SHORELINE SCHOOL DISTRICT NO. 412 Capital Projects Advisory Review Board (CPARB) Project Review Committee (PRC) GC/CM Application: Einstein and Kellogg Middle Schools SEPTEMBER 1, 2017
34

SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

Jun 25, 2018

Download

Documents

vantuyen
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

SHORELINESCHOOLDISTRICTNO.412

CapitalProjectsAdvisoryReviewBoard(CPARB)ProjectReviewCommittee(PRC)GC/CMApplication:EinsteinandKelloggMiddleSchools

SEPTEMBER1,2017

Page 2: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application i September2017

Page 3: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application i September2017

TABLEOFCONTENTSTableofContents..........................................................................................................................................i

1. IDENTIFICATIONOFAPPLICANT...........................................................................................................1

2. BRIEFDESCRIPTIONOFPROPOSEDPROJECT.......................................................................................1

3. PROJECTEDTOTALCOSTFORTHEPROJECT.........................................................................................3

4. ANTICIPATEDPROJECTDESIGNANDCONSTRUCTIONSCHEDULE.......................................................4

5. WHYTHEGC/CMCONTRACTINGPROCEDUREISAPPROPRIATEFORTHISPROJECT...........................6

6. PUBLICBENEFIT....................................................................................................................................9

7. PUBLICBODYQUALIFICATIONS..........................................................................................................10

8. PUBLICBODY(SHORELINESCHOOLDISTRICT)CONSTRUCTIONHISTORY.........................................21

9. PRELIMINARYCONCEPTS,SKETCHES,ORPLANSDEPICTINGTHEPROJECT.......................................22

Exhibit1:MilestoneSchedule................................................................................................................23

Exhibit2:BondProgramPhasingPlan...................................................................................................24

Exhibit3:KelloggMiddleSchoolExistingSitePlan................................................................................25

Exhibit4:KellogMiddleSchoolExistingSiteConditionsandAccess.....................................................26

Exhibit5:KelloggConceptualSitePlan..................................................................................................27

Exhibit6:EinsteinMiddleSchoolExistingSitePlan...............................................................................28

Exhibit7:EinsteinMiddleSchoolExistingSiteConditionsandAccess..................................................29

Exhibit8:EinsteinConceptualSitePlan.................................................................................................30

10. RESOLUTIONOFAUDITFINDINGSONPREVIOUSPUBLICWORKSPROJECTS....................................33

Page 4: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 1 September2017

1. IDENTIFICATIONOFAPPLICANT

a. LegalNameofPublicBody:ShorelineSchoolDistrictNo.412

b. Address:

ShorelineSchoolDistrictMainOffice185601stAveNEShoreline,WA98155

c. ContactPersonName:MarlaMiller,Title:DeputySuperintendent

d. PhoneNumber:(206)393-4514Fax:(206)619-393-4204Email:[email protected]

2. BRIEFDESCRIPTIONOFPROPOSEDPROJECT

TheShorelineSchoolDistrict(theDistrict)isseekingapprovaltousetheGeneralContractor/ConstructionManageralternateprocurementprocessforbothEinsteinandKelloggMiddleSchools.RebuildingthesetwoschoolswillresolvecrowdingissuesatShorelineelementaryschoolsfortheforeseeablefuture,butwillrequirereconfigurationandreconstructionoftheDistrict’sexistingtwomiddleschoolsontheirexistingsites.ThetwoprojectsmaybebuiltbyasingleGC/CMormaybeawardedseparately–theprocurementprocesswillincludebothoptionsandwillcontainscoringcriteriaforbothseparateandcombinedprojects.

TheDistrictisrapidlygrowingandovercrowdingissuesareanongoingissueatDistrictfacilities.ArecentdemographystudyconductedbyDr.LesKendrickpredictsourstudentpopulationwillgrowbynearly1,500studentsoverthenext10years.WithShoreline’selementaryschoolfacilitiescurrentlyat96.4percentcapacity,additionalclassroomspaceneedstobecreatedtoprovidesuitablelearningenvironmentsforallShorelineandLakeForestParkstudentswithoutovercrowdingclassrooms.Duringthe2015-2016schoolyeartheDistrictformedanInstructionalProgramPlanningCommittee(IPPC)toevaluatefutureinstructionalprogramconfigurationstomeettheneedsofstudents.TheIPPCrecommendedthata6/7/8middleschoolconfigurationwouldbestsupporttheinstructionalandsocial-emotionalneedsofShorelinestudents.

TheDistrictreceivedbondapprovalbyover74%ofvotersfora$250millioncapitalimprovementsprogramonFebruary14,2017,whichisexpectedtoqualifyfor10percentstateschoolconstructionmatchinggrants.Thedriversofthebondprogramare:

• Alleviateelementaryovercrowdingandprepareforstate-fundedclasssizereductionsthatwillincreasetheneedforclassrooms;

• Providelearningenvironmentstosupportstudentachievement;

Page 5: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 2 September2017

• Expandandenhanceearlylearningopportunities;and

• Designnewbuildingstoenhanceschoolsafetyandsecurity.

TheseprojectsfundedbythebondwillprovidetheDistrictwiththecapacityandflexibilitytomeettheneedsofourgrowingstudentcommunity.

Projectstobecompletedaspartofthebondprograminclude:

• RebuildingEinsteinMiddleSchool(includedinthisapplication)

• RebuildingKelloggMiddleSchool(includedinthisapplication)

• ConstructinganEarlyLearningCenter(ELC)attheShorelineChildren’sCentersitetohousetuition-basedpreschool,HeadStartandEarlyChildhoodEducation(projectpreviouslyapprovedforGC/CMandcurrentlyinpre-constructionphase)

• RebuildingParkwoodElementarySchool(finaldesignandpre-constructionunderway)

EinsteinMiddleSchoolOverview

EinsteinMiddleSchool,locatedinthenorthwestpartoftheDistrict,hasacurrentenrollmentofapproximately750seventhandeighthgradestudents.Itwasbuiltin1968,andmostrecentlyremodeledin1992.Thecurrentbuildingisapproximately116,000squarefeetona430,000s.f.siteapproximatelytwomilesfromtheShorelineSchoolDistrictOffices.TheschoolhasbothspecialeducationandEnglishlanguagelearner(ELL)classes,andworkstointegratespecialneedsstudentsintoregularclasses.

ThenewEinsteinMiddleSchoolwillbeapproximately150,000s.f.andwillhouseapproximately1,000studentsingrades6-8.andconsistofgeneralclassrooms,agym,variousoutdoorplayareas,atrackandfield,commercialkitchen,cafeteria,andadministrativeofficesandsupportspaces.Thesiteimprovementswillincludereconfiguringon-siteparkingforstaffandvisitors,busload/unloadzones,busaccessandegress,newsidewalks,landscaping,andupgradingexistingutilityservicefeedsintothebuilding.

KelloggMiddleSchoolOverview

KelloggMiddleSchool,locatedinthesoutheastportionoftheShorelineSchoolDistrict,hasacurrentenrollmentofapproximately625seventhandeighthgradestudents.Kelloggwasbuiltin1952andthelatestschool-wideremodelwascompletedin1986.Kellogg’sHangTimeafterschoolprogramoffersstudentstheopportunitytofinishhomework,socializeandparticipateindiverseactivities,allinasafeschoolenvironment.

Thecurrentschoolbuildingisapproximately132,000squarefeetona895,000s.f.site.Itisapproximately2.7milestotheShorelineSchoolDistrictOffices.

