Top Banner
Copyright by Goodidar Hemmanoor Arjun Shounak 2016
93

SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

May 05, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

Copyright

by

Goodidar Hemmanoor Arjun Shounak

2016

Page 2: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

The Thesis Committee for Goodidar Hemmanoor Arjun Shounak Certifies that this is the approved version of the following thesis:

Extension of Activity Analysis Methodology to Maintenance, Shutdown,

and Turnarounds in Petrochemical Facilities

APPROVED BY

SUPERVISING COMMITTEE:

Carlos H. Caldas

John D. Borcherding

Supervisor:

Page 3: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

Extension of Activity Analysis Methodology to Maintenance and

Shutdown Turnarounds for Petrochemical Facilities

by

Goodidar Hemmanoor Arjun Shounak, B.E

Thesis

Presented to the Faculty of the Graduate School of

The University of Texas at Austin

in Partial Fulfillment

of the Requirements

for the Degree of

Master of Science in Engineering

The University of Texas at Austin

August 2016

Page 4: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

iv

Acknowledgements

First, I would like to thank my advisor Dr. Carlos H. Caldas who always kept the

door to his office open whenever I needed guidance, professionally and personally. He

consistently motivated me to put in my own thoughts into research, and also steered me

in the right direction whenever he thought I needed it.

I would also like to acknowledge Dr. John D. Borcherding as the second reader of

this thesis, and I am gratefully indebted to him and my colleague Jungyeol Kim for

providing field study opportunities, hands on training and valuable comments on various

topics related to this research. I express my gratitude to Dr. Steven Mulva and Dr. Daniel

Oliveira for grooming me as a researcher at Construction Industry Institute, and Dr. Bon

Gang Hwang and his research team for their continuous support and feedback during the

past year.

I am thankful to my roommates Shariq Iqbal and Surya Dhulipala for the lessons

– “living in the United States 101”. My journey at the university would have never been

as enjoyable without my fellow longhorns Harsha Shetty, Pratik Kakkar, Piyush Jajpuria,

Ashish Gupta, Varad Kelkar, Edwin Thomas, Jojo France-Mensah, Ankur Bhambotta,

Bharathwaj Sankaran, Gurpreet Kaur, Nassim Hamed, Samuel P Dal Ross and Ryan

Griego.

Page 5: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

v

Be it from the southern hemisphere or the northern half of the globe, online, or

offline, Bhushan Suresh, Sharath Simha, Rohan Shenoy, Gaurav Shetty, Harsha Shetty,

Amit Jain, Anand Rajavikrama, Praneeth Rachapalli, Aditya MP, Jatin Shetty and Anil

Hunagund have stood by me and supported all my endeavors.

Finally, I must express my very profound gratitude to Amma and Appa for their

faith in me with unfailing support, opportunities and continuous encouragement

throughout my life, to make me a better person. This accomplishment would not have

been possible without them. I would like to thank my grandparents, and family for their

support and love. Most importantly, I would like to thank my wife Nayantara Kurpad for

enduring and sharing this experience with me as a graduate student, with tolerance,

patience and unwavering love.

Page 6: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

vi

Abstract

Extension of Activity Analysis Methodology to Maintenance and

Shutdown Turnarounds in Petrochemical Facilities

Goodidar Hemmanoor Arjun Shounak, M.S.E

The University of Texas at Austin, 2016

Supervisor: Carlos H. Caldas

Studies show that construction productivity has been stagnant for decades.

Interestingly, other industries like manufacturing, automobile and agriculture have

witnessed a steep increase in productivity, nearly twice, over the same period of time. It

has been the norm for many continuous improvement methods, employed by these

industries, to claim credit for this trend. While inadequacies in a range of parameters like

management practices, organizational behavior, contractual differences, and other

planning functions affect poor productivity, the first step towards any improvement

program is to measure the existing condition. The importance of measuring and

improving productivity has become increasingly critical and significant with raging

project capital costs and complexity, especially in the petroleum industry.

Page 7: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

vii

This research focusses on providing a productivity language for petrochemical

owners and contractors. The developed methodology helps them to communicate

improvement strategies with each other and within their organization beyond construction

leading into maintenance and shutdown turnarounds. Activity Analysis is a productivity

assessment and improvement method developed by the Construction Industry Institute

(CII) in 2010.

This thesis describes the adaptation of activity analysis methodology that was

developed to measure productivity indicators at petrochemical facilities on construction,

maintenance and shutdown turnaround activities between 2015 and 2016. It also provides

an overview on the activity analysis software developed for data collection, which is a

byproduct of this research. This study also provides a summary of expected trends and

challenges in petrochemical industries, and strategies that could be implemented to

enhance the direct work rate in both construction and maintenance environment.

Page 8: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

viii

Table of Contents

List of Tables ....................................................................................................... xiii

List of Figures ...................................................................................................... xiv

Chapter 1: Introduction ............................................................................................1

RESEARCH MOTIVATION .........................................................................1

RESEARCH OBJECTIVES ...........................................................................2

RESEARCH SCOPE AND LIMITATIONS ..................................................3

READER’S GUIDE........................................................................................4

Chapter 2: Research Framework ..............................................................................5

CONDUCT BACKGROUND RESEARCH ..................................................6

EXTEND ACTIVIVTY ANALYSIS PLANNING PHASE ..........................7

DEVELOP ACTIVITY ANALYSIS SOFTWARE .......................................8

EXTEND ACTIVIVTY ANALYSIS SAMPLE PHASE...............................9

DEVELOP ACTIVIVTY ANALYSIS REPORT GENERATION TOOL ..10

Page 9: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

ix

RECOMMEND PRACTICES TO PLAN AND IMPLEMENT

PRODUCTIVITY IMPROVEMENTS ...............................................10

WRITE RESEARCH REPORT ....................................................................11

Chapter 3: Background Review .............................................................................12

PRODUCTIVITY AND PERFORMANCE .................................................12

WORK SAMPLING .....................................................................................13

CII’S ACTIVITY ANALYSIS OVERVIEW ...............................................13

SAMPLE SIZE AND ERRORS IN ACTIVITY ANALYSIS .....................16

DIRECT WORK AVERAGES IN THE PAST ............................................20

Chapter 4: Extending Activity Analysis Plan Phase ..............................................29

ACTIVITY CATEGORY DEFINITION .....................................................29

Direct work ..........................................................................................29

Waiting .................................................................................................33

Preparatory work ..................................................................................36

Material handling .................................................................................38

Tools and equipment ............................................................................39

Page 10: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

x

Travel ...................................................................................................40

Personal ................................................................................................41

Other issues ..........................................................................................41

ACTIVITY ANALYSIS SOFTWARE ........................................................43

Features ................................................................................................43

Observation summary ..........................................................................46

Chapter 5: Extending Activity Analysis Sample Phase .........................................47

PREPARING FOR DATA COLLECTION .................................................47

DATA COLLECTION CHALLENGES ......................................................49

ACTIVITY ANALYSIS SAMPLING .........................................................50

MINIMUM NUMBER OF SAMPLES ........................................................50

Chapter 6: Activity Analysis Report Generation ...................................................53

EXPORT DATA FROM ACTIVITY ANALYSIS SOFTWARE ...............53

EXAMPLE CALCULATION FOR ANALYSIS .........................................55

ACTIVITY ANALYSIS REPORT GENERATION ....................................57

Page 11: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

xi

Report Generation Sheet (RGS) Content .............................................57

Datasheet .....................................................................................57

Direct Work Dashboard ..............................................................58

Aggregate Results .......................................................................58

Results by Trade .........................................................................59

Using the Report Generation Sheet......................................................61

Step 1 – Copy Data .....................................................................61

Step 2 – Paste Data .....................................................................61

Step 3 – Review Result Tabs ......................................................62

Chapter 7: Recommendations to Plan and Implement Improvements ...................63

Expected proportions in activity category percentages .......................63

Interpretation of results ........................................................................64

Probable causes for low direct work rates ...........................................65

World class direct work rates ...............................................................67

Best Practices - First and Last Work Hours of the Day .......................68

Page 12: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

xii

Best Practices - Lunch Breaks .............................................................71

Best Practices - Weather Breaks ..........................................................72

Best Practices - Transition Periods for Multiple Shifts .......................73

