleted from sick well list.
Group of wells F: Data insufficient.
Plan to acquire data
Step IV: Carry out Financial Analysis
Step VII: Priority
The results of analysis are the first lead for priority
assignment. However apart from techno economical superiority a few
more factors are important for execution schedule as follows.
Specific need of the organization
Oil well
Gas well
Injection well.
-Potential of the well
Average output with routine work over.
Substantial gain with major work over.
Environment
Logistic and Social
EXECUTION
A flow chart of work over operation is presented here. The chart
shows the relevant connection between Planning and Execution.
The project coordinator has a very important role to play in the
management. He is the key person between various groups. The
working style of a coordinator is discussed here.
Review of a project is a continuous process .A PERT (Project
Evaluation and Review technique) is convenient tool for day-to-day
monitoring, as it breaks down all the direct and hidden activities
within a time frame. Alternately a bar chart also can be used form
the same purpose.
Frequent meeting should be held involving all concerned
people. Working site is a convenient place to hold such
meeting. Every one should be made aware about the common
goal.
It is not a secret that operators tend to incline towards
softer
option and the planners are rigid about their decision. The
coordinator must find a solution for such conflicts without
sacrificing the objective.
It has been observed that any failure (either in planning or
execution) has tremendous negative impact in the minds of
the
concerned people. The coordinator must keep the moral and
the
spirit of the people high. Mid course correction plan should
be
discussed and be implemented.
Sometimes, same nature of job creates monotony in a person
resulting loss of interest in the work. The coordinator should
try
to rotate people. How ever it should be done judiciously
avoiding any possibility of a misfit.
-Post operational appraisal of any work over is an important
aspect especially in case of unsuccessful attempts. After a
project is concluded a detailed evaluation both from
engineering
and economic point of view. Sometimes the apparent success
may not reflect the real achievement An unbiased appraisal
only
will say if the work over was really profitable and if not
why?
The appraisal can be based on some frequently asked
questions
- Did the work over go as per planning? If not why?
.. Inadequate planning?
.. Unforeseen problems?
.. Uncontrollable environment?
. Attitude of the people?
- Is the objective fulfilled? How the result compares
with expectation? If not why?
.. High expectation? Data quality?
.. Lack of knowledge?
.. Resources constraint?
..Too many compromise?
- Was the work over really profitable? If not why?
.. Did the cost of material go up?
.. Did the price of the produced fluids reduced?
.. Is there change in tax structure?
.. Were there excess of breakdown?
- What can be done?
..Carry on with the present set up but with
more meticulous attitude?
.. Hire an expert for constant guidance?
.. Recommend for a technology provider?
In a total flow system (from reservoir to the well bore and from
well bore up to the gathering point) different nodes are involved.
These nodes can be broadly identified as
Reservoir
Well bore
Casing and completion (packer etc)
Tubing
Well head.
Gathering system
For the performance analysis of any well all these nodes are to
be thoroughly examined before coming to any conclusion. Apart from
the history of the well, to gather additional information, two
tests are very handy to start with
Production logging
Well testing
However, before recommending to carry out either test objective
must be very clear and it should be ensured that the well is made
ready to carry out the test.
-WHAT IS PRODUCTION LOGGING?
Production logging consists of running Geophysical
instruments
called logging tools, into a well to measure various
parameters.
These logs are run in producing as well as injection wells.
They can be under dynamic (flowing) or static (shut in)
conditions.
Production logging is one of the most important aspects of
oil
field management. It provides an insight into the type and
rates
of fluid flow in reservoir and well. It helps in problems
like
Water entry location and sources
Non-performing perforations
Flow behind casing or tubing
Cross flow identification
Leaks in the tubing, casing or packer
Lost circulation zone
There is a family of tools provided by Schlumberger which is
intended primarily for measuring the performance of producing and
injecting wells. The tools include
Thermometer
Gradiometer
Continuous flow meter
Manometer
Caliper
Thermometer: Measure the temperature of well bore fluid under
either shut in or flowing conditions. Particularly useful in
detecting flow in casing annulus.
Gradiometer: Measure the difference in pressure over 2 feet of
well bore, which is related to the mean density of the well bore
fluids In some cases it may be affected by the hole deviation or
friction component.
Continuous flow meter: With a spinner velocimeter it measures
the velocity of the fluid, which is related to the volumetric flow
rate. Primarily the tool should be used essentially
for monophasic flow regimes.
Manometer: Measure the pressure of the well bore fluid. Helpful
in determination of productivity index for gas as well as oil
wells.
Caliper: Measure the diameter of the casing or the hole.
Temperature logs : The temperature response can be seen as a
function of depth, flow rate, and time of injection in an injection
well in the following fig.
Similar relationship controls the temperature in producing
wells, but the flow rates are usually lower. Difference between
injection and producing wells is that the temperature in the latter
group is commonly higher than the geothermal profile. A typical
plot is shown
Case Histories:
Anomalous fluid flow behind the casing: The shut in and flowing
Temperature on a water injection well is shown in the figure ( ). A
continuous flow meter log indicated that there was no downward flow
of fluid in the casing below 600 ft. Yet both the shut in or
flowing temperature logs indicated that the water is being injected
into the formation opposite the perforations. The flowing
Temperature Log follows the classic pattern described in the
literature. Below 3000 ft the slope of the Temperature Log
approaches the slope of the geothermal profile down to the top of
the zone where the water is being injected. Then below the zone of
water injection, the temperature quickly returns to the geothermal
profile. It is to be noted that just above the zone of water
injection the injected water is more than 200 C cooler than the
geothermal gradient even though the water injected from the surface
is quite hot. The shut in
Temperature logs also follow the classic pattern. After the well
has been shut in for 20 hours, the temperature is approaching the
geothermal profile.(except in the water injection zone)
Evidently, this is a very unusual case, the injected water is
leaving the casing at 600 ft, traveling down to the annulus, and
entering the desired zone.
The necessary remedial actions are to cement off the casing the
casing leak at 600 ft, and if necessary re perforate the zone at
3200 ft. Here, a single Production Log would have given the
misleading information.
Leakage through casing:
Routine pressure measurement in one of the gas wells in a gas
field showed much lower pressure than earlier recorded, although
the well was not on production. There was no surface leakage also.
To ascertain the cause, a temperature survey was carried out. The
temperature log shows a drop in temperature around 700m. This was
interpreted as movement of gas through damaged casing and being
lost in the upper zone. The casing was perforated at the top and
bottom of the suspected damaged zone and cement squeeze job was
carried out. Again a temperature survey was carried out which shows
no anomaly proving the job to be successful.
Though the interpretation of the temperature survey proved to be
correct, but similar indication could have been due to tubing
leakage as well. But the pressure recorded indicated some movement
of gas. A spinner survey might have helped to confirm the cause of
anomalous pressure. Unfortunately this was not available and
decision had to be taken based on the temperature and pressure
reading