ThenewKelloggMiddleSchoolwilladdgeneralclassrooms,reconfiguredstaffandvisitorparking,newbusload/unloadzones,akitchenandcafeteria,administrativeofficesandsupportareas,playareas,upgradestothetenniscourts,atrackandfieldrefresh,varioussiteamenities,andlandscaping

Page 6: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 3 September2017

throughoutthesite.ThenewKelloggMiddleSchoolwillbeapproximately150,000s.f.andwillhouseapproximately1,000students.

TheDistrictisbeginningtheprocessofcreatingEducationSpecificationsforthemiddleschoolsnow,andwillbegintheprocessofselectingaGC/CMforoneorbothprojectsimmediatelyuponapproval–wewanttohavetheGC/CM(s)onboardaswecompleteeducationspecificationsandpreparetobeginSchematicDesignatthebeginningof2018.DesignDevelopmentisscheduledtobecompleteinJuly2018andbiddingisscheduledtobegininlate2018withbothschoolsopeninginSeptember2020.

3. PROJECTEDTOTALCOSTFORTHEPROJECT

A. PROJECTBUDGETS:

A.1KELLOGGMIDDLESCHOOL

Item ProjectBudget

ProfessionalServices $6.1Million

EstimatedConstructionCosts $55.6Million

EquipmentandFurnishings $0.9Million

GC/CMConstructionContingency(3%) $1.6MillionSSDConstructionContingency(7%) $3.8Million

DistrictProjectContingency $0.8Million

Off-SiteCosts(permitsandutilities) $0.6Million

ContractAdministration $3.1MillionOtherCosts(Movingandlegalcosts) $0.4Million

SalesTax $6.3Million

ProjectTotal $80Million

A.2EINSTEINMIDDLESCHOOL

Item ProjectBudget

ProfessionalServices $6.1Million

EstimatedConstructionCosts $55.6Million

EquipmentandFurnishings $0.9Million

GC/CMConstructionContingency(3%) $1.6MillionSSDConstructionContingency(7%) $3.8Million

DistrictProjectContingency $0.8Million

Off-SiteCosts(permitsandutilities) $0.6Million

ContractAdministration $3.1Million

OtherCosts(Movingandlegalcosts) $0.4MillionSalesTax $6.3Million

ProjectTotal $80Million

B. FUNDINGSTATUS

Page 7: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 4 September2017

BothEinsteinandKelloggMiddleSchoolsarefundedbythe$250millioncapitalimprovementbondthatwasapprovedbyvotersonFebruary14,2017.Theentirecapitalprogramdoesnotrelyonstatematchingfunds.

4. ANTICIPATEDPROJECTDESIGNANDCONSTRUCTIONSCHEDULE

ThefollowingexhibitcontainstheGC/CMprocurementschedulethatwillbefollowedforbothschools,eitherasoneortwoseparateGC/CMcontracts.Theschedulealsooutlinesthemajormilestonesforthedesign,pre-construction,constructionandcloseout.Currently,theDistrictisplanningtorunthesetwoprojectsconcurrently,andthereforewillshowonescheduleforbothschoolsinthisapplication.Exhibit1alsoprovidesabreakdownofmajordesignandconstructionmilestonesfortheprojects.

GC/CMProcurementSchedule

Activity Dates

PRCApplication 9/1/17

PRCMeeting 9/28/17

FirstpublicationofRFPforGC/CMServices 10/2/17

SecondpublicationofRFPforGC/CMServices 10/9/17

ProjectInformationMeeting(tentative) 10/16/17

GC/CMRFPSubmittalDeadlinetoShorelineSDby10:00am(PST) 10/27/17

Open&ScoreSubmittalsReceivedforRFPs 10/30/17

NotifySubmittersofMostHighlyQualifiedSubmittersandInvitetoInterview 11/3/17

InterviewswithShort-ListedFirms 11/17/17

NotifySubmittersofMostHighlyQualifiedFirmsandInvitetoSubmitRFFP 11/20/17

RFFPSubmittalDeadlineandOpeningby10:00am(PST) 12/1/17

NotifySubmittersofScoringandMostQualifiedGC/CM 12/4/17

NTP/PreliminaryContractAwardbySchoolBoard 12/1/17

SchoolBoardApprovalofGC/CMSelection 12/4/17

Pre-ConstructionWorkPlanDue 12/15/17

GC/CMAgreementw/Pre-ConServicesExecuted 12/30/17

Pre-ConstructionServicesbyGC/CM 1/1/18-5/5/2019

MACCEstimate/Negotiation(90%CDs) Q32018

SchoolBoardApprovalofMACC/GMP Q42018

GMPAmendmentExecuted Q42018

{Note,theprojectschedulesforbothschoolsareidentical,andarethereforebeingshownasonescheduleinthisapplication.Detailedschedulesforeachsitewilldiffer,butGC/CMselectionandopeningdaywillremainidenticalwhetheroneGC/CMortwoisselected}TheDistrictisbeginningtheprocessofcreatingEducationSpecificationsforthemiddleschoolsnow,andwillbegintheprocessofselectingaGC/CMforoneorbothprojectsbeginningimmediatelyuponapprovalwiththeintenttohavetheGC/CM(s)onboardaswecompleteeducationspecificationsand

Page 8: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 5 September2017

preparetobeginSchematicDesignatthebeginningof2018.DesignDevelopmentisscheduledtobecompleteinJuly2018andsubcontractprocurementisscheduledtobegininlate2018withbothschoolsopeninginSeptember2020.

Duetothelackof‘swingspace’,theDistrictexpectsthatbothschoolswillremainoccupiedduringconstruction.Foreachschool,theDistrictwillworkwiththeGC/CMtodevelopaphasingsequencetominimizeimpactsoneachschool’sschedulesandoperations.Atemporarycertificateofoccupancy(TCO)willbeneededtoallowthestaffateachschooltosetuproomsaftertheFF&EprovidedbytheDistrictisinstalled.TCOisanticipatedaftertheenddateofmove-in,latesummer2020.Earlybidpackages(sitework,siteutilities,partialdemoandabatement)andpotentiallyaseriesofmini-MACCswillbeconsideredandmaybeutilizedtomaximizeconstructionefficiency,meettheprojectschedule,andminimizecostimpacts.

TheaboveDesignandConstructiondatesarepreliminaryandmaybeadjustedaftertheProjectteamhasevaluatedprojectphasing,biddingstrategies,andutilizationofanyMC/CMorEC/CMpackages.

ScheduleStatus

Ifyourprojectisalreadybeyondcompletionof30%drawingsorschematicdesign,pleaselistcompellingreasonsforusingtheGC/CMcontractingprocedure.

ThisdoesnotapplyasbothprojectsareinthedevelopmentoftheeducationspecificationsandtheconceptualdesignphaseandtheGC/CM(s)willbeaboardearlyinschematicdesign.Thefollowingscheduleoutlinestheapproximatetimeframesforeachproject,whichwillbebuiltconcurrently,andpossiblydeliveredaswithoneGC/CMortwo.