Chapter 8: Conclusions and Recommendations ....................................................74

CONCLUSIONS...........................................................................................74

RECOMMENDATIONS FOR FUTURE RESEARCH ...............................76

References ..............................................................................................................78

Page 13: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

xiii

List of Tables

Table 1: Aggregate work sampling result for 123 construction projects (Gong et

al. 2010) ............................................................................................21

Table 2: Direct work rate by industry type (Gong et al. 2010) .......................22

Table 3: Direct work rate in E.L Hamm’s study (Waidelich 1997) ................22

Table 4: Wrench time study in US paper mill (Yolton 2008) .........................23

Table 5: Case studies by Strandell, 1976 and Hedding, 2003 (Smith 2006) ..25

Table 6: Work sampling results by trade or craft (Oglesby, Parker, and Howell

1989) .................................................................................................26

Table 7: Work sampling results by trade for a power plant construction

(Strandell, 1976) ...............................................................................27

Table 8: Maintenance management improvement case study result (Palmer 2006)

...........................................................................................................28

Table 9: Minimum sample size based on number of workers (“Guide to Activity

Analysis” 2010) ................................................................................51

Table 10: Organization of activity analysis data - example ..............................54

Table 11: Direct work calculation - example ....................................................55

Table 12: Direct work rate quartile ranges ........................................................67

Page 14: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

xiv

List of Figures

Figure 1: Research framework ...........................................................................5

Figure 2: Activity analysis methodology (“Guide to Activity Analysis” 2010) 7

Figure 3: Activity analysis software ...................................................................9

Figure 4: Activity analysis phases and guidelines (CII IR252_2d, 2013) ........15

Figure 5: Sample size for varying confidence levels (Thompson, 1987) .........18

Figure 6: Work sampling projects in Austin Texas - Industry types (Gong et al.

2010) .................................................................................................20

Figure 7: US paper mill wrench time case study hourly trend (Yolton 2008) .24

Figure 8: A screenshot of the observation setup screen ...................................44

Figure 9: Export .csv file example ...................................................................53

Figure 10: Example activity category distribution pie chart ..............................56

Figure 11: An example of direct work dashboard tab ........................................58

Figure 12: An example of aggregate result tab in RGS.....................................60

Figure 13: Screenshot of pasting software export data into RGS ......................61

Page 15: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

1

Chapter 1: Introduction

RESEARCH MOTIVATION

Activity analysis can be extended to be effective on different types of projects

ranging from medium to large capital projects, construction to maintenance, and low to

high performing teams. It can help a project team monitor labor’s work efficiency and

maintain high performance. Some of the features and objectives of activity analysis

include (“Guide to Activity Analysis” 2010):

• Identifies challenges and implements processes to reduce the number of work

hours required to complete a certain unit of work.

• Helps to clearly understand what is happening throughout the day at construction

work-faces with a focus on craft workers.

• Maximizes “Direct Work” rate by identifying and optimizing support work and

idle times observed on a project.

• Facilitates performance assessment in less time and lower cost as compared to

other continuous observation studies.

• Provides an opportunity to canvas and inspect or study an entire job site.

• Does not require disruption of regular job site activities.

• Avoids resistance to study from craft workers since they are more likely to accept

activity analysis over other continuous observation studies.

Page 16: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

2

• Identifies specific areas for productivity improvement.

RESEARCH OBJECTIVES

Activity Analysis is a productivity assessment and improvement method

developed by the Construction Industry Institute (CII). This method was further

developed to adapt to the conditions and activities seen in petrochemical facilities.

Activity Analysis aims to categorize activities of craft workers into direct work,

supportive work, and non-productive work. The result is the classification or distribution

of labor time represented in percentages along with relevant observations and

recommendations to improve direct work.

The key objectives of extending the activity analysis methodology for petrochemical

facilities included the following:

• Provide a common productivity language and a yardstick for petrochemical

facility owners and contractors to communicate improvement strategies.

• Extend activity categories and develop activity analysis software customized to

activities and conditions observed on petrochemical construction, maintenance,

shutdown and turnarounds.

• Develop a report generation tool to process the data extracted from the software

• Identify potential opportunities and provide best practices to plan and implement

productivity improvements for petrochemical facilities.

Page 17: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

3

RESEARCH SCOPE AND LIMITATIONS

The purpose of activity analysis is to study and identify productivity barriers and then

implement improvements to eliminate or reduce these barriers. The intent is to reduce

activities that do not actively advance the finished product, thereby increasing the direct

work rate. In case of maintenance activities a new finished product may not exist, and

hence it is important to understand the classification of productive work, supportive work

and other categories that are considered non-productive. This research thesis focuses on

extending the scope of activity analysis methodology to be effective on:

• Construction projects

• Maintenance of plants or units

• Shutdown, turnaround and outages at petrochemical facilities

The research aims to identify the various categories of work time on a craft person’s

typical work day that are relevant to the above mentioned scenarios in different

petrochemical plants. The activity analysis software developed also revolves around these

activities and conditions. The study intends to provide a methodology to sample

productivity indicators on construction, maintenance and shutdown turnaround projects

before activity analysis, implement improvement strategies and re-measure changes and

improvements after a period of time. The study however does not evaluate individual

activities observed on construction projects or maintenance activities.

Page 18: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

4

READER’S GUIDE

The thesis is organized into eight chapters. Chapter 1 presents the motivation,

objectives and scope of the research along with this outline of the thesis. Chapter 2

discusses the framework of the research that guided the preparation, methodology

development, and documentation of recommendations. Chapter 3 provides an overview

of the findings from background review that will help in understanding the concept of

work sampling, the relationship between direct work and labor productivity, and similar

studies conducted in the past. Chapter 4 presents the extension of activity categories

developed to incorporate maintenance and shutdown turnaround activities, and also

provides an overview of the software that supports this methodology. Chapter 5 describes

the extension of sample phase, along with the data collection challenges and methods.

Chapter 6 discusses the type of data collected, and the various analyses that can be

conducted using the developed report generation tool. Chapter 7 identifies trends

observed, key improvement opportunities on projects, recommendations, strategies and

some best practices to improve direct work. Finally, Chapter 8 concludes the thesis with

discussions and recommendations to the industry along with the future scope for research

and implementation.

Page 19: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

5

Chapter 2: Research Framework

The milestones of this research can be placed on a time line between August 2015

and July 2016. The following section entails the framework of the study with the major

tasks as shown in Figure 1 below.

Figure 1: Research framework

Page 20: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

6

CONDUCT BACKGROUND RESEARCH

Planning and preparing involved background research on existing sampling

methodologies, and adapting these to suit the needs of the petrochemical facilities. To

meet the research objectives of measuring labor time utilization on construction,

maintenance and shutdown turnaround in petrochemical facilities, it was important to

determine the appropriate activity categories. The features of the tool had to

accommodate these customized categories and support the data collection.

A cyclic five step activity analysis methodology, developed by CII (“Guide to

Activity Analysis” 2010) was used as a starting point to develop the extended

methodology for petrochemical maintenance, shutdown and turnarounds. Figure 2 below

shows this continuous improvement methodology adopted for pilot projects.

Page 21: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

7

Figure 2: Activity analysis methodology (“Guide to Activity Analysis” 2010)

This background review also provided direct work averages for various industries

and trades, which are presented in Chapter 3 of this thesis.

EXTEND ACTIVIVTY ANALYSIS PLANNING PHASE

After conducting exhaustive brainstorming sessions with the researchers at the

Construction Industry Institute and UT Austin, a comprehensive list of activity categories

was developed to accommodate the various kinds of activities observed on petrochemical

plants. The sub categories chosen were carefully designed to suit the most commonly

observed activity categories for different phases including construction, maintenance and

shutdown turnarounds in a plant. The final set of categories is summarized in Chapter 4.

Plan Study

Sample

Analyze Plan Improvements

Implement Improvements

Page 22: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

8

DEVELOP ACTIVITY ANALYSIS SOFTWARE

The tool conceptualization involved establishing the various variables and

parameters involved in data collection like plants, projects, weather conditions, and other

observation details along with the categories. An entity relation was established to design

the database and a preliminary user interface, using MS access. Various test cases were

documented and handed over to a New York based software development firm.

