WHAT’S HAPPENING NOW? • Building is fully enclosed! • Dry wall hanging complete mid March • Administration offices work has begun • Interior painting has started • Organ coordination has begun • Flooring preparation underway • Interior finishes materials to begin arriving in March CONSTRUCTION ADMINISTRATION UPDATE Shepherd of the Prairie New Worship & Gathering Space 10805 Main Street Huntley, IL SHEPHERD OF THE PRAIRIE SCOPE New Worship & Gathering Space COMPLETION 2018 SQ FT 14,300 CONSTRUCTION MANAGER Shales McNutt Construction Issued 02/23/18 ARCHITECT Dan Konczal, RA PROJECT DESIGNER Jessica Boyung CONSTRUCTION ADMIN. Mike McGraw, CDT CONSTRUCTION SUPPORT Caitlin Duerr
3
Embed
sHepHerd oF tHe prAirie - static1.squarespace.com · Dave Lamb GROTH DESIGN PARTNER/ARCHITECT Steve Petitt, AIA GROTH DESIGN PROJECT MANAGER Nathan Pamperin ... Sister Charlotte w/GROTH
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
WHAT’S HAPPENING NOW?• Building is fully enclosed!
• Dry wall hanging complete mid March
• Administration offices work has begun
• Interior painting has started
• Organ coordination has begun
• Flooring preparation underway
• Interior finishes materials to begin arriving in March
ConstruCtion AdministrAtion updAte
Shepherd of the Prairie New Worship & Gathering Space10805 Main StreetHuntley, IL
sHepHerd oF tHe prAirie
SCOPE New Worship & Gathering Space
COMPLETION2018
SQ FT14,300
CONSTRUCTION MANAGER Shales McNutt Construction
Issued 02/23/18
ARCHITECT Dan Konczal, RA
PROJECT DESIGNER Jessica Boyung
CONSTRUCTION ADMIN. Mike McGraw, CDT
CONSTRUCTION SUPPORT Caitlin Duerr
WHAT’S HAPPENING NOW?Building 1:
• Precast erection complete• Underground plumbing and electrical ongoing• Steel erection starting early March
Building 2:• Footing work at the deep basement area nearly finished• Deep foundation walls ongoing• Precast erection in early March
Building 3:• Frost wall work complete• Underground plumbing and electrical nearly complete• Installation of pre-fabricated walls plans starting mid-March
ConstruCtion AdministrAtion updAte
Sisters of St. Francis of Assisi New Convent3221 South Lake Drive, St. Francis, WI