Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ® Copyright © 2017 IHI Corporation All Rights Reserved. Gastech2017 -Technical sessions- Stream 3: Gas & LNG Storage & Containment Onshore Tanks Tank Project Dept. Field Engineering Manager, Hirotsugu TATEISHI
21

Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Mar 28, 2018

Download

Documents

buihanh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Shortening LNG Storage Tank Construction Period

by the Jack Climbing Method®

Copyright © 2017 IHI Corporation All Rights Reserved.

Gastech2017 -Technical sessions-

Stream 3: Gas & LNG Storage & Containment – Onshore Tanks

Tank Project Dept.

Field Engineering Manager, Hirotsugu TATEISHI

Page 2: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

IHI Corporation

Copyright © 2017 IHI Corporation All Rights Reserved.

Social Infrastructure and Offshore Facilities(Bridge, Transportation System, Security, etc.)

Aero Engines and Space (Jet Engine, Rocket)

General-Purpose Machinery(Compressor, Separator, Turbo charger, etc.)

Industrial Systems(Steel Manufacturing Furnaces, Heat/Surface Treatment

Equipment, Logistics Systems, Material Handling Equipment, etc.)

Resources, Energy and and Environment(Boiler, Gas Turbine/Gas Engine, LNG Terminal, Process Plant, Nuclear Eqipment, etc.)

Resources,

Energy and

Environment

Aero Engines

and Space

Industrial Systems

and

General-Purpose

Machinery

Social

Infrastructure

and

Offshore Facilities

Page 3: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Construction Period of LNG Receiving Terminal

Copyright © 2017 IHI Corporation All Rights Reserved.

Tank Civil

Terminal Civil

Tank Mechanical

Terminal Mechanical

Start of Construction Ready for Cool Down

1st year 2nd year 3rd year 4th year

Page 4: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Structure of Double Roof Type Tank

Copyright © 2017 IHI Corporation All Rights Reserved.

OUTER ROOF

INNER ROOF

KNUCKLE PLATE

BOTTOM INSULATION

INNER BOTTOM PLATE

BOTTOM LINER PLATE

ROOF STRUCTURE / PIPING

PC WALL

BASE SLAB

INNER SHELL PLATE

OUTER SHELL LINER PLATE

SHELL INSULATION

Page 5: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Structure of Deck Type Tank

Copyright © 2017 IHI Corporation All Rights Reserved.

SUSPENDED DECK / INSULATION

OUTER ROOF

CONCRETE ROOF

INNER SHELL PLATE

OUTER SHELL LINER PLATE

SHELL INSULATION

BOTTOM INSULATION

INNER BOTTOM PLATE

ROOF STRUCTURE / PIPING

PC WALL

BOTTOM LINER PLATE

BASE SLAB

Page 6: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Conventional Tank Construction Method #1

Copyright © 2017 IHI Corporation All Rights Reserved.

PC WALL

KNUCKLE PLATE INNER ROOF

OUTER ROOF

AIR RAISING OUTER ROOF

BASE SLAB

INNER SHELL PLATE

OUTER SHELL LINER PLATE

Outer Tank Air Rising Method

Page 7: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Copyright © 2017 IHI Corporation All Rights Reserved.

Pros and Cons of Outer Tank Air Rising Method

Pros

Less weather interruption / damage

(Higher quality construction)

Cons

Longer construction period

Higher risk of accident

Outer Tank Air Rising Method

Page 8: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Conventional Tank Construction Method #2

Copyright © 2017 IHI Corporation All Rights Reserved.

PC WALL

BASE SLAB

KNUCKLE PLATE

INNER ROOF

OUTER ROOF

OUTER SHELL LINER PLATE

INNER SHELL PLATE

OUTER ROOF

AIR RAISING

Inner Tank Air Rising Method

Page 9: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Pros and Cons of Inner Tank Air Rising Method

Copyright © 2017 IHI Corporation All Rights Reserved.

Pros

Shorter construction period

Cons

More weather interruption / damage

Higher risk of accident

Inner Tank Air Rising Method

Page 10: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Overview of JCM

Copyright © 2017 IHI Corporation All Rights Reserved.

JCM realizes…

Simultaneous construction of PC wall and inner shell plate

Minimum aerial / lifting work

Shorter construction period

Higher level of safety / efficiency / quality

Significant features of JCM

Page 11: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

JCM Sequence for Double Roof Type Tank

Copyright © 2017 IHI Corporation All Rights Reserved.

1 2 3 4

5 6 7 8

Page 12: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

JCM Sequence for Double Roof Type Tank

Copyright © 2017 IHI Corporation All Rights Reserved.

9 10 11 12

13 14 15

Page 13: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Effect of JCM for Double Roof Type Tank

Copyright © 2017 IHI Corporation All Rights Reserved.

Base Slab

PC Wall

Bottom Insulation/Inner Bottom Plate

Inner Shell Plate

Outer Shell Liner

InnerRoof

Test

Shell Insulation

OuterRoof

1st J/U Final J/D

Roof Structure/Piping

Base Slab

PC Wall

Test

Inner Roof/Outer Roof

Inner Shell Plate

Bottom Insulation/Inner Bottom Plate

Shell InsulationRoof A/R

Outer Shell Liner

Roof Structure/Piping

About 9 months

WORK FLOOR

WELDER

INSPECTOR

WORK FLOOR

INNER SHELL PLATE

Fitting / Welding / Inspection Jack Up

JCM

Outer Tank Air Rising Method Inner shell plate construction

Page 14: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Quick summary- Double Roof Type Tank and Deck Type Tank

Copyright © 2017 IHI Corporation All Rights Reserved.

INNER SHELL PLATE

INNER ROOF

OUTER ROOF

(METALLIC)

SUSPENDED DECK

CONCRETE ROOF

INNER SHELL PLATE

OUTER ROOF

(METALLIC)

Double Roof Type Deck Type

Page 15: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

JCM Sequence for Deck Type Tank

Copyright © 2017 IHI Corporation All Rights Reserved.

1 2 3 4

5 6 7 8

Page 16: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

JCM Sequence for Deck Type Tank

Copyright © 2017 IHI Corporation All Rights Reserved.

9 10 11 12

13 14 15

Page 17: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Effect of JCM for Deck Type Tank

Copyright © 2017 IHI Corporation All Rights Reserved.

Base Slab

PC Wall

Outer Shell Liner

OuterRoof

BottomInsulation

Inner Shell Plate

※For Annular Part

Roof A/R

RoofConc.

Roof Structure/Piping

Test

Bottom Insulation/Inner Bottom Plate

Shell Insulation

Base Slab

Outer Shell Liner

PC Wall

OuterRoof

BottomInsulation

Inner Shell Plate

※For Annular Part

1st Roof J/UFinal Roof J/U

RoofConc.

Roof Structure/Piping

Bottom Insulation/Inner Bottom Plate

Test

Shell Insulation

About 6 months

Outer Tank Air Rising Method

JCM

Page 18: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Experience #1 (Shin-Sendai Project)

Copyright © 2017 IHI Corporation All Rights Reserved.

Page 19: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Experience #2 (Soma Project)

Copyright © 2017 IHI Corporation All Rights Reserved.

Page 20: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF

Overall Summary

Copyright © 2017 IHI Corporation All Rights Reserved.

What can JCM realize?

• Shorter construction period

• High level of safety / efficiency / quality

This is an ideal method for constructing LNG tanks!

Page 21: Shortening LNG Storage Tank Construction Period by the ... Tateishi... · Shortening LNG Storage Tank Construction Period by the Jack Climbing Method ... SUSPENDED DECK CONCRETE ROOF