Researchers partnered with Enstoa to develop the software and after numerous

conversations, touch based user interface screens and features of the activity analysis

software were developed to operate on a Windows 8 platform.

In order to use the activity analysis software in a petrochemical plant, the device

(Tablet) used in the facility had to be intrinsically safe and research revealed some

options and common industry practices in this regard. Intrinsically safe tablet

manufacturing companies across the United States were consulted to ensure adequate

certification to make sure these tablets would be safe to be used in plants. The rugged

tablets from Xplore technologies – “Bobcat” with class 1 division-2 certification were

procured provided to Enstoa for final application development.

The activity analysis software (shown in Figure 3 below) was installed on all the

devices (intrinsically safe tablets) and tested for errors. Minor bugs were fixed.

Page 23: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

9

Figure 3: Activity analysis software

Chapter 4 summarizes the features of the activity analysis tool and describes how

it supports data collection.

EXTEND ACTIVIVTY ANALYSIS SAMPLE PHASE

Activity sampling should be conducted in order to collect a representative data

sample from the various activities observed during construction, maintenance and

shutdown turnarounds. Each discrete data sample or observation should be categorized as

direct work, preparatory work, tools and equipment, material handling, waiting (and its

sub categories), travel, or personal. These categories and sub categories developed can be

sampled effectively using the software. Chapter 5 describes the sampling phase with

insights to collecting data in petrochemical facilities.

Page 24: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

10

DEVELOP ACTIVIVTY ANALYSIS REPORT GENERATION TOOL

The data collected from activities observed on petrochemical facilities, can be

tabulated in MS excel spreadsheets to determine activity category percentages. A report

generation sheet was developed to accommodate the data from the activity analysis

software and generate analysis tables and charts. The resulting percentages were analyzed

to determine which types of activities were beyond acceptable ranges. Chapter 6

describes the type of data collected and some examples to demonstrate the analyses that

can be conducted.

RECOMMEND PRACTICES TO PLAN AND IMPLEMENT PRODUCTIVITY

IMPROVEMENTS

After the potential causes for unacceptable variances were identified, several

potential solutions, especially the low hanging fruits to improve productivity were

considered. These improvement strategies were based on a set of factors that included

feasibility, logistics, schedule, and costs. Improvements selected in the planning stage

should be implemented to increase the direct work rate and reduce other support

categories and ones that cause delay.

Trends with activity categories were recognized, key opportunities were identified

and best practices to improve direct work were documented. Chapter 7 captures these

best practices to plan and implement productivity improvements.

Page 25: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

11

WRITE RESEARCH REPORT

This thesis includes the extended methodology, identified patterns and best

practices for improving direct work on construction, maintenance and shutdown

turnaround activities. The recommendations from this thesis are broader to the

petrochemical industry. The conclusion and recommendations of this research is

summarized in Chapter 8.

Page 26: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

12

Chapter 3: Background Review

PRODUCTIVITY AND PERFORMANCE

A project’s performance can be assessed using the following (Oglesby, Parker,

and Howell 1989):

• Quality compliance refers to meeting the specifications agreed in the contract.

• Schedule compliance involves completing tasks on time by sticking to the

promised timeline of project milestones

• Safety compliance aims at achieving an accident free project

• Productivity addresses the challenge of delivering the project at a fair price to the

owner with reasonable profit to the contractor

Productivity is defined by the relationship between completed work in place or

outputs and the amount of effort put in to accomplish it, in the construction industry.

However, depending on the scope of work, companies and context, definition of unit of

output and input can vary. Most of the time, output is a unit of the physical output in

place, when a unit of input is defined by unit cost of labor, equipment and material or

work hours. To evaluate predictability, some companies’ measure “Performance

Productivity” (“Guide to Activity Analysis” 2010) which is a ratio of actual work hours

to budgeted or expected work hours on a project.

Page 27: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

13

WORK SAMPLING

Work sampling is an effective way of gathering data to measure and classify the

utilization of craft workers time on construction projects (Waidelich 1997). During work

sampling on a job site, craft worker’s activity time is classified into either direct work,

support work or non-contributory work to identify particular areas that require

improvement. Direct work involves tasks adding to unit being constructed while support

work like reading plans, site clean-up, handling material (Waidelich 1997) help workers

to perform direct work. Non-Contributory work involves delay, personal time and idle

time. It is a statistical technique that collects random observation samples from the work

force engaged on various activities, and determines the proportion of time spent on the

categories mentioned above. Work sampling has been derived from industrial engineers

and was documented to have been used by the construction industry as early as 1969 by

the Great Britain Building Research Station (Goodrum et al. 2012).

Although work sampling results may not determine the actual productivity

numbers, direct work rates on projects can be used as an effective indicator in a

productivity projection model (Liou & Borcherding, 1986).

CII’S ACTIVITY ANALYSIS OVERVIEW

Established in 1983 at the University of Texas at Austin, the Construction

Industry Institute (CII) is a consortium of owners, engineering and construction

contractors and academia. CII funds research projects led by faculty from various

Page 28: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

14

universities in the United States along with research team members from industry, to

develop best practices that address various challenges in the construction industry.

Inspired by the continuous improvement process suggested by Oglesby, Parker and

Howell in 1989, one such research program on craft productivity at CII, developed the

activity analysis process in 2010 (Goodrum et al. 2012).

Activity analysis is a workface assessment tool developed as an extension of work

sampling to conduct deeper analysis and monitor progress continuously (CII IR252_2d,

2013). CII’s implementation resource 252_2a Guide to Activity Analysis provides a five

step methodology to conduct activity analysis. A set of activity categories, that capture

the different activities observed on a selected project, is defined during the planning

phase. An example of activity category set is – direct work, waiting, material handling,

tools and equipment, preparatory work, travel, and personal time (“Guide to Activity

Analysis” 2010). The collected data is tabulated under these categories to derive the

activity category percentages which will help in identifying categories that are outside the

norm, in comparison with historical data and experience. Once potential productivity

barriers have been identified, ways to improve the situation on projects are evaluated on

various parameters like feasibility, logistics, impact on cost and schedule. Developed

strategies are documented and implemented on projects with a goal to enhance direct

work percentage.

Page 29: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

15

Figure 4 (CII IR252_2d, 2013) below shows the five phases and guidelines to

complete sub tasks within this 5 phased continuous productivity improvement cycle:

Figure 4: Activity analysis phases and guidelines (CII IR252_2d, 2013)

Page 30: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

16

SAMPLE SIZE AND ERRORS IN ACTIVITY ANALYSIS

Since activity analysis methodology is driven by statistics, it is important to

understand the challenges and errors in data collection. Hence it is also critical to

determine the number of observations that need to be collected during activity analysis

for the results to significantly reflect the actual site conditions observed.

Thomas in 1982 published an article that lists the errors that would apply to

activity analysis as well (Thomas Jr. et al., 1982):

• Human Limitations to cover all areas on a job site

• Variation between observers

• Procedural deficiencies that may not be anticipated

• Bias in observer judgment

• Fatigue during hourly data collection

• Identification of population under observation

• Hawthorne effect leading to abnormal worker’s behavior

Page 31: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

17

One way to reduce these errors is to have defined sampling procedures and

training material to achieve consistency in the process (“Guide to Activity Analysis”

2010). Sampling errors can be quantified using statistics however, during activity

analysis planning; errors can be limited by increasing the number of samples (Goodrum

et al. 2012)

Five percent error with a confidence level of 95% is generally acceptable in most

industries. The minimum sample size to achieve this sample size can be obtained

considering the data as binomial distribution or multinomial distribution. A binomial

sample size equation would govern the activity categories that fall into either one or the

other category for example – productive work and non-productive work. However,

activity analysis involves more than two categories and hence the solution proposed by

S.K Thompson in 1987, to determine sample size for multinomial distribution, is used for

activity analysis. He wrote an article – “Sample size for estimating multinomial

proportions” in The American Statistician which presented a table to determine the

sample size of a multinomial distribution for different confidence levels as shown in

Figure 5 below:

Page 32: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

18

Figure 5: Sample size for varying confidence levels (Thompson, 1987)

In the above figure, the 5% error (alpha = 5) corresponds to 510 observations.

Further, it is noted that the samples being collected is not the worker but worker’s

behavior at a given time and hence the minimum number of samples can be collected for

each work hour (Example 8am to 9am). This constantly changing behavior of workers is

the population being measured, which although is not infinite, it is large enough that the

true population is difficult to estimate (Goodrum et al. 2012). In order not to overestimate

Page 33: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

19

sample size and collect redundant samples a finite population correction factor can be

applied as shown below (Goodrum et al. 2012):

Minimum sample size per hour = 1/((1/(𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁𝑁 𝑜𝑜𝑜𝑜 𝑤𝑤𝑜𝑜𝑁𝑁𝑤𝑤𝑁𝑁𝑁𝑁𝑤𝑤) + 1/𝑛𝑛0) )

Where n0 is determined from Figure 5, for example:

Minimum number of observations with a confidence level of 95% for 300 workers can be

determined as follows:

Minimum sample size per hour = 1/((1/300 + 1/510) ) = 189 samples per hour.

Since it may be difficult to collect so many samples in one hour, sample

collection may be distributed over several data collection days during the same one hour

period (Goodrum et al. 2012). Table 9 summarizes the number of samples to be collected

across a range of worker population observed during activity analysis (“Guide to Activity

Analysis” 2010).

Page 34: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

20

DIRECT WORK AVERAGES IN THE PAST

Work sampling results from the past can help in setting a baseline and form a basis for

comparison of results. Jie Gong’s article on the assessment of direct work utilization at

the workface in the U.S. construction industry (Gong et al. 2010) summarizes work

sampling results of 123 construction projects in Austin, Texas between 1972 and 2008.

These construction projects comprise of 7 different types of industries as shown in Figure

6 below:

Figure 6: Work sampling projects in Austin Texas - Industry types (Gong et al. 2010)

15

Page 35: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

21

The aggregate results from this study can be tabulated as shown in Table 1 below (Gong

et al. 2010):

Activity Category Percentage

Direct Work 44%

Travel 14%

Transport 10%

Instruction 7%

Delay 19%

Personal time 6%

Table 1: Aggregate work sampling result for 123 construction projects (Gong et al.

2010)

Page 36: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

22

Jie Gong’s study also presents average direct work rates by industry type as shown in

Table 2 below:

Industry Number of Projects Direct Work Percentage

Commercial 38 51%

Public 11 47%

Highway 15 44%

Hospital 5 37%

Industrial 3 47%

Institutional 48 42%

Residential 4 46%

Table 2: Direct work rate by industry type (Gong et al. 2010)

E.L Hamm studied a project to improve the performance of PWC maintenance

department and provided work sampling results as shown in Table 3 below:

Activity Category Percentage

Direct Work 47.6%

Support (Indirect Work) 37.1%

Non-Contributory Work Time 15.3%

Table 3: Direct work rate in E.L Hamm’s study (Waidelich 1997)

Page 37: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

23

As part of maintenance improvement initiatives, sometimes, direct work is referred as

“wrench time” while following similar data collection and analysis methodology as work

sampling. SKF reliability systems published one such study in an article (Yolton 2008).

The results of this study conducted in a paper mill in USA are shown in Table 4 below.

Activity Category Percentage

Wrench Time 24.7%

Travel and Waiting 19.0%

Material Handling 9.6%

Meeting & Personal time 35.8%

Remaining (Not accounted) 10.9%

Table 4: Wrench time study in US paper mill (Yolton 2008)

Page 38: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

24

The study also presents the variation of wrench time over time on a typical work day as

shown in Figure 7 below.

Figure 7: US paper mill wrench time case study hourly trend (Yolton 2008)

Page 39: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

25

In his thesis, Francois Smith tabulated results of studies from 1976 by Strandell

and another case study on Sasol Synfuels in Secunda by Hedding in 2003. Table 5 below

shows the results from these studies:

Activity Percentage

Strandell, 1976 Hedding, 2003

Direct Work 32% 29%

Waiting 29% 13%

Travelling 13% 11%

Instructions 8% 12%

Tools, Materials and Transportation 7% 17%

Late starts / early quits 6%

Personal breaks 5% 13%

Administration 4%

Table 5: Case studies by Strandell, 1976 and Hedding, 2003 (Smith 2006)

Page 40: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

26

A large construction firm collected work sampling data for two years for the

many trades involved on their projects. The book productivity improvement in

construction captures the results as “good performance” and classifies labor time into

effective, contributory and not useful time as shown in Table 6 below (Oglesby, Parker,

and Howell 1989)

Percent of total time in category Trade or craft Effective Contributory Not useful

Bricklayer 42 33 25 Carpenter 29 38 33

Cement finisher 37 41 22 Electrician 28 35 37

Instrument installer 30 30 40 Insulator 45 28 27

Ironworker 31 36 33 Laborer 44 26 30

Millwright 34 36 30 Equipment operator 38 22 40

Painter 46 26 28 Rigger 27 57 16

Sheetmetal 38 33 29 Pipefitter 27 36 37 Teamster 45 16 39

Average of above 36 33 31

Table 6: Work sampling results by trade or craft (Oglesby, Parker, and Howell 1989)

Page 41: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

27

Marjjata Strandell also captured in the 1976 AACE transactions, direct work rates

of trades working in a power plant construction project. Table 7 below shows the finding

from this study.

Trade or craft Direct work (%)

Pipefitters/Welders 28%

Boilermakers 27%

Electrical Workers 28%

Laborers 41%

Carpenters 42%

Insulators 26%

Operating Engineers 39%

Ironworkers 31%

Millwrights 32%

Table 7: Work sampling results by trade for a power plant construction (Strandell,

1976)

Page 42: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

28

A maintenance management improvement case study in Palmers book (2006)

published wrench time by trades working on maintenance as shown in Table 8 below.

Trade or craft Wrench time % Hours/10-hour day

Mechanics 34.24 3.5

Painters 35.69 2.5

Welders 33.75 3.5

Machinists 50.67 5

Apprentices 40.21 4

Trainees 30.80 3

Table 8: Maintenance management improvement case study result (Palmer 2006)

Page 43: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

29

Chapter 4: Extending Activity Analysis Plan Phase

ACTIVITY CATEGORY DEFINITION

Defining the objectives of a study is crucial to providing relevant and useful data.

Categories were customized to specific objectives. For this study, the objective was to

quantify time expended by a craft worker on productive and non-productive activities

into various sub categories so that productivity improvements may be determined and

implemented.

This study incorporated the following activity categories to reflect construction,

maintenance, and shutdown turnaround activities. Each of these categories includes

examples of events which helped as references to achieve consistency in judgment during

observation with the activity analysis software. Most of these categories and examples

are an adaptation from the CII’s implementation resource 252 (“Guide to Activity

Analysis” 2010).

Direct work

Exerting physical effort directed towards an activity or physically assisting in

these activities, direct work often involved workers installing materials and/or equipment

but also included the physical effort of support groups. Direct work was observed during

installation or demolition work. The following are some specific examples of direct work

during construction or maintenance activities:

Page 44: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

30

Laborers:

• Installing forms, pipes, and other equipment

• Casting concrete

• Carrying out excavation works

Scaffolders:

• Erecting or dismantling scaffolding

• Modifying scaffolding

Pipefitters:

• Fitting or dismantling pipes

• Grinding or welding an installation

• Connecting or disconnecting a pump or other equipment

• Installing or uninstalling blinds

• Hydro testing or physically assisting in similar activities

Carpenters:

• Erecting or stripping formwork

• Erecting or dismantling temporary structures

• Installing doors and finishes

• Installation of shoring

Page 45: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

31

Truck drivers: (only those involved in the work being observed)

• Driving trucks to pick up or discard material

• Delivering material and equipment

• Decommissioning and transporting material or equipment

Ironworkers:

• Erecting, welding, grinding, bolting, and positioning

• Dismantling steel structures

• Rigging material

• Positioning, tying, and placing rebar

Cement finishers:

• Actively engaged in a concrete pour or assisting with a concrete pour

• Finishing concrete

• Grouting

Operators: (only those involved in the work being observed)

• Lifting or transporting materials

• Actively positioning equipment, boom, or hook

• Oilers actively engaged in maintenance of equipment

• Assisting with placement of equipment

Page 46: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

32

Millwrights:

• Installing equipment

• Aligning equipment

• Adjusting equipment

• Installing or adjusting shims

Electricians:

• Installing temporary power

• Installing raceway

• Cable pulling

• Installing duct bank

• Pulling or terminating cable

• Testing systems

Painters:

• Preparing surfaces

• Applying coating material

• Removal of paint

Page 47: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

33

Insulators:

• Laying out patterns

• Shearing metal

• Fitting components

• Installing insulation

• Removing old insulation

Sheet metal workers:

• Cutting or shaping metal

• Fabricating activities

• Welding, fitting, or repair activities

• Installing or demolition of ductwork

Note: Indirect labor like management or safety officers/engineers involved with such

work should not be counted in the sampling process.