KelloggandEinsteinMiddleSchoolsDesignandConstructionSchedule

Activity Start Finish

ArchitectSelection July2017 July2017

SiteInvestigation 8/1/2017 9/1/2017

EdSpec./ConceptPhase 8/14/2017 12/31/2017

SchematicDesign 1/1/2018 4/16/2018

DesignDevelopment 4/16/2018 7/31/2018

LandUse/Environmental 4/16/2018 6/18/2018

ConditionalUsePermit 6/1/2018 10/31/2018

ConstructionDocuments 8/1/2018 2/11/2019

EarlyWork(Mobilization/Demo) 2/1/2019 4/30/2019

Construction 5/6/2019 5/30/2020

Punchlist 2/3/2020 5/30/2020

SubstantialCompletion n/a 7/1/2020

MoveIn 7/1/2020 8/10/2020

StartofSchool(tentativedate) n/a 9/7/2020

Closeout 7/1/2020 12/31/2020

Page 9: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 6 September2017

5.WHYTHEGC/CMCONTRACTINGPROCEDUREISAPPROPRIATEFORTHISPROJECT

Pleaseprovideadetailedexplanationofwhyuseofthecontractingprocedureisappropriatefortheproposedproject.Pleaseaddressthefollowing,asappropriate:

OfthesixcriteriaoutlinedinRCW39.10.340,threeareapplicable:

• Complexscheduling,phasing,orcoordination,

• Constructionatanexistingoccupiedfacility,

• InvolvementoftheGC/CMiscriticalduringthedesignphase,

Ifimplementationoftheprojectinvolvescomplexscheduling,phasing,orcoordination,whatarethecomplexities?

A. ComplexScheduling,Phasing,andCoordination

Thetwonewmiddleschoolswilleachbebuiltonthesiteoftheexistingschoolandathleticfields.Theaverageconstructionscheduleateachofthesetwoschoolsisapproximately14.5monthsforconstruction.

EachschoolmustbecompletedandoperationalbyearlyAugust2020inordertobeopenonthefirstdayofschool,whichistentativelysetforSeptember7,2020.Eachprojectwillhavemultiplephases,suchasearlywork(demo/abatementofexistingfacilities),newconstruction,renovationofexistingfacilities(ifrequired)andsiteamenities(landscaping,outdoorgatheringspaces,parkingandbusloadingzones).

TheDistricthasnoavailablespacetotemporarilyhousestudentsfromeitherschoolduringtheconstructionphase,thereforeaphasedapproachutilizingexistingclassroomsandsupportspaceswillbedeveloped.Eachschoolsitealsohaslimitedavailablespaceonsite.Assuch,constructionateachschoolwillrequirephaseddemolitionandconstruction,requiringdetailedcoordinationofutilityservices,circulation,andaccessforemergencyservices. Locationsofclassroomswilltransitionthroughouttheacademicyear,andwillrequireclearcoordinationasstudentsmovefromonespacetothenext.Duetothelackof‘swingspace’atothersiteswithintheDistrict,eachprojectmustbetreatedasa‘stand-alone’projectthataccommodatescarefulphasingandtransitionofstudentsinspacesthroughoutallphasesofconstruction.

Constructionactivities,fromcommencementtofinalpunchlist,willrequirediligentcoordinationwiththeDistrict,GC/CM(s),thesurroundingcommunities,staff,andstudents.Theteamswillneedtoworktogetherwiththeschoolcommunitytocoordinateanychangestoon-sitewalkwaysandcorridorsaffectedbyconstruction,temporaryutilityconnections,emergencyanddeliveryaccess,andbusaccess.

Eachschoolisanticipatedtohavephasedconstructionactivities,withaseriesofearlyworkactivities.Theseearlyworkactivitiesinclude,butarenotlimitedto:

• Earlysitework(TESC,siteclearing,removalofwalkways,setupofconstructionlogisticsandsitefencing)

Page 10: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 7 September2017

• Buildingabatement

• Buildingdemolition

• Earlyutilityinfrastructure

Thesecondphaseofconstructionwillincludemajorconstructionandabove-gradeactivitiessuchas:

• Newconstructionofthefacilitiesateachschoolsite

• Facilitiestoincludeclassrooms,specializedinstructionspaces,foodservice,andadministrativeandsupportspaces.

• Newparkingareasforstaffandvisitors.

• Newpassengerdrop-offareas.

• Newbusloading/unloadingareas.

• Sitelandscapingandoutdoorspacesamenities

Theschedulingcomplexitiesateachprojectthathavebeenidentifiedcannotbeovercomeusingatraditionaldesign-bid-build(D/B/B)approach.TodelivertheseprojectsintimeforthefirstdayofschoolinSeptember2020,theDistrictdesirestousetheGC/CMdeliverymethodtooptimizethedesign,construction,commissioning,andactivationoftheKelloggandEinsteinMiddleSchoolsandworkwiththeDistricttoimplementsuitableriskmanagementstrategies.Complexitiesinclude:

• OccupancybyearlyAugust2020forbothschools.

• ExpeditedpermittingprocesseswiththeAHJsthathavelittletonowindowforerror.

• Completingallhazmatandabatementactivitiesbythesummerof2019.

• Completingalldemolitionbetweenlatesummer2019toearlyfallof2019.

• Completingallsiteworkamenitiesandparkingconfigurationduringmidtolatesummer2020priortostaffmove-in.

• Completingallmajorexcavationsateachsitepriortothestartofthewetweatherwindowinthefallof2019.

• Optimizingconstructionactivitiesduringregularlyscheduledbreaks,holidays,andinterimstaffdays.

• SchedulingshutdownsandinterruptionstoutilitiesduringwindowsoftimewhereitdoesnotaffecttheDistrictfacilities,thesurroundingcommunity,orneighboringproperties.

• Executingconstructabilityandvalueengineeringactivitiesinparalleleffortstominimizeimpactstoconstructiondocuments.

• ObtainingatemporarycertificateofoccupancywiththeCityofShorelinepriortoanymove-inbystafforFF&Einstallationateachproject.

• ProvidingenoughtimeforKelloggandEinstein’sstaffandDistrictOperations&Maintenancerepresentativestogothroughanytrainingofnewsystemsinthefacilitiespriortothestartofschool.

Page 11: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 8 September2017

Iftheprojectinvolvesconstructionatanexistingfacilitythatmustcontinuetooperateduringconstruction,whataretheoperationalimpactsonoccupantsthatmustbeaddressed?

B. ConstructionatanExistingFacility

Bothschoolswillbebuiltonexistingsitesthatarecurrentlyfullyoperationalandin-use.EinsteinMiddleSchoolisadjacenttoaresidentialcommunityandpublicpark.KelloggMiddleSchoolsiteisadjacenttoShorecrestHighSchool.Bothschoolsarelocatedonbusyarterialstreetsaswell.Therefore,theprojectdemolitionandconstructionactivitieswillneedtoaccountfortheactivitiesattheadjacentpropertiesandconstantlyaddressthestudent,staffandgeneralpublic’ssafetywhileworkingunderthetypicaloperatingbusinesshours.Specialoccasionssuchasschoolorcommunityevents,holidaybreaks,andstaffbreakdayswillalsoneedtobeconsideredwhenplanningallconstructionactivities.

TheGC/CMteam(s)willneedtoaccommodatetheexistingsitepedestrianandvehicleflowsincludingbusdropoffandpickupareazonesforallPhaseIandPhaseIIactivities.Duringtimessuchasathleticorseasonaleventsonthesites,theGC/CM(s)willneedtoprovideamitigationplanforconstructionaccess,trafficcontrol,andcommunitynotificationtopreventdisruption.Inparticular,sinceeachsiteislocatedrelativelyclosetoresidentialdwellings,theGC/CM(s)willneedtoincorporateadditionalmeasuresandcommunicatethemtoensurethesafetyofthecommunity,schoolstaff,andthestudentsaremaintainedatalltimes.Additionally,theGC/CM(s)willhavetocoordinatewiththeDistrictstaffforanyutilityshutdowns,overnight,off-shiftorweekendworktomakesureanycommunityorschooleventsarenotnegativelyimpacted.

IfinvolvementoftheGC/CMiscriticalduringthedesignphase,whyisthisinvolvementcritical?

C. InvolvementoftheGC/CMisCriticalduringtheDesignPhase

Pleasenotethesetwoprojectsareslatedtostartandfinishwithinthesametimeframes.

Developingworkablephasingplansiscriticaltothefundamentalsofthedesignoftheprojects,giventhenear-certaintyofpartialdemolitionandoccupancyofnewspaceduringtheconstructionphase.TheDistrictwillrelyontheGC/CM’sexpertisefrompastprojects;and,therefore,theGC/CMwillleadthedevelopmentofthephaseplanningduringthepreconstruction.Themiddleschoolphasingplanswilldetailtheprecisestepsneededbyeachsub-tradetoeffectivelyandsafelycompletethework.Withexpertiseincontracting,theGC/CMwillperformduediligenceonallinformationgatheredduringthisplanningperiodandassessitforsafetyandefficiency.TheseearlyinvestigationsbytheGC/CMwillinformalldesigndecisionsandstreamlinetheconstructionprocess.

Thepreconstructionphasewillbeginatthebeginningof2018,andwilloverlapwiththeschematicdesign,designdevelopmentandconstructiondocumentdesignsubmittals.Aspartoftheirrole,theGC/CMwillworkwiththeteamtodevelopthebestwaystomaximizethesiteforallphasesofconstructiontoidentifytradeaccess,phasedstagingareas,truckhaulroutes,jobofficesandamenities,andpedestrianpathwaysalongtheperimeterofthesite.

Page 12: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 9 September2017

6. PUBLICBENEFIT

A. HowuseoftheGC/CMcontractingprocedurewillservethepublicinterest

Forexample,yourdescriptionmustaddress,butisnotlimitedto:Howthiscontractingmethodprovidesasubstantialfiscalbenefit:

ReducedCosts–Inperiodsofconstructioninflationarycycles,aswearecurrentlyexperiencing,theriskofcontractorsandsubcontractorfinancialfailuresissubstantial.TheGC/CMprocessprovidesameansfortheDistricttoinvestigatethefinancialstabilityofthefirmwithwhichitiscontracting,minimizingriskofcostlylitigationortimeextensionsduetosubcontractorfailures.TheGC/CMwillevaluatethedesigndocumentsandparticipateduringthedesignprocess,reducingunforeseenimpactsandleadingtoreducedcostsandscheduleimpacts.Duringthedesign,theGC/CMwillbechargedwithfindingbuildable,cost-effectivesolutionsthatenabletheDistricttocontrolconstructionphasechanges.ConstructabilityandvalueengineeringexerciseswillalsobeemployedbytheGC/CMasameanstoidentifybettersolutionsfornotonlyconstruction,butfortheoveralloperationallifeofthemiddleschools.

ExperiencedPartner–UsingaContractorthathasbeenthoroughlyvetted,withaproventrackrecordofsimilarprojectexperience,budgetmanagement,scheduling,claimavoidance,projectphasing,effectivesafetyplansforconstruction,leanconstructionpractices,andbeingaproactivememberoftheteamwillensurestudentsafetyandprotecttheDistrict’sscheduleandbudget.

AllocationofRisk–Theorganizationoftheteamallowsforintegratedandcollaborativeapproachestorisk,changes,andissuesthatarise:

• TheGC/CM(s)willdevelopatrueunderstandingoftheworkbybeinginvolvedinthedesign,andwillhaveafullunderstandingoftheOwner’sexpectationspriortoanybiddingofthework.

• TheGC/CM(s)willparticipateandprovidefeedbackduringconstructabilityreviewsandvalueanalysisexercises,andwillhaveownershipofanychangestheysuggestthatbecomeincorporated.Thisprovidesrealbuy-infromtheGC/CMandnotahands-offapproachtodecisionsinvolvingthedesign.

• Phasingofbidbuy-outandflexibilitytoadjustbidpackagesastheworkisboughtoutallowsforcostmanagementbytheDistrictandtheGC/CMteam(s).

• TheGC/CMprocessprovides‘openbook’,transparentaccountingandfinancialreportingtotheOwner.

IntegratedApproachtoSafety–Measurestokeepthestudents,staff,andneighboringcommunitiessafemustbeexhibitedbyallpartiesinvolvedintheproject.Byutilizinganalternatedeliverymethod,theDistrictwillrequiretheGC/CM(s)to:

• Developaprogram-widesafetyplanforallphasesofconstructionthatiscommunicatedtoschoolstaff,DistrictOfficials,andtheneighboringcommunities.

• DevelopaplanforcommunicatingmajorconstructionactivitiesandeventswiththeDistrict,parents,andneighboringcommunity.

Page 13: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 10 September2017

• Createandimplementplanstocommunicateandenforceconstructionvs.non-constructionzones,pedestriantravelpathwaysandwalkways,constructiontrafficroutes,emergencymusterpoints,andwherelaydownareaswilloccurastheprojectevolves.

B. Howtheuseofthetraditionalmethodofawardingcontractsinalumpsum(the“design-bid-buildmethod”)isnotpracticalformeetingdesiredqualitystandardsordeliveryschedules

RealTime,Market-BasedCostEstimates–ThePacificNorthwestregionhasexperiencedconstructioncostinflationratesof7.5to10percentoverthelast3years.ItiscriticaltothesuccessofbothprojectsthataGC/CMContractorisselected,sotheycanutilizereal-time,currentmarketpricingtovalidatescopingandbudgetingduringthedesignprocess;thiswouldnotbepracticalwithD-B-B.

AccuratePhasingPlans–TheGC/CM(s)willstudytheexistingconditions,desiredscopeofwork,anduniqueschedulingconstraintsofthemiddleschoolstobuildthesafest,mostefficientphasingplanpossibleaspartofthedesignprocess,whichwouldnotbepossibleusingDBB

IncreasedEngagementwiththeSmallBusinessTradeCommunity–TheGC/CM(s)willbeabletousetheirphasingplansandbiddingstrategiesastoolstodeveloptargetedopportunitiesforsmallbusinesseswithinthetrades,includingM/W/B/Esubcontractors.

EnhancedCoordinationofMaterialsandEquipmentPurchases–AGC/CMwillprovidebettercoordinationwithmaterialsandequipmentpurchases,includingMEPcoordination,vendorcoordination,timing,rough-in,delivery,off-loading,andstorage,thanwouldbefeasiblewithaDBBcontractor.

MoreResponsiveandResponsibleBids–Becauseofthescaleandcomplexityoftheseprojects,aGC/CMwillhaveagreaterabilitythanaD/B/Bcontractortoprequalifyandattractfirmswithresourcesneededtodotheworkandmeettheschedule.

OngoingValueAnalysisandConstructabilityReview–TheGC/CMwilldeliverreal-timeValueAnalysisandConstructabilityReviewProcessduringdesign,resultinginamoreeconomicaldesignandabetterbidpackagewithfewerchangeordersandlessriskoflosttimeordelaytotheprojectcompletion.

7. PUBLICBODYQUALIFICATIONS

A. Abriefsummaryoftheconstructionexperienceofyourorganization’sprojectmanagementteamrelevanttotheproject

ConstructionexperienceforeachproposedstaffmemberandconsultantisdescribedintheStaffandConsultantBiographiesinthefollowingsection.

ShorelinePublicSchools

MarlaMiller,DeputySuperintendent

Page 14: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 11 September2017

MarlaMiller,DeputySuperintendentofShorelinePublicSchools,hasservedK-12publiceducationintheStateofWashingtonsince1979.Marla’sconstructionandpropertydevelopment/managementexperiencehasprimarilybeengainedasExecutiveDirectorinEdmondsSchoolDistrictfrom1998to2012,andasDeputySuperintendentwithShorelinesince2012.HerpositioninShorelineincludesprimaryresponsibilityforlaborrelations/employeenegotiations,aswellasleadershipoftheteamresponsibleforMaintenanceandOperations,HumanResources,FoodService/Warehouse,Transportation,BusinessOperations/Payroll,Safety/EmergencyPlanning,andCapitalProjects.

Inadditiontonegotiatingpropertydevelopmentleases,sales,andpurchases,Marlahasdevelopednumerousconstructioncontractsandledresolutionofconstruction-relatedmatterswithcontractors,consultants,regulatoryagencies,andschoolandcommunitystakeholders.SheworkedwiththedesignteamfortheGC/CMapprovalforreplacementofMeadowdaleMiddleSchoolandwasanintegralpartofthedevelopmentoftheGC/CMcontractandanongoingparticipantintheprojectmanagementteamforthatproject.ShewasalsoapartoftheShorelineteamrecentlyapprovedforGC/CMcontractingfortheDistrict’sEarlyLearningCenter.

ConstructionProjects ProjectValue

ProcurementMethod Role CompletionDate

MeadowdaleMiddleSchool ~$48,000,000 GC/CM

ResponsibleDistrictAdministrator&WeeklyProject

ManagementTeam2011

ShorecrestHighSchool $84,000,000 D/B/B

ResponsibleDistrictAdministrator&WeeklyProject

ManagementTeam2014

ShorewoodHighSchool $95,000,000 D/B/B

ResponsibleDistrictAdministrator&WeeklyProject

ManagementTeam2014

AldercrestElementaryRenovation

$21,500,000 D/B/BResponsibleDistrict

Administrator&OngoingProjectManagementTeam

2016-2018

NorthCityElementaryRenovation

$12,000,000 D/B/BResponsibleDistrict

Administrator&OngoingProjectManagementTeam

2017-2018

Redevelopmentof40-acreFormerLynnwoodHighSite

$425,000,00099-yearlease,Costco&mixed

use

ResponsibleDistrictAdministrator&LeadNegotiator 2012/2013

ParkwoodElementary $27,000,000 D/B/B ResponsibleDistrict

Administrator&LeadNegotiator2016-present

(inconstruction)

EarlyLearningCenter $26,000,000 GC/CM ResponsibleDistrict

Administrator&LeadNegotiator

2017-present(inearly

construction)

Page 15: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 12 September2017

DanStevens,CapitalProjectsManager

Danhasover35yearsofexperienceintheconstructionindustry,rangingfromcontractorandfacilitiesmanagertoOwner’sRepresentative.Dan’sbackgroundincludesbothpublicandprivateprojectsthroughouttheNorthwest.Previously,DanworkedastheOwner’sRepresentativefortheYakimaCourthouseModernizationprojectwiththeCityofYakima,Washington.HiscurrentrangeofprojectswiththeDistrictincludesmajorrenovationoftwoexistingelementaryschools,andvariousHVAC,siteamenitiesimprovements,renovations,andphasingoffacilitiesinpreparationforthis$250mbondprogram.DanwasalsoinanoversightroleontheEarlyLearningCenterprojectandwillserveastheconstructionprojectmanagerfortheKelloggMiddleSchoolproject.

ConstructionProjects ProjectValueProcurement

Method Role CompletionDate

YakimaCity/CountyRailRoadOverpassProject

$10,000,000 CityProcedure Owner’sRepresentativeforYakimaCounty

ProjectwasunderwaywhenDan

departed

ShorewoodHSFieldandTrackReplacements

$7,969,729 D/B/B DistrictProjectManager August2013

AldercrestCampusPhase1

$5,600,000 D/B/B DistrictProjectManager September2016

NorthCityElementaryRenovation

$12,000,000 D/B/B DistrictProjectManager OnGoing

ParkwoodElementary $27,000,000 D/B/B DistrictProjectManager2016-present

(inconstruction)

MichaelRomero,ConstructionProjectManager(ShorelinePublicSchools)

MichaelRomerohasover18yearsofexperienceinpublicprojectandconstructionmanagement.MichaelrecentlyjoinedtheShorelinePublicSchoolsCapitalProjectsteamafterthepassageofthe2017bond.Previously,Michaelworkedasproject/constructionmanagerfortheLakeWashingtonandSeattleSchoolDistricts,theCityofBainbridgeIsland,andWashingtonStateoncomplexprojects,typicallyinvolvingahighdegreeofcoordinationwithoperatingpublicfacilitiesandhighlyinvolvedconstituencies.MichaelhassupportedseveralGC/CMprojectsandpreviouslycompletedtheAGC/UWGC/CMtraining.HeistheleadConstructionProjectManagerontheShorelineteamrecentlyapprovedforGC/CMcontractingfortheDistrict’sEarlyLearningCenter,andwillbetheDistrict’sconstructionprojectmanagerfortheEinsteinMiddleSchoolproject.

Page 16: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 13 September2017

Project ProjectValueDeliveryMethod Role Timeframe

EarlyLearningCenter(inearlyconstruction)

$26,000,000 GC/CM ConstructionManager 2017-present

AnnualSystemsPrograms,LakeWashingtonSchoolDistrict

$10-24MillionAnnualbudget

D/B/B,JOCD/B/B

ProgramManagerProjectManager

2016-20172013-2016

RedmondElementaryAddition,LakeWashingtonSchoolDistrict

$12,000,000 D/B/B ProjectManager 2014-2016

RoseHillMiddleSchool,LakeWashingtonSchoolDistrict

$72,000,000 D/B/B ProjectManager 2010-2013

HamiltonMiddleSchool,SeattleSchoolDistrict

$68,000,000 D/B/B ProjectManager 2005-2010

WinslowWay,CityofBainbridgeIsland $12,000,000 D/B/B ProjectManager 2007-2009

EastCapitolCampus,Olympia,Washington

$14,000,000 D/B/B ConstructionManager 2002-2005

GC/CMAdvisors:Parametrix

ParametrixwillsupporttheDistrictforallissuesrelatedtotheGC/CMprocess.Parametrixhasservedasadvisorand/orprojectmanageronover16currentandrecentGC/CMprojectsconductedundertheauthorityofRCW39.10.

HowardHillingerhasextensiveGC/CMexperienceonrecentandcurrentGC/CMprojectsforTacomaandWashougalschooldistricts,WashingtonStateFerries,MetropolitanParksDistrictandseveralothers.AnneTimmermanshasextensiveGC/CMexperiencewiththePortofSeattleprograms,andiscurrentlyconsultingonthePort/AlaskaAirGroup’srenovationattheNorthSatelliteattheSeaTacAirport.

HowardHillinger,GC/CMAdvisor(Parametrix)

ParametrixisaSeattle-basedconsultingfirmwhichsupportsavarietyofpublicagenciesintheplanning,design,andconstructionmanagementofcomplexfacilitiesprojects.Parametrixhasemergedasoneoftheleadingpractitionersinalternativeprojectdelivery,withover20recentandcurrentGC/CMprojects.

HowardHillingeristheGC/CMProgramAdvisorandhasover30yearsofprojectmanagementandconstructionmanagementexperience.HeisaPrincipalConsultantwithParametrixforProjectandConstructionManagementServices,wherehehassupportedownersonmorethanadozenrecentprojectsutilizingalternativeprojectdelivery.HeisaGC/CMadvisorwhohassupportedtwohistoricschoolmodernizationsforTacomaPublicSchoolsandtheColmanDock/SeattleMultimodalTerminalforWashingtonStateFerries.HeservedasamemberofGC/CMHeavyCiviltaskforce,andhascompletedAGC/UWGC/CMclass.HowardisaCertifiedConstructionManager.

Page 17: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 14 September2017

Project ProjectValueDeliveryMethod Role Timeframe

EarlyLearningCenter,ShorelineSchoolDistrict

$26,000,000 GC/CM GC/CMAdvisor 2017-Present

NewMiddleSchool,RidgefieldSchoolDistrict

$72,500,000 GC/CM GC/CMAdvisor 2016-Present

SeattleMultiModalTerminalatColmanDock

$230,000,000 GC/CM GC/CMAdvisor 2015-Present

JemtegaardMiddleSchool,WashougalSchoolDistrict

$37,800,000 GC/CM GC/CMAdvisor 2015-Present

ExcelsiorHighSchool,WashougalSchoolDistrict

$4,100,000 GC/CM GC/CMAdvisor 2015-Present

McCarverElementarySchoolHistoricModernization,TacomaPublicSchools

$39,000,000 GC/CM GC/CMAdvisor 2013-2015

StewartMiddleSchoolHistoricModernization,TacomaPublicSchools

$66,000,000 GC/CM GC/CMAdvisor 2013-2015

AnneTimmermans,GC/CMProjectManager(Parametrix)

Annehas14yearsofexperienceworkingonconstructionprojectsthroughoutthePacificNorthwest.Shehasworkedonmostlypubliccommercialprojects,rangingfromlarge-scaleaviationfacilitiestoK-12projects.SheisaCertifiedConstructionManager(CCM)andaLEEDAccreditedProfessional.

Project ProjectValueDeliveryMethod Role Timeframe

EarlyLearningCenter,ShorelineSchoolDistrict

$26,000,000 GC/CM GC/CMProjectManager

2017-present

NorthSatelliteRenovation,PortofSeattle

$425,000,000 GC/CM ResidentEngineer 2017-present

777xCompositeWingFacility,NewChillerBuildingandSitework,Boeing

$1,000,000,000 IPD ConstructionManager 2014-2017

ConsolidatedRentalCarFacility,PortofSeattle

$419,000,000 GC/CM ProjectManager 2006-2012

KristaLutz,GC/CMProjectManager(Parametrix)

Kristahas19yearsofexperienceworkingondesignandconstructionprojects.Herexperienceincludescommercial,residential,historicrenovation,andpublicfacilitiesincludingK-12projects.SheisfamiliarwithDBBandGC/CMdeliverymethodsonboththecontractorandconsultantside.SheisGC/CM(AGC)trained,aCertifiedConstructionManager(CCM),andaLEEDAccredited

Page 18: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 15 September2017

Professional.Kristaisanadditionalresourcethatmaybeutilizedbytheteamforsupportthroughouttheprocurement,design,andconstructionphases.

Project ProjectValueDeliveryMethod Role Timeframe

OlympicViewMiddleSchoolAddition,MukilteoSchoolDistrict

$12,000,000 DBB ConstructionManager 2016-present

DiscoveryElementarySchoolAddition,MukilteoSchoolDistrict

$3,000,000 DBB ConstructionManager 2016-present

PikePlaceMarketRenovationphase1-3 $60,000,000 GC/CM GC/CM 2010-2013

SeattleMultimodalTerminal,WSDOT $140,000,000 GC/CM PreconGC/CMAdvisor 2014-2015

DistrictLegalCounsel:PerkinsCoie,LLP

GraehmWallace,LegalCounsel(PerkinsCoie)

PerkinsCoieisanationallyrecognizedleaderinconstructionlaw.Theirteamofconstructionattorneyspracticesalltypesofconstructionlawonbehalfofowners,contractors,suppliers,architects,engineers,consultants,andgovernmentalentitiesinallstagesofconstructionprojects—fromprocurementthroughprojectmanagementtodisputeresolution.Thefirmdraftsandnegotiatesawidevarietyofcontractsonabroadspectrumofprojectsnationallyandinternationally.Inrecentyears,thecombinedannualvalueofcontractsPerkinsCoiehaspreparedhasbeenwellinexcessof$1billion.Graehm’spracticefocusesonrepresentationoflocalK-12schooldistricts,includingdraftingandreviewinglegaldocumentsregardingconstructionandrealestatematters,withaspecialfocusinalternatedeliverymethods.

KelloggMiddleSchoolArchitect:MahlumArchitects

WithmainofficesinSeattle,Washington,MahlumhasextensiveexperienceworkingwiththeGC/CMprocessoncomplexnewconstructionandrenovationprojects,andconsiderspartneringwiththecontractortobeverybeneficial.Mahlum’sexperiencewithK-12GC/CMprojectsbeganwiththefirstpilotproject,NorthshoreJuniorHigh.TheteamadvocatesforthebenefitsoftheGC/CMprocess,includingon-goingvalueengineering,constructabilitycritiques,andcostupdatingasweworkthroughallphasesoftheproject.

MahlumhasalsoledandparticipatedinmultiplepresentationsabouttheGC/CMprocessregionally,andactivelyengagesinlegislativediscussionsaboutitscontinuationandimprovement.

DavidMount,Principal-in-Charge(Mahlum)

Anaward-winningarchitectofeducationalfacilities,Davidhasmorethan23yearsofexperience.HeservesastheK-12EducationStudioDirectorandmanagesallaspectsofthismarketsectorforMahlum.Davidoffersbroadperspectiveintocosteffectiveopportunitiestoenhancecommunity

Page 19: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 16 September2017

andlearningbothinsideandoutoftheclassroom.ALEEDAccreditedProfessional,heblendstechnicalunderstandinganddesignsensitivitywithinsustainablesiteandbuildingconceptsforeducationalfacilities.DavidholdsaBachelorofArchitecturefromtheUniversityofArizona,andisaregisteredarchitectinWashingtonandOregon.HehasworkedonsevenK-12andhighereducationGC/CMprojectsandhasworkedwithShorelineSchoolDistrictontherecentAldercrestCampusModernizationprojects.

RoleDuringProjectPhases

ExperienceProjectValue

ProjectType Planning Design Construction

RoleStart

RoleFinish

EarlyLearningCenter,ShorelineSchoolDistrict

$26M GC/CM P-I-C P-I-C P-I-C 4/2017 10/2018

RobertEaglestaffMiddleSchool,

SeattlePublicSchools

$46M GC/CM – P-I-C P-I-C 5/2013 8/2017

CascadiaElementarySchool,

SeattlePublicSchools

$28M GC/CM – P-I-C P-I-C 5/2013 8/2017

LynndaleElementarySchool,

EdmondsSchoolDistrict

$25M GC/CM P-I-C P-I-C P-I-C 9/2014 1/2017

MadronaSchool,EdmondsSchoolDistrict

$35M GC/CM P-I-C P-I-C P-I-C 7/2015 8/2018

IssaquahMiddleSchool,IssaquahSchoolDistrict

$47M GC/CM P-I-C P-I-C P-I-C 6/2012 9/2016

RoweMiddleSchoolRenovation,NorthClackamasSchool

District

$13m GC/CM ProjectManager

ProjectManager

ProjectManager

6/2018 8/2019

EarlBoylesEarlyChildhoodCenter,DavidDouglasSchoolDistrict

$7M GC/CM ProjectDesigner

ProjectDesigner

ProjectDesigner

9/2012 9/2014

AcademicBuildingExpansion,CentralCatholicHighSchool

$11M GC/CM ProjectManager

ProjectManager

ProjectManager

6/2014 9/2015

AdministrationandEntryAddition,LaSalle

CatholicCollegePreparatory

$3M GC/CM ProjectManager

ProjectManager

ProjectManager

2015 2016

ChapelConversion,LaSalleCatholicCollege

Preparatory

$699K GC/CM ProjectDesigner

ProjectDesigner

ProjectDesigner

2006 2006

EinsteinMiddleSchoolArchitect:Integrus

IntegrusArchitecturehasextensiveexperienceworkingwiththeGCCMdeliverymodel,particularlywiththedesignandconstructionofcomplexphasedmodernizations.Thefirmhasparticipatedin

Page 20: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 17 September2017

theevolutionofGC/CMprocessasanacceptedandallowabledeliverymodelinWashingtonthroughseveralwayssuchas:

• IntegrusArchitecturewasselectedforoneofthefirstGC/CMpilotprojectsinWashingtonin1995

• TheCEO,BrianCarter,hasservedonOSPI’sTechnicalAdvisoryCommitteefor14years,andplayedaroleinadaptingtheD-FormprocesstoaccommodateGC/CMdelivery

• ThefirmhasmaintainedmembershipatCPARBandattheProjectReviewBoardforthepastfiveyears

• IntegrushasappearedbeforethePRCseventimes,eachinsupportofourclientsastheyhavepursuedpermissiontoutilizeGC/CM,havesuccessfullysupportedourclients,includingtheirrequestfor“agencystatus.”

RebeccaBaibak,Principal-in-Charge

Fornearly25years,Rebeccahasdedicatedhercareertounderstandinghowschooldesigncancapturetheimaginationofstudentsandstrengthentheirsurroundingneighborhoods.Rebecca’sexpertiseextendsintoworkingcloselywithcontractors,clients,anddesignteammemberstocoordinatedesignapproachesthatarelong-standingcivicstructuresthatareadaptableovertime,creatingfullyintegratedlearningenvironmentsthatoftenincludecomplicatedphasingandsiteconstraints.RebeccaisaregisteredFacilityPlannerwiththeAssociationforLearningEnvironments,andaLEEDAccreditedProfessionalwhoworksintegrallywithprojectteamstoenvisionlearningenvironmentsthatmeettoday’sneedswhileanticipatingfuturegoals.AsaregisteredarchitectintheStateofWashingtonshehaspersonallyworkedonfourK-12GC/CMprojectsandhasworkedwithShorelineSchoolDistrictontherecentmodernizationofShorecrestHighSchool.

RoleDuringProjectPhases

ExperienceProjectValue

ProjectType Planning Design Construction

RoleStart

RoleFinish

JuanitaHighSchool,LakeWashingtonSchoolDistrict

$98M GC/CM P-I-C P-I-C P-I-C 2014 2020

ParkPlaceMiddleSchool,MonroeSchoolDistrict

$45M GC/CM ProjectManager

P-I-C P-I-C 2010 2018

RushElementarySchool,LakeWashingtonSchoolDistrict

$32M GC/CM ProjectManager

P-I-C P-I-C 2010 2013

NorthshoreJuniorHighSchool,NorthshoreSchoolDistrict

$16M GC/CM ProjectArchitect

ProjectArchitect

ProjectArchitect

2001 2004

Page 21: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 18 September2017

Theproposedteamsareoutlinedinthefollowingorganizationchart:

Page 22: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 19 September2017

B. Adescriptionofthecontrolsyourorganizationwillhaveinplacetoensurethattheprojectis

adequatelymanaged

TheDistrictwillsetinplacespecificcontrolstomanagetheproject,beginningwithamanagementplandevelopedbyParametrixandreviewedandapprovedbytheDistrictteam.Proceduresandlimitsofauthoritywithregardstobudget,schedule,andchangeintheworkapprovalswereestablishedduringthekick-offofthedesignphase.ThisplanwillprovidearesponsibilitymatrixandwilladdressspecificexpectationsfortheDistrict,thedesignteam,andtheprojectmanagementteams.SubsequentexpectationsoftheGC/CMteam(s)willbeidentifiedintheRFP,RFFP,andGC/CMagreement.

Projectbudgets,schedules,MACCs,andTCCwillbeestablishedearlyonandreviewedateachdesignphasebytheSuperintendentandSchoolBoard.Theconstructionprojectmanagementteam,DanStevensandMichaelRomero,willcoordinatewiththeDistrict’sDeputySuperintendentandtoguaranteethatallpartiesareawareofanydevelopmentthatmightaffectthebudgetandthatallexpendituresareapprovedpriortopayment.Expenditurelimitsonaper-occurrencebasiswillbeestablishedbytheSuperintendentandtheBoardandalineofsignatureauthoritywillbeimplemented.

TheDistricthasandwillcontinuetoadequatelymanagetheprojectbysurroundingitselfwithprofessionalsthathaveaproventrackrecordofsuccessfulGC/CMprojects.ThefirmsofMahlumArchitects,IntegrusArchitecture,PerkinsCoie,andParametrixareprovenentities.TheDistrictexpectsthesefourfirmswillhelpguidethetwoprojectstosuccessfulandtimelycompletionsfortheopeningdayofschoolin2020.

Aspartofthetotalbondprogram,eachoftheprojectswillbetrackedindividuallytomaintainbettercontrolofdesign,schedule,andcosts.BothEinsteinandKelloggMiddleSchoolswillbefollowingthisstructure,andmayopttouseaseriesofMini-MACCcostsdevelopedbytheGC/CMteam(s)inanefforttobettercontrolthebudgetprocessandidentifydesign,schedule,orqualityshortfalls.Contingencieswillincludestatute-drivencontingenciesandconservativeownercontingenciestoprovidecushionbeyondthosefiguresestablishedintheGC/CM(s)contractandOfficeofSuperintendentofPublicInstruction(OSPI)recommendations.

Aspartofthepreconstructionservices,theGC/CM(s)willdevelopasubcontractingbidplanandscheduleforbidding,aswellasforphasedconstructionandearlyprocurementasagreedtobytheDistrict.TheArchitect’sdesigndeliverableswillbeintegratedwiththeGC/CMbiddingandconstructionplan,andupdatedonaregularbasis.EarlyandfrequentmeetingswiththeCitypermitagencies,firedepartment,andothercodeofficialspriortopermitintakeswillhelpensurethatpermitcommentrequirementsthatmayaffecttheMACC(s)willbemitigated.

C. ABriefDescriptionofYourPlannedGC/CMProcurementProcess.

TheGC/CMprocurementprocesswillbeginiftheprojectsreceivePRCapprovalbytheCommitteeonSeptember28th.TheFirstadvertisementoftheRFPisslatedforearlyOctober2018.TheprocesswillfollowtherequirementsofRCW39.10,andwillbeapproximatelynineweeksintotalduration,withtheawardofeitheroneortwoGC/CMcontractsaspartoftheRFFPfinalprocesses.Final

Page 23: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 20 September2017

approvalofthecontract(s)isscheduledtooccurattheregularlyscheduledSchoolBoardmeetingonDecember4,2017.

Thegeneralprocessbeingadheredtobytheteamisasfollows:

• MarketingoftheprojecttoexperiencedpotentialGC/CMcandidates.

• AdvertisingRFPforGC/CM(twoadvertisementsintheDailyJournalofCommerceandBuilder’sExchange).

• Holdingapre-proposalconferenceforbothprojectsattheDistrictheadquarters.

• Publishingaddendainatimelymannerafterthepre-proposalconference.

• InterviewingshortlistedGC/CMfirms.

• RequestingRFFPsfromhighestrankedfirmsfrominterviews.

• ReviewingRFFPsandrecommendingawardtohighestrankedfirm.

• ConductinglegalcounselreviewinparalleltoRFPandRFFPprocesses.

• NotificationofintenttoawardtoselectedGC/CM.

• PresentationtoShorelineSchoolBoard.

• ApprovalreceivedfromShorelineSchoolBoard

• GC/CMcontractexecuted.

D. VerificationThatYourOrganizationHasAlreadyDeveloped(orProvideYourPlantoDevelop)SpecificGC/CMContractTerms.

TheDistrictplanstoutilizetheGC/CMdocumentsdevelopedbyPerkinsCoie,whichwerefirstdevelopedfortheEarlyLearningCenterwhichiscurrentlybeginningconstruction.Thecontractswillbedevelopedwithtwooptionsfordeliveringtheprojects,eitherasoneGC/CMinaprogram-wideapproachforthetwoschools,orwithseparatecontractsfortwoseparateGC/CMs.

Thedocumentswillbedevelopedspecifictotheneedsofthetwoprojects.OurintentistoreleasethesedocumentsforreviewandcommentsshortlyafterPRCapprovalonSeptember28th.PriortoissuingthefinalRFFP,thedocumentswillbeupdatedtoreflecttherecommendationoftheGC/CMContractorsandcurrentindustrybestpractices.Aspartofthereview,theDistrictwillsolicitinputfromourlegalcounselandrevisetoincorporateanyrecentstatutoryupdates.FinalconstructiondocumentswillbemodeledupondocumentsthathavesuccessfullybeenusedwithotherWashingtonschooldistrictsandGC/CMprojectslocally.

Page 24: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 21 September2017

8. PUBLICBODY(SHORELINESCHOOLDISTRICT)CONSTRUCTIONHISTORY

Provideamatrixsummaryofyourorganization’sconstructionactivityforthepastsixyearsoutliningprojectdataincontentandformatpertheattachedsampleprovided:

Project DescriptionProjectValue

ContractingMethod

Schedule(start/finish)

PlannedBudget&ActualBudget*

ModularUnits Purchaseandinstallationof19modularelementaryclassunits

$5,000,000 D/B/B/ May2008-Fall2008

$5,000,000$5,000,000

CentralKitchen/Warehouse

Installationofanewcentralkitchenatexistingwarehouse

$6,390,000 D/B/B Spring2010-March2011

$6,390,000$4,222,374

KelloggMSPainting&GutterUpgrades

Exteriorpaintingandinstallationofnewgutters $1,758,626 D/B/B 5/11/2009-

8/21/2009$1,758,626$1,712,630

2009ElemPlayfieldUpgradeProject,multiplesites

Designandinstallationofmodifiedgrass/syntheticplayfieldsat3ESsites

$1,355,689 D/B/B December2008-August2009

$1,355,689$1,153,658

FlooringUpgrades,District-Wide

Completeflooringreplacementfor2ES&walk-offmats9otherschools

$1,207,412 D/B/B May2009-10/5/2009

$1,207,412$1,097,941

SLCRoofUpgrade CompletereplacementoftheShorelineCenterroofingmaterial

$1,541,000 D/B/B 5/1/11-July2012Info

Unavailable$2,313,087

MPBaseball/SoftballFieldImprovement

ConstructionofVarsityBaseball&SoftballFields $3,700,00 D/B/B 8/8/11-

3/12/2012$4,621,000$4,446,498

SCHSReplacement(w/oFields)

Replacement(NewIn-lieu)Shareof$192m D/B/B 2009-February

2014

Shareof$192m

$82,146,701

SWHSReplacement(w/Fields&RonaldSchool)

Replacement(NewIn-lieu)Shareof$192m D/B/B 2009-August

2013

Shareof$192m

$95,826,571

SyreElementaryHVAC ReplacementoftheexistingHVACsystem(likeforlike)

$1,240,00 D/B/B 200-August2013 $1,240,000$1,047,101

SCBaseball&SoftballFieldImprovement

Replacementoftheexistingbaseballandsoftballfield S5,000,000 D/B/B 6/15/15-3/23/16

$5,000,000$4,182,835

District-wideSafety&Security/ElectronicAccess

Designandinstallationofaccesscontrolatallschools $1,000,000 D/B/B June2015-

ongoing

$1,000,000$134,775(to

date)

RidgecrestFields Replacementoftheexistingplayfield $1,400,000 D/B/B 7/27/16-2/3/17

$1,400,000$890,278

Page 25: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProjectReviewCommittee(PRC)Application 22 September2017

Project DescriptionProjectValue

ContractingMethod

Schedule(start/finish)

PlannedBudget&ActualBudget*

AldercrestPhaseI Phase1oftheAldercrestCampusModernizationProject

$5,600,000 D/B/B 6/1/2016-9/6/2016

$5,600,000$5,595,076

NorthCityElementaryCampusModernization(TempTransitionSite)

NorthCityElementaryCampusModernization(TempTransitionSite)

$12,000,000 D/B/B 5/9/17-ongoing$3,000,000$3,000,000

EarlyLearningCenter DemolitionandConstructionofnewELC $36,000,000 GC/CM 4/6/17-ongoing

$36,000,000$1,000,000(todate)

*Thesefiguresdonotincludeencumberedmonies,andareonlyactualexpendituresthroughAugust31,2017.

9. PRELIMINARYCONCEPTS,SKETCHES,ORPLANSDEPICTINGTHEPROJECT

IndexofExhibits:

Exhibit1:MilestoneSchedule

Exhibit2:ShorelineSchoolDistrict2017BondProjectPhasingPlan

Exhibit3:KelloggMiddleSchoolExistingSitePlan

Exhibit4:KelloggMiddleSchoolExistingSiteConditionsandAccess

Exhibit5:KelloggMiddleSchoolConceptualSitePlan

Exhibit6:EinsteinMiddleSchoolExistingSitePlan

Exhibit7:EinsteinMiddleSchoolExistingSiteConditionsandAccess

Exhibit8:EinsteinMiddleSchoolConceptualSitePlan

Page 26: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 557-7937-001ProfessionalRegulationCommission(PRC)Application 23 April2017

Exhibit1:MilestoneSchedule

Page 27: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProfessionalRegulationCommission(PRC)Application 24 September2017

Exhibit2:BondProgramPhasingPlan

Page 28: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProfessionalRegulationCommission(PRC)Application 25 September2017

Exhibit3:KelloggMiddleSchoolExistingSitePlan

Page 29: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProfessionalRegulationCommission(PRC)Application 26 September2017

Exhibit4:KelloggMiddleSchoolExistingSiteConditionsandAccess

Page 30: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProfessionalRegulationCommission(PRC)Application 27 September2017

Exhibit5:KelloggMiddleSchoolConceptualSitePlan

Page 31: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProfessionalRegulationCommission(PRC)Application 28 September2017

Exhibit6:EinsteinMiddleSchoolExistingSitePlan

Page 32: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProfessionalRegulationCommission(PRC)Application 29 September2017

Exhibit7:EinsteinMiddleSchoolExistingSiteConditionsandAccess

Page 33: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProfessionalRegulationCommission(PRC)Application 30 September2017

Exhibit8:EinsteinMiddleSchoolConceptualSitePlan

Page 34: SHORELINE SCHOOL DISTRICT NO. 412 - Department of … · 2017-09-05 · SHORELINE SCHOOL DISTRICT NO. 412 ... Kellog Middle School Existing Site Conditions and Access ... Equipment

ShorelineSchoolDistrictNo.412 ProfessionalRegulationCommission(PRC)Application 31 September2017

10. RESOLUTIONOFAUDITFINDINGSONPREVIOUSPUBLICWORKSPROJECTS

TheShorelineSchoolDistricthasreceivednoauditfindingsonanyproject.