Waiting

Periods of waiting or idleness even if attentive to ongoing work by other craft was

classified as waiting and here are some of examples that helped in identifying the

subcategories under waiting.

Page 48: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

34

Permits:

• Waiting for permits or to be signed off the task

• Waiting to gain access to the work area

• Waiting at the clock to clock in or clock out

Instruction:

• Waiting for instruction or a job assignment from foreman or other supervisor

• Stand by activities caused by trade practices or jurisdictions

• Waiting to receive instructions at the gang box or foreman’s station (Craft

personnel are not attentive to the work going on)

Material:

• Waiting in line at a warehouse or any other material or parts storage area

• Waiting for a concrete bucket to return with the next load of concrete

• Waiting for a truck to be loaded or unloaded (truck driver)

• Waiting for a weld or material to cool down

Page 49: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

35

Equipment:

• Waiting on scaffolding

• Waiting for a truck, crane, or a bus to arrive to transport material or personnel

• Waiting for a cable pull to begin

• Waiting for a crane to hook to return for the next lift

• Waiting for an opportunity to maintain equipment

• Waiting for an opportunity to assist an operator (oiler)

• Waiting for an item to lift or move (operator)

• Waiting for the elevator

• Waiting for equipment to cool down

• Waiting for another crew or technician to finish using tools or equipment

QA/QC:

• Waiting for safety/QA/QC to sniff out a tank before entering

Page 50: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

36

Unknown:

Since it was challenging to distinguish and classify some of these instances, they

were categorized under “unknown”. In such scenarios, a voice recording narrating the

observations of the site conditions at that time helped during the development of the

observation summary. Here are some such instances:

• Waiting for a welder to complete a weld (pipefitter).

• A worker waiting at the top of the column.

• A utility crew waits while a back hoe operator digs a trench.

• Millwrights wait while electricians disconnect a pump.

• Waiting on a crew member while he gets material or parts.

Preparatory work

Activities related to receiving assignments and determining requirements prior to

performing tasks was categorized as preparatory time. They included stretching activities,

safety talks, and start card processes. This also includes discussions to explain or plan the

task at the work location. These discussions took place between craft persons or between

supervisor and craft.

• Receiving preparatory instructions at the gang box or foreman’s station (craft

personnel were observed to be attentive).

Page 51: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

37

• Any craft actively engaged in performing fire watch, confined space watch,

providing tool or rod room attendant services, or physically assisting in another

crafts direct work.

• Setting-up works, such as covering the work area with canvas prior to welding

works.

• Painters mixing paint prior to carrying out the task.

• Providing flagging or rigging support.

• Flagging an operator.

• Actively involved in general traffic flagging or control.

• Assisting with concrete pours.

• Assisting with excavations.

• Distributing water and assisting other crafts with direct work.

• Clearing debris and housekeeping works.

• Receiving drawings, specifications, or other task related and necessary

information.

• Using telephones or radios for work related reasons.

• Inspecting the work area with supervision, safety, or other craft to determine task

requirements.

• Discussing material, tool, or equipment needs.

• Actively participating in stretching, safety talks, or the start card process.

Page 52: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

38

Material handling

This category included activities associated with obtaining, adjusting, and

transporting material from one part of the facility to another. This category did not

include moving items such as beams, pipe spools, permanent plant equipment, conduit,

wire, rebar, etc. in the general area of the task or into their final position.

• Supporting crafts transporting bulk materials from the laydown area to project

work areas (operators and teamsters are direct work, but supporting crafts are

material handling.)

• All craft persons physically carrying steel, pipe, insulation, etc. from one location

to another.

• Scaffolders handling materials and unloading materials at different locations.

Page 53: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

39

Tools and equipment

This category included activities associated with obtaining, transporting, or

adjusting tools or equipment in preparation of performing direct work. Specific instances

like the ones below were used to describe this category.

• Locating a grinder or other tool in a gang box and transporting it to the task area.

• Running welding leads to the work area or adjusting the welding machine.

• Connecting electrical supply or air supply to tools or construction equipment.

• Obtaining and transporting slings, shackles, or similar tools equipment.

• Putting on safety harnesses, face shields, cleaning safety glasses, or physically

adjusting PPE (does not include donning/ doffing or adjusting personal clothing).

• Adjusting the location of a JGL, Scissors lift in the immediate vicinity of the

work.

Page 54: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

40

Travel

Walking or riding empty handed or without tools, materials or technical

information was categorized as travel. Following are some instances that described travel.

• Any craftsperson walking or riding with empty hands or carrying normal tool belt

tools.

• An operator of any equipment using the equipment to travel from one site location

to another.

• If the travel of equipment does not include adjusting position in the general

vicinity of the work.

• Craftsmen travelling to and from work areas and store during normal working

hours.

• Walking to or from breaks and lunch.

• Travelling for work at height.

• Walking with drawings, prints, work packages, etc.

Page 55: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

41

Personal

• Rest periods or coffee breaks during normal work hours.

• Smoking breaks or snack breaks during normal work hours.

• Rest room or water breaks during normal work hours.

• Obvious socializing and being non attentive to work on the job site.

• Sleeping during normal work hours.

• Donning, doffing, or adjusting personal clothing.

• Personal clean up time before or after breaks.

• Personal conversation not related to the task.

Other issues

Although the above list tries to capture various activities and their categories,

there are instances during the time of observation where it is difficult to categorize an

activity under a particular category. Some of these instances may be:

Craft working in hidden areas, confined spaces and work at height

Craft workers working in areas without access or clear vision for observation are

hard to sample.

Page 56: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

42

Weather delays due to lightning, rain etc.

When work at the job site is paused due to weather, the activity analysis software

should be paused. In order to capture additional information and explain some of these

specific challenges observed at the site, the recording feature of the software is useful.

Page 57: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

43

ACTIVITY ANALYSIS SOFTWARE

Researchers in collaboration with Enstoa (Software development firm) developed

activity analysis software to help with the sampling process of activity analysis at

Singaporean petrochemical facilities. The tool consists of an intrinsically safe tablet

computer that runs the activity analysis application on a windows 8 platform.

Features

This software allows a user to organize activity analysis data by capturing the

following:

• Name of plant or facility being observed

• Project name

• Companies (Contractors/Subcontractors) involved in the projects

It also allows observers to capture the following parameters that may impact labor

productivity:

• Study location (field or shop).

• Activity type (construction, maintenance or shutdown turnaround )

• Weather (temperature/humidity/rain)

• Number of workers (to determine the minimum sample size)

Page 58: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

44

The tool also automatically calculates (using the information in Table 9) the

minimum number of samples required per hour, after entering the number of workers in

the software.

During the setup, the screen provides a text box for users to include instructions

for the day that may be specific to the project on the day of data collection.

The activity analysis screen shown below in Figure 8 is used for collecting

samples by classifying observations into the activity categories on this screen.

Figure 8: A screenshot of the observation setup screen

Page 59: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

45

The software keeps track of the total number of samples observed at the top of the

screen. The number in front of each category represents the count for that category.

By default, the tool records each craft worker as a full time employee; however

the tool also provides an option of selecting short service employees.

The record audio feature on the tool can be enabled by selecting “start recording”

on the screen. This feature can be used to capture observations, challenges, and

communications with workers or superintendents on the field. These are especially useful

during analysis to generate recommendations to improve direct work time

After collecting the required number of samples, the observation can be exported

to a .csv file from the activity analysis software. The .csv file exported from this software

is easier to work with when saved as an MS Excel file. This can be done by opening the

exported .csv file and clicking on “save as” under the file menu. This spreadsheet is now

ready to proceed with further analysis as described in Chapter 6.

Page 60: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

46

Observation summary

While the tool provides support in collecting samples, capturing and making notes

about other observations and comments on the site during activity analysis provides

critical data that will be extremely useful during the analysis and recommendation phases

of the study. The team performing activity analysis is highly encouraged to make several

relevant comments be them in audio or written notes. It is recommended that the written

notes and other comments are compiled frequently and electronically as an “observation

summary” in the interest of preserving every observation and to enable future sharing of

data.

Page 61: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

47

Chapter 5: Extending Activity Analysis Sample Phase

PREPARING FOR DATA COLLECTION

The following steps will help in planning and executing activity analysis data

collection effectively in both construction and maintenance environments at

petrochemical facilities:

1. Provide an overview of activity analysis to the selected project team

2. Collect project details shown below, from the project manager using an

information sheet:

a. Location.

b. Area description.

c. Scope of work.

d. Safety instructions.

Complete the required safety training a few days before the

sampling day.

Verify the safety requirements and ensure the availability of

Personal Protective Equipment (PPE).

Page 62: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

48

e. Description of contractors and subcontractors on the project.

Identify the companies (contractor and subcontractors) involved in

the project and observe the differences in uniform, safety vest

colors, logos, and hard hat colors, etc. to differentiate one from the

other during sampling.

Look for identifiers to differentiate craft from foreman,

superintendents, safety, quality personnel, and management.

f. Propose and coordinate for meeting and data collection dates.

3. Study the scope of work along with the information collected in the previous step.

4. Coordinate logistics, facility permits and finalize data collection dates.

5. Request and attend a preparatory meeting and site walk through with project

manager.

6. Conduct data collection.

a. Request the plant manager to provide a site layout and sketch random

routes within the vicinity of the plan to ensure significant workers on the

job site.

b. Schedule sufficient days to achieve the minimum number of observations

based on the expected number of workers on the project being observed.

Page 63: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

49

DATA COLLECTION CHALLENGES

The observers may experience a few challenges in a petrochemical setting and

being prepared for the following will make the process effective:

• Observations may have to be paused during weather breaks (rain or lightning).

• Observing workers in confined spaces or at heights can be challenging.

Sometimes a crew supervisor may be consulted to understand the activity

category in such cases.

• It can be difficult to keep track and be consistent while observing a large group of

workers clustered in a work area. On the other hand, it may be hard to meet the

number of observations for smaller groups.

• Although it might take some time to get used to, it is important to differentiate

indirect labor like management, or safety officers and engineers involved in

projects being observed.

Page 64: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

50

ACTIVITY ANALYSIS SAMPLING

In order to maintain consistency across the observers within the data collection team,

the following rules of sampling were implemented.

• Every observation in a tour was a mental snapshot, which was recorded as a count

under the relevant category for each craft worker.

• The rating was taken at the first instant of observation and observers avoided

anticipation of a worker’s action.

• Observers kept moving and tried to vary the routes to keep the process of

sampling random.

• Observations were not be made during lunch hours.

• Observers did not consider foreman or site management during sampling and

focused only on the labor or craft workers.

MINIMUM NUMBER OF SAMPLES

For the data to reflect the distribution of work time effectively, it was critical to

collect a significant number of samples from the activities being observed. Table 9 below

was used to define the minimum number of samples to be collected based on the number

of craft workers involved with the activities that were being observed (“Guide to Activity

Analysis” 2010):

Page 65: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

51

Number of craft workers Minimum sample size per hour

0-50 46

51-100 84

101-150 116

151-200 144

201-250 168

251-300 189

301-350 208

351-400 225

401-450 240

451-500 253

501-550 265

551-600 276

601-650 286

651-700 296

701-750 304

751-800 312

801-850 319

851-900 326

901-950 332

951-1000 338

Table 9: Minimum sample size based on number of workers (“Guide to Activity

Analysis” 2010)

Page 66: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

52

Note: when the number of workers exceeds 1000, the minimum sample size per hour for

a specific number of workers “n”, was calculated using the following formula (Thompson

1987): Minimum sample size per hour = (n*510) / (n+510)

The following example shows the process that was used to monitor the minimum

number of samples collected:

Assuming the number of workers on a certain project to be observed is 300; Table

9 suggests that a minimum of 189 observations for every hour of a typical work day

should be collected to reach 95% confidence level. To make 189 observations in each

hour, sampling could be spread across 3 days in order to satisfy this minimum sample

size per hour. Here are two hypothetical cases that meet the minimum requirement:

Case 1

63 observations from 8am to 9am on each of the three days of the study

Case 2

50 observations from 8am to 9am on day 1;

69 observations from 8am to 9am on day 2;

70 observations from 8am to 9am on day 3;

The intent is to capture the minimum required samples under each hour of a work

day spread across all the days of the study.

Page 67: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

53

Chapter 6: Activity Analysis Report Generation

EXPORT DATA FROM ACTIVITY ANALYSIS SOFTWARE

Shown below in Figure 9 is a screenshot of the .csv file generated from activity

analysis software.

Figure 9: Export .csv file example

The information from this file can be tabulated and organized using MS Excel

spreadsheets. An example of one such spreadsheet is shown in Table 10 below. Note that

the data in this Table 10 is for demonstration purposes only.

Page 68: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

54

Analysis Time 7:00 8:00 9:00 10:00 11:00 1:00 2:00 3:00 4:00

Daily Total

Category total

Percent of observations

8:00 9:00 10:00 11:00 12:00 2:00 3:00 4:00 5:00

Direct work

Day 1 52 42 37 55 36 38 44 35 61 364

916 44.88% Day 2 35 38 32 31 38 32 32 42 24 266

Day 3 28 36 33 39 42 25 35 40 50 286

Prep work

Day 1 18 8 8 12 11 8 8 12 18 92

285 13.96% Day 2 6 12 21 15 25 15 20 24 16 129

Day 3 8 5 7 12 8 7 5 12 8 64

Tools/equip

Day 1 22 12 8 2 3 10 12 2 15 83

214 10.49% Day 2 15 6 5 5 4 5 6 5 12 59

Day 3 12 16 2 6 2 2 16 6 12 72

Material Handling

Day 1 20 8 12 9 18 6 8 19 1 83

187 9.16% Day 2 3 4 8 13 12 8 6 13 3 58

Day 3 4 8 7 4 5 7 8 4 4 46

Waiting

Day 1 3 5 9 10 12 9 5 10 3 54

189 9.26% Day 2 8 12 12 8 5 8 11 8 12 79

Day 3 2 12 8 6 7 8 12 6 2 56

Travel

Day 1 5 11 8 8 9 8 11 8 5 64

208 10.19% Day 2 7 6 11 9 4 11 6 5 7 62

Day 3 8 8 12 12 11 12 9 12 9 82

Personal

Day 1 3 1 2 3 2 0 5 1 2 17

42 2.06% Day 2 0 3 1 0 2 3 2 2 2 13

Day 3 1 2 2 2 3 2 0 2 1 12

Total Hourly 260 255 245 261 259 224 261 268 267 2041 2041 100.00%

Table 10: Organization of activity analysis data - example

Page 69: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

55

EXAMPLE CALCULATION FOR ANALYSIS

Shown below in Table 11 is an example for calculating the direct work percentage

from the above Table 10:

Analysis Time 7:00 8:00 9:00 10:00 11:00

Lunch 1:00 2:00 3:00 4:00 Daily

Total Category

total Percent of

observations 8:00 9:00 10:00 11:00 12:00 2:00 3:00 4:00 5:00

Direct work

Day 1 52 42 37 55 36

N/A

38 44 35 61 364

916 44.88% Day 2 35 38 32 31 38 32 32 42 24 266

Day 3 28 36 33 39 42 25 35 40 50 286

Table 11: Direct work calculation - example

Total Direct Work for day 1: 52 + 42 + 37 + 55 + 36 + 38 + 44 + 35 + 61 = 364

Total Direct Work for day 2: 35 + 38 + 32 + 31 + 38 + 32 + 32 + 42 + 24 = 266

Total Direct Work for day 3: 28 + 36 + 33 + 39 + 42 + 25 + 35 + 40 + 50 = 286

Total Direct Work for all days: 364 + 266 + 286 = 916

Direct work percentage: (Category Total/Total number of observations) *100

= (916/2041) *100 = 44.88%

Page 70: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

56

Similarly, percentages for all the other categories can be calculated. To further

analyze the results, Pie charts and hourly distributions can be generated using Excel or

similar tools as shown below in Figure 10.

Figure 10: Example activity category distribution pie chart

Page 71: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

57

ACTIVITY ANALYSIS REPORT GENERATION

Report Generation Sheet (RGS) Content

A report generation sheet (RGS) was developed using Microsoft Excel to analyze

the data exported from the activity analysis software in an aggregated manner; query by

trades; and also to visualize time trends. RGS contains the following tabs:

• Datasheet

• Direct Work Dashboard

• Aggregate Results

• Results by Trade

Datasheet

The datasheet tab holds the raw data exported from the activity analysis software

as seen earlier in Figure 9. The data from all the multiple projects can be collated into this

datasheet for aggregate analysis. The result tabs are classified into three sections – direct

work dashboard, aggregate results and results by trade.

Page 72: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

58

Direct Work Dashboard

This dashboard presents a quick glimpse of the direct work percentages for the types of

project or trade as shown in this Figure 11 below.

Figure 11: An example of direct work dashboard tab

Aggregate Results

Aggregate result tabs present activity analysis results for:

• All types of activities combined

• Construction activities

• Maintenance and Shutdown/Turnaround activities combined

• Maintenance activities

• Shutdown/Turnaround activities

Page 73: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

59

Results by Trade

These tabs query the activity category percentages for the different trades to be observed

during sampling:

• Equipment

• Site Work

• Scaffolding

• Piping

• Electrical

• Structural Steel

• Insulation

• Concrete

• Cleaning/Blasting

• Painting

• Instrumentation

Page 74: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

60

Each result tab mentioned above contains the following representations as shown in

Figure 12:

• Table and pie charts with activity category percentages

• Table and Histogram representing variation of activity category percentages with

time during a typical 8 hour work day

Figure 12: An example of aggregate result tab in RGS

Page 75: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

61

Using the Report Generation Sheet

Step 1 – Copy Data

1. Open the saved excel spreadsheet that was exported from the activity analysis

software. (Combine data from projects for aggregated analysis as desired)

2. Select all the cells that contains the data

3. Right click and copy all the selected cells

Step 2 – Paste Data

1. Open the Report Generation Spreadsheet (RGS)

2. Select the “Data sheet” tab

3. Right click on the highlighted cell (A1) and paste the copied data as shown in

Figure 13 below:

Figure 13: Screenshot of pasting software export data into RGS

Page 76: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

62

Step 3 – Review Result Tabs

1. Once the data has been pasted on to the datasheet tab correctly, all the result tabs

will be automatically populated

2. Now, the desired result tabs can be view to analyze the respective result tables

and charts

Page 77: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

63

Chapter 7: Recommendations to Plan and Implement Improvements

Multiple cycles of activity analysis will facilitate verification of the

implementation of productivity enhancements at petrochemical facilities.

The intention of collecting data in cycles is to measure improvements after

implementing intervention between cycles.

Percent change for direct work can be measured as:

(Direct work in cycle 2 – Direct Work in Cycle 1) / (Direct Work in Cycle 1)

The following section compiles some trends that can help in comparing and

analyzing activity analysis studies at petrochemical facilities.

Expected proportions in activity category percentages

Many projects witness a significant amount of time on preparatory work, material

handling and traveling, in proportion with the observed productive direct work time while

performing construction, maintenance and shutdown turnarounds activities. A

considerable amount of time is also spent on information exchange while maintaining

these facilities.

Page 78: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

64

Interpretation of results

The primary objective here is to decipher the numbers and prepare

recommendations to improve the direct work time and other activity categories observed.

This can be achieved by following these steps:

• Compare collected data with industry averages and world class direct work rates

available from background review, past experience of researchers and subject

matter experts from the industry (presented in Table 12 in the next section of this

chapter).

• Determine the categories that are outside the norm and identified the main reasons

causing this discrepancy. The observations and notes from activity analysis will

come in handy during this stage.

• Analyze how policies, execution flaws, challenges, or management processes

affect too much waiting, too much travel, or too much personal time.

• Each project and/or plant is unique, but the data provides clues on what to look

for and a sense of direction for improvement.

• Based on these interpretations, each team can develop recommendations to

implement improvements on their projects

Page 79: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

65

The direct work percentage can be ranked into its respective quartile from Table 12

and prepare for realistic targets to eventually reach the first quartile. Reviewing the

results in detail and analyzing other activity categories pointed towards key areas of

opportunity for improvement.

Probable causes for low direct work rates

This section discusses some potential causes for certain scenarios such as high

waiting time, high travel time, or high personal time, which was observed during activity

analysis. However other project specific causes may need further investigation in addition

to the following:

Page 80: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

66

• Lack of supervision in both front line and superintendents.

• Significant design issues.

• Overmanning issues.

• Poor planning of material availability on site.

• Tools and equipment availability issues.

• Site access issues such as toilets and stores in isolated locations.

• Workers waiting for the scaffolding modification during the course of work.

• Material and tools store are placed far away from work place travel.

• Constantly changing priorities due to management decisions, for instance material

procurement.

• Poor coordination between trades.

• Unestablished first line supervision and job expectations.

• Weather conditions.

• Permits.

• Resources not scheduled or levelled appropriately.

• Poorly managed starts, stops, and breaks.

Page 81: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

67

World class direct work rates

The total daily direct work rates considering all times of the work day and all

disciplines involved can be used for benchmarking purposes and identifying

improvement strategies. Historical data, literature review and past experience of

researchers and subject matter experts from the industry, suggested the following

quartiles shown in Table 12 below, for the total daily direct work rates in construction

and maintenance activities:

Quartiles Maintenance environment Construction environment

First quartile 42% and above 50% and above

Second quartile 32% to 42% 38% to 50%

Third quartile 20% to 32% 27% to 38%

Fourth quartile Below 20% Below 27%

Table 12: Direct work rate quartile ranges

Along with the numbers, in order to identify what and where to improve as well

as to implement improvements, it is crucial that the observation points during activity

analysis (data collection) can be documented and correlated with the final results.

Based on the observation points and the analysis results, and meeting with the

management team will help in identifying plausible solutions to increase direct work and

to reduce non-productive activities.

Page 82: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

68

Best Practices - First and Last Work Hours of the Day

The first and last work hours of the day typically experience lower direct work rates.

Certain steps when planning and scheduling maintenance activities are suggested to

reduce and control this drop:

• Weekly planning meetings should be scheduled with the participation of all

interested parties from both the owner and contractors to discuss and finalize the

schedule for the next week. Attendees should include planners, schedulers,

operations personnel, and maintenance teams.

• The maintenance team should have an adequate number of maintenance planners

and schedulers. A typical rate is one planner for every 25 maintenance workers

and one scheduler for every four planners.

• Once the work orders for the next week have been created by the planner, the

ready-to-schedule information should be shared with the scheduler to verify

conflicts and schedule the tasks. The planner should confirm the approval of the

tasks from operations and ensure that the materials are procured and reserved for

the task using a maintenance management information system.

• Daily plans should be confirmed on the previous day and shared with front line

supervisors and foremen in advance.

• Supervisors and foremen should arrive one hour earlier than the start of the work

day to check the plan and start obtaining work permits.

Page 83: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

69

• Supervisors and foremen should set up detailed objectives and clear work

expectations for the maintenance team in advance.

• Planners and schedulers should account for the possibility of emergency

corrective maintenance tasks being requested on a given day. Organizing short

early morning planning meetings should help in adjusting the plans and schedules

to resolve such last minute requests.

• The “first job rule” should be applied when considering last minute maintenance

requests. This means that the schedule for the first job of the day should not be

altered even in the case of corrective maintenance requests (pending an

emergency). This will enable the craft workers to get the permits and begin to

work according to the original plan. The remaining part of the day can be re-

adjusted by the planners, schedulers, supervisors, and foremen to accommodate

the last minute corrective maintenance requests.

• Schedule compliance is a top priority for many contractors. A common practice to

achieve this compliance has been to resource load the schedule to 80% and not

100% of their potential resources. This may impact the direct work rates by

having unaccounted resources on the job site to handle emergency corrective

tasks that may come up during the day.

• In order to improve direct work rates and better coordination between workers

and supervisors, it is highly recommended to conduct a short pre-start talk/ tool

box meeting every day prior to the commencement of work.

Page 84: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

70

• The supervisor/ foreman should conduct a pre inspection of the work location

prior to pre-start talk.

• The pre-start talk should be conducted adjacent to the work locations if possible.

• All workers involved in the task and the safety personals should be present during

the pre-start talk.

• The specific task of the day should be clearly explained in detail to all the

workers.

• It is recommended the person who conducts the pre-start talk should be

enthusiastic and able to speak the same language as the group of workers assigned

for the task.

• The supervisor should actively encourage the workers to participate in the pre

start talk.

• A pre-start talk form should be developed in order to document the specific work

task in steps, work site hazard, mitigation measures and identify nearby

operations.

Page 85: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

71

Best Practices - Lunch Breaks

Following are recommended practices to enhance direct work around breaks:

• Employees should be allowed to take breaks when it is convenient for the job

under way, rather than at a specific time of the day. This would allow workers to

take a break when in route to a new task instead of taking a separate trip.

• Some permits expire when a worker breaks for lunch. Thus, it is important to plan

and streamline the process of renewing permits for the tasks to be performed in

the afternoon.

• In some situations, it may be advantageous to stagger lunch hours for different

crews. This can help in ensuring continuity of work throughout the day and also

in controlling traffic at the permit offices.

• Supervisors and foremen should actively supervise the work in the hour before

and after the lunch break.

• Ensuring adequate transportation and sufficient restrooms in the vicinity of the

work area could reduce travel and personal time.

Page 86: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

72

Best Practices - Weather Breaks

Following are some recommended practices to be prepared for weather breaks:

• Weather stoppages may require workers to renew some permits depending on

their type. (e.g.: hot work permit, welding permit). Thus, it is important to plan

and streamline the process of renewing permits for the tasks to be performed after

the work resumes.

• Supervisors and foremen should actively direct the workers to return to the work

place as soon as the activities are authorized to resume.

• In some cases, the office that issue permits may be understaffed and not able to

issue multiple permits in a short period of time. Setting up multiple permitting

desks may help reduce the time involved in preparing to start the work after such

breaks.

• Supervisors and foremen should be able to start working on permits before the

work resumes.

• Some maintenance tasks may be conducted in shelters during weather stoppages.

Page 87: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

73

Best Practices - Transition Periods for Multiple Shifts

These suggestions are provided to help with monitoring transition between shifts:

• Shutdowns and turnarounds typically require more front end planning since it

involves larger crews that are usually not familiar with the facility and permitting

processes. In this situation, supervisors and foremen should arrive one hour early

to arrange work permits and confirm the schedule of the day.

• Shut down and turnarounds may involve multiple shifts (e.g.: two 12-hour shifts)

during a prolonged period of time. Workers’ motivation and health should be

considered when planning and scheduling the work.

• Craft workers should be incentivized to keep high motivation levels. To ensure

effectiveness and reliability of the work, incentives may be designed to consider

metrics such as productivity, quality, safety, schedule, and rework.

• Ergonomics of the nature of work may impact direct work and hence it is

important to create an appropriate work environment, especially on shifts with

such long hours.

• Alternative work shifts may be considered. For instance, two 10-hour shifts may

be more effective to address the concerns mentioned above. In this case, a small

transition crew may work in the two hours’ in-between shifts to plan the transition

and make it more effective.

Page 88: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

74

Chapter 8: Conclusions and Recommendations

CONCLUSIONS

The main objective of this study was to establish the idea of implementing a

continuous improvement program to enhance labor productivity at petrochemical

facilities. The activity analysis software that was developed worked well and safely with

the intrinsically safe tablets at various petrochemical units that were studied. The

extended methodology also provides a way to monitor the various trades working on

projects and help in recognizing the benefits of this continuous improvement program.

The first round of activity analysis in a plant provides an assessment of the

existing conditions and provides a baseline for monitoring a labor productivity indicator –

“direct work”. Trends with activity categories and fluctuation of direct work over a work

day especially around day start, end, breaks and during transition of shifts can be

expected in petrochemical maintenance and construction activities.

Selecting projects with similar scope of work in multiple activity analysis cycles

will help in analyzing and monitoring results that are truly reflective of the conditions

observed at the job site. Sampling craft working in enclosed spaces or at heights in a

maintenance environment can make it difficult for observers to predict the nature of work

and categorize the activity. Direct work on projects may or may not improve much as

Page 89: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

75

within the first few cycles, but sticking to the continuous improvement process will

eventually enhance the performance.

Improvement depends on identifying and removing constraints and also

management and supervisory effort to identify problems and implement suggestions.

Multiple cycles of activity analysis can demonstrate quantifiable improvements to

monitor progress. Identifying key improvement opportunities, especially the low hanging

fruits, will help to see the value of activity analysis, get comfortable with the process and

spread awareness among several teams on construction projects, maintenance and

shutdown turnaround activities.

Page 90: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

76

RECOMMENDATIONS FOR FUTURE RESEARCH

This research has provided a framework along with results for a continuous

improvement technique that works on various types of activities in a petrochemical

facility. In order to practice this efficiently, it is important for the top management of

companies to believe in the methodology and stay committed to the process. Nominating

a productivity sponsor for an organization can drive a dedicated task force to select

appropriate projects and measure, monitor and enhance performance. This can be

achieved by identifying challenges such as reduction of direct work around first hour,

lunch, weather breaks and taking steps to focus, schedule, plan and prepare for such

situations. Documenting, prioritizing and acting upon the identified opportunities can

help in reducing the time spent on preparatory work, material handling, tools and

equipment, and travel.

Creating a systematic lessons learned practice in the organization and recording

every strategy developed and implemented over the various activity analysis cycles can

lead to a comprehensive knowledge database for productivity improvement.

Along with time stamp data, collecting location coordinates for observations can

help in mapping the routes and further extend the scope of analyses to identify

bottlenecks on site, coordination issues between trades due to site layout, material storage

and tool room distances from work site.

Page 91: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

77

Technology is rapidly changing the way things work in all industries. Work

sampling in the past was manually conducted using paper and pencil and we have come a

long way by using touch screen tablet computers to work efficiently and collect a lot

more samples in a given time. In the future, controlling such software remotely, using

technology like drones can address the challenge of getting around hazardous areas or

work at height with much less human fatigue.

Page 92: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

78

References

Goodrum, Paul M., Dong Zhai, Yongwei Shan, Gabriel Dadi, Carl T. Haas, Michael C.

Gouett, Mahdi Safa, Di Zhang, Carlos H. Caldas, and Maria Benzekri. 2012.

“Craft Productivity Research Program Phase 2.” Research Report 252-11a.

Construction Industry Institute.

“Guide to Activity Analysis.” 2010. Construction Industry Institute.

Oglesby, Clarkson H., Henry W. Parker, and Gregory A. Howell. 1989. Productivity

Improvement In Construction. McGraw-Hill Book Company.

Palmer, Richard D. 2006. Maintenance Planning and Scheduling Handbook. Second

Edition. McGraw-Hill Book Company.

Smith, Francois. 2006. “A Human Resource Forecast Model to Support New Plants in the

Oil and Gas Industry.” University of Stellenbosch.

Waidelich, Scott Jacob. 1997. “THE NAVY PUBLIC WORKS CENTER SAN DIEGO

CRAFTSMEN PRODUCTIVITY ANALYSIS.” The University of Texas at

Austin.

Yolton, John. 2008. “Calculating Wrench Time - Statistical Activity Surveys.” San

Diego, CA: SKF Reliability Systems.

Thompson, S.K. (1987). “Sample size for estimating multinomial proportions.” The

American Statistician, 41, 42-46.

Page 93: SHOUNAK-THESIS-2016.pdf - The University of Texas at Austin

79

Liou, F. & Borcherding, J. D (1986). “Work sampling can predict unit rate productivity.”

Journal of Construction Engineering and Management, 112(1).

“Calculating Wrench Time – Statistical Activity Surveys” 2008. SKF Group

Marjatta Strandell (1976). “Productivity in power plant construction.” 1976 AACE

Transactions, pp. 